Escolar Documentos
Profissional Documentos
Cultura Documentos
consultants ltd
RESUMO
FINAL REPORT
SUMMARY..............................................................................................................3
1.0 INTRODUCTION..............................................................................................6
3.10 INTRODUCTION..........................................................................................16
4.10 Introduction.......................................................................................29
This report covers the testing and development work undertaken on a composite
physical hydraulic model of three individual proposed pumping stations, designated
Stations EBV-1 and EBV-2, that each form part of the Sao Francisco river water intake
scheme.
The composite model was used to develop arrangements that worked well under all of
the potential operating scenarios. EBV-1 and EBV-2 were simulated at a scale of
1:12.9 full size, whilst maintaining fully turbulent conditions at the inlet to each of the
eight suctions under both scales, which can be confirmed by calculation of the model
Reynolds Number, ensuring it exceeds the recommended minimum values.
Testing was undertaken on each pumping station arrangement in turn and the results
of the initial testing, development and final testing programmes may be summarised
as follows.
Pumping Station EBV-1 - Initial testing
The initial testing programme undertaken on Station EBV-1 demonstrated that pump
intake conditions were similar to those exhibited on Station EBI-1 and were therefore
compromised by the presence of submerged side wall vortices generated where
opposing approach flows to the suction intake were forced to mix and a rotational
element, sufficient to form a fully coherent and penetrating vortex core, was generated
as a result. In addition, a strong and stable fully penetrating free surface vortex was
also noted, when operating at lower water levels, when the top of the vertical vane
was exposed. Despite the presence of these adverse hydraulic features, the general
pump intake conditions were characterised by a uniform approach flow and smooth,
radial draw at the suction. Pre-swirl rotation was maintained within acceptable limits,
with no bulk rotation identified.
As the approach flow entering the individual pump cells were considered acceptable
and the variations in pump combinations and designation had no measurable effect
on intake conditions, it was not considered necessary to develop the inlet
arrangement in any form. The adverse features were all a function of localised
disturbances in the region of the suction intakes of each individual pump cell and as
they were common in both form and intensity, in each case, similar modifications were
anticipated for each of the four pump cells.
The initial testing programme for Pumping Station EBV-1 is documented in Section
4.20 of this report. The initially proposed arrangement is detailed Drawings 03 and
04, located in Appendix 2.0.
Pumping Station EBV-1 - Development
Further development of the initially proposed arrangement was required local to the
pump suctions only and no alteration was necessary around the inlet to each of the
cells or within the distribution bay. The modifications developed for Pumping Station
EBV-1 were similar in concept to those developed for Station EBI-1 and consisted of
45-degree infill fillets located at base, level local to the pump suction intakes. A
vane/cone hybrid was also installed in addition to a rear profiled (45-degree) vane,
extending vertically upwards, terminating below the minimum water level. Testing
demonstrated that no further modifications were required to ensure satisfactory pump
intake conditions could be achieved.
Following the development and installation of the modifications within the four
individual pump cells, as detailed in Drawings 10 to 12, the initially defined maximum
and minimum operating levels maintained and the pump discharge retained at
7000 l/s, the final proposed arrangement of the Sao Francisco Pumping Station EBV-
1 ensured a satisfactory operating environment could be achieved.
Acceptable pump intake conditions were maintained under all anticipated station
inflow rates, sump water levels and approach profiles. Pump intake conditions were
free from surface and submerged vorticity, jetting flows, the ingestion of entrained air
and pre-swirl rotation was maintained at zero degrees. The swirl meter vanes were
generally characterised by very minor bi-directional fluttering, which is indicative of
stable flow passing the position of the prototype impeller.
Undertaking velocity scans, using a pitot static tube array, at the minimum and
maximum water levels on Pump 1, confirmed our visual assessment and determined
that a radial draw was achieved with an acceptable velocity distribution across the
plane of the intake, at the position of the prototype impeller.
The maximum deviation from the mean velocity occurred when operating at the
minimum water level of 298.64 m, with a peak value of 3.13 % recorded. This was
within the limiting value of 10 % total, or 5 % plus or minus from the mean as defined
in the ANSI standards (Ref : 9.8.5.6 - Acceptance Criteria) and confirmed that
acceptable pump intake conditions were maintained. A second velocity scan
undertaken demonstrated slightly improved intake conditions, with a maximum
variation of 2.40 %. This could be attributed to the increased cross sectional area of
the pump cell and the reduction in forward flow velocity as a result.
The modifications proposed were again kept as simple as possible and were
conceptually very similar to those installed in Station EBI-1. No alteration to the main
structure or pump locations was necessary. The modifications are detailed in
Drawings 10 to 12 in Appendix 2.
The Final confirmatory testing programme for Pumping Station EBV-1 is documented
in Section 4.40 of this report.
The initial testing programme for Pumping Station EBV-2 is documented in Section
5.20 of this report. The initially proposed arrangement is detailed Drawings 05 and
06, located in Appendix 2.0.
Following the development and installation of the modifications within the four
individual pump cells, as detailed in Drawings 13 to 15, the initially defined maximum
and minimum operating levels maintained and the pump discharge retained at
7000 l/s, the final proposed arrangement of the Sao Francisco Pumping Station EBV-
2 ensured a satisfactory operating environment could be achieved.
Acceptable pump intake conditions were maintained under all anticipated station
inflow rates, sump water levels and approach profiles. Pump intake conditions were
free from surface and submerged vorticity, jetting flows, the ingestion of entrained air
and pre-swirl rotation was maintained at zero degrees. The swirl meter vanes were
generally characterised by very minor bi-directional fluttering, which is indicative of
stable flow passing the position of the prototype impeller.
Undertaking velocity scans, using a pitot static tube array, at the minimum and
maximum water levels on Pump 1, confirmed our visual assessment and determined
that a radial draw was achieved with an acceptable velocity distribution across the
plane of the intake, at the position of the prototype impeller.
The maximum deviation from the mean velocity occurred when operating at the
minimum water level of 359.68 m, with a peak value of 2.53 % recorded. This was
within the limiting value of 10 % total, or 5 % plus or minus from the mean as defined
in the ANSI standards and confirmed that acceptable pump intake conditions were
maintained. A second velocity scan undertaken demonstrated slightly improved intake
conditions, with a maximum variation of 2.24 %. This could be attributed to the
increased cross sectional area of the wetted sump area and the reduction in forward
flow velocity as a result.
The modifications proposed were again kept as simple as possible and were
conceptually very similar to those installed in Stations EBI-1 and more significantly,
EBV-2. No alteration to the main structure or pump locations was necessary. The
modifications are detailed in Drawings 13 to 15 in Appendix 2.
The Final confirmatory testing programme for Pumping Station EBV-2 is documented
in Section 5.40 of this report.
As part of the Sao Francisco River Intake Project it is proposed to construct three new
pumping stations, designated Pumping Stations EBV-1 and EBV-2. Each pump
station will draw flow directly from the Sao Francisco River via dedicated trapezoidal
channels.
Station EBV-1 will ultimately be fitted with four vertical spindle mixed flow pumps,
specifically Sulzer type BK 1400-1870-1s/033. The four pumps will be operated on a
fixed speed basis and will deliver a nominal maximum flow of 7.00 m 3/s each to the
downstream system. Up to four pumps will be operated simultaneously, resulting in a
maximum potential pumped outflow of 28.00 m 3/s. The pumps will be initiated on a
demand basis and will be operated between levels of 298.64 m and 304.09 m (the
minimum and maximum anticipated levels accordingly), resulting in a total potential
band width of 5.45 m and a maximum and minimum station depth of 11.69 m and 6.24
m appropriately. The actual station level will be determined by river level and on this
basis, is likely to fluctuate seasonally, rather than on a regular daily basis.
Each of the four pumps will draw centrally from individual 5160 mm wide pump cells
with the pump centreline being off-set from the rear sump wall by 2500 mm. Each
pump cell will be fitted with coarse screens and isolation stop logs at the upstream
end. It is assumed that ultimately, the station will be operated with all pump cells
open, except during periods of maintenance, when the stop logs will be introduced.
We understand that the intention is initially to install two of the four pumps units; the
remaining two pump cells will be isolated using the proposed stop logs.
The proposed coarse screens will consist of a 5.160 m x 6.312 m screen face with
vertical bars of 12.7 mm x 150 mm profile and 100 mm spacing’s. In addition,
horizontal support bars with a similar profile and approximately 1050 mm spacing’s will
also be installed.
Figures 1.13 and 1.14 that follow illustrate the individual cell geometry in plan and
section for Station EBV-1, according to the originally proposed design.
20590
35
R1 3
A A
2580
5160
3160
2580
1000
1200
R105 0
2500
12900
Figure 1.13 – Plan of one of four similar pump cells on Station EBV-1, of the Sao
Francisco River Intake Scheme.
R8000
577
MIN W.L. 289.64m
12400
1000
4973
6600
5000
150
1050
292.40m
6646 12900
Figure 1.14 – Section A – A through the centre of one of the similar four pump
cells on Station EBV-1, of the Sao Francisco River Intake Scheme.
Station EBV-2 will ultimately be fitted with four vertical spindle mixed flow pumps,
specifically Sulzer type BKn 1400-1470-1s/030. The four pumps will be operated on a
fixed speed basis and will deliver a nominal maximum flow of 7.00 m 3/s each to the
downstream system. Up to four pumps will operate simultaneously, resulting in a
maximum potential pumped outflow of 28.00 m 3/s. The pumps will be initiated on a
demand basis and will be operated between levels of 359.68 m and 361.80 m (the
minimum and maximum anticipated levels accordingly), resulting in a total potential
band width of 2.12 m and a maximum and minimum station depth of 8.12 m and 6.00
m appropriately. The actual station level will be determined by river level and on this
basis, is likely to fluctuate seasonally, rather than on a regular daily basis.
Each of the four pumps will draw centrally from individual 5160 mm wide pump cells
with the pump centreline being off-set from the rear sump wall by 2400 mm. Each
pump cell will be fitted with coarse screens and isolation stop logs at the upstream
end. It is assumed that ultimately, the station will be operated with all pump cells
open, except during periods of maintenance, when the stop logs will be introduced.
We understand that the intention is initially to install two of the four pumps units; the
remaining two pump cells will be isolated using the proposed stop logs.
The proposed coarse screens will consist of a 5.160 m x 6.312 m screen face with
vertical bars of 12.7 mm x 150 mm profile and 100 mm spacing’s. In addition,
horizontal support bars with a similar profile and approximately 1050 mm spacing’s will
also be installed.
Figures 1.15 and 1.16 that follow illustrate the individual cell geometry in plan and
section for Station EBV-2, according to the initially proposed design.
17985
3 35
A A
2580
3160
5160
2580
1000
R1050
2500
12900
1420
MIN W.L. 359.68m
1000
6600
353.68m
2600 2400
20202
Figure 1.16 – Section A – A through the centre of one of the similar four pump
cells on Station EBV-2, of the Sao Francisco River Intake Scheme.
The detailed general arrangement drawings of the three proposed pumping station
arrangements are shown on Drawings 01 to 06 in Appendix 2, at the back of this
report.
The American National Standards Institute (ANSI/HI 9.8 - 1998) publication ‘Pump
Intake Design’ has been adopted to provide the following minimum acceptance
standards for the model testing programme. Acceptance criteria for pre-swirl rotation,
free surface and submerged vorticity stated by the American National Standards
Institute (ANSI/HI 9.8 - 1998) publication is stated below:-
Pre-swirl
Pre-swirl angles both the short term (10 to 30 second model) maximum and long term
(10 minute model) average indicated by the swirl meter rotation, must be less than 5
degrees. Maximum short term (10 to 30 second model) swirl angles up to 7 degrees
may be acceptable, only if they occur less than 10% of the time or for infrequent
pump operating conditions.
The swirl meter rotation should be reasonably steady, with no abrupt changes in
direction when rotating near the maximum allowable rate (angle). The maximum
permitted swirl angle should be 5 degrees for both short term and long term average
conditions. Whilst 7 degrees has been defined as acceptable as a short term
maximum value for infrequent occurrence (<10% time).
Free surface vortices
Free surface vortices entering the pump must be less severe than vortices with
coherent (dye) cores, Type 3 classification, see Appendix 1 – Section A1.4. Dye core
vortices may be acceptable only if they occur for less than 10% of the time or only for
infrequent pump operating conditions.
Submerged vortices
Submerged vortices entering the pump must be less severe than Type 2 classification,
see Appendix 1 – Section A1.4.
Air Intake
The purpose of the model test was to establish the operating characteristics of the
three proposed pumping station arrangements and to develop the designs, where
considered necessary, to achieve a satisfactory hydraulic environment over the full
range of inflows and potential water levels. There are several specific hydraulic
phenomena that can adversely affect the performance of pump operation. It is
important that these phenomena are minimised or eradicated on the prototype to
ensure the pump performance and reliability can be optimised. The key areas of
interest on these three particular models may therefore be summarised as follows :-
SC-RW P1
Dia.
uth
l mo
RBe
The model pump fabrications were constructed from information issued by the pump
supplier and very accurately fabricated to a scale of 1:12.9 for stations EBV-1 and
EBV-2.
Overall view of the model test rig (set up for Station EBV-1)
Overall view of the model test rig (set up for Station EBV-2)
Coarse screens located on the upstream end of each individual pump cell.
3.31 Development of Pumping Station EBV-1
Dimensional checks were first undertaken to confirm whether of not the key sump
dimensions were in general agreement with the “American National Standard for
Pump Intake Design” publication, as issued by the Hydraulic Institute. The sump
proved to be in general accordance with the sump cell, being approximately 2 suction
diameters wide and of sufficient length to eliminate any adverse condition at the cell
entry. On this basis, no infill sections were considered to be necessary to reduce the
width of the sump, local to the suction intake.
In an attempt to eliminate the formation point for submerged side wall vorticity, evident
in all four pump cells, connecting with both the right and left hand walls, and to
improve the transition of flow into the suction intakes by infilling potential low velocity
stall areas, 45-degree low level infill benching fillets were introduced. The sloping
angle face is critical in denying the vortex mechanism a formation point and the
optimum angle is 45-degrees. As it was important that no vertical face of the sump
side wall was exposed local to the suction, the height of the infill fillets was extended
to a similar elevation to the suction intake plane. This resulted in relatively large infill
fillets, when maintaining a slope angle of 45-degrees. The infill fillets were extended
approximately two suction diameters upstream and a profiled 45-degree transition
was installed on the upstream end, to minimise any potential for flow separation of the
approach flow off the leading edges of the benching.
While there was no evidence of a coherent floor vortex noted on station EBV-1 this
could be attributed to the reduced suction draw of the appropriate pumps. A stall zone
was generated and on this basis, it was considered that a similar cone/vane hybrid
design should be adopted. It was considered that this would eliminate the stall zone
and in addition, improve the transition of flow into the suction arrangement. The
proposed cone should have a base diameter of 2500 mm with the centre-point
elevated 1100 mm. This will result in a cone face angle of approximately 41 degrees.
A 200 mm clearance will also be maintained between the top of the cone and the
suction intake plain elevation. This will ensure that should any solid matter enter the
pump cells, it will not become trapped at the intake, minimising the risk of potential
blockage. An intermediate horizontal plate or vane should be installed between the
cone and the rear vane.
The proposed arrangement for each cell in Pumping Station EBV-1 is illustrated in the
drawings and images that follow.
B
141
4
1000
1100
1100
1480
503
356
1580
A R 12 5 A
0
1100
2249
5160
2960
1100
1580
356
6
155
1480
1100
1100
1000
2500
B
1500 1000
Plan of the proposed modifications to each of the four pump cells on Pumping
Station EBV-1.
305.00
298.64
BWL = 298.64
297.89
296.79
1100
1100
1100
3290
3290
293.50
292.40
1100
1100
1100 5144 356 1100 1000 1580 1580 1000
Section A- A Section B - B
Following the definition of the modifications (see Section 4.30) a study of the
proposed final arrangement was undertaken to confirm the pumping environment
when operated between the minimum and maximum anticipated water levels of
298.64 m and 304.09 m, with fixed individual pump rates of 7000 l/s (7.00 m 3/s) with
varying numbers and combinations of operative pumps between one and four
Solids transportation
The control range is again defined by the variation in level of the Sao Francisco River,
which has been confirmed by the client as between 298.64 m and 304.09 m, a total
range of 5.45 m.
At the minimum anticipated river level of 298.64 m the depth of water in the pumping
station will be 6.24 m. With a suction height of 1.20 m above the sump base level of
292.40 m, the total suction submergence is 5.04 m. Testing demonstrated that
acceptable pump intake conditions could be maintained at the minimum level. Further
testing confirmed operation across the full anticipated range. On this basis, we do not
recommend any alteration to the pumping station base elevation and can confirm that
the operational depth in the station is acceptable, regardless of the number of pumps
being operated.
In each of the defined test scenarios, there was no evidence of either surface or
submerged vorticity, air entrainment local to the intakes and pre-swirl rotation was
maintained at zero degrees, (i.e., no coherent rotation noted). The swirl meter vane
was characterised by very mild bi-directional fluttering, which is indicative of stable
Undertaking velocity scans, using a pitot static tube array, at the minimum and
maximum water levels on Pump 1, confirmed our visual assessment and determined
that a radial draw was achieved with an acceptable velocity distribution across the
plane of the intake, at the position of the prototype impeller.
The maximum deviation from the mean velocity occurred when operating at the
minimum water level of 298.64 m, with a peak value of 3.13 % recorded. This was
within the limiting value of 10 % total, or 5 % plus or minus from the mean as defined
in the ANSI standards and confirmed that acceptable pump intake conditions were
maintained. A second velocity scan undertaken demonstrated slightly improved intake
conditions, with a maximum variation of 2.40 %. This could be attributed to the
increased cross sectional area of the pump cell and the reduction in forward flow
velocity as a result.
No alteration to the main structure or pump locations was necessary. The
modifications are detailed in Drawings 10 to 12 in Appendix 2.
The modifications to Station EBV-2 were similar to those recommended for Station
EBV-1 and included 45-degree infill fillets local to the suction intake, a revised
vane/cone hybrid to replace the existing horizontal vane and a variation of the initially
proposed vertical vane. The modification are detailed in the drawings below. Images
of the revised arrangement follow.
141
4
1000
1100
1100
1480
503
356
1580
A R 12 5 A
0
1100
2249
5160
2960
1100
1580
356
6
155
1480
1100
1100
1000
2500
B
1500 1000
Proposed modifications to each of the four pump cells on station EBV-2 – Plan.
305.00
298.64
BWL = 298.64
297.89
296.79
1100
1100
1100
3290
3290
293.50
292.40
1100
1100
1100 5144 356 1100 1000 1580 1580 1000
Section A- A Section B - B
View of the revised vane/cone hybrid design located beneath and along the
centre-line of each pump suction intake.
Following the definition of the modifications (see Section 5.30) a study of the
proposed final arrangement was undertaken to confirm the pumping environment
when operated between the minimum and maximum anticipated water levels of
359.68 m and 361.80 m, with fixed individual pump rates of 7000 l/s (7.00 m 3/s) with
varying numbers and combinations of operative pumps between one and four
(incremental station inflow rises of 7000 l/s up to a maximum inflow rate of 28000 l/s.
Both straight and oblique pump cell approach flow patterns were achieved depending
on the pump combination being studied. In addition, a detailed velocity scan at the
Solids transportation
The pumps in Pumping Station EBV-2, like EBV-1 and EBI-1, will not be operated on a
level control basis, but will react to demand rather than water level. The control range
is therefore defined by the localised level variation of the Sao Francisco River, which
the client has confirmed as between 359.68 m and 361.80 m above the datum level, a
fluctuation of 2.12 m.
At the minimum anticipated river elevation of 359.68 m, the water depth in the
pumping station will be 6.00 m above the base level of 353.68 m. The plane of the
pump suction intake is elevated 1200 mm above the base, resulting in a total
minimum suction submergence of 4.80 m. This exceeds the pump manufacturers
defined minimum submergence. Testing demonstrated that acceptable pump intake
conditions could be maintained at the minimum level. Further testing confirmed
operation across the full anticipated range. On this basis, we do not recommend any
alteration to the pumping station base elevation and can confirm that the operational
depth in the station is acceptable, regardless of the duty pump number and
designation.
4.42 EBV-2 – Final testing - Pump Intake conditions
On completion of the development programme, a detailed evaluation of pump intake
conditions was undertaken across the defined flow and level range to identify any
submerged or surface vorticity, to confirm that no air will enter the pump suctions and
to determine the magnitude of pre-swirl rotation. The sump was operated in its fully
modified form, as detailed in Drawings 13 to 15 in Appendix 2.0. Testing was
undertaken with various combinations of one, two, three and four pumps operating
simultaneously across the anticipated level range.
Testing of the proposed modified arrangement demonstrated that acceptable pump
intake conditions were achieved, regardless of the sump level (within the defined
range of between 359.68 m and 361.80 m), station inflow (between 7000 l/s and
28000 l/s), number of operative pumps (between 1 and 4) and pump
designation/combination.
A comprehensive number of operating variations, based on level, inflow, pump
combination etc., confirmed that in each case, there was no evidence of either
surface or submerged vorticity, entrained air entering the region of the suction intakes
and pre-swirl rotation was within acceptable limits, maintained at zero degrees with no
bulk rotation noted. The swirl meter vane was characterised by relatively mild bi-
directional movement, which is indicative of stable flow passing the position of the
prototype impeller. The transition of flow into the suction intakes was, in all cases,
smooth, uniform and radial and considered to be acceptable.
Undertaking velocity scans, using a pitot static tube array, at the minimum and
maximum water levels on Pump 1, confirmed our visual assessment and determined
that a radial draw was achieved with an acceptable velocity distribution across the
plane of the intake, at the position of the prototype impeller.
The maximum deviation from the mean velocity occurred when operating at the
minimum water level of 359.68 m, with a peak value of 2.53 % recorded. This was
within the limiting value of 10 % total, or 5 % plus or minus from the mean as defined
in the ANSI standards and confirmed that acceptable pump intake conditions were
maintained. A second velocity scan undertaken demonstrated slightly improved intake
conditions, with a maximum variation of 2.24 %. This could be attributed to the
increased cross sectional area of the pump cell and the reduction in forward flow
velocity as a result.
The modifications proposed were again kept as simple as possible. No alteration to
the main structure or pump locations was necessary. The modifications are detailed in
Drawings 13 to 15 in Appendix 2.
APPENDIX 2 DRAWINGS
Development Drawings
Detail of modifications – Plan – Station EBV-1 Drawing 10
Detail of modifications – Section A – A and B – B – Station EBV-1 Drawing 11
Detail of modifications – Vane/cone hybrid design – Station EBV-1 Drawing 12
Detail of modifications – Plan – Station EBV-2 Drawing 13
Detail of modifications – Section A – A and B – B – Station EBV-2 Drawing 14
08-2 0GEN-0 3
20590
R13 5
A A
2580
3160
5160
2580
1000
1200
R1050
2500
12900
26
hydrotec
consultants ltd
08-2 0GEN-0 4
R8000
577
1000
4973
6600
5000
150
1050
292.40m
27
hydrotec
consultants ltd
08-2 0GEN-0 6
17985
R13 5
A A
2580
3160
5160
2580
1000
R1050
2500
12900
28
hydrotec
consultants ltd
08-2 0GEN-0 6
2860
6313
6600
6225
1200
353.6 8m
1050
2600 2400
1 92 611 0 12900
20202
29
hydrotec
consultants ltd
14 14
1000
1 00
1 00
1480
50 3
356
1580
A A
1 00
R1250
5160
2960
2249
1 00
1580
356
15 56
1480
1 00
1 00
1000
B 2500
1500 1000
30
hydrotec
consultants ltd
1 00
1 00
1 00
3290
3290
293.5 0
292.4 0
1 00
1 00
31
hydrotec
consultants ltd
08-2 0GEN-1 2
B
1250 150 1 00
A A
1 00
1 00
R1250
1400 1 00
B
1 00 1 00
41 41
1 00
1 00
150 1 00
1250 1250 1250 1250 1250
32
hydrotec
consultants ltd
14 1 4
1000
1 00
1 00
1480
50 3
356
1580
A R125 0 A
1 00
5160
2960
2249
1 00
1580
356
15 6
1480
1 00
1 00
1000
B 2500
1500 1000
33
hydrotec
consultants ltd
08-2 0GEN-1 4
5160
1500 1000 2580 2580
1 00
1 00
1 00
3290
3290
354.78
353.68
1 00
1 00
34
hydrotec
consultants ltd
08-2 0GEN-1 5
B
1250 150 1 00
A A
1 00
1 00
R1250
1400 1 00
B
1 00 1 00
41 41
1 00
1 00
150 1 00
1250 1250 1250 1250 1250
35