Você está na página 1de 5

Optimization of Daily Operation of Micro Hydro

Power Plant Coupled with Compress Air Storage


Usama Bin Irshad*, M.S Javaid, Saifullah Shafiq, Md
Tahir Mumtaz
Shafiul Alam, M.A Abido Department of Electrical Engineering
Department of Electrical Engineering
National University of Science and Technology
King Fahd University of Petroleum and Minerals
Rawalpindi, Pakistan
Dhahran, Saudi Arabia
*usama.bin.irshad@gmail.com

Abstract—some areas lack access for electricity and grid An axial turbine functions in the way of a cascaded set of
extension may not be economically feasible solution. Thus off- shrouded windmills, is used to generate electricity directly
grid technologies are normally the suitable options. Among the from compress air. The blades of turbine act like blades of
off-grid technologies, micro hydro-power often matches local windmills and with pressure at 22.4 atm and
conditions. However, the main problem with these micro power cross-sectional area about 1.0 m2 flow speed of 1.75 m/s
plants is lack of significant storage capacity. This work proposes
the utilization of compress air storage to improve the run of the yields a power of about 20 MW [7], [8]. This air storage
river micro hydro power plant operational economic gains and capability allows storing energy in depleted gas reservoir in
also increases its reliability. A generic hourly optimization high water discharge period and to be used afterwards for
technique is developed to analyze the optimized daily operational filling the power gap, it also helps in fulfilling the
strategy followed by the hydro turbine and compressor motor commitment to meet local electricity demand. The proposed
equipment provided that the forecasted load and water flow are algorithm also integrates the option to import power from grid
available. The plan of hydro plant situated at Dor River in if needed. The ROR power plants can be installed after every
Pakistan is investigated and the optimization problem is solved 3 km on same river if conditions allow. In this formulation,
using AIMMS software. The obtained results are well presented
import power from grid means taking power from nearby
and discussed.
power plant.
Keywords— Rural electrification, optimization, scheduling of In the present analysis, the forecasted data of load and
micro hydro plant water discharge are determined. A daily operation scheme is
analyze by performing hourly based optimization. The
I. INTRODUCTION objective function is formulated in order to maximize the
Major population does not have the access to electricity due to daily profit of hydro plant. Active power output limits of
lack of latest techniques for power generation and that still hydro turbines and compressors storage limits are explicitly
depend on traditional systems. In 2010, more than 1.27 billion considered. Moreover, formulation also included the other
people in the world does not have access to electricity[1]. operational limitations like the storage capacity, maximum
Previously in order to increase electricity access in remote and minimum discharge.
areas is extension of existing grid [1]. But these remote areas The proposed optimization technique is used to find the
have less load demand and investing in to provide electricity daily optimal operational scheme of a combine hydro-
by grid extinction is not economically feasible [2],[3]. In these compressor power plant with a little compress air storage
cases, standalone systems become the suitable option. Off grid capacity while defining the amount of power generation from
or stand alone is installed near to remote areas and fuel by hydro and compressor. Hourly compressor power utilization
local resources. These kind of power station connect together and the compressed air storage level profiles are also
to form a separate small power system [4]. Among renewable- incorporated in the formulation. In this formulation, only
based power generation techniques, if nature allows then active power generation is taken into account. However,
micro hydro-power plant, utilizing small rivers, is perfect fit reactive power generation can also be added.
to supply power nearby areas [5], [6]. Moreover, Hydro In this paper, an hourly-based discretize optimization
Power (M&SHP) is a preferable option as it is environmental algorithm is proposed. The main purpose is to develop the
friendly and needs less maintenance and has negligible fueling best hourly operational strategy followed by hydro generation
cost. and compressed air storage, provided that the hourly
Run of the river (ROR) micro hydro power plant is consider forecasting of water discharge and local electricity demand is
in this work, generation through ROR is totally depending on available. The develop methodology has two main objectives:
the discharge of the water and it lacks the ability to store 1) to increase the daily hydro plant profit and 2) to meet the
water. On the day time, the quantity and flow of water local load by keeping the generated power within its limits.
decreases due to water evaporation and use by locals while Obtaining the optimum daily operation schedule will decrease
demand is high. At night, in the off-peak hours there is excess the daily operating cost of the power plant hence significantly
of water for generation but ROR does not have any reservoir increasing the overall profit.
to store that water. To overcome the issue of storage, this II. Optimization Algorithm
paper proposes to add a compressor facility with ROR hydro
power plant [5]. The model is proposed by considering the controlling of
power production by hydro turbines assuring that the required
power is being supplied to the load whatever the water flow
978-1-5090-4300-2/16/$31.00 ©2016 IEEE is. To improve the output of the hydro generation through run
of the river, an air compressor system consisting of a motor sto = sto + h η P −
( )
(3)
( )
that compresses the air from atmosphere and store it in
depleted gas reservoir at a pressure of 20 atm is added which
generates the electricity up to few megawatts.
The main focus of this work is to increase profit by P + P + P = Load (4)
optimizing the operation schedule. Problem is mathematically
formulated that maintained the power delivered to the local P ≤P ≤P (5)
load incorporating the limitation and operational restrictions Q ≤Q ≤Q (6)
of the hydro plant in a discrete period of 24-hours and gives
the operational strategy for the following hours. 0 ≤ sto ≤ sto (7)
P ≤P ≤P (8)
P ≤P ≤P (9)
P ≤P ≤P (10)
where:

P Hourly power delivered from hydro generator


P Hourly power imported from spot market
P Hourly power supplied from compressor
Π Price of power per hour
sto Net storage in storage tank
Fig. 1 Daily forecasted water discharge per hour in m /s Q Hourly discharge of water
A. Input Data The variables “a” and “b” in objective function are the
In order to calculate the daily operation schedule, the operating costs of the hydro and compressor generators and c
model needs some data as an input: forecasted local demand, is the tariff of import power, where a=0.8, b=10, c=30. Eq. (2)
estimated active power prices, forecasted water flow shows that a fraction of the available hydro power is right
discharges and desired output limit curves. The daily away delivered to the load during the specific interval whereas
forecasted data of water discharge of Dor River is taken from portion of generated power can be stored and delivered in
National Engineering Services Pakistan (Pvt.) limited subsequent interval. Sometimes, the energy generated from
(NESPAK) which is shown in Figure 1. The load of nearby hydro cannot meet the load. In (3), P is the energy that
village and COMSATS University (CIIT) is calculated by drives the motor to operate compressors.
survey which is shown in Figure 2. In the proposed formulation, initial and the final level of the
compressed air storage is described. Initially the storage level
is taken as zero. The initial value of storage capacity is
known, it is the final value of the previous day but the final
value of current day is unknown and final value of current day
is rely on the operational strategy of the next day.
Output powers generated by hydro and compressor turbines
remains in a given upper and lower range as shown in (5) and
(8). These output limits represent the operational limitations
of the power plant usually associated with the thermal limits
of the generators or stability constraints if imposed in a certain
period of operation. Eqs. (5) to (10) describe the operation
Fig. 2 Daily forecasted load per hour in MW limitations of the hydro-compressor generators, motor unit
and the storage capacity. The above formulation is the linear
B. Formulation optimization problems with 193 variables, 169 equality
constrains and 598 inequalities constrains. This problem is
In this approach, coordination between compressor turbine
solved using CPLEX 12.6.
(axial turbine) and hydro power plant is developed to
The generation through run of the river hydro power plant
minimize
the overall operating cost of the system while maximizing the is mainly depending on the discharge rate of water. Hydro
overall profit. So, an optimization problem was formulated generation also depend on the efficiency of the generator and
that maximized the profit through scheduling of output power turbines, the density of the water, and the height from where
delivered to the load. The outcome of this optimization is the the water falls on the turbine. The speed of water reduces in
operational strategy of compressor – hydro units for the next the penstock due to viscosity of water, friction of wall of
hours. The overall objective function is descried below penstock, and due to trash rack. The reduction of speed affects
power generation. In this paper, the reduction of speed is
Objective Function: measured in terms of height loss in meters. This research
develops a generic mathematical model of penstock to find the
max π ∗ Pgen − ((a ∗ Ph) + (b ∗ Pc) + (c ∗ Pi)) (1) velocity loss of water in terms of head losses. In (11), it is
s.t: clear that the density of water, gross head, gravitational
constant, discharge of water, reduction of velocity of water in
P =P +P +P (2) penstock and the efficiency of turbine and generator directly
affect the hydro generation. Eq. (11) is used to calculate the f = (14)
power generation for specific hourly discharge of water.

Where R is Reynolds number. When the flow is practically


The formula for generation through hydro is turbulent (Re>2000), the friction factor becomes more rely on
the relative roughness of the pipe inner surface and pipe
P = ⍴GQ H − (H + H ) η η (11) diameter [9]. Here R = 2000 so the friction factor f is 0.032.
A screen is used at the entry of both pressure pipes to avoid
Where the entrance of floating debris. The flow of water through the
rack is quantify as a head loss [10]. It can be calculated by
Kirschmer formula so the head loss in trash rack is described
H Gross head (m) in (15)
P Generation through Hydro in MW
ρ Density of Water h =K sin ∅ (15)
G Gravitational acceleration (9.81 m/s )
Q Discharge (m /s) where
H Head loss due to friction h Head loss (mm)
H Head loss due to trash rack t Bar thickness (mm)
η Turbine efficiency b Width between bars (mm)
η Generator efficiency V Approach velocity (m/s)
g Gravitational constant
In (11), the density of water is taken as 1,000 kg/m³ whereas φ Angle of inclination from horizontal surface
η ∗ η is 89.9%. In order to get accurate value of power
The thickness of bar has a major impact on head loss, in
generated from hydro in (11), the loss of velocity and pressure
this case t is 14 mm and the width between bar b is 1.5 mm.
of water in the penstock have to be considered. The loss of
The angle of inclination is 44 degrees from the horizontal
velocity of water is found in term of head loss using (12),
surface.
(14), and (15). After calculating the total head loss, now
Loses in head is also created due to geometric changes of
calculate the total power generation from specific discharge of
penstock such as bends, racks, elbows, joints, sudden
water. Other parameters are given in Table I.
contraction or enlargements of the penstock sections. In
C. Head loss in penstock: sudden contraction, head is loss due to the rise in velocity of
water flow and the high turbulence is produced by the
The height and the velocity of water give the potential
variation of structure of penstock and these losses can be
energy to it, which is known as its head. In (12), the
taken into consideration for large hydro power plants. After
energy head is the water flowing in a closed conduit of
calculating the head loss in penstock, power output can be
circular cross section, under a certain pressure, is given by
calculated for run of the river hydro power plant.
Bernoulli’s equation
III. Case Study
H =h + + (12) This paper describes the hourly operation plan of a run of
Where: the river hydro power plant situated at Dor River in Pakistan
H Total energy head (34°03'28.8"N 73°08'14.5"E). The forecasted load of
COMSATS University and village near it, forecasted
H Elevation from datum plane
discharge of water and electricity tariff is provided. The run of
P Pressure the river hydro plant has no reservoir to store water so this
γ Specific weight of water in kN/m kind of plant has the storage problem. This paper presents a
V Velocity of water model that has a compressed air storage facility that store
The sum of the potential energy h , pressure energy P /y and energy in the form of compressed air and generates electricity
the kinetic energy V /2 gives velocity head and its shown in when needed which helps in meeting demand during peak
hours. It provides the daily optimized operation schedule that
equation (12). Here specific weight of water is 9.807 kN/m
maximizes daily profit. The tariff from 1 am to 9 am is 120
and the total energy head H is 73.1 meters from datum. $/MWh, from 10 am to 7 pm it is 90 $/MWh and from 8 pm
In [9], Darcy and Weisbach applying the principle of to 1 am it is 130 $/MWh. Using the daily forecasted discharge
conservation of mass to volume of fluid in a pipe and derived of water per hour, the hourly generation can be calculated.
the following equation (13) for calculating loss of head due to The hourly power generation for the whole day is shown in
friction. Figure3.
h =f . (13)

h Head loss due to friction of penstock


f Friction factor
L Length of the penstock in meter
D Diameter of Penstock in meter
V Average velocity m/s
In a laminar flow, friction factor (f) is defined as (14)
Figure 3 Hourly hydro power generation
It can be seen from above figures that the generation is 2.6 by using all the sources and the daily profit will increase from
MW in first hour whereas the load is just 0.8MW. The extra 1290 $/day to 1629 $/day by optimize scheduling.
1.8 MW is stored in the compressor by using motors. There
are four motors each of 0.4 MW to store air at a pressure of 20
bar.
IV. Results
The upper and lower limits of generator and storage capacity
are described in Table 1. Here L is the length of penstock, D is
diameter of penstock and V is the velocity of water flow.
Using these parameters, the obtained results are shown below.

TABLE I. System parameters


P 3 MW
Fig. 6 Hourly power delivered to load in MW
P 2 MW
V 1.5 m/s The power delivered to the load in Figure 6 is same as the
L 110 meter forecasted load in Figure 2. The purpose of coupling storage
technique is to utilize the maximum amount of resources
sto 7 MW
available in that specific area.
D 0.5 meter
V. Conclusion
K 2.4
P 616.7 Pa A daily optimal scheduling technique is proposed to analyze
the optimal operational strategy to be adopted in a hydro –
compressor plant. The application of compress air storage
It can be seen from above figures that the maximum demand facility allows a significant rise in the hydro power plant
occurs in day time from hour 11 to hour 21 but during that profit on daily bases since the hydro energy is preferentially
time the discharge of water is low. delivered to the system. The extra hydro energy is used to
In Figure 4, shows the storage of compress air in the store compressed air during off-peak hours. The predicted
form of MW and Pcompressor is the output power generation daily annual profit of power plant is in-between 1529 to 1686
by compressor storage in MW. The generation in the first hour $/day for the analyzed case. The compressed air storage
is greater than load by 1.8 MW and that extra power is given ability also increases the controllability over the output power
to motor for storage or compress air.. and it helps in meeting the demand during peak hours.
Objectives that are accomplished so far are: 1) to meet the
load during peak hours, 2) to optimize the daily operational
schedule to maximize the profit, 3) to analyze that the storage
technique enhances profit of power plant and is compatible
with existing hydro power plant.
VI. REFERENCE
[1] S. C. Bhattacharyya, “Energy access programs and sustainable
development: A critical review and analysis,” Energy Sustain. Dev., vol.
16, no. 3, pp. 260–271, Sept. 2012.
[2] S. Mahapatra and S. Dasappa, “Rural electrification: Optimising the
choice between decentralised renewable energy sources and grid
extension,” Energy Sustain. Dev., vol. 16, no. 2, pp. 146–154, June
Fig. 4 Compressor storage and its output power per hour in MW 2012.
[3] D. P. Kaundinya, P. Balachandra, and N. H. Ravindranath, “Grid-
connected versus stand-alone energy systems for decentralized power—
The total power delivered to load is the summation of power A review of literature,” Renew. Sustain. Energy Rev., vol. 13, no. 8, pp.
supplied from hydro, compressor and import power. In Figure 2041–2050, Oct. 2009.
5, the daily optimized hourly operational schedule is shown. [4] M. A. Velasquez, C. Tautiva, and A. I. Cadena, “Technical and
The commitment of meeting demand will be fulfilled economic assessment of distributed generation to increase energy
coverage in rural areas,” Sixth IEEE/PES Transmission and
Distribution: Latin America Conference and Exposition (T&D-LA), pp.
1-8, 2012.
[5] O. Paish, “Small hydro power: technology and current status,” Renew.
Sustain. Energy Rev., vol. 6, no. 6, pp. 537–556, Dec. 2002.
[6] E. Martinot, A. Chaurey, D. Lew, J. R. Moreira, and N. Wamukonya,
“Renewable energy markets in developing countries,” Annu. Rev.
Energy Environ., vol. 27, no. 1, pp. 309–348, Nov. 2002.
[7] “Power generation directly from compressed air for exploiting wind and
solar power.” Jan. 2013.
[8] Ji-Hoon Park, Byeong-Jun Kim, Nak-Joong Lee and Young-Ho Lee,
“Numerical analysis on the closed tank of energy storage system during
discharge using CFD,” in ISFMFE - 6th International Symposium on
Fluid Machinery and Fluid Engineering, pp. 104 in 2004.
Figure 5: Output power of all sources in MW
[9] “The History of the Darcy - Weisbach Equation for Pipe Flow
Resistance .” [Online]. Available:
http://ascelibrary.org/doi/pdf/10.1061/40650(2003)
[10] S. P. Clark, J. M. Tsikata, and M. Haresign, “Experimental study of
energy loss through submerged trashracks,” J. Hydraul. Res., vol. 48,
no. 1, pp. 113–118, Feb. 2010.

Você também pode gostar