Bangladesh Rural Electrification Board

On going project’s Information :


Sl. Name of Project’s Project Cost (Tk. in Lac) Project Consumer Line Sub-station Develo
connection p-ment
No period (km) Capacity Partner
GOB BREB PA Total (Nos.) SS.
. (MVA)
(Nos.)

01. Rural Electrification 138520 - - 138520 01/07/2014 325000 8500 42 380 -


Expansion Rajshahi - to
Rangpur Division 30/06/2019
program-II
02. Rural Electrification 168730 - - 168730 01/07/2014 450000 10500 45 450 -
Expansion Chittagong to
- Sylhet Division 30/06/2019
program-II
03. Up-gradation of Rural 99973 20000 370500 490473 01/07/2014 - 6249 110 1840 IDA
Electricity Distribution to
System 30/06/2020
(Dhaka,Chittagong &
Sylhet Division)
04. Rural Electrification 164537 - - 164537 01/07/2014 400000 10000 50 600 -
Expansion Dhaka to
Division program-II 30/06/2019
05. Rural Electrification 99550 - - 99550 01/07/2014 250000 6500 23 215 -
Expansion Khulna to
Division program-II 30/06/2019
06. Rural Electrification 83890 - - 83890 01/07/2014 200000 5500 15 150 -
Expansion Barisal to
Division program-II 30/06/2019
07. Technical Assistance 1114 - 4680 5794 01/07/2015 - - - - IDA
Project for to
Institutional 31/12/2019
Strengthening of Rural
Electrification
Program

08. Pre-payment e- 10369 325 32951 43645 01/07/2015 - - - - ADB


metering in Dhaka to
Division under Rural 30/06/2020
Electrification
Program (Phase-I)
09. 1.5 Million Consumer 691541 - - 691541 01/01/2016 1500000 44000 118 1006 -
Connection through to
Rural Electrification 31/12/2018
Expansion
10. Replacement of 70,000 75520 4474 - 79994 01/01/2016 - - - - -
nos. Overloaded to
Distribution 31/12/2018
Transformer under
Rural Electrification
Program
11. Rural Electrification 140711 999 - 141710 01/01/2016 320000 7300 31 215 -
Expansion Program in to
Sylhet Division & 31/12/2018
Infrastructure
Development of
BREB Headquarter
12. Up-gradation, 135557 427 204399 340383 01/07/2016 500000 27000 - - ADB
Rehabilitation and to
Intensification of 30/06/2019

C:\Users\ASUS\Desktop\Project_Updated\On-going_Project.docx
Sl. Name of Project’s Project Cost (Tk. in Lac) Project Consumer Line Sub-station Develo
connection p-ment
No period (km) Capacity Partner
GOB BREB PA Total (Nos.) SS.
. (MVA)
(Nos.)

Distribution System
(Dhaka, Mymensingh,
Chittagong & Sylhet
Divisions)
13. Up-gradation, 120177 427 187150 307754 01/07/2016 450000 23500 - - ADB
Rehabilitation and to
Intensification of 30/06/2019
Distribution System
(Rajshahi, Rangpur,
Khulna & Barisal
Divisions)
14. Distribution Network 711541 1690 713231 01/01/2017 1370000 39100 158 1715
Expansion for 100% to
Rural Electrification 31/12/2019
(Dhaka, Mymensingh,
Chittagong & Sylhet
Divisions)
15. Distribution Network 676001 1690 677691 01/01/2017 1330000 38010 104 875
Expansion for 100% to
Rural Electrification 31/12/2019
(Rajshahi, Rangpur,
Khulna & Barisal
Divisions)
16. Solar Photovoltaic 3794.09 163.47 36762.57 40720.13 01/01/2018 2000 nos. - - - -
Solar pump
Pumping for to
irrigation
Agricultural Irrigation 31/12/2020
17. Translating Electricity 584.64 59.43 1659.60 2303.67 01/07/2017 - - - - -
Supply into to
Improvements of 30/06/2020
Rural Households
18. Emergency Assistance 2461.34 163.72 7818.47 10443.53 01/07/2018 - 50 01 10
Project-BREB to
Component 30/06/2020
(Electrification for
Displaced Myanmar
Nationals in Cox’s
Bazar)

C:\Users\ASUS\Desktop\Project_Updated\On-going_Project.docx