Você está na página 1de 130

PERHITUNGAN VOLUME PEMBUATAN PINTU AIR

TYPE C 1

PROYEK :
DAERAH IRIGASI : Selowongko (DAM Selowongko, Pintu Intake)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.20
h = 2.50
I. BAHAN H' = 4.00

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 36.240 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 295.960 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 18.120 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 25.670 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 35.424 Kg
Sub Total = 411.414 Kg
Sub Total x 1,1 = 452.555 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 253.485 Kg

Sub Total = 253.485 Kg


Sub Total x 1,1 = 278.834 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 45.274 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 58.930 Kg
Sub Total x 1,1 = 64.823 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 19.58 Kg


Sub Total x 1,1 = 21.538 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 62.805 Kg
Sub Total x 1,1 = 69.086 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C- 1
PROYEK :
DAERAH IRIGASI : Selowongko (DAM Selowongko, Pintu Intake)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan
URAIAN PEKERJAAN : Engkol Tidak Ada B = 1.20 m
h = 2.50 m
H' = 4.00 m

Harga
No. Macam Pekerjaan Satuan Kuantitas Satuan Jumlah
( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 -
- Besi kanal Kg 12,500.00 -
- Besi balk Kg 30,000.00 -
- Besi plate Kg 7.00 12,500.00 87,500.00
- Besi plate strip Kg 0.00 12,500.00 -
- Besi beton Kg 0.00 12,500.00 -
-Pipa Kg 0.00 12,500.00 -
87,500.00

2. Bahan bantu kontruksi % 10.00 87,500.00 8,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg
- Besi bulat st 60 Kg 0.00 25,000.00 -
-Bronze Kg 0.00 100,000.00 -
- Besi cor Kg 0.00 6,700.00 -
- Baja cor Kg 1,870,000.00 -
-

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 0.00 12,900.00 -
- Paku keling 3/4",5/8",7/8" Kg 0.00 9,800.00 -
- Nipple Bh 0.00 3,000.00 -
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 -
- Seal Bh -
- Kayu jati M3 3,190,000.00 -
- Na F + ring Bh 0.00 110,000.00 -

136,000.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin Kg 0.00 21,200.00 -
- Ongkos kerja kayu M3 510,000.00 -
- Sandblasting & cat M2 0.00 57,000.00 -
- Pengecatan tanpa sand M2 0.00 36,000.00 -
21,000.00

III PE MASAN GAN : Kg 6.00 1,100.00 6,600.00


IV PE M B O N G KARAN : Kg 6.00 1,500.00 9,000.00
V TRAN S PO RT : Kg 6.00 600.00 3,600.00
19,200.00
Sub Total 272,450.00

VI Jumlah Harga 272,450.00


VII Harga Satuan Pekerjaan per - Buah

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 1

PROYEK :
DAERAH IRIGASI : Paras (PA BPR 1, Pintu Spey)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.50
I. BAHAN H' = 2.00

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 175.160 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 272.630 Kg
Sub Total x 1,1 = 299.893 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 128.511 Kg

Sub Total = 128.511 Kg


Sub Total x 1,1 = 141.362 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 26.410 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 40.066 Kg
Sub Total x 1,1 = 44.073 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 10.68 Kg


Sub Total x 1,1 = 11.748 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 38.955 Kg
Sub Total x 1,1 = 42.851 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C- 1
PROYEK :
DAERAH IRIGASI : Paras (PA BPR 1, Pintu Spey)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan
URAIAN PEKERJAAN : Pangkon & Kuningan Hilang B = 1.0 m
H = 1.5 m
H' = 2.0 m

Harga
No. Macam Pekerjaan Satuan Kuantitas Satuan Jumlah
( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 30.00 12,500.00 375,000.00
- Besi kanal Kg 12,500.00 -
- Besi balk Kg 30,000.00 -
- Besi plate Kg 0.00 12,500.00 -
- Besi plate strip Kg 0.00 12,500.00 -
- Besi beton Kg 0.00 12,500.00 -
-Pipa Kg 0.00 12,500.00 -
375,000.00

2. Bahan bantu kontruksi % 10.00 375,000.00 37,500.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg
- Besi bulat st 60 Kg 0.00 25,000.00 -
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 0.00 6,700.00 -
- Baja cor Kg 1,870,000.00 -
1,000,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 0.00 9,800.00 -
- Nipple Bh 0.00 3,000.00 -
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 -
- Seal Bh -
- Kayu jati M3 3,190,000.00 -
- Na F + ring Bh 0.00 110,000.00 -

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 30.00 3,000.00 90,000.00
- Ongkos kerja mesin Kg 10.00 21,200.00 212,000.00
- Ongkos kerja kayu M3 510,000.00 -
- Sandblasting & cat M2 57,000.00 -
- Pengecatan tanpa sand M2 0.00 36,000.00 -
302,000.00

III PE MASAN GAN : Kg 36.00 1,100.00 39,600.00


IV PE M B O N G KARAN : Kg 36.00 1,500.00 54,000.00
V TRAN S PO RT : Kg 36.00 600.00 21,600.00
115,200.00
Sub Total 2,030,200.00

VI Jumlah Harga 2,030,200.00


VII Harga Satuan Pekerjaan per - Buah 2,030,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 1

PROYEK :
DAERAH IRIGASI : Sindupati
LO KAS I : PA DAM Sindupati ( Intake Ki )
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.50
I. BAHAN H' = 5.00

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 356.360 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 453.830 Kg
Sub Total x 1,1 = 499.213 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 128.511 Kg

Sub Total = 128.511 Kg


Sub Total x 1,1 = 141.362 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 54.706 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 68.362 Kg
Sub Total x 1,1 = 75.199 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 24.03 Kg


Sub Total x 1,1 = 26.433 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 86.655 Kg
Sub Total x 1,1 = 95.321 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C- 1
PROYEK :
DAERAH IRIGASI : Sindupati
LO KAS I : PA DAM Sindupati ( Intake Ki )
CABANG DINAS PENGAIRAN : Kejayan
URAIAN PEKERJAAN : Daun Pintu Keropos ( Bocor ) B = 1.0 m
H = 1.5 m
H' = 5.0 m

Harga
No. Macam Pekerjaan Satuan Kuantitas Satuan Jumlah
( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 -
- Besi kanal Kg 12,500.00 -
- Besi balk Kg 30,000.00 -
- Besi plate Kg 141.00 12,500.00 1,762,500.00
- Besi plate strip Kg 0.00 12,500.00 -
- Besi beton Kg 0.00 12,500.00 -
-Pipa Kg 0.00 12,500.00 -
1,762,500.00

2. Bahan bantu kontruksi % 10.00 1,762,500.00 176,250.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg
- Besi bulat st 60 Kg 0.00 25,000.00 -
-Bronze Kg 0.00 100,000.00 -
- Besi cor Kg 0.00 6,700.00 -
- Baja cor Kg 1,870,000.00 -
-

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 15.00 9,800.00 147,000.00
- Nipple Bh 0.00 3,000.00 -
- Splite pen Bh 0.00 31,300.00 -
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 -
- Seal Bh -
- Kayu jati M3 3,190,000.00 -
- Na F + ring Bh 0.00 110,000.00 -

284,900.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 141.00 3,000.00 423,000.00
- Ongkos kerja mesin Kg 0.00 21,200.00 -
- Ongkos kerja kayu M3 510,000.00 -
- Sandblasting & cat M2 57,000.00 -
- Pengecatan tanpa sand M2 16.23 36,000.00 584,208.00
1,007,208.00

III PE MASAN GAN : Kg 128.00 1,100.00 140,800.00


IV PE M B O N G KARAN : Kg 128.00 1,500.00 192,000.00
V TRAN S PO RT : Kg 128.00 600.00 76,800.00
409,600.00
Sub Total 3,640,458.00

VI Jumlah Harga 3,640,458.00


VII Harga Satuan Pekerjaan per - Buah 3,640,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 1

PROYEK :
DAERAH IRIGASI : Gedangan
LO KAS I : PA DAM Gedangan ( Intake Ka )
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.40
h = 1.30
I. BAHAN H' = 2.40

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 42.280 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 199.320 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 21.140 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 28.690 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 41.328 Kg
Sub Total = 332.758 Kg
Sub Total x 1,1 = 366.034 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 152.248 Kg

Sub Total = 152.248 Kg


Sub Total x 1,1 = 167.473 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 30.182 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 43.839 Kg
Sub Total x 1,1 = 48.223 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 12.46 Kg


Sub Total x 1,1 = 13.706 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 46.905 Kg
Sub Total x 1,1 = 51.596 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C- 1
PROYEK :
DAERAH IRIGASI : Gedangan
LO KAS I : PA DAM Gedangan ( Intake Ka )
CABANG DINAS PENGAIRAN : Kejayan
URAIAN PEKERJAAN : Tidak Bisa Dioperasikan B = 1.40 m
( Daun Rusak Berat ) H = 1.30 m
H' = 2.40 m

Harga
No. Macam Pekerjaan Satuan Kuantitas Satuan Jumlah
( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 -
- Besi kanal Kg 12,500.00 -
- Besi balk Kg 30,000.00 -
- Besi plate Kg 167.00 12,500.00 2,087,500.00
- Besi plate strip Kg 0.00 12,500.00 -
- Besi beton Kg 0.00 12,500.00 -
-Pipa Kg 0.00 12,500.00 -
2,087,500.00

2. Bahan bantu kontruksi % 10.00 2,087,500.00 208,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg
- Besi bulat st 60 Kg 0.00 25,000.00 -
-Bronze Kg 0.00 100,000.00 -
- Besi cor Kg 0.00 6,700.00 -
- Baja cor Kg 1,870,000.00 -
-

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 15.00 9,800.00 147,000.00
- Nipple Bh 0.00 3,000.00 -
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 -
- Seal Bh -
- Kayu jati M3 3,190,000.00 -
- Na F + ring Bh 0.00 110,000.00 -

347,500.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 167.00 3,000.00 501,000.00
- Ongkos kerja mesin Kg 0.00 21,200.00 -
- Ongkos kerja kayu M3 510,000.00 -
- Sandblasting & cat M2 57,000.00 -
- Pengecatan tanpa sand M2 13.82 36,000.00 497,664.00
998,664.00

III PE MASAN GAN : Kg 152.00 1,100.00 167,200.00


IV PE M B O N G KARAN : Kg 152.00 1,500.00 228,000.00
V TRAN S PO RT : Kg 152.00 600.00 91,200.00
486,400.00
Sub Total 4,128,814.00

VI Jumlah Harga 4,128,814.00


VII Harga Satuan Pekerjaan per - Buah 4,128,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 1

PROYEK :
DAERAH IRIGASI : Gedangan
LO KAS I : PA DAM Gedangan ( Spey Ka )
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.40
h = 1.40
I. BAHAN H' = 2.40

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 42.280 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 199.320 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 21.140 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 28.690 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 41.328 Kg
Sub Total = 332.758 Kg
Sub Total x 1,1 = 366.034 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 163.960 Kg

Sub Total = 163.960 Kg


Sub Total x 1,1 = 180.356 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 30.182 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 43.839 Kg
Sub Total x 1,1 = 48.223 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 12.46 Kg


Sub Total x 1,1 = 13.706 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 46.110 Kg
Sub Total x 1,1 = 50.721 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C- 1
PROYEK :
DAERAH IRIGASI : Gedangan
LO KAS I : PA DAM Gedangan ( Spey Ka )
CABANG DINAS PENGAIRAN : Kejayan
URAIAN PEKERJAAN : Tidak Bisa Dioperasikan B = 1.4 m
( Daun Rusak Berat ) H = 1.4 m
H' = 2.4 m

Harga
No. Macam Pekerjaan Satuan Kuantitas Satuan Jumlah
( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 -
- Besi kanal Kg 12,500.00 -
- Besi balk Kg 30,000.00 -
- Besi plate Kg 180.00 12,500.00 2,250,000.00
- Besi plate strip Kg 0.00 12,500.00 -
- Besi beton Kg 0.00 12,500.00 -
-Pipa Kg 0.00 12,500.00 -
2,250,000.00

2. Bahan bantu kontruksi % 10.00 2,250,000.00 225,000.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg
- Besi bulat st 60 Kg 0.00 25,000.00 -
-Bronze Kg 0.00 100,000.00 -
- Besi cor Kg 0.00 6,700.00 -
- Baja cor Kg 1,870,000.00 -
-

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 15.00 9,800.00 147,000.00
- Nipple Bh 0.00 3,000.00 -
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 -
- Seal Bh -
- Kayu jati M3 3,190,000.00 -
- Na F + ring Bh 0.00 110,000.00 -

347,500.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 180.00 3,000.00 540,000.00
- Ongkos kerja mesin Kg 0.00 21,200.00 -
- Ongkos kerja kayu M3 510,000.00 -
- Sandblasting & cat M2 57,000.00 -
- Pengecatan tanpa sand M2 14.12 36,000.00 508,392.00
1,048,392.00

III PE MASAN GAN : Kg 164.00 1,100.00 180,400.00


IV PE M B O N G KARAN : Kg 164.00 1,500.00 246,000.00
V TRAN S PO RT : Kg 164.00 600.00 98,400.00
524,800.00
Sub Total 4,395,692.00

VI Jumlah Harga 4,395,692.00


VII Harga Satuan Pekerjaan per - Buah 4,395,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 1

PROYEK :
DAERAH IRIGASI : Ngantungan
LO KAS I : PA Ngantungan ( Spey Ki )
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.20
h = 2.75
I. BAHAN H' = 4.90

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 36.240 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 350.320 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 18.120 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 25.670 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 35.424 Kg
Sub Total = 465.774 Kg
Sub Total x 1,1 = 512.351 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 278.834 Kg

Sub Total = 278.834 Kg


Sub Total x 1,1 = 306.717 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 53.762 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 67.419 Kg
Sub Total x 1,1 = 74.161 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 23.585 Kg


Sub Total x 1,1 = 25.944 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 75.128 Kg
Sub Total x 1,1 = 82.640 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C- 1
PROYEK :
DAERAH IRIGASI : Ngantungan
LO KAS I : PA Ngantungan ( Spey Ki )
CABANG DINAS PENGAIRAN : Kejayan
URAIAN PEKERJAAN : Daun Pintu Bocor B = 1.20 m
H = 2.75 m
H' = 4.90 m

Harga
No. Macam Pekerjaan Satuan Kuantitas Satuan Jumlah
( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 -
- Besi kanal Kg 12,500.00 -
- Besi balk Kg 30,000.00 -
- Besi plate Kg 307.00 12,500.00 3,837,500.00
- Besi plate strip Kg 0.00 12,500.00 -
- Besi beton Kg 0.00 12,500.00 -
-Pipa Kg 0.00 12,500.00 -
3,837,500.00

2. Bahan bantu kontruksi % 10.00 3,837,500.00 383,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg
- Besi bulat st 60 Kg 0.00 25,000.00 -
-Bronze Kg 0.00 100,000.00 -
- Besi cor Kg 0.00 6,700.00 -
- Baja cor Kg 1,870,000.00 -
-

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 15.00 9,800.00 147,000.00
- Nipple Bh 0.00 3,000.00 -
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 -
- Seal Bh -
- Kayu jati M3 3,190,000.00 -
- Na F + ring Bh 0.00 110,000.00 -

347,500.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 307.00 3,000.00 921,000.00
- Ongkos kerja mesin Kg 0.00 21,200.00 -
- Ongkos kerja kayu M3 510,000.00 -
- Sandblasting & cat M2 57,000.00 -
- Pengecatan tanpa sand M2 20.47 36,000.00 736,884.00
1,657,884.00

III PE MASAN GAN : Kg 279.00 1,100.00 306,900.00


IV PE M B O N G KARAN : Kg 279.00 1,500.00 418,500.00
V TRAN S PO RT : Kg 279.00 600.00 167,400.00
892,800.00
Sub Total 7,119,434.00

VI Jumlah Harga 7,119,434.00


VII Harga Satuan Pekerjaan per - Buah 7,119,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 1

PROYEK :
DAERAH IRIGASI : Ngantungan
LO KAS I : PA Ngantungan ( Spey Ki )
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.20
h = 2.75
I. BAHAN H' = 4.90

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 36.240 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 350.320 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 18.120 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 25.670 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 35.424 Kg
Sub Total = 465.774 Kg
Sub Total x 1,1 = 512.351 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 278.834 Kg

Sub Total = 278.834 Kg


Sub Total x 1,1 = 306.717 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 53.762 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 67.419 Kg
Sub Total x 1,1 = 74.161 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 23.585 Kg


Sub Total x 1,1 = 25.944 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 75.128 Kg
Sub Total x 1,1 = 82.640 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C- 1
PROYEK :
DAERAH IRIGASI : Ngantungan
LO KAS I : PA Ngantungan ( Spey Ki )
CABANG DINAS PENGAIRAN : Kejayan
URAIAN PEKERJAAN : Daun Pintu Bocor B = 1.20 m
H = 2.75 m
H' = 4.90 m

Harga
No. Macam Pekerjaan Satuan Kuantitas Satuan Jumlah
( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 -
- Besi kanal Kg 12,500.00 -
- Besi balk Kg 30,000.00 -
- Besi plate Kg 307.00 12,500.00 3,837,500.00
- Besi plate strip Kg 0.00 12,500.00 -
- Besi beton Kg 0.00 12,500.00 -
-Pipa Kg 0.00 12,500.00 -
3,837,500.00

2. Bahan bantu kontruksi % 10.00 3,837,500.00 383,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg
- Besi bulat st 60 Kg 0.00 25,000.00 -
-Bronze Kg 0.00 100,000.00 -
- Besi cor Kg 0.00 6,700.00 -
- Baja cor Kg 1,870,000.00 -
-

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 15.00 9,800.00 147,000.00
- Nipple Bh 0.00 3,000.00 -
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 -
- Seal Bh -
- Kayu jati M3 3,190,000.00 -
- Na F + ring Bh 0.00 110,000.00 -

347,500.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 307.00 3,000.00 921,000.00
- Ongkos kerja mesin Kg 0.00 21,200.00 -
- Ongkos kerja kayu M3 510,000.00 -
- Sandblasting & cat M2 57,000.00 -
- Pengecatan tanpa sand M2 20.47 36,000.00 736,884.00
1,657,884.00

III PE MASAN GAN : Kg 279.00 1,100.00 306,900.00


IV PE M B O N G KARAN : Kg 279.00 1,500.00 418,500.00
V TRAN S PO RT : Kg 279.00 600.00 167,400.00
892,800.00
Sub Total 7,119,434.00

VI Jumlah Harga 7,119,434.00


VII Harga Satuan Pekerjaan per - Buah 7,119,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA BSW. 13 Ka ( sadap )
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 0.50
I. BAHAN H' = 1.65

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 0.000 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = *0 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 0.000 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 0.000 Kg
Sub Total = 30.200 Kg
Sub Total x 1,1 = 33.220 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 42.837 Kg

Sub Total = 42.837 Kg


Sub Total x 1,1 = 47.121 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 23.108 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 36.765 Kg
Sub Total x 1,1 = 40.442 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 9.1225 Kg


Sub Total x 1,1 = 10.035 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 41.340 Kg
Sub Total x 1,1 = 45.474 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA BSW. 13 Ka ( sadap )
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Engkol Tidak A h = 0,50 m
H' = 1,65 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 33.00 12,500.00 412,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
500,000.00

2. Bahan bantu kontruksi % 10.00 500,000.00 50,000.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 45.00 25,000.00 1,125,000.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 0.00 6,700.00 0.00
- Baja cor Kg 1,870,000.00 0.00
2,125,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 0.00 9,800.00 0.00
- Nipple Bh 0.00 3,000.00 0.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 40.00 3,000.00 120,000.00
- Ongkos kerja mesin Kg 55.00 21,200.00 1,166,000.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 36,000.00 0.00
1,286,000.00

III PE MASAN GAN : Kg 86.00 1,100.00 94,600.00


IV PE M B O N G KARAN : Kg 86.00 1,500.00 129,000.00
V TRAN S PO RT : Kg 86.00 600.00 51,600.00
275,200.00
Sub Total 4,436,700.00

VI Jumlah Harga 4,436,700.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 4,436,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA BSW. 13 Ki ( sadap )
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 0.80
h = 0.50
I. BAHAN H' = 1.65

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 24.160 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 0.000 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 0.000 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 0.000 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 0.000 Kg
Sub Total = 24.160 Kg
Sub Total x 1,1 = 26.576 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 34.977 Kg

Sub Total = 34.977 Kg


Sub Total x 1,1 = 38.475 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 23.108 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 36.765 Kg
Sub Total x 1,1 = 40.442 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 9.1225 Kg


Sub Total x 1,1 = 10.035 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 41.340 Kg
Sub Total x 1,1 = 45.474 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA BSW. 13 Ki ( sadap )
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Dratstang, Kuningan, Pangkon h = 0,50 m
& Kunci H' = 1,65 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 27.00 12,500.00 337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
425,000.00

2. Bahan bantu kontruksi % 10.00 425,000.00 42,500.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 45.00 25,000.00 1,125,000.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 0.00 6,700.00 0.00
- Baja cor Kg 1,870,000.00 0.00
2,125,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 0.00 9,800.00 0.00
- Nipple Bh 0.00 3,000.00 0.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 34.00 3,000.00 102,000.00
- Ongkos kerja mesin Kg 55.00 21,200.00 1,166,000.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 36,000.00 0.00
1,268,000.00

III PE MASAN GAN : Kg 81.00 1,100.00 89,100.00


IV PE M B O N G KARAN : Kg 81.00 1,500.00 121,500.00
V TRAN S PO RT : Kg 81.00 600.00 48,600.00
259,200.00
Sub Total 4,320,200.00

VI Jumlah Harga 4,320,200.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 4,320,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Wijeng
LO KAS I : PA Dam Wijeng ( Intake Ki )
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.30
I. BAHAN H' = 2.30

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 0.000 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 0.000 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 0.000 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 0.000 Kg
Sub Total = 30.200 Kg
Sub Total x 1,1 = 33.220 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 111.376 Kg

Sub Total = 111.376 Kg


Sub Total x 1,1 = 122.514 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 29.239 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 42.896 Kg
Sub Total x 1,1 = 47.186 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 12.015 Kg


Sub Total x 1,1 = 13.217 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 45.315 Kg
Sub Total x 1,1 = 49.847 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Wijeng
LO KAS I : PA Dam Wijeng ( Intake Ki )
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Mur Kuningan Hilang h = 1,30 m
H' = 2,30 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
87,500.00

2. Bahan bantu kontruksi % 10.00 87,500.00 8,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 0.00 25,000.00 0.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 0.00 6,700.00 0.00
- Baja cor Kg 1,870,000.00 0.00
1,000,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 0.00 9,800.00 0.00
- Nipple Bh 0.00 3,000.00 0.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin Kg 10.00 21,200.00 212,000.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 11.47 36,000.00 412,992.00
645,992.00

III PE MASAN GAN : Kg 15.00 1,100.00 16,500.00


IV PE M B O N G KARAN : Kg 15.00 1,500.00 22,500.00
V TRAN S PO RT : Kg 15.00 600.00 9,000.00
48,000.00
Sub Total 1,990,742.00

VI Jumlah Harga 1,990,742.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 1,990,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI :
LO KAS I : PA Pasrepan ( Intake Ki )
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 0.80
h = 1.00
I. BAHAN H' = 2.30

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 24.160 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 0.000 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = *0 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 0.000 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 0.000 Kg
Sub Total = 24.160 Kg
Sub Total x 1,1 = 26.576 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 69.954 Kg

Sub Total = 69.954 Kg


Sub Total x 1,1 = 76.949 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 0.000 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 0.000 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 0.000 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 6.897 Kg
Sub Total x 1,1 = 8.139 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 12.015 Kg


Sub Total x 1,1 = 13.217 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 47.700 Kg
Sub Total x 1,1 = 52.470 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI :
LO KAS I : PA Pasrepan ( Intake Ki )
CABANG DINAS PENGAIRAN : Kejayan B = 0,80 m
URAIAN PEKERJAAN : Dratstang Hilang h = 1,00 m
H' = 2,30 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 8.00 12,500.00 100,000.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
100,000.00

2. Bahan bantu kontruksi % 10.00 100,000.00 10,000.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 52.00 25,000.00 1,300,000.00
-Bronze Kg 0.00 100,000.00 0.00
- Besi cor Kg 0.00 6,700.00 0.00
- Baja cor Kg 1,870,000.00 0.00
1,300,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 0.00 9,800.00 0.00
- Nipple Bh 2.00 3,000.00 6,000.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 1.00 110,000.00 110,000.00

316,500.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 8.00 3,000.00 24,000.00
- Ongkos kerja mesin Kg 52.00 21,200.00 1,102,400.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 9.84 36,000.00 354,312.00
1,480,712.00

III PE MASAN GAN : Kg 55.00 1,100.00 60,500.00


IV PE M B O N G KARAN : Kg 55.00 1,500.00 82,500.00
V TRAN S PO RT : Kg 55.00 600.00 33,000.00
176,000.00
Sub Total 3,383,212.00

VI Jumlah Harga 3,383,212.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 3,383,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI :
LO KAS I : PA DAM Menggah ( Intake Ki )
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.50
I. BAHAN H' = 2.20

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 0.000 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 0.000 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 0.000 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 0.000 Kg
Sub Total = 30.200 Kg
Sub Total x 1,1 = 33.220 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 128.511 Kg

Sub Total = 128.511 Kg


Sub Total x 1,1 = 141.362 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 0.000 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 0.000 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 0.000 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 6.897 Kg
Sub Total x 1,1 = 7.587 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 11.57 Kg


Sub Total x 1,1 = 12.727 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 42.135 Kg
Sub Total x 1,1 = 46.349 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI :
LO KAS I : PA DAM Menggah ( Intake Ki )
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Kuningan h = 1,50 m
H' = 2,20 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 8.00 12,500.00 100,000.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
100,000.00

2. Bahan bantu kontruksi % 10.00 100,000.00 10,000.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 0.00 25,000.00 0.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 0.00 6,700.00 0.00
- Baja cor Kg 1,870,000.00 0.00
1,000,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 0.00 9,800.00 0.00
- Nipple Bh 0.00 3,000.00 0.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 8.00 3,000.00 24,000.00
- Ongkos kerja mesin Kg 10.00 21,200.00 212,000.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 11.75 36,000.00 422,928.00
658,928.00

III PE MASAN GAN : Kg 16.00 1,100.00 17,600.00


IV PE M B O N G KARAN : Kg 16.00 1,500.00 24,000.00
V TRAN S PO RT : Kg 16.00 600.00 9,600.00
51,200.00
Sub Total 2,020,628.00

VI Jumlah Harga 2,020,628.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 2,020,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Sindupati
LO KAS I : PA BS. 12 ( Spey Ki )
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.00
I. BAHAN H' = 1.50

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 144.960 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 242.430 Kg
Sub Total x 1,1 = 266.673 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 85.674 Kg

Sub Total = 85.674 Kg


Sub Total x 1,1 = 94.241 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 21.694 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 35.350 Kg
Sub Total x 1,1 = 38.885 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 8.455 Kg


Sub Total x 1,1 = 9.301 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 34.980 Kg
Sub Total x 1,1 = 38.478 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Sindupati
LO KAS I : PA BS. 12 ( Spey Ki )
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Berat h = 1,00 m
H' = 1,50 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 267.00 12,500.00 3,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 39.00 12,500.00 487,500.00
- Besi beton Kg 9.00 12,500.00 112,500.00
-Pipa Kg 1.00 12,500.00 12,500.00
5,125,000.00

2. Bahan bantu kontruksi % 10.00 5,125,000.00 512,500.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 38.00 25,000.00 950,000.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 10.00 6,700.00 67,000.00
- Baja cor Kg 1,870,000.00 0.00
2,017,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 15.00 9,800.00 147,000.00
- Nipple Bh 1.00 3,000.00 3,000.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 1.00 423,500.00 423,500.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.09 110,000.00 9,900.00

783,900.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 410.00 3,000.00 1,230,000.00
- Ongkos kerja mesin Kg 58.00 21,200.00 1,229,600.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 9.54 57,000.00 543,666.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
3,003,266.00

III PE MASAN GAN : Kg 425.00 1,100.00 467,500.00


IV PE M B O N G KARAN : Kg 425.00 1,500.00 637,500.00
V TRAN S PO RT : Kg 425.00 600.00 255,000.00
1,360,000.00
Sub Total 12,801,666.00

VI Jumlah Harga 12,801,666.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 12,801,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Selowongko (PA Selowongko , Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.00
I. BAHAN H' = 2.00

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 175.160 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 272.630 Kg
Sub Total x 1,1 = 299.893 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 85.674 Kg

Sub Total = 85.674 Kg


Sub Total x 1,1 = 94.241 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 26.410 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 40.066 Kg
Sub Total x 1,1 = 44.073 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 10.68 Kg


Sub Total x 1,1 = 11.748 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 42.930 Kg
Sub Total x 1,1 = 47.223 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Selowongko (PA Selowongko , Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Engkol & Pintu Tdk Dapat Dioperasika h = 1,00 m
H' = 2,00 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
87,500.00

2. Bahan bantu kontruksi % 10.00 87,500.00 8,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 0.00 25,000.00 0.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 0.00 6,700.00 0.00
- Baja cor Kg 1,870,000.00 0.00
1,000,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 0.00 9,800.00 0.00
- Nipple Bh 0.00 3,000.00 0.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin Kg 10.00 21,200.00 212,000.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
233,000.00

III PE MASAN GAN : Kg 15.00 1,100.00 16,500.00


IV PE M B O N G KARAN : Kg 15.00 1,500.00 22,500.00
V TRAN S PO RT : Kg 15.00 600.00 9,000.00
48,000.00
Sub Total 1,577,750.00

VI Jumlah Harga 1,577,750.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 1,577,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw Ka.4 Ki , Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.20
I. BAHAN H' = 2.50

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 205.360 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 302.830 Kg
Sub Total x 1,1 = 333.113 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 102.809 Kg

Sub Total = 102.809 Kg


Sub Total x 1,1 = 113.090 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 31.126 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 44.782 Kg
Sub Total x 1,1 = 49.261 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 12.905 Kg


Sub Total x 1,1 = 14.196 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 49.290 Kg
Sub Total x 1,1 = 54.219 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw Ka.4 Ki , Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Engkol Tidak A h = 1,20 m
H' = 2,50 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
87,500.00

2. Bahan bantu kontruksi % 10.00 87,500.00 8,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 54.00 25,000.00 1,350,000.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 0.00 6,700.00 0.00
- Baja cor Kg 1,870,000.00 0.00
2,350,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 0.00 9,800.00 0.00
- Nipple Bh 0.00 3,000.00 0.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin Kg 64.00 21,200.00 1,356,800.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 36,000.00 0.00
1,377,800.00

III PE MASAN GAN : Kg 65.00 1,100.00 71,500.00


IV PE M B O N G KARAN : Kg 65.00 1,500.00 97,500.00
V TRAN S PO RT : Kg 65.00 600.00 39,000.00
208,000.00
Sub Total 4,232,550.00

VI Jumlah Harga 4,232,550.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 4,232,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 5 Ka.Ki , Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.20
I. BAHAN H' = 2.50

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 205.360 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 302.830 Kg
Sub Total x 1,1 = 333.113 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 102.809 Kg

Sub Total = 102.809 Kg


Sub Total x 1,1 = 113.090 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 31.126 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 44.782 Kg
Sub Total x 1,1 = 49.261 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 12.905 Kg


Sub Total x 1,1 = 14.196 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 49.290 Kg
Sub Total x 1,1 = 54.219 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 5 Ka.Ki , Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Engkol Tidak A h = 1,20 m
H' = 2,50 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
87,500.00

2. Bahan bantu kontruksi % 10.00 87,500.00 8,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 54.00 25,000.00 1,350,000.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 0.00 6,700.00 0.00
- Baja cor Kg 1,870,000.00 0.00
2,350,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 0.00 9,800.00 0.00
- Nipple Bh 0.00 3,000.00 0.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin Kg 64.00 21,200.00 1,356,800.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 36,000.00 0.00
1,377,800.00

III PE MASAN GAN : Kg 65.00 1,100.00 71,500.00


IV PE M B O N G KARAN : Kg 65.00 1,500.00 97,500.00
V TRAN S PO RT : Kg 65.00 600.00 39,000.00
208,000.00
Sub Total 4,232,550.00

VI Jumlah Harga 4,232,550.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 4,232,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw 6 Ka. Ki , Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 0.70
h = 0.80
I. BAHAN H' = 2.50

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 21.140 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 205.360 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 10.570 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 18.120 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 20.664 Kg
Sub Total = 275.854 Kg
Sub Total x 1,1 = 303.439 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 49.675 Kg

Sub Total = 49.675 Kg


Sub Total x 1,1 = 54.643 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 31.126 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 44.782 Kg
Sub Total x 1,1 = 49.261 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 12.905 Kg


Sub Total x 1,1 = 14.196 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 52.470 Kg
Sub Total x 1,1 = 57.717 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw 6 Ka. Ki , Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 0,70 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Engkol Tidak A h = 0,80 m
H' = 2,50 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
87,500.00

2. Bahan bantu kontruksi % 10.00 87,500.00 8,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 58.00 25,000.00 1,450,000.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 0.00 6,700.00 0.00
- Baja cor Kg 1,870,000.00 0.00
2,450,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 0.00 9,800.00 0.00
- Nipple Bh 0.00 3,000.00 0.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin Kg 68.00 21,200.00 1,441,600.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 36,000.00 0.00
1,462,600.00

III PE MASAN GAN : Kg 68.00 1,100.00 74,800.00


IV PE M B O N G KARAN : Kg 68.00 1,500.00 102,000.00
V TRAN S PO RT : Kg 68.00 600.00 40,800.00
217,600.00
Sub Total 4,426,950.00

VI Jumlah Harga 4,426,950.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 4,426,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw 10 Ka. Ki, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.00
I. BAHAN H' = 2.00

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 175.160 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 272.630 Kg
Sub Total x 1,1 = 299.893 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 85.674 Kg

Sub Total = 85.674 Kg


Sub Total x 1,1 = 94.241 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 26.410 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 40.066 Kg
Sub Total x 1,1 = 44.073 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 10.68 Kg


Sub Total x 1,1 = 11.748 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 42.930 Kg
Sub Total x 1,1 = 47.223 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw 10 Ka. Ki, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Engkol Tidak A h = 1,00 m
H' = 2,00 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
87,500.00

2. Bahan bantu kontruksi % 10.00 87,500.00 8,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 47.00 25,000.00 1,175,000.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 0.00 6,700.00 0.00
- Baja cor Kg 1,870,000.00 0.00
2,175,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 0.00 9,800.00 0.00
- Nipple Bh 0.00 3,000.00 0.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin Kg 57.00 21,200.00 1,208,400.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 36,000.00 0.00
1,229,400.00

III PE MASAN GAN : Kg 58.00 1,100.00 63,800.00


IV PE M B O N G KARAN : Kg 58.00 1,500.00 87,000.00
V TRAN S PO RT : Kg 58.00 600.00 34,800.00
185,600.00
Sub Total 3,886,750.00

VI Jumlah Harga 3,886,750.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 3,886,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw 2 Ka. Ki , Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.20
I. BAHAN H' = 2.50

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 205.360 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 302.830 Kg
Sub Total x 1,1 = 333.113 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 102.809 Kg

Sub Total = 102.809 Kg


Sub Total x 1,1 = 113.090 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 31.126 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 44.782 Kg
Sub Total x 1,1 = 49.261 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 12.905 Kg


Sub Total x 1,1 = 14.196 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 49.290 Kg
Sub Total x 1,1 = 54.219 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw 2 Ka. Ki , Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Engkol Tidak A h = 1,20 m
H' = 2,50 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
87,500.00

2. Bahan bantu kontruksi % 10.00 87,500.00 8,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 54.00 25,000.00 1,350,000.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 0.00 6,700.00 0.00
- Baja cor Kg 1,870,000.00 0.00
2,350,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 0.00 9,800.00 0.00
- Nipple Bh 0.00 3,000.00 0.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin Kg 64.00 21,200.00 1,356,800.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 36,000.00 0.00
1,377,800.00

III PE MASAN GAN : Kg 65.00 1,100.00 71,500.00


IV PE M B O N G KARAN : Kg 65.00 1,500.00 97,500.00
V TRAN S PO RT : Kg 65.00 600.00 39,000.00
208,000.00
Sub Total 4,232,550.00

VI Jumlah Harga 4,232,550.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 4,232,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Selowongko (PA BSW 4, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.00
I. BAHAN H' = 2.50

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 0.000 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 97.470 Kg
Sub Total x 1,1 = 107.217 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 85.674 Kg

Sub Total = 85.674 Kg


Sub Total x 1,1 = 94.241 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 31.126 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 44.782 Kg
Sub Total x 1,1 = 49.261 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 12.905 Kg


Sub Total x 1,1 = 14.196 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 50.880 Kg
Sub Total x 1,1 = 55.968 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Selowongko (PA BSW 4, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total h = 1,00 m
H' = 2,50 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 49.00 12,500.00 612,500.00
- Besi beton Kg 14.00 12,500.00 175,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,312,500.00

2. Bahan bantu kontruksi % 10.00 3,312,500.00 331,250.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 56.00 25,000.00 1,400,000.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 10.00 6,700.00 67,000.00
- Baja cor Kg 1,870,000.00 0.00
2,467,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 15.00 9,800.00 147,000.00
- Nipple Bh 1.00 3,000.00 3,000.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.14 110,000.00 14,850.00

365,350.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 265.00 3,000.00 795,000.00
- Ongkos kerja mesin Kg 76.00 21,200.00 1,611,200.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 11.14 57,000.00 634,866.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
3,041,066.00

III PE MASAN GAN : Kg 310.00 1,100.00 341,000.00


IV PE M B O N G KARAN : Kg 310.00 1,500.00 465,000.00
V TRAN S PO RT : Kg 310.00 600.00 186,000.00
992,000.00
Sub Total 10,509,166.00

VI Jumlah Harga 10,509,166.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 10,509,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 5, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.00
I. BAHAN H' = 2.50

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 0.000 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 97.470 Kg
Sub Total x 1,1 = 107.217 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 85.674 Kg

Sub Total = 85.674 Kg


Sub Total x 1,1 = 94.241 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 31.126 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 44.782 Kg
Sub Total x 1,1 = 49.261 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 12.905 Kg


Sub Total x 1,1 = 14.196 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 50.880 Kg
Sub Total x 1,1 = 55.968 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 5, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total h = 1,00 m
H' = 2,50 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 49.00 12,500.00 612,500.00
- Besi beton Kg 14.00 12,500.00 175,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,312,500.00

2. Bahan bantu kontruksi % 10.00 3,312,500.00 331,250.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 56.00 25,000.00 1,400,000.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 10.00 6,700.00 67,000.00
- Baja cor Kg 1,870,000.00 0.00
2,467,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 15.00 9,800.00 147,000.00
- Nipple Bh 1.00 3,000.00 3,000.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.14 110,000.00 14,850.00

365,350.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 265.00 3,000.00 795,000.00
- Ongkos kerja mesin Kg 76.00 21,200.00 1,611,200.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 11.14 57,000.00 634,866.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
3,041,066.00

III PE MASAN GAN : Kg 310.00 1,100.00 341,000.00


IV PE M B O N G KARAN : Kg 310.00 1,500.00 465,000.00
V TRAN S PO RT : Kg 310.00 600.00 186,000.00
992,000.00
Sub Total 10,509,166.00

VI Jumlah Harga 10,509,166.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 10,509,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Selowongko (PA Penguras Kaliputih, Pintu Pembuang)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.00
I. BAHAN H' = 2.50

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 0.000 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 97.470 Kg
Sub Total x 1,1 = 107.217 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 85.674 Kg

Sub Total = 85.674 Kg


Sub Total x 1,1 = 94.241 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 31.126 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 44.782 Kg
Sub Total x 1,1 = 49.261 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 12.905 Kg


Sub Total x 1,1 = 14.196 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 50.880 Kg
Sub Total x 1,1 = 55.968 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Selowongko (PA Penguras Kaliputih, Pintu Pembuang)
liputih, Pintu Pembuang) LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total h = 1,00 m
H' = 2,50 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 49.00 12,500.00 612,500.00
- Besi beton Kg 14.00 12,500.00 175,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,312,500.00

2. Bahan bantu kontruksi % 10.00 3,312,500.00 331,250.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 56.00 25,000.00 1,400,000.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 10.00 6,700.00 67,000.00
- Baja cor Kg 1,870,000.00 0.00
2,467,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 15.00 9,800.00 147,000.00
- Nipple Bh 1.00 3,000.00 3,000.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.14 110,000.00 14,850.00

365,350.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 265.00 3,000.00 795,000.00
- Ongkos kerja mesin Kg 76.00 21,200.00 1,611,200.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 11.14 57,000.00 634,866.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
3,041,066.00

III PE MASAN GAN : Kg 310.00 1,100.00 341,000.00


IV PE M B O N G KARAN : Kg 310.00 1,500.00 465,000.00
V TRAN S PO RT : Kg 310.00 600.00 186,000.00
992,000.00
Sub Total 10,509,166.00

VI Jumlah Harga 10,509,166.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 10,509,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 13, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.00
I. BAHAN H' = 2.50

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 0.000 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 97.470 Kg
Sub Total x 1,1 = 107.217 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 85.674 Kg

Sub Total = 85.674 Kg


Sub Total x 1,1 = 94.241 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 31.126 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 44.782 Kg
Sub Total x 1,1 = 49.261 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 12.905 Kg


Sub Total x 1,1 = 14.196 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 50.880 Kg
Sub Total x 1,1 = 55.968 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 13, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total h = 1,00 m
H' = 2,50 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 49.00 12,500.00 612,500.00
- Besi beton Kg 14.00 12,500.00 175,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,312,500.00

2. Bahan bantu kontruksi % 10.00 3,312,500.00 331,250.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 56.00 25,000.00 1,400,000.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 10.00 6,700.00 67,000.00
- Baja cor Kg 1,870,000.00 0.00
2,467,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 15.00 9,800.00 147,000.00
- Nipple Bh 1.00 3,000.00 3,000.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.14 110,000.00 14,850.00

365,350.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 265.00 3,000.00 795,000.00
- Ongkos kerja mesin Kg 76.00 21,200.00 1,611,200.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 11.14 57,000.00 634,866.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
3,041,066.00

III PE MASAN GAN : Kg 310.00 1,100.00 341,000.00


IV PE M B O N G KARAN : Kg 310.00 1,500.00 465,000.00
V TRAN S PO RT : Kg 310.00 600.00 186,000.00
992,000.00
Sub Total 10,509,166.00

VI Jumlah Harga 10,509,166.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 10,509,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Domas (PA BW 1, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.00
I. BAHAN H' = 2.00

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 0.000 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 97.470 Kg
Sub Total x 1,1 = 107.217 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 85.674 Kg

Sub Total = 85.674 Kg


Sub Total x 1,1 = 94.241 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 26.410 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 40.066 Kg
Sub Total x 1,1 = 44.073 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 10.68 Kg


Sub Total x 1,1 = 11.748 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 42.930 Kg
Sub Total x 1,1 = 47.223 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Domas (PA BW 1, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total/ Tidak Biasa Dioperasikan h = 1,00 m
H' = 2,00 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 44.00 12,500.00 550,000.00
- Besi beton Kg 12.00 12,500.00 150,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,225,000.00

2. Bahan bantu kontruksi % 10.00 3,225,000.00 322,500.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 47.00 25,000.00 1,175,000.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 10.00 6,700.00 67,000.00
- Baja cor Kg 1,870,000.00 0.00
2,242,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 15.00 9,800.00 147,000.00
- Nipple Bh 1.00 3,000.00 3,000.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.11 110,000.00 12,375.00

362,875.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 258.00 3,000.00 774,000.00
- Ongkos kerja mesin Kg 67.00 21,200.00 1,420,400.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 10.34 57,000.00 589,266.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
2,783,666.00

III PE MASAN GAN : Kg 295.00 1,100.00 324,500.00


IV PE M B O N G KARAN : Kg 295.00 1,500.00 442,500.00
V TRAN S PO RT : Kg 295.00 600.00 177,000.00
944,000.00
Sub Total 9,880,041.00

VI Jumlah Harga 9,880,041.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 9,880,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Domas (PA BW 2, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.00
I. BAHAN H' = 2.00

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 0.000 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 97.470 Kg
Sub Total x 1,1 = 107.217 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 85.674 Kg

Sub Total = 85.674 Kg


Sub Total x 1,1 = 94.241 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 26.410 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 40.066 Kg
Sub Total x 1,1 = 44.073 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 10.68 Kg


Sub Total x 1,1 = 11.748 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 42.930 Kg
Sub Total x 1,1 = 47.223 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Domas (PA BW 2, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total/ Tidak Biasa Dioperasikan h = 1,00 m
H' = 2,00 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 44.00 12,500.00 550,000.00
- Besi beton Kg 12.00 12,500.00 150,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,225,000.00

2. Bahan bantu kontruksi % 10.00 3,225,000.00 322,500.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 47.00 25,000.00 1,175,000.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 10.00 6,700.00 67,000.00
- Baja cor Kg 1,870,000.00 0.00
2,242,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 15.00 9,800.00 147,000.00
- Nipple Bh 1.00 3,000.00 3,000.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.11 110,000.00 12,375.00

362,875.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 258.00 3,000.00 774,000.00
- Ongkos kerja mesin Kg 67.00 21,200.00 1,420,400.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 10.34 57,000.00 589,266.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
2,783,666.00

III PE MASAN GAN : Kg 295.00 1,100.00 324,500.00


IV PE M B O N G KARAN : Kg 295.00 1,500.00 442,500.00
V TRAN S PO RT : Kg 295.00 600.00 177,000.00
944,000.00
Sub Total 9,880,041.00

VI Jumlah Harga 9,880,041.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 9,880,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Domas (PA BW 3, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.00
I. BAHAN H' = 2.00

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 0.000 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 97.470 Kg
Sub Total x 1,1 = 107.217 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 85.674 Kg

Sub Total = 85.674 Kg


Sub Total x 1,1 = 94.241 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 26.410 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 40.066 Kg
Sub Total x 1,1 = 44.073 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 10.68 Kg


Sub Total x 1,1 = 11.748 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 42.930 Kg
Sub Total x 1,1 = 47.223 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Domas (PA BW 3, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total/ Tidak Biasa Dioperasikan h = 1,00 m
H' = 2,00 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 44.00 12,500.00 550,000.00
- Besi beton Kg 12.00 12,500.00 150,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,225,000.00

2. Bahan bantu kontruksi % 10.00 3,225,000.00 322,500.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 47.00 25,000.00 1,175,000.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 10.00 6,700.00 67,000.00
- Baja cor Kg 1,870,000.00 0.00
2,242,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 15.00 9,800.00 147,000.00
- Nipple Bh 1.00 3,000.00 3,000.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.11 110,000.00 12,375.00

362,875.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 258.00 3,000.00 774,000.00
- Ongkos kerja mesin Kg 67.00 21,200.00 1,420,400.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 10.34 57,000.00 589,266.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
2,783,666.00

III PE MASAN GAN : Kg 295.00 1,100.00 324,500.00


IV PE M B O N G KARAN : Kg 295.00 1,500.00 442,500.00
V TRAN S PO RT : Kg 295.00 600.00 177,000.00
944,000.00
Sub Total 9,880,041.00

VI Jumlah Harga 9,880,041.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 9,880,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Domas (PA BW 4, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.00
I. BAHAN H' = 2.00

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 0.000 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 97.470 Kg
Sub Total x 1,1 = 107.217 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 85.674 Kg

Sub Total = 85.674 Kg


Sub Total x 1,1 = 94.241 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 26.410 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 40.066 Kg
Sub Total x 1,1 = 44.073 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 10.68 Kg


Sub Total x 1,1 = 11.748 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 42.930 Kg
Sub Total x 1,1 = 47.223 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Domas (PA BW 4, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total/ Tidak Biasa Dioperasikan h = 1,00 m
H' = 2,00 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 44.00 12,500.00 550,000.00
- Besi beton Kg 12.00 12,500.00 150,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,225,000.00

2. Bahan bantu kontruksi % 10.00 3,225,000.00 322,500.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 47.00 25,000.00 1,175,000.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 10.00 6,700.00 67,000.00
- Baja cor Kg 1,870,000.00 0.00
2,242,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 15.00 9,800.00 147,000.00
- Nipple Bh 1.00 3,000.00 3,000.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.11 110,000.00 12,375.00

362,875.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 258.00 3,000.00 774,000.00
- Ongkos kerja mesin Kg 67.00 21,200.00 1,420,400.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 10.34 57,000.00 589,266.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
2,783,666.00

III PE MASAN GAN : Kg 295.00 1,100.00 324,500.00


IV PE M B O N G KARAN : Kg 295.00 1,500.00 442,500.00
V TRAN S PO RT : Kg 295.00 600.00 177,000.00
944,000.00
Sub Total 9,880,041.00

VI Jumlah Harga 9,880,041.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 9,880,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 0.90
I. BAHAN H' = 2.10

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 0.000 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 97.470 Kg
Sub Total x 1,1 = 107.217 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 77.107 Kg

Sub Total = 77.107 Kg


Sub Total x 1,1 = 84.817 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 0.000 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 0.000 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 0.000 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 6.897 Kg
Sub Total x 1,1 = 7.587 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 11.125 Kg


Sub Total x 1,1 = 12.238 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 45.315 Kg
Sub Total x 1,1 = 49.847 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA BSW. 8c
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Kuningan & Kunci hilang h = 0,90 m
H' = 2,10 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 8.00 12,500.00 100,000.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
100,000.00

2. Bahan bantu kontruksi % 10.00 100,000.00 10,000.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 0.00 25,000.00 0.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 0.00 6,700.00 0.00
- Baja cor Kg 1,870,000.00 0.00
1,000,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 0.00 12,900.00 0.00
- Paku keling 3/4",5/8",7/8" Kg 0.00 9,800.00 0.00
- Nipple Bh 0.00 3,000.00 0.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.00 110,000.00 0.00

136,000.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 8.00 3,000.00 24,000.00
- Ongkos kerja mesin Kg 10.00 21,200.00 212,000.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 10.28 36,000.00 370,080.00
606,080.00

III PE MASAN GAN : Kg 16.00 1,100.00 17,600.00


IV PE M B O N G KARAN : Kg 16.00 1,500.00 24,000.00
V TRAN S PO RT : Kg 16.00 600.00 9,600.00
51,200.00
Sub Total 1,903,280.00

VI Jumlah Harga 1,903,280.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 1,903,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2

PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 13, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 1.00
I. BAHAN H' = 2.50

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.100.100.10) :


= B x 2 x 15,10 = 30.200 Kg
- Frame tegak (L.100.100.10) :
= (H' + 0,90) x 4 x 15,10 = 0.000 Kg
- Frame tengah (L.100.100.10) :
= B x 1 x 15,10 = 15.100 Kg
- Frame dasar (L.100.100.10) :
= (B + 0,50 ) x 1 x 15,10 = 22.650 Kg
- Penguat D. pintu (L.70.70.7) :
= B x 4 x 7,38 = 29.520 Kg
Sub Total = 97.470 Kg
Sub Total x 1,1 = 107.217 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.10 mm)


= (B + 0,09) x H x 1 x 78,60 = 85.674 Kg

Sub Total = 85.674 Kg


Sub Total x 1,1 = 94.241 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,22 x 0,15 x 2 x 78,60 = 5.188 Kg


- (T.10 mm.) = 0,10 x 0,10 x 2 x 78,60 = 1.572 Kg
- Frame tegak ( T.12 mm) :
= (H'+ 0,80) x 0,05 x 2 x 94,32 = 31.126 Kg
- Pemutar ( T.15 mm) :
= 0,09 x 0,65 x 1 x 117,90 = 6.897 Kg
Sub Total = 44.782 Kg
Sub Total x 1,1 = 49.261 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 12.905 Kg


Sub Total x 1,1 = 14.196 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 15,9 = 50.880 Kg
Sub Total x 1,1 = 55.968 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2

PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 13, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total h = 1,00 m
H' = 2,50 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 49.00 12,500.00 612,500.00
- Besi beton Kg 14.00 12,500.00 175,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,312,500.00

2. Bahan bantu kontruksi % 10.00 3,312,500.00 331,250.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 Kg 0.00
- Besi bulat st 60 Kg 56.00 25,000.00 1,400,000.00
-Bronze Kg 10.00 100,000.00 1,000,000.00
- Besi cor Kg 10.00 6,700.00 67,000.00
- Baja cor Kg 1,870,000.00 0.00
2,467,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" Kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" Kg 15.00 9,800.00 147,000.00
- Nipple Bh 1.00 3,000.00 3,000.00
- Splite pen Bh 2.00 31,300.00 62,600.00
- Gembok Bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar Bh 0.00 423,500.00 0.00
- Seal Bh 0.00
- Kayu jati M3 3,190,000.00 0.00
- Na F + ring Bh 0.14 110,000.00 14,850.00

365,350.00

II ONGKOS KERJA
- Ongkos kerja konst Kg 265.00 3,000.00 795,000.00
- Ongkos kerja mesin Kg 76.00 21,200.00 1,611,200.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 11.14 57,000.00 634,866.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
3,041,066.00

III PE MASAN GAN : Kg 310.00 1,100.00 341,000.00


IV PE M B O N G KARAN : Kg 310.00 1,500.00 465,000.00
V TRAN S PO RT : Kg 310.00 600.00 186,000.00
992,000.00
Sub Total 10,509,166.00

VI Jumlah Harga 10,509,166.00


Wdp/Pintu/Grati 1 .
VII Harga Satuan Pekerjaan per - Buah 10,509,000.00

Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK : IRIGASI JAWA TIMUR


DAERAH IRIGASI : Selowongko (PA SW 2 Te, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 0.60
h = 0.60
I. BAHAN H' = 1.50

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

0
= B x 2 x 9,66 = 11.592 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 91.963 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 5.796 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 10.240 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 9.756 Kg
Sub Total = 129.347 Kg
Sub Total x 1,1 = 142.281 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.8 mm)


= (B + 0,07) x H x 1 x 62,88 = 25.278 Kg

Sub Total = 25.278 Kg


Sub Total x 1,1 = 27.806 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,13 x 0,17 x 2 x 78,60 = 3.474 Kg


- (T.10 mm.) = 0,08 x 0,08 x 2 x 78,60 = 1.006 Kg
- Frame tegak ( T.10 mm) :
= (H'+ 0,80) x 0,05 x 2 x 78,60 = 18.078 Kg
- Pemutar ( T.15 mm) :
= 0,08 x 0,65 x 1 x 117,90 = 6.131 Kg
Sub Total = 28.689 Kg
Sub Total x 1,1 = 31.558 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 8.455 Kg


Sub Total x 1,1 = 9.301 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 12,5 = 30.000 Kg
Sub Total x 1,1 = 33.000 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK :
DAERAH IRIGASI : Selowongko (PA SW 2 Te, Pintu Bang. Bagi)
W 2 Te, Pintu Bang. Bagi) LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 0,60 m
URAIAN PEKERJAAN : Engkol & Dratstang Rusak h = 0,60 m
H' = 1,50 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 6.00 12,500.00 75,000.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
75,000.00

2. Bahan bantu kontruksi % 0.10 75,000.00 7,500.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 kg 0.00
- Besi bulat st 60 kg 33.00 25,000.00 825,000.00
-Bronze kg 0.00 100,000.00 0.00
- Besi cor kg 0.00 6,700.00 0.00
- Baja cor ps 1,870,000.00 0.00
825,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" kg 0.00 12,900.00 0.00
- Paku keling 3/4",5/8",7/8" kg 0.00 9,800.00 0.00
- Nipple bh 0.00 3,000.00 0.00
- Splite pen bh 2.00 31,300.00 62,600.00
- Gembok bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar bh 0.00 423,500.00 0.00
- Seal bh 0.00
- Kayu jati m3 3,190,000.00 0.00
- Na F + ring bh 0.00 110,000.00 0.00

136,000.00

II ONGKOS KERJA
- Ongkos kerja konst kg 6.00 3,000.00 18,000.00
- Ongkos kerja mesin kg 33.00 21,200.00 699,600.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 0.00 57,000.00 0.00
- Pengecatan tanpa sand m2 36,000.00 0.00
717,600.00

III PE MASAN GAN : kg 35.00 1,100.00 38,500.00


IV PE M B O N G KARAN : kg 35.00 1,500.00 52,500.00
V TRAN S PO RT : kg 35.00 600.00 21,000.00
112,000.00
Sub Total 1,873,100.00

VI Jumlah Harga 1,873,100.00


VII Harga satuan pekerjaan per-buah 1,873,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK : IRIGASI JAWA TIMUR


DAERAH IRIGASI :
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 0.60
h = 0.60
I. BAHAN H' = 1.50

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

0
= B x 2 x 9,66 = 11.592 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 91.963 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 5.796 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 10.240 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 9.756 Kg
Sub Total = 129.347 Kg
Sub Total x 1,1 = 142.281 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.8 mm)


= (B + 0,07) x H x 1 x 62,88 = 25.278 Kg

Sub Total = 25.278 Kg


Sub Total x 1,1 = 27.806 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,13 x 0,17 x 2 x 78,60 = 3.474 Kg


- (T.10 mm.) = 0,08 x 0,08 x 2 x 78,60 = 1.006 Kg
- Frame tegak ( T.10 mm) :
= (H'+ 0,80) x 0,05 x 2 x 78,60 = 18.078 Kg
- Pemutar ( T.15 mm) :
= 0,08 x 0,65 x 1 x 117,90 = 6.131 Kg
Sub Total = 28.689 Kg
Sub Total x 1,1 = 31.558 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 8.455 Kg


Sub Total x 1,1 = 9.301 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 12,5 = 30.000 Kg
Sub Total x 1,1 = 33.000 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 6, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 0,60 m
URAIAN PEKERJAAN : Stang Rusak, Engkol & h = 0,60 m
Mur Kuningan Hilang H' = 1,50 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 6.00 12,500.00 75,000.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
75,000.00

2. Bahan bantu kontruksi % 0.10 75,000.00 7,500.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 kg 0.00
- Besi bulat st 60 kg 33.00 25,000.00 825,000.00
-Bronze kg 10.00 100,000.00 1,000,000.00
- Besi cor kg 0.00 6,700.00 0.00
- Baja cor ps 1,870,000.00 0.00
1,825,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" kg 0.00 9,800.00 0.00
- Nipple bh 0.00 3,000.00 0.00
- Splite pen bh 2.00 31,300.00 62,600.00
- Gembok bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar bh 0.00 423,500.00 0.00
- Seal bh 0.00
- Kayu jati m3 3,190,000.00 0.00
- Na F + ring bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst kg 6.00 3,000.00 18,000.00
- Ongkos kerja mesin kg 43.00 21,200.00 911,600.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 57,000.00 0.00
- Pengecatan tanpa sand m2 36,000.00 0.00
929,600.00

III PE MASAN GAN : kg 45.00 1,100.00 49,500.00


IV PE M B O N G KARAN : kg 45.00 1,500.00 67,500.00
V TRAN S PO RT : kg 45.00 600.00 27,000.00
144,000.00
Sub Total 3,181,600.00

VI Jumlah Harga 3,181,600.00


VII Harga satuan pekerjaan per-buah 3,181,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK : IRIGASI JAWA TIMUR


DAERAH IRIGASI : Selowongko (PA Sw 6 Ka Ki, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 0.50
h = 0.60
I. BAHAN H' = 1.50

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

0
= B x 2 x 9,66 = 9.660 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 91.963 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 4.830 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 9.274 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 8.130 Kg
Sub Total = 123.857 Kg
Sub Total x 1,1 = 136.242 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.8 mm)


= (B + 0,07) x H x 1 x 62,88 = 21.505 Kg

Sub Total = 21.505 Kg


Sub Total x 1,1 = 23.655 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,13 x 0,17 x 2 x 78,60 = 3.474 Kg


- (T.10 mm.) = 0,08 x 0,08 x 2 x 78,60 = 1.006 Kg
- Frame tegak ( T.10 mm) :
= (H'+ 0,80) x 0,05 x 2 x 78,60 = 18.078 Kg
- Pemutar ( T.15 mm) :
= 0,08 x 0,65 x 1 x 117,90 = 6.131 Kg
Sub Total = 28.689 Kg
Sub Total x 1,1 = 31.558 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 8.455 Kg


Sub Total x 1,1 = 9.301 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 12,5 = 30.000 Kg
Sub Total x 1,1 = 33.000 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw 6 Ka Ki, Pintu Bang. Bagi)
w 6 Ka Ki, Pintu Bang. Bagi) LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 0,50 m
URAIAN PEKERJAAN : Stang Rusak, Engkol & h = 0,60 m
Mur Kuningan Hilang H' = 1,50 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 0.00 12,500.00 0.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
0.00

2. Bahan bantu kontruksi % 0.10 0.00 0.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 kg 0.00
- Besi bulat st 60 kg 33.00 25,000.00 825,000.00
-Bronze kg 10.00 100,000.00 1,000,000.00
- Besi cor kg 0.00 6,700.00 0.00
- Baja cor ps 1,870,000.00 0.00
1,825,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" kg 0.00 9,800.00 0.00
- Nipple bh 0.00 3,000.00 0.00
- Splite pen bh 2.00 31,300.00 62,600.00
- Gembok bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar bh 0.00 423,500.00 0.00
- Seal bh 0.00
- Kayu jati m3 3,190,000.00 0.00
- Na F + ring bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst kg 0.00 3,000.00 0.00
- Ongkos kerja mesin kg 43.00 21,200.00 911,600.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 57,000.00 0.00
- Pengecatan tanpa sand m2 36,000.00 0.00
911,600.00

III PE MASAN GAN : kg 39.00 1,100.00 42,900.00


IV PE M B O N G KARAN : kg 39.00 1,500.00 58,500.00
V TRAN S PO RT : kg 39.00 600.00 23,400.00
124,800.00
Sub Total 3,061,900.00

VI Jumlah Harga 3,061,900.00


VII Harga satuan pekerjaan per-buah 3,061,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK : IRIGASI JAWA TIMUR


DAERAH IRIGASI : Selowongko (PA BKB 3 & 4, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 0.70
h = 0.80
I. BAHAN H' = 2.10

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

0
= B x 2 x 9,66 = 13.524 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 115.147 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 6.762 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 11.206 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 11.382 Kg
Sub Total = 158.021 Kg
Sub Total x 1,1 = 173.823 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.8 mm)


= (B + 0,07) x H x 1 x 62,88 = 38.734 Kg

Sub Total = 38.734 Kg


Sub Total x 1,1 = 42.607 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,13 x 0,17 x 2 x 78,60 = 3.474 Kg


- (T.10 mm.) = 0,08 x 0,08 x 2 x 78,60 = 1.006 Kg
- Frame tegak ( T.10 mm) :
= (H'+ 0,80) x 0,05 x 2 x 78,60 = 22.794 Kg
- Pemutar ( T.15 mm) :
= 0,08 x 0,65 x 1 x 117,90 = 6.131 Kg
Sub Total = 33.405 Kg
Sub Total x 1,1 = 36.746 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 11.125 Kg


Sub Total x 1,1 = 12.238 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 12,5 = 36.250 Kg
Sub Total x 1,1 = 39.875 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 3 & 4, Pintu Bang. Bagi)
KB 3 & 4, Pintu Bang. Bagi) LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 0,70 m
URAIAN PEKERJAAN : Stang Rusak, Engkol & h = 0,80 m
Mur Kuningan Hilang H' = 2,10 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 6.00 12,500.00 75,000.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
75,000.00

2. Bahan bantu kontruksi % 0.10 75,000.00 7,500.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 kg 0.00
- Besi bulat st 60 kg 40.00 25,000.00 1,000,000.00
-Bronze kg 10.00 100,000.00 1,000,000.00
- Besi cor kg 0.00 6,700.00 0.00
- Baja cor ps 1,870,000.00 0.00
2,000,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" kg 0.00 9,800.00 0.00
- Nipple bh 0.00 3,000.00 0.00
- Splite pen bh 2.00 31,300.00 62,600.00
- Gembok bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar bh 0.00 423,500.00 0.00
- Seal bh 0.00
- Kayu jati m3 3,190,000.00 0.00
- Na F + ring bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst kg 6.00 3,000.00 18,000.00
- Ongkos kerja mesin kg 50.00 21,200.00 1,060,000.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 57,000.00 0.00
- Pengecatan tanpa sand m2 36,000.00 0.00
1,078,000.00

III PE MASAN GAN : kg 51.00 1,100.00 56,100.00


IV PE M B O N G KARAN : kg 51.00 1,500.00 76,500.00
V TRAN S PO RT : kg 51.00 600.00 30,600.00
163,200.00
Sub Total 3,524,200.00

VI Jumlah Harga 3,524,200.00


VII Harga satuan pekerjaan per-buah 3,524,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK : IRIGASI JAWA TIMUR


DAERAH IRIGASI : Selowongko (PA Sadap, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 0.60
h = 0.60
I. BAHAN H' = 1.50

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

0
= B x 2 x 9,66 = 11.592 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 0.000 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 5.796 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 10.240 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 9.756 Kg
Sub Total = 37.384 Kg
Sub Total x 1,1 = 41.122 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.8 mm)


= (B + 0,07) x H x 1 x 62,88 = 25.278 Kg

Sub Total = 25.278 Kg


Sub Total x 1,1 = 27.806 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,13 x 0,17 x 2 x 78,60 = 3.474 Kg


- (T.10 mm.) = 0,08 x 0,08 x 2 x 78,60 = 1.006 Kg
- Frame tegak ( T.10 mm) :
= (H'+ 0,80) x 0,05 x 2 x 78,60 = 18.078 Kg
- Pemutar ( T.15 mm) :
= 0,08 x 0,65 x 1 x 117,90 = 6.131 Kg
Sub Total = 28.689 Kg
Sub Total x 1,1 = 31.558 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 8.455 Kg


Sub Total x 1,1 = 9.301 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 12,5 = 30.000 Kg
Sub Total x 1,1 = 33.000 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK :
DAERAH IRIGASI : Selowongko (PA Sadap, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 0,60 m
URAIAN PEKERJAAN : Rusak Total h = 0,60 m
H' = 1,50 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 41.00 12,500.00 512,500.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 28.00 12,500.00 350,000.00
- Besi plate strip kg 32.00 12,500.00 400,000.00
- Besi beton kg 9.00 12,500.00 112,500.00
-Pipa kg 1.00 12,500.00 12,500.00
1,387,500.00

2. Bahan bantu kontruksi % 0.10 1,387,500.00 138,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 kg 0.00
- Besi bulat st 60 kg 33.00 25,000.00 825,000.00
-Bronze kg 10.00 100,000.00 1,000,000.00
- Besi cor kg 10.00 6,700.00 67,000.00
- Baja cor ps 1,870,000.00 0.00
1,892,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" kg 11.00 9,800.00 107,800.00
- Nipple bh 1.00 3,000.00 3,000.00
- Splite pen bh 2.00 31,300.00 62,600.00
- Gembok bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar bh 0.00 423,500.00 0.00
- Seal bh 0.00
- Kayu jati m3 3,190,000.00 0.00
- Na F + ring bh 1.00 110,000.00 110,000.00

421,300.00

II ONGKOS KERJA
- Ongkos kerja konst kg 111.00 3,000.00 333,000.00
- Ongkos kerja mesin kg 53.00 21,200.00 1,123,600.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 7.03 57,000.00 400,938.00
- Pengecatan tanpa sand m2 0.00 36,000.00 0.00
1,857,538.00

III PE MASAN GAN : kg 149.00 1,100.00 163,900.00


IV PE M B O N G KARAN : kg 149.00 1,500.00 223,500.00
V TRAN S PO RT : kg 149.00 600.00 89,400.00
476,800.00
Sub Total 6,173,888.00

VI Jumlah Harga 6,173,888.00


VII Harga satuan pekerjaan per-buah 6,173,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK : IRIGASI JAWA TIMUR


DAERAH IRIGASI : Selowongko
LO KAS I : PA BSW 13 Ka kuarter
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 0.35
I. BAHAN H' = 1.50

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

0
= B x 2 x 9,66 = 19.320 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 0.000 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 9.660 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 14.104 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 16.260 Kg
Sub Total = 59.344 Kg
Sub Total x 1,1 = 65.278 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.8 mm)


= (B + 0,07) x H x 1 x 62,88 = 23.549 Kg

Sub Total = 23.549 Kg


Sub Total x 1,1 = 25.903 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,13 x 0,17 x 2 x 78,60 = 0.000 Kg


- (T.10 mm.) = 0,08 x 0,08 x 2 x 78,60 = 0.000 Kg
- Frame tegak ( T.10 mm) :
= (H'+ 0,80) x 0,05 x 2 x 78,60 = 0.000 Kg
- Pemutar ( T.15 mm) :
= 0,08 x 0,65 x 1 x 117,90 = 6.131 Kg
Sub Total = 6.131 Kg
Sub Total x 1,1 = 6.744 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 8.455 Kg


Sub Total x 1,1 = 9.301 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 12,5 = 31.563 Kg
Sub Total x 1,1 = 34.719 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA BSW 13 Ka kuarter
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Kunci h = 0,35 m
H' = 1,50 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 7.00 12,500.00 87,500.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
87,500.00

2. Bahan bantu kontruksi % 0.10 87,500.00 8,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 kg 0.00
- Besi bulat st 60 kg 35.00 25,000.00 875,000.00
-Bronze kg 10.00 100,000.00 1,000,000.00
- Besi cor kg 0.00 6,700.00 0.00
- Baja cor ps 1,870,000.00 0.00
1,875,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" kg 0.00 9,800.00 0.00
- Nipple bh 0.00 3,000.00 0.00
- Splite pen bh 2.00 31,300.00 62,600.00
- Gembok bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar bh 0.00 423,500.00 0.00
- Seal bh 0.00
- Kayu jati m3 3,190,000.00 0.00
- Na F + ring bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin kg 45.00 21,200.00 954,000.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 0.00 57,000.00 0.00
- Pengecatan tanpa sand m2 8.12 36,000.00 292,356.00
1,267,356.00

III PE MASAN GAN : kg 47.00 1,100.00 51,700.00


IV PE M B O N G KARAN : kg 47.00 1,500.00 70,500.00
V TRAN S PO RT : kg 47.00 600.00 28,200.00
150,400.00
Sub Total 3,589,506.00

VI Jumlah Harga 3,589,506.00


VII Harga satuan pekerjaan per-buah 3,589,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK : IRIGASI JAWA TIMUR


DAERAH IRIGASI : Selowongko
LO KAS I : PA Linggo ( Penguras )
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 0.60
h = 1.00
I. BAHAN H' = 2.65

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

0
= B x 2 x 9,66 = 11.592 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 0.000 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 5.796 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 10.240 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 9.756 Kg
Sub Total = 37.384 Kg
Sub Total x 1,1 = 41.122 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.8 mm)


= (B + 0,07) x H x 1 x 62,88 = 42.130 Kg

Sub Total = 42.130 Kg


Sub Total x 1,1 = 46.343 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,13 x 0,17 x 2 x 78,60 = 0.000 Kg


- (T.10 mm.) = 0,08 x 0,08 x 2 x 78,60 = 0.000 Kg
- Frame tegak ( T.10 mm) :
= (H'+ 0,80) x 0,05 x 2 x 78,60 = 0.000 Kg
- Pemutar ( T.15 mm) :
= 0,08 x 0,65 x 1 x 117,90 = 6.131 Kg
Sub Total = 6.131 Kg
Sub Total x 1,1 = 6.744 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 13.5725 Kg


Sub Total x 1,1 = 14.930 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 12,5 = 41.875 Kg
Sub Total x 1,1 = 46.063 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA Linggo ( Penguras )
CABANG DINAS PENGAIRAN : Kejayan B = 0,60 m
URAIAN PEKERJAAN : Kuningan Hilang h = 1,00 m
H' = 2,65 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 7.00 12,500.00 87,500.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
87,500.00

2. Bahan bantu kontruksi % 0.10 87,500.00 8,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 kg 0.00
- Besi bulat st 60 kg 0.00 25,000.00 0.00
-Bronze kg 10.00 100,000.00 1,000,000.00
- Besi cor kg 0.00 6,700.00 0.00
- Baja cor ps 1,870,000.00 0.00
1,000,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" kg 0.00 9,800.00 0.00
- Nipple bh 0.00 3,000.00 0.00
- Splite pen bh 2.00 31,300.00 62,600.00
- Gembok bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar bh 0.00 423,500.00 0.00
- Seal bh 0.00
- Kayu jati m3 3,190,000.00 0.00
- Na F + ring bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin kg 10.00 21,200.00 212,000.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 0.00 57,000.00 0.00
- Pengecatan tanpa sand m2 9.43 36,000.00 339,336.00
572,336.00

III PE MASAN GAN : kg 15.00 1,100.00 16,500.00


IV PE M B O N G KARAN : kg 15.00 1,500.00 22,500.00
V TRAN S PO RT : kg 15.00 600.00 9,000.00
48,000.00
Sub Total 1,917,086.00

VI Jumlah Harga 1,917,086.00


VII Harga satuan pekerjaan per-buah 1,917,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK : IRIGASI JAWA TIMUR


DAERAH IRIGASI : Selowongko
LO KAS I : PA Sek K. Boto ( BKB. 5 Ka Sadap )
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 0.60
h = 0.60
I. BAHAN H' = 2.25

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

0
= B x 2 x 9,66 = 11.592 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 0.000 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 5.796 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 10.240 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 9.756 Kg
Sub Total = 37.384 Kg
Sub Total x 1,1 = 41.122 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.8 mm)


= (B + 0,07) x H x 1 x 62,88 = 25.278 Kg

Sub Total = 25.278 Kg


Sub Total x 1,1 = 27.806 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,13 x 0,17 x 2 x 78,60 = 0.000 Kg


- (T.10 mm.) = 0,08 x 0,08 x 2 x 78,60 = 0.000 Kg
- Frame tegak ( T.10 mm) :
= (H'+ 0,80) x 0,05 x 2 x 78,60 = 0.000 Kg
- Pemutar ( T.15 mm) :
= 0,08 x 0,65 x 1 x 117,90 = 6.131 Kg
Sub Total = 6.131 Kg
Sub Total x 1,1 = 6.744 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 11.7925 Kg


Sub Total x 1,1 = 12.972 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 12,5 = 39.375 Kg
Sub Total x 1,1 = 43.313 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA Sek K. Boto ( BKB. 5 Ka Sadap )
CABANG DINAS PENGAIRAN : Kejayan B = 0,60 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Kunci h = 0,60 m
H' = 2,25 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 7.00 12,500.00 87,500.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
87,500.00

2. Bahan bantu kontruksi % 0.10 87,500.00 8,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 kg 0.00
- Besi bulat st 60 kg 43.00 25,000.00 1,075,000.00
-Bronze kg 10.00 100,000.00 1,000,000.00
- Besi cor kg 0.00 6,700.00 0.00
- Baja cor ps 1,870,000.00 0.00
2,075,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" kg 0.00 9,800.00 0.00
- Nipple bh 0.00 3,000.00 0.00
- Splite pen bh 2.00 31,300.00 62,600.00
- Gembok bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar bh 0.00 423,500.00 0.00
- Seal bh 0.00
- Kayu jati m3 3,190,000.00 0.00
- Na F + ring bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin kg 53.00 21,200.00 1,123,600.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 0.00 57,000.00 0.00
- Pengecatan tanpa sand m2 8.23 36,000.00 296,424.00
1,441,024.00

III PE MASAN GAN : kg 55.00 1,100.00 60,500.00


IV PE M B O N G KARAN : kg 55.00 1,500.00 82,500.00
V TRAN S PO RT : kg 55.00 600.00 33,000.00
176,000.00
Sub Total 3,988,774.00

VI Jumlah Harga 3,988,774.00


VII Harga satuan pekerjaan per-buah 3,988,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK : IRIGASI JAWA TIMUR


DAERAH IRIGASI : Selowongko
LO KAS I : PA Sek K. Boto ( BKB. 5 Ki Sadap )
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 0.60
h = 0.60
I. BAHAN H' = 2.25

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

0
= B x 2 x 9,66 = 11.592 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 0.000 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 5.796 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 10.240 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 9.756 Kg
Sub Total = 37.384 Kg
Sub Total x 1,1 = 41.122 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.8 mm)


= (B + 0,07) x H x 1 x 62,88 = 25.278 Kg

Sub Total = 25.278 Kg


Sub Total x 1,1 = 27.806 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,13 x 0,17 x 2 x 78,60 = 0.000 Kg


- (T.10 mm.) = 0,08 x 0,08 x 2 x 78,60 = 0.000 Kg
- Frame tegak ( T.10 mm) :
= (H'+ 0,80) x 0,05 x 2 x 78,60 = 0.000 Kg
- Pemutar ( T.15 mm) :
= 0,08 x 0,65 x 1 x 117,90 = 6.131 Kg
Sub Total = 6.131 Kg
Sub Total x 1,1 = 6.744 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 11.7925 Kg


Sub Total x 1,1 = 12.972 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 12,5 = 39.375 Kg
Sub Total x 1,1 = 43.313 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA Sek K. Boto ( BKB. 5 Ki Sadap )
CABANG DINAS PENGAIRAN : Kejayan B = 0,60 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Kunci h = 0,60 m
H' = 2,25 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 7.00 12,500.00 87,500.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
87,500.00

2. Bahan bantu kontruksi % 0.10 87,500.00 8,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 kg 0.00
- Besi bulat st 60 kg 43.00 25,000.00 1,075,000.00
-Bronze kg 10.00 100,000.00 1,000,000.00
- Besi cor kg 0.00 6,700.00 0.00
- Baja cor ps 1,870,000.00 0.00
2,075,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" kg 0.00 9,800.00 0.00
- Nipple bh 0.00 3,000.00 0.00
- Splite pen bh 2.00 31,300.00 62,600.00
- Gembok bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar bh 0.00 423,500.00 0.00
- Seal bh 0.00
- Kayu jati m3 3,190,000.00 0.00
- Na F + ring bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin kg 53.00 21,200.00 1,123,600.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 0.00 57,000.00 0.00
- Pengecatan tanpa sand m2 8.23 36,000.00 296,424.00
1,441,024.00

III PE MASAN GAN : kg 55.00 1,100.00 60,500.00


IV PE M B O N G KARAN : kg 55.00 1,500.00 82,500.00
V TRAN S PO RT : kg 55.00 600.00 33,000.00
176,000.00
Sub Total 3,988,774.00

VI Jumlah Harga 3,988,774.00


VII Harga satuan pekerjaan per-buah 3,988,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK : IRIGASI JAWA TIMUR


DAERAH IRIGASI : Selowongko
LO KAS I : PA Sek K. Boto ( BKB. 5 Te Sadap )
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 1.00
h = 0.65
I. BAHAN H' = 2.25

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

0
= B x 2 x 9,66 = 19.320 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 0.000 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 9.660 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 14.104 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 16.260 Kg
Sub Total = 59.344 Kg
Sub Total x 1,1 = 65.278 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.8 mm)


= (B + 0,07) x H x 1 x 62,88 = 43.733 Kg

Sub Total = 43.733 Kg


Sub Total x 1,1 = 48.106 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,13 x 0,17 x 2 x 78,60 = 0.000 Kg


- (T.10 mm.) = 0,08 x 0,08 x 2 x 78,60 = 0.000 Kg
- Frame tegak ( T.10 mm) :
= (H'+ 0,80) x 0,05 x 2 x 78,60 = 0.000 Kg
- Pemutar ( T.15 mm) :
= 0,08 x 0,65 x 1 x 117,90 = 6.131 Kg
Sub Total = 6.131 Kg
Sub Total x 1,1 = 6.744 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 11.7925 Kg


Sub Total x 1,1 = 12.972 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 12,5 = 39.063 Kg
Sub Total x 1,1 = 42.969 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA Sek K. Boto ( BKB. 5 Te Sadap )
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Kunci h = 0,65 m
H' = 2,25 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 7.00 12,500.00 87,500.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
87,500.00

2. Bahan bantu kontruksi % 0.10 87,500.00 8,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 kg 0.00
- Besi bulat st 60 kg 43.00 25,000.00 1,075,000.00
-Bronze kg 10.00 100,000.00 1,000,000.00
- Besi cor kg 0.00 6,700.00 0.00
- Baja cor ps 1,870,000.00 0.00
2,075,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" kg 0.00 9,800.00 0.00
- Nipple bh 0.00 3,000.00 0.00
- Splite pen bh 2.00 31,300.00 62,600.00
- Gembok bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar bh 0.00 423,500.00 0.00
- Seal bh 0.00
- Kayu jati m3 3,190,000.00 0.00
- Na F + ring bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin kg 53.00 21,200.00 1,123,600.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 0.00 57,000.00 0.00
- Pengecatan tanpa sand m2 9.98 36,000.00 359,100.00
1,503,700.00

III PE MASAN GAN : kg 55.00 1,100.00 60,500.00


IV PE M B O N G KARAN : kg 55.00 1,500.00 82,500.00
V TRAN S PO RT : kg 55.00 600.00 33,000.00
176,000.00
Sub Total 4,051,450.00

VI Jumlah Harga 4,051,450.00


VII Harga satuan pekerjaan per-buah 4,051,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK : IRIGASI JAWA TIMUR


DAERAH IRIGASI : Paras
LO KAS I : PA Sek Jogorepuh Ki
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 0.60
h = 0.60
I. BAHAN H' = 2.25

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

0
= B x 2 x 9,66 = 11.592 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 0.000 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 5.796 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 10.240 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 9.756 Kg
Sub Total = 37.384 Kg
Sub Total x 1,1 = 41.122 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.8 mm)


= (B + 0,07) x H x 1 x 62,88 = 25.278 Kg

Sub Total = 25.278 Kg


Sub Total x 1,1 = 27.806 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,13 x 0,17 x 2 x 78,60 = 0.000 Kg


- (T.10 mm.) = 0,08 x 0,08 x 2 x 78,60 = 0.000 Kg
- Frame tegak ( T.10 mm) :
= (H'+ 0,80) x 0,05 x 2 x 78,60 = 0.000 Kg
- Pemutar ( T.15 mm) :
= 0,08 x 0,65 x 1 x 117,90 = 6.131 Kg
Sub Total = 6.131 Kg
Sub Total x 1,1 = 6.744 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 11.7925 Kg


Sub Total x 1,1 = 12.972 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 12,5 = 39.375 Kg
Sub Total x 1,1 = 43.313 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK :
DAERAH IRIGASI : Paras
LO KAS I : PA Sek Jogorepuh Ki
CABANG DINAS PENGAIRAN : Kejayan B = 0,60 m
URAIAN PEKERJAAN : Rusak Ringan h = 0,60 m
H' = 2,25 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 7.00 12,500.00 87,500.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
87,500.00

2. Bahan bantu kontruksi % 0.10 87,500.00 8,750.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 kg 0.00
- Besi bulat st 60 kg 43.00 25,000.00 1,075,000.00
-Bronze kg 10.00 100,000.00 1,000,000.00
- Besi cor kg 0.00 6,700.00 0.00
- Baja cor ps 1,870,000.00 0.00
2,075,000.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" kg 0.00 9,800.00 0.00
- Nipple bh 0.00 3,000.00 0.00
- Splite pen bh 2.00 31,300.00 62,600.00
- Gembok bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar bh 0.00 423,500.00 0.00
- Seal bh 0.00
- Kayu jati m3 3,190,000.00 0.00
- Na F + ring bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin kg 53.00 21,200.00 1,123,600.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 0.00 57,000.00 0.00
- Pengecatan tanpa sand m2 8.23 36,000.00 296,424.00
1,441,024.00

III PE MASAN GAN : kg 55.00 1,100.00 60,500.00


IV PE M B O N G KARAN : kg 55.00 1,500.00 82,500.00
V TRAN S PO RT : kg 55.00 600.00 33,000.00
176,000.00
Sub Total 3,988,774.00

VI Jumlah Harga 3,988,774.00


VII Harga satuan pekerjaan per-buah 3,988,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK : IRIGASI JAWA TIMUR


DAERAH IRIGASI : Ngantungan
LO KAS I : PA Ngantungan ( Intake Ki ) 2 pintu
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 0.50
h = 0.75
I. BAHAN H' = 4.25

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

0
= B x 2 x 9,66 = 9.660 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 0.000 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 4.830 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 9.274 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 8.130 Kg
Sub Total = 31.894 Kg
Sub Total x 1,1 = 35.083 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.8 mm)


= (B + 0,07) x H x 1 x 62,88 = 26.881 Kg

Sub Total = 26.881 Kg


Sub Total x 1,1 = 29.569 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,13 x 0,17 x 2 x 78,60 = 0.000 Kg


- (T.10 mm.) = 0,08 x 0,08 x 2 x 78,60 = 0.000 Kg
- Frame tegak ( T.10 mm) :
= (H'+ 0,80) x 0,05 x 2 x 78,60 = 0.000 Kg
- Pemutar ( T.15 mm) :
= 0,08 x 0,65 x 1 x 117,90 = 6.131 Kg
Sub Total = 6.131 Kg
Sub Total x 1,1 = 6.744 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 20.6925 Kg


Sub Total x 1,1 = 22.762 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 12,5 = 63.438 Kg
Sub Total x 1,1 = 69.781 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3

PROYEK :
DAERAH IRIGASI : Ngantungan
LO KAS I : PA Ngantungan ( Intake Ki ) 2 pintu
CABANG DINAS PENGAIRAN : Kejayan B = 0,50 m
URAIAN PEKERJAAN : Daun pintu bocor h = 0,75 m
H' = 4,25 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 30.00 12,500.00 375,000.00
- Besi plate strip kg 0.00 12,500.00 0.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
375,000.00

2. Bahan bantu kontruksi % 0.10 375,000.00 37,500.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 kg 0.00
- Besi bulat st 60 kg 0.00 25,000.00 0.00
-Bronze kg 0.00 100,000.00 0.00
- Besi cor kg 0.00 6,700.00 0.00
- Baja cor ps 1,870,000.00 0.00
0.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" kg 5.00 12,900.00 64,500.00
- Paku keling 3/4",5/8",7/8" kg 0.00 9,800.00 0.00
- Nipple bh 0.00 3,000.00 0.00
- Splite pen bh 2.00 31,300.00 62,600.00
- Gembok bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar bh 0.00 423,500.00 0.00
- Seal bh 0.00
- Kayu jati m3 3,190,000.00 0.00
- Na F + ring bh 0.00 110,000.00 0.00

200,500.00

II ONGKOS KERJA
- Ongkos kerja konst kg 30.00 3,000.00 90,000.00
- Ongkos kerja mesin kg 0.00 21,200.00 0.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 0.00 57,000.00 0.00
- Pengecatan tanpa sand m2 11.20 36,000.00 403,308.00
493,308.00

III PE MASAN GAN : kg 27.00 1,100.00 29,700.00


IV PE M B O N G KARAN : kg 27.00 1,500.00 40,500.00
V TRAN S PO RT : kg 27.00 600.00 16,200.00
86,400.00
Sub Total 1,192,708.00

VI Jumlah Harga 1,192,708.00


VII Harga satuan pekerjaan per-buah 1,192,000.00
TOTAL 2,384,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 5

PROYEK : IRIGASI JAWA TIMUR


DAERAH IRIGASI : Tengger (PA Sumber Gedang , Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan

PAKET PEKERJAAN :

B = 0.30
h = 0.70
I. BAHAN H' = 0.90

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

0
= B x 2 x 9,66 = 5.796 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 68.779 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 2.898 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 7.342 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 4.878 Kg
Sub Total = 89.693 Kg
Sub Total x 1,1 = 98.662 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.8 mm)


= (B + 0,07) x H x 1 x 62,88 = 16.286 Kg

Sub Total = 16.286 Kg


Sub Total x 1,1 = 17.915 Kg
1.3. BESI PLAT STRIP :

- Plat simpul = 0,13 x 0,17 x 2 x 78,60 = 3.474 Kg


- (T.10 mm.) = 0,08 x 0,08 x 2 x 78,60 = 1.006 Kg
- Frame tegak ( T.10 mm) :
= (H'+ 0,80) x 0,05 x 2 x 78,60 = 13.362 Kg
- Pemutar ( T.15 mm) :
= 0,08 x 0,65 x 1 x 117,90 = 6.131 Kg
Sub Total = 23.973 Kg
Sub Total x 1,1 = 26.370 Kg
1.4. BESI BETON :

- Angker ½" = 0,50 x (H'/0,4+1) x 4 x 0,89 = 5.785 Kg


Sub Total x 1,1 = 6.364 Kg

1.5. P I P A = 1.000 Kg

2. BAHAN DIKERJAKAN MESIN :

2.1. BESI BULAT ST.60 (Drat Stang)


(H' + 1,2 - 0,5 . H) x 1 x 12,5 = 21.875 Kg
Sub Total x 1,1 = 24.063 Kg

2.2. BRONZE (MURHES) = 10.000 Kg

2.3. BESI COR (BLOCK) = 10.000 Kg

Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 5

PROYEK :
DAERAH IRIGASI : Tengger (PA Sumber Gedang , Pintu Bang. Bagi)
ber Gedang , Pintu Bang. Bagi) LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 0,30 m
URAIAN PEKERJAAN : Daun Pintu Rusak h = 0,70 m
H' = 0,90 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 18.00 12,500.00 225,000.00
- Besi plate strip kg 0.00 12,500.00 0.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
225,000.00

2. Bahan bantu kontruksi % 0.10 225,000.00 22,500.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 kg 0.00
- Besi bulat st 60 kg 0.00 25,000.00 0.00
-Bronze kg 0.00 100,000.00 0.00
- Besi cor kg 0.00 6,700.00 0.00
- Baja cor ps 1,870,000.00 0.00
0.00

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" kg 0.00 12,900.00 0.00
- Paku keling 3/4",5/8",7/8" kg 0.00 9,800.00 0.00
- Nipple bh 0.00 3,000.00 0.00
- Splite pen bh 2.00 31,300.00 62,600.00
- Gembok bh 2.00 36,700.00 73,400.00
- Drucklager kecil/besar bh 1.00 423,500.00 423,500.00
- Seal bh 0.00
- Kayu jati m3 3,190,000.00 0.00
- Na F + ring bh 0.00 110,000.00 0.00

559,500.00

II ONGKOS KERJA
- Ongkos kerja konst kg 18.00 3,000.00 54,000.00
- Ongkos kerja mesin kg 0.00 21,200.00 0.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 4.93 57,000.00 280,896.00
- Pengecatan tanpa sand m2 0.00 36,000.00 0.00
334,896.00

III PE MASAN GAN : kg 16.00 1,100.00 17,600.00


IV PE M B O N G KARAN : kg 16.00 1,500.00 24,000.00
V TRAN S PO RT : kg 16.00 600.00 9,600.00
51,200.00
Sub Total 1,193,096.00

VI Jumlah Harga 1,193,096.00


VII Harga satuan pekerjaan per-buah 1,193,000.00

Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
SKIP

PROYEK : IRIGASI JAWA TIMUR


DAERAH IRIGASI : Selowongko
LOKASI : PA BSW. 13 Ka ( Kuarter )
CAB. DPU PENGAIR : GRATI
PAKET PEKERJAAN :
B = 0.4
h = 0.5
H' = 1.2
I. BAHAN

1. BAHAN KONSTRUKSI :

1.1. BESI SIKU :

- Frame atas (L.60.60.6) :


= (0,12 + B) x 1 x 5,42 = 2.8184 Kg
- Frame tegak (L.60.60.6) :
= (H' + 0,46) x 4 x 5,42 = 35.9888 Kg
- Frame tengah (L.60.60.6) :
= B x 1 x 5,42 = 2.168 Kg
- Frame dasar (L.60.60.6) :
= (B + 0,36 ) x 1 x 5,42 = 4.1192 Kg
- Sekur Frame Atas (L.60.60.6) :
= 0,06 x 2 x 5,42 = 0.6504 Kg
Sub Total = 45.745 Kg
Sub Total x 1,1 = 50.319 Kg
1.2. BESI KANAL :

- Penarik (NP.5)
= (H' + 0,57 - 0,5 . H) x 1 x 5,59 = 8.497 Kg
- Pengunci (NP.10)
= 0,06 x 1 x 10,60 = 0.636 Kg
Sub Total = 9.133 Kg
Sub Total x 1,1 = 10.046 Kg
1.2. BESI PLAT :

- Daun Pintu ( T.8 mm)


= (B + 0,05) x H x 1 x 62,88 = 14.148 Kg
- Plat simpul = 0,06 x 0,06 x 2 x 62,88 = 0.453 Kg
Sub Total = 14.601 Kg
Sub Total x 1,1 = 16.061 Kg
1.3. BESI PLAT STRIP :

- Frame tegak ( T.8 mm) :


= (H'+ 0,40) x 0,03 x 2 x 62,88 = 6.036 Kg
Sub Total = 6.036 Kg
Sub Total x 1,1 = 6.640 Kg
1.4. BESI BETON :

- Angker ½" = 0,32 x (H'/0,4+1) x 4 x 0,89 = 4.56 Kg


- Penarik = 0,49 x 1 x 2,23 = 1.09 Kg
Sub Total = 5.650 Kg
Sub Total x 1,1 = 6.214 Kg

2 BAHAN - BAHAN LAIN :


PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
SKIP
PROYEK :
DAERAH IRIGASI : Selowongko
LOKASI : PA BSW. 13 Ka ( Kuarter )
CABANG DINAS PENGAIRAN : GRATI B = 0,4 m
URAIAN PEKERJAAN : Daun Keropos h = 0,5 m
H' = 1,2 m

Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN:
1. Bahan konstruksi :
- Besi siku kg - 7,300.00 -
- Besi kanal kg - 8,340.00 -
- Besi balk kg 26,400.00 -
- Besi plate kg 16.00 7,350.00 117,600.00
- Besi plate strip kg - 7,820.00 -
- Besi beton kg - 5,600.00 -
-Pipa kg 9,250.00 -
117,600.00

2. Bahan bantu kontruksi % 0.10 117,600.00 11,760.00

3. Bahan dikerjakan mesin


- Besi bulat st 42 kg -
- Besi bulat st 60 kg -
-Bronze kg -
- Besi cor kg -
- Baja cor ps -
-

4. Bahan bahan lain :


- Mur Baut 1/2",5/8",7/8" kg 2.00 12,900.00 25,800.00
- Paku keling 3/4",5/8",7/8" kg 4.00 9,800.00 39,200.00
- Nipple bh 3,000.00 -
- Splite pen bh 1.00 31,300.00 31,300.00
- Gembok bh 1.00 12,900.00 12,900.00
- Drucklager kecil/besar bh 423,500.00 -
- Seal bh -
- Kayu jati m3 3,190,000.00 -
- Na F + ring bh 110,000.00 -

109,200.00

II ONGKOS KERJA
- Ongkos kerja konst kg 16.00 1,300.00 20,800.00
- Ongkos kerja mesin kg - 6,400.00 -
- Ongkos kerja kayu m3 510,000.00 -
- Sandblasting & cat m2 2.86 57,000.00 163,270.80
- Pengecatan tanpa sandbl m2 28,500.00 -
184,070.80

III PEMASANGAN : kg 15.00 1,100.00 16,500.00


IV PEMBONGKARAN : kg 600.00 -
V TRANSPORT : kg 15.00 600.00 9,000.00
25,500.00
Sub Total 448,130.80

VI Jumlah Harga 448,130.80


VII Harga satuan pekerjaan per-buah 448,000.00

Você também pode gostar