Escolar Documentos
Profissional Documentos
Cultura Documentos
TYPE C 1
PROYEK :
DAERAH IRIGASI : Selowongko (DAM Selowongko, Pintu Intake)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.20
h = 2.50
I. BAHAN H' = 4.00
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C- 1
PROYEK :
DAERAH IRIGASI : Selowongko (DAM Selowongko, Pintu Intake)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan
URAIAN PEKERJAAN : Engkol Tidak Ada B = 1.20 m
h = 2.50 m
H' = 4.00 m
Harga
No. Macam Pekerjaan Satuan Kuantitas Satuan Jumlah
( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 -
- Besi kanal Kg 12,500.00 -
- Besi balk Kg 30,000.00 -
- Besi plate Kg 7.00 12,500.00 87,500.00
- Besi plate strip Kg 0.00 12,500.00 -
- Besi beton Kg 0.00 12,500.00 -
-Pipa Kg 0.00 12,500.00 -
87,500.00
136,000.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin Kg 0.00 21,200.00 -
- Ongkos kerja kayu M3 510,000.00 -
- Sandblasting & cat M2 0.00 57,000.00 -
- Pengecatan tanpa sand M2 0.00 36,000.00 -
21,000.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 1
PROYEK :
DAERAH IRIGASI : Paras (PA BPR 1, Pintu Spey)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.50
I. BAHAN H' = 2.00
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C- 1
PROYEK :
DAERAH IRIGASI : Paras (PA BPR 1, Pintu Spey)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan
URAIAN PEKERJAAN : Pangkon & Kuningan Hilang B = 1.0 m
H = 1.5 m
H' = 2.0 m
Harga
No. Macam Pekerjaan Satuan Kuantitas Satuan Jumlah
( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 30.00 12,500.00 375,000.00
- Besi kanal Kg 12,500.00 -
- Besi balk Kg 30,000.00 -
- Besi plate Kg 0.00 12,500.00 -
- Besi plate strip Kg 0.00 12,500.00 -
- Besi beton Kg 0.00 12,500.00 -
-Pipa Kg 0.00 12,500.00 -
375,000.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 30.00 3,000.00 90,000.00
- Ongkos kerja mesin Kg 10.00 21,200.00 212,000.00
- Ongkos kerja kayu M3 510,000.00 -
- Sandblasting & cat M2 57,000.00 -
- Pengecatan tanpa sand M2 0.00 36,000.00 -
302,000.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 1
PROYEK :
DAERAH IRIGASI : Sindupati
LO KAS I : PA DAM Sindupati ( Intake Ki )
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.50
I. BAHAN H' = 5.00
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C- 1
PROYEK :
DAERAH IRIGASI : Sindupati
LO KAS I : PA DAM Sindupati ( Intake Ki )
CABANG DINAS PENGAIRAN : Kejayan
URAIAN PEKERJAAN : Daun Pintu Keropos ( Bocor ) B = 1.0 m
H = 1.5 m
H' = 5.0 m
Harga
No. Macam Pekerjaan Satuan Kuantitas Satuan Jumlah
( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 -
- Besi kanal Kg 12,500.00 -
- Besi balk Kg 30,000.00 -
- Besi plate Kg 141.00 12,500.00 1,762,500.00
- Besi plate strip Kg 0.00 12,500.00 -
- Besi beton Kg 0.00 12,500.00 -
-Pipa Kg 0.00 12,500.00 -
1,762,500.00
284,900.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 141.00 3,000.00 423,000.00
- Ongkos kerja mesin Kg 0.00 21,200.00 -
- Ongkos kerja kayu M3 510,000.00 -
- Sandblasting & cat M2 57,000.00 -
- Pengecatan tanpa sand M2 16.23 36,000.00 584,208.00
1,007,208.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 1
PROYEK :
DAERAH IRIGASI : Gedangan
LO KAS I : PA DAM Gedangan ( Intake Ka )
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.40
h = 1.30
I. BAHAN H' = 2.40
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C- 1
PROYEK :
DAERAH IRIGASI : Gedangan
LO KAS I : PA DAM Gedangan ( Intake Ka )
CABANG DINAS PENGAIRAN : Kejayan
URAIAN PEKERJAAN : Tidak Bisa Dioperasikan B = 1.40 m
( Daun Rusak Berat ) H = 1.30 m
H' = 2.40 m
Harga
No. Macam Pekerjaan Satuan Kuantitas Satuan Jumlah
( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 -
- Besi kanal Kg 12,500.00 -
- Besi balk Kg 30,000.00 -
- Besi plate Kg 167.00 12,500.00 2,087,500.00
- Besi plate strip Kg 0.00 12,500.00 -
- Besi beton Kg 0.00 12,500.00 -
-Pipa Kg 0.00 12,500.00 -
2,087,500.00
347,500.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 167.00 3,000.00 501,000.00
- Ongkos kerja mesin Kg 0.00 21,200.00 -
- Ongkos kerja kayu M3 510,000.00 -
- Sandblasting & cat M2 57,000.00 -
- Pengecatan tanpa sand M2 13.82 36,000.00 497,664.00
998,664.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 1
PROYEK :
DAERAH IRIGASI : Gedangan
LO KAS I : PA DAM Gedangan ( Spey Ka )
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.40
h = 1.40
I. BAHAN H' = 2.40
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C- 1
PROYEK :
DAERAH IRIGASI : Gedangan
LO KAS I : PA DAM Gedangan ( Spey Ka )
CABANG DINAS PENGAIRAN : Kejayan
URAIAN PEKERJAAN : Tidak Bisa Dioperasikan B = 1.4 m
( Daun Rusak Berat ) H = 1.4 m
H' = 2.4 m
Harga
No. Macam Pekerjaan Satuan Kuantitas Satuan Jumlah
( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 -
- Besi kanal Kg 12,500.00 -
- Besi balk Kg 30,000.00 -
- Besi plate Kg 180.00 12,500.00 2,250,000.00
- Besi plate strip Kg 0.00 12,500.00 -
- Besi beton Kg 0.00 12,500.00 -
-Pipa Kg 0.00 12,500.00 -
2,250,000.00
347,500.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 180.00 3,000.00 540,000.00
- Ongkos kerja mesin Kg 0.00 21,200.00 -
- Ongkos kerja kayu M3 510,000.00 -
- Sandblasting & cat M2 57,000.00 -
- Pengecatan tanpa sand M2 14.12 36,000.00 508,392.00
1,048,392.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 1
PROYEK :
DAERAH IRIGASI : Ngantungan
LO KAS I : PA Ngantungan ( Spey Ki )
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.20
h = 2.75
I. BAHAN H' = 4.90
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C- 1
PROYEK :
DAERAH IRIGASI : Ngantungan
LO KAS I : PA Ngantungan ( Spey Ki )
CABANG DINAS PENGAIRAN : Kejayan
URAIAN PEKERJAAN : Daun Pintu Bocor B = 1.20 m
H = 2.75 m
H' = 4.90 m
Harga
No. Macam Pekerjaan Satuan Kuantitas Satuan Jumlah
( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 -
- Besi kanal Kg 12,500.00 -
- Besi balk Kg 30,000.00 -
- Besi plate Kg 307.00 12,500.00 3,837,500.00
- Besi plate strip Kg 0.00 12,500.00 -
- Besi beton Kg 0.00 12,500.00 -
-Pipa Kg 0.00 12,500.00 -
3,837,500.00
347,500.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 307.00 3,000.00 921,000.00
- Ongkos kerja mesin Kg 0.00 21,200.00 -
- Ongkos kerja kayu M3 510,000.00 -
- Sandblasting & cat M2 57,000.00 -
- Pengecatan tanpa sand M2 20.47 36,000.00 736,884.00
1,657,884.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 1
PROYEK :
DAERAH IRIGASI : Ngantungan
LO KAS I : PA Ngantungan ( Spey Ki )
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.20
h = 2.75
I. BAHAN H' = 4.90
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C- 1
PROYEK :
DAERAH IRIGASI : Ngantungan
LO KAS I : PA Ngantungan ( Spey Ki )
CABANG DINAS PENGAIRAN : Kejayan
URAIAN PEKERJAAN : Daun Pintu Bocor B = 1.20 m
H = 2.75 m
H' = 4.90 m
Harga
No. Macam Pekerjaan Satuan Kuantitas Satuan Jumlah
( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 -
- Besi kanal Kg 12,500.00 -
- Besi balk Kg 30,000.00 -
- Besi plate Kg 307.00 12,500.00 3,837,500.00
- Besi plate strip Kg 0.00 12,500.00 -
- Besi beton Kg 0.00 12,500.00 -
-Pipa Kg 0.00 12,500.00 -
3,837,500.00
347,500.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 307.00 3,000.00 921,000.00
- Ongkos kerja mesin Kg 0.00 21,200.00 -
- Ongkos kerja kayu M3 510,000.00 -
- Sandblasting & cat M2 57,000.00 -
- Pengecatan tanpa sand M2 20.47 36,000.00 736,884.00
1,657,884.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA BSW. 13 Ka ( sadap )
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 0.50
I. BAHAN H' = 1.65
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA BSW. 13 Ka ( sadap )
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Engkol Tidak A h = 0,50 m
H' = 1,65 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 33.00 12,500.00 412,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
500,000.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 40.00 3,000.00 120,000.00
- Ongkos kerja mesin Kg 55.00 21,200.00 1,166,000.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 36,000.00 0.00
1,286,000.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA BSW. 13 Ki ( sadap )
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 0.80
h = 0.50
I. BAHAN H' = 1.65
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA BSW. 13 Ki ( sadap )
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Dratstang, Kuningan, Pangkon h = 0,50 m
& Kunci H' = 1,65 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 27.00 12,500.00 337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
425,000.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 34.00 3,000.00 102,000.00
- Ongkos kerja mesin Kg 55.00 21,200.00 1,166,000.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 36,000.00 0.00
1,268,000.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Wijeng
LO KAS I : PA Dam Wijeng ( Intake Ki )
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.30
I. BAHAN H' = 2.30
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Wijeng
LO KAS I : PA Dam Wijeng ( Intake Ki )
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Mur Kuningan Hilang h = 1,30 m
H' = 2,30 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
87,500.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin Kg 10.00 21,200.00 212,000.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 11.47 36,000.00 412,992.00
645,992.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI :
LO KAS I : PA Pasrepan ( Intake Ki )
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 0.80
h = 1.00
I. BAHAN H' = 2.30
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI :
LO KAS I : PA Pasrepan ( Intake Ki )
CABANG DINAS PENGAIRAN : Kejayan B = 0,80 m
URAIAN PEKERJAAN : Dratstang Hilang h = 1,00 m
H' = 2,30 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 8.00 12,500.00 100,000.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
100,000.00
316,500.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 8.00 3,000.00 24,000.00
- Ongkos kerja mesin Kg 52.00 21,200.00 1,102,400.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 9.84 36,000.00 354,312.00
1,480,712.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI :
LO KAS I : PA DAM Menggah ( Intake Ki )
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.50
I. BAHAN H' = 2.20
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI :
LO KAS I : PA DAM Menggah ( Intake Ki )
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Kuningan h = 1,50 m
H' = 2,20 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 8.00 12,500.00 100,000.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
100,000.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 8.00 3,000.00 24,000.00
- Ongkos kerja mesin Kg 10.00 21,200.00 212,000.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 11.75 36,000.00 422,928.00
658,928.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Sindupati
LO KAS I : PA BS. 12 ( Spey Ki )
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.00
I. BAHAN H' = 1.50
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Sindupati
LO KAS I : PA BS. 12 ( Spey Ki )
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Berat h = 1,00 m
H' = 1,50 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 267.00 12,500.00 3,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 39.00 12,500.00 487,500.00
- Besi beton Kg 9.00 12,500.00 112,500.00
-Pipa Kg 1.00 12,500.00 12,500.00
5,125,000.00
783,900.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 410.00 3,000.00 1,230,000.00
- Ongkos kerja mesin Kg 58.00 21,200.00 1,229,600.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 9.54 57,000.00 543,666.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
3,003,266.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Selowongko (PA Selowongko , Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.00
I. BAHAN H' = 2.00
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Selowongko (PA Selowongko , Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Engkol & Pintu Tdk Dapat Dioperasika h = 1,00 m
H' = 2,00 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
87,500.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin Kg 10.00 21,200.00 212,000.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
233,000.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw Ka.4 Ki , Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.20
I. BAHAN H' = 2.50
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw Ka.4 Ki , Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Engkol Tidak A h = 1,20 m
H' = 2,50 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
87,500.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin Kg 64.00 21,200.00 1,356,800.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 36,000.00 0.00
1,377,800.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 5 Ka.Ki , Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.20
I. BAHAN H' = 2.50
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 5 Ka.Ki , Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Engkol Tidak A h = 1,20 m
H' = 2,50 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
87,500.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin Kg 64.00 21,200.00 1,356,800.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 36,000.00 0.00
1,377,800.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw 6 Ka. Ki , Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 0.70
h = 0.80
I. BAHAN H' = 2.50
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw 6 Ka. Ki , Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 0,70 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Engkol Tidak A h = 0,80 m
H' = 2,50 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
87,500.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin Kg 68.00 21,200.00 1,441,600.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 36,000.00 0.00
1,462,600.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw 10 Ka. Ki, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.00
I. BAHAN H' = 2.00
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw 10 Ka. Ki, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Engkol Tidak A h = 1,00 m
H' = 2,00 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
87,500.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin Kg 57.00 21,200.00 1,208,400.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 36,000.00 0.00
1,229,400.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw 2 Ka. Ki , Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.20
I. BAHAN H' = 2.50
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw 2 Ka. Ki , Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Engkol Tidak A h = 1,20 m
H' = 2,50 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 7.00 12,500.00 87,500.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
87,500.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin Kg 64.00 21,200.00 1,356,800.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 36,000.00 0.00
1,377,800.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Selowongko (PA BSW 4, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.00
I. BAHAN H' = 2.50
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Selowongko (PA BSW 4, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total h = 1,00 m
H' = 2,50 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 49.00 12,500.00 612,500.00
- Besi beton Kg 14.00 12,500.00 175,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,312,500.00
365,350.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 265.00 3,000.00 795,000.00
- Ongkos kerja mesin Kg 76.00 21,200.00 1,611,200.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 11.14 57,000.00 634,866.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
3,041,066.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 5, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.00
I. BAHAN H' = 2.50
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 5, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total h = 1,00 m
H' = 2,50 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 49.00 12,500.00 612,500.00
- Besi beton Kg 14.00 12,500.00 175,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,312,500.00
365,350.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 265.00 3,000.00 795,000.00
- Ongkos kerja mesin Kg 76.00 21,200.00 1,611,200.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 11.14 57,000.00 634,866.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
3,041,066.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Selowongko (PA Penguras Kaliputih, Pintu Pembuang)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.00
I. BAHAN H' = 2.50
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Selowongko (PA Penguras Kaliputih, Pintu Pembuang)
liputih, Pintu Pembuang) LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total h = 1,00 m
H' = 2,50 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 49.00 12,500.00 612,500.00
- Besi beton Kg 14.00 12,500.00 175,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,312,500.00
365,350.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 265.00 3,000.00 795,000.00
- Ongkos kerja mesin Kg 76.00 21,200.00 1,611,200.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 11.14 57,000.00 634,866.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
3,041,066.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 13, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.00
I. BAHAN H' = 2.50
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 13, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total h = 1,00 m
H' = 2,50 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 49.00 12,500.00 612,500.00
- Besi beton Kg 14.00 12,500.00 175,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,312,500.00
365,350.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 265.00 3,000.00 795,000.00
- Ongkos kerja mesin Kg 76.00 21,200.00 1,611,200.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 11.14 57,000.00 634,866.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
3,041,066.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Domas (PA BW 1, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.00
I. BAHAN H' = 2.00
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Domas (PA BW 1, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total/ Tidak Biasa Dioperasikan h = 1,00 m
H' = 2,00 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 44.00 12,500.00 550,000.00
- Besi beton Kg 12.00 12,500.00 150,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,225,000.00
362,875.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 258.00 3,000.00 774,000.00
- Ongkos kerja mesin Kg 67.00 21,200.00 1,420,400.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 10.34 57,000.00 589,266.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
2,783,666.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Domas (PA BW 2, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.00
I. BAHAN H' = 2.00
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Domas (PA BW 2, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total/ Tidak Biasa Dioperasikan h = 1,00 m
H' = 2,00 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 44.00 12,500.00 550,000.00
- Besi beton Kg 12.00 12,500.00 150,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,225,000.00
362,875.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 258.00 3,000.00 774,000.00
- Ongkos kerja mesin Kg 67.00 21,200.00 1,420,400.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 10.34 57,000.00 589,266.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
2,783,666.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Domas (PA BW 3, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.00
I. BAHAN H' = 2.00
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Domas (PA BW 3, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total/ Tidak Biasa Dioperasikan h = 1,00 m
H' = 2,00 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 44.00 12,500.00 550,000.00
- Besi beton Kg 12.00 12,500.00 150,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,225,000.00
362,875.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 258.00 3,000.00 774,000.00
- Ongkos kerja mesin Kg 67.00 21,200.00 1,420,400.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 10.34 57,000.00 589,266.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
2,783,666.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Domas (PA BW 4, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.00
I. BAHAN H' = 2.00
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Domas (PA BW 4, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total/ Tidak Biasa Dioperasikan h = 1,00 m
H' = 2,00 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 44.00 12,500.00 550,000.00
- Besi beton Kg 12.00 12,500.00 150,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,225,000.00
362,875.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 258.00 3,000.00 774,000.00
- Ongkos kerja mesin Kg 67.00 21,200.00 1,420,400.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 10.34 57,000.00 589,266.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
2,783,666.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 0.90
I. BAHAN H' = 2.10
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA BSW. 8c
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Kuningan & Kunci hilang h = 0,90 m
H' = 2,10 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 0.00 12,500.00 0.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 0.00 12,500.00 0.00
- Besi plate strip Kg 8.00 12,500.00 100,000.00
- Besi beton Kg 0.00 12,500.00 0.00
-Pipa Kg 0.00 12,500.00 0.00
100,000.00
136,000.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 8.00 3,000.00 24,000.00
- Ongkos kerja mesin Kg 10.00 21,200.00 212,000.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 0.00 57,000.00 0.00
- Pengecatan tanpa sand M2 10.28 36,000.00 370,080.00
606,080.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C 2
PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 13, Pintu Bang. Bagi)
LO KAS I :
CAB. DPU PENGAIRAN : Kejayan
PAKET PEKERJAAN :
B = 1.00
h = 1.00
I. BAHAN H' = 2.50
1. BAHAN KONSTRUKSI :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1 .
2.3. BESI COR (BLOCK) = 10.000 Kg
Wdp/Pintu/Grati 1 .
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C-2
PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 13, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Rusak Total h = 1,00 m
H' = 2,50 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas Satuan Harga
( Rp. ) ( Rp. )
I. BAHAN
1. Bahan konstruksi :
- Besi siku Kg 107.00 12,500.00 1,337,500.00
- Besi kanal Kg 12,500.00 0.00
- Besi balk Kg 30,000.00 0.00
- Besi plate Kg 94.00 12,500.00 1,175,000.00
- Besi plate strip Kg 49.00 12,500.00 612,500.00
- Besi beton Kg 14.00 12,500.00 175,000.00
-Pipa Kg 1.00 12,500.00 12,500.00
3,312,500.00
365,350.00
II ONGKOS KERJA
- Ongkos kerja konst Kg 265.00 3,000.00 795,000.00
- Ongkos kerja mesin Kg 76.00 21,200.00 1,611,200.00
- Ongkos kerja kayu M3 510,000.00 0.00
- Sandblasting & cat M2 11.14 57,000.00 634,866.00
- Pengecatan tanpa sand M2 0.00 36,000.00 0.00
3,041,066.00
Wdp/Pintu/Grati 1 .
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3
PAKET PEKERJAAN :
B = 0.60
h = 0.60
I. BAHAN H' = 1.50
1. BAHAN KONSTRUKSI :
0
= B x 2 x 9,66 = 11.592 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 91.963 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 5.796 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 10.240 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 9.756 Kg
Sub Total = 129.347 Kg
Sub Total x 1,1 = 142.281 Kg
1.2. BESI PLAT :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3
PROYEK :
DAERAH IRIGASI : Selowongko (PA SW 2 Te, Pintu Bang. Bagi)
W 2 Te, Pintu Bang. Bagi) LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 0,60 m
URAIAN PEKERJAAN : Engkol & Dratstang Rusak h = 0,60 m
H' = 1,50 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 6.00 12,500.00 75,000.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
75,000.00
136,000.00
II ONGKOS KERJA
- Ongkos kerja konst kg 6.00 3,000.00 18,000.00
- Ongkos kerja mesin kg 33.00 21,200.00 699,600.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 0.00 57,000.00 0.00
- Pengecatan tanpa sand m2 36,000.00 0.00
717,600.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3
PAKET PEKERJAAN :
B = 0.60
h = 0.60
I. BAHAN H' = 1.50
1. BAHAN KONSTRUKSI :
0
= B x 2 x 9,66 = 11.592 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 91.963 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 5.796 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 10.240 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 9.756 Kg
Sub Total = 129.347 Kg
Sub Total x 1,1 = 142.281 Kg
1.2. BESI PLAT :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3
PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 6, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 0,60 m
URAIAN PEKERJAAN : Stang Rusak, Engkol & h = 0,60 m
Mur Kuningan Hilang H' = 1,50 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 6.00 12,500.00 75,000.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
75,000.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst kg 6.00 3,000.00 18,000.00
- Ongkos kerja mesin kg 43.00 21,200.00 911,600.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 57,000.00 0.00
- Pengecatan tanpa sand m2 36,000.00 0.00
929,600.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3
PAKET PEKERJAAN :
B = 0.50
h = 0.60
I. BAHAN H' = 1.50
1. BAHAN KONSTRUKSI :
0
= B x 2 x 9,66 = 9.660 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 91.963 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 4.830 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 9.274 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 8.130 Kg
Sub Total = 123.857 Kg
Sub Total x 1,1 = 136.242 Kg
1.2. BESI PLAT :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3
PROYEK :
DAERAH IRIGASI : Selowongko (PA Sw 6 Ka Ki, Pintu Bang. Bagi)
w 6 Ka Ki, Pintu Bang. Bagi) LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 0,50 m
URAIAN PEKERJAAN : Stang Rusak, Engkol & h = 0,60 m
Mur Kuningan Hilang H' = 1,50 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 0.00 12,500.00 0.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
0.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst kg 0.00 3,000.00 0.00
- Ongkos kerja mesin kg 43.00 21,200.00 911,600.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 57,000.00 0.00
- Pengecatan tanpa sand m2 36,000.00 0.00
911,600.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3
PAKET PEKERJAAN :
B = 0.70
h = 0.80
I. BAHAN H' = 2.10
1. BAHAN KONSTRUKSI :
0
= B x 2 x 9,66 = 13.524 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 115.147 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 6.762 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 11.206 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 11.382 Kg
Sub Total = 158.021 Kg
Sub Total x 1,1 = 173.823 Kg
1.2. BESI PLAT :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3
PROYEK :
DAERAH IRIGASI : Selowongko (PA BKB 3 & 4, Pintu Bang. Bagi)
KB 3 & 4, Pintu Bang. Bagi) LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 0,70 m
URAIAN PEKERJAAN : Stang Rusak, Engkol & h = 0,80 m
Mur Kuningan Hilang H' = 2,10 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 6.00 12,500.00 75,000.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
75,000.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst kg 6.00 3,000.00 18,000.00
- Ongkos kerja mesin kg 50.00 21,200.00 1,060,000.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 57,000.00 0.00
- Pengecatan tanpa sand m2 36,000.00 0.00
1,078,000.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3
PAKET PEKERJAAN :
B = 0.60
h = 0.60
I. BAHAN H' = 1.50
1. BAHAN KONSTRUKSI :
0
= B x 2 x 9,66 = 11.592 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 0.000 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 5.796 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 10.240 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 9.756 Kg
Sub Total = 37.384 Kg
Sub Total x 1,1 = 41.122 Kg
1.2. BESI PLAT :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3
PROYEK :
DAERAH IRIGASI : Selowongko (PA Sadap, Pintu Bang. Bagi)
LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 0,60 m
URAIAN PEKERJAAN : Rusak Total h = 0,60 m
H' = 1,50 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 41.00 12,500.00 512,500.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 28.00 12,500.00 350,000.00
- Besi plate strip kg 32.00 12,500.00 400,000.00
- Besi beton kg 9.00 12,500.00 112,500.00
-Pipa kg 1.00 12,500.00 12,500.00
1,387,500.00
421,300.00
II ONGKOS KERJA
- Ongkos kerja konst kg 111.00 3,000.00 333,000.00
- Ongkos kerja mesin kg 53.00 21,200.00 1,123,600.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 7.03 57,000.00 400,938.00
- Pengecatan tanpa sand m2 0.00 36,000.00 0.00
1,857,538.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3
PAKET PEKERJAAN :
B = 1.00
h = 0.35
I. BAHAN H' = 1.50
1. BAHAN KONSTRUKSI :
0
= B x 2 x 9,66 = 19.320 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 0.000 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 9.660 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 14.104 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 16.260 Kg
Sub Total = 59.344 Kg
Sub Total x 1,1 = 65.278 Kg
1.2. BESI PLAT :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3
PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA BSW 13 Ka kuarter
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Kunci h = 0,35 m
H' = 1,50 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 7.00 12,500.00 87,500.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
87,500.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin kg 45.00 21,200.00 954,000.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 0.00 57,000.00 0.00
- Pengecatan tanpa sand m2 8.12 36,000.00 292,356.00
1,267,356.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3
PAKET PEKERJAAN :
B = 0.60
h = 1.00
I. BAHAN H' = 2.65
1. BAHAN KONSTRUKSI :
0
= B x 2 x 9,66 = 11.592 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 0.000 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 5.796 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 10.240 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 9.756 Kg
Sub Total = 37.384 Kg
Sub Total x 1,1 = 41.122 Kg
1.2. BESI PLAT :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3
PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA Linggo ( Penguras )
CABANG DINAS PENGAIRAN : Kejayan B = 0,60 m
URAIAN PEKERJAAN : Kuningan Hilang h = 1,00 m
H' = 2,65 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 7.00 12,500.00 87,500.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
87,500.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin kg 10.00 21,200.00 212,000.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 0.00 57,000.00 0.00
- Pengecatan tanpa sand m2 9.43 36,000.00 339,336.00
572,336.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3
PAKET PEKERJAAN :
B = 0.60
h = 0.60
I. BAHAN H' = 2.25
1. BAHAN KONSTRUKSI :
0
= B x 2 x 9,66 = 11.592 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 0.000 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 5.796 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 10.240 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 9.756 Kg
Sub Total = 37.384 Kg
Sub Total x 1,1 = 41.122 Kg
1.2. BESI PLAT :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3
PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA Sek K. Boto ( BKB. 5 Ka Sadap )
CABANG DINAS PENGAIRAN : Kejayan B = 0,60 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Kunci h = 0,60 m
H' = 2,25 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 7.00 12,500.00 87,500.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
87,500.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin kg 53.00 21,200.00 1,123,600.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 0.00 57,000.00 0.00
- Pengecatan tanpa sand m2 8.23 36,000.00 296,424.00
1,441,024.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3
PAKET PEKERJAAN :
B = 0.60
h = 0.60
I. BAHAN H' = 2.25
1. BAHAN KONSTRUKSI :
0
= B x 2 x 9,66 = 11.592 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 0.000 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 5.796 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 10.240 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 9.756 Kg
Sub Total = 37.384 Kg
Sub Total x 1,1 = 41.122 Kg
1.2. BESI PLAT :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3
PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA Sek K. Boto ( BKB. 5 Ki Sadap )
CABANG DINAS PENGAIRAN : Kejayan B = 0,60 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Kunci h = 0,60 m
H' = 2,25 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 7.00 12,500.00 87,500.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
87,500.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin kg 53.00 21,200.00 1,123,600.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 0.00 57,000.00 0.00
- Pengecatan tanpa sand m2 8.23 36,000.00 296,424.00
1,441,024.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3
PAKET PEKERJAAN :
B = 1.00
h = 0.65
I. BAHAN H' = 2.25
1. BAHAN KONSTRUKSI :
0
= B x 2 x 9,66 = 19.320 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 0.000 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 9.660 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 14.104 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 16.260 Kg
Sub Total = 59.344 Kg
Sub Total x 1,1 = 65.278 Kg
1.2. BESI PLAT :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3
PROYEK :
DAERAH IRIGASI : Selowongko
LO KAS I : PA Sek K. Boto ( BKB. 5 Te Sadap )
CABANG DINAS PENGAIRAN : Kejayan B = 1,00 m
URAIAN PEKERJAAN : Dratstang, Kuningan & Kunci h = 0,65 m
H' = 2,25 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 7.00 12,500.00 87,500.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
87,500.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin kg 53.00 21,200.00 1,123,600.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 0.00 57,000.00 0.00
- Pengecatan tanpa sand m2 9.98 36,000.00 359,100.00
1,503,700.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3
PAKET PEKERJAAN :
B = 0.60
h = 0.60
I. BAHAN H' = 2.25
1. BAHAN KONSTRUKSI :
0
= B x 2 x 9,66 = 11.592 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 0.000 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 5.796 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 10.240 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 9.756 Kg
Sub Total = 37.384 Kg
Sub Total x 1,1 = 41.122 Kg
1.2. BESI PLAT :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3
PROYEK :
DAERAH IRIGASI : Paras
LO KAS I : PA Sek Jogorepuh Ki
CABANG DINAS PENGAIRAN : Kejayan B = 0,60 m
URAIAN PEKERJAAN : Rusak Ringan h = 0,60 m
H' = 2,25 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 0.00 12,500.00 0.00
- Besi plate strip kg 7.00 12,500.00 87,500.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
87,500.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst kg 7.00 3,000.00 21,000.00
- Ongkos kerja mesin kg 53.00 21,200.00 1,123,600.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 0.00 57,000.00 0.00
- Pengecatan tanpa sand m2 8.23 36,000.00 296,424.00
1,441,024.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 3
PAKET PEKERJAAN :
B = 0.50
h = 0.75
I. BAHAN H' = 4.25
1. BAHAN KONSTRUKSI :
0
= B x 2 x 9,66 = 9.660 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 0.000 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 4.830 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 9.274 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 8.130 Kg
Sub Total = 31.894 Kg
Sub Total x 1,1 = 35.083 Kg
1.2. BESI PLAT :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 3
PROYEK :
DAERAH IRIGASI : Ngantungan
LO KAS I : PA Ngantungan ( Intake Ki ) 2 pintu
CABANG DINAS PENGAIRAN : Kejayan B = 0,50 m
URAIAN PEKERJAAN : Daun pintu bocor h = 0,75 m
H' = 4,25 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 30.00 12,500.00 375,000.00
- Besi plate strip kg 0.00 12,500.00 0.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
375,000.00
200,500.00
II ONGKOS KERJA
- Ongkos kerja konst kg 30.00 3,000.00 90,000.00
- Ongkos kerja mesin kg 0.00 21,200.00 0.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 0.00 57,000.00 0.00
- Pengecatan tanpa sand m2 11.20 36,000.00 403,308.00
493,308.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
TYPE C - 5
PAKET PEKERJAAN :
B = 0.30
h = 0.70
I. BAHAN H' = 0.90
1. BAHAN KONSTRUKSI :
0
= B x 2 x 9,66 = 5.796 Kg
- Frame tegak (L.80.80.8) :
= (H' + 0,88) x 4 x 9,66 = 68.779 Kg
- Frame tengah (L.80.80.8) :
= B x 1 x 9,66 = 2.898 Kg
- Frame dasar (L.80.80.8) :
= (B + 0,46 ) x 1 x 9,66 = 7.342 Kg
- Penguat D. pintu (L.60.60.6) :
= B x 3 x 5,42 = 4.878 Kg
Sub Total = 89.693 Kg
Sub Total x 1,1 = 98.662 Kg
1.2. BESI PLAT :
1.5. P I P A = 1.000 Kg
Wdp/Pintu/Grati 1
PERHITUNGAN HARGA SATUAN PEMBUATAN PINTU AIR
TYPE C - 5
PROYEK :
DAERAH IRIGASI : Tengger (PA Sumber Gedang , Pintu Bang. Bagi)
ber Gedang , Pintu Bang. Bagi) LO KAS I :
CABANG DINAS PENGAIRAN : Kejayan B = 0,30 m
URAIAN PEKERJAAN : Daun Pintu Rusak h = 0,70 m
H' = 0,90 m
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN :
1. Bahan konstruksi :
- Besi siku kg 0.00 12,500.00 0.00
- Besi kanal kg 12,500.00 0.00
- Besi balk kg 30,000.00 0.00
- Besi plate kg 18.00 12,500.00 225,000.00
- Besi plate strip kg 0.00 12,500.00 0.00
- Besi beton kg 0.00 12,500.00 0.00
-Pipa kg 0.00 12,500.00 0.00
225,000.00
559,500.00
II ONGKOS KERJA
- Ongkos kerja konst kg 18.00 3,000.00 54,000.00
- Ongkos kerja mesin kg 0.00 21,200.00 0.00
- Ongkos kerja kayu m3 510,000.00 0.00
- Sandblasting & cat besi m2 4.93 57,000.00 280,896.00
- Pengecatan tanpa sand m2 0.00 36,000.00 0.00
334,896.00
Wdp/Pintu/Grati 1
PERHITUNGAN VOLUME PEMBUATAN PINTU AIR
SKIP
1. BAHAN KONSTRUKSI :
- Penarik (NP.5)
= (H' + 0,57 - 0,5 . H) x 1 x 5,59 = 8.497 Kg
- Pengunci (NP.10)
= 0,06 x 1 x 10,60 = 0.636 Kg
Sub Total = 9.133 Kg
Sub Total x 1,1 = 10.046 Kg
1.2. BESI PLAT :
Harga Jumlah
No. Macam Pekerjaan Satuan Kuantitas satuan Harga
( Rp.) ( Rp.)
I BAHAN:
1. Bahan konstruksi :
- Besi siku kg - 7,300.00 -
- Besi kanal kg - 8,340.00 -
- Besi balk kg 26,400.00 -
- Besi plate kg 16.00 7,350.00 117,600.00
- Besi plate strip kg - 7,820.00 -
- Besi beton kg - 5,600.00 -
-Pipa kg 9,250.00 -
117,600.00
109,200.00
II ONGKOS KERJA
- Ongkos kerja konst kg 16.00 1,300.00 20,800.00
- Ongkos kerja mesin kg - 6,400.00 -
- Ongkos kerja kayu m3 510,000.00 -
- Sandblasting & cat m2 2.86 57,000.00 163,270.80
- Pengecatan tanpa sandbl m2 28,500.00 -
184,070.80