Activity Schedule for ESS-MRSS1 Relocation

Civil front
Sl No Description Qty Duration Start Date End Date Handing Over
(days) (R0) (R0) Dates
Civil activity schedule tantative
Transformer Foundation
1 Dismentalling of existing building 1 30 5.10.17 05.11.17
2 Trial trench of Transformer foundation 1 30 05.11.17 05.12.17
3 Clearance from six party 1 4 06.12.17 10.12.17
4 Excavation of Transformer foundation 1 10 11.12.17 22.12.17
5 foundation Raf 1 10 23.12.17 03.12.18
6 construction of foundation with rail fixing 2 30 03.12.18 6.1.18
7 construction of transformer trench 2 30 7.1.18 7.2.18
8 6.6kV foundation modification at MRSS 1 lot 60 15.01.18 17.03 18
9 NGBS civil and Core cutting 1 lot 30 18.3.18 18.4.18
10 33 kV Gantry trial trench 1 lot 30 18.4.18 18.5.18
Gantry foundation Excavation 1 lot 10 19.5.18 30.5.18
11 Gantry foundation Casting 1 lot 30 1.06.18 30.6.18
12 Barrication of Ganntry and transformer area 1 lot 30 30.6.18 30.7.18

Installation , Testing & Commissioning of 20 MVA Transformer


1 Shifing of 20 MVA Transformer from IM Section 2 6 26.04.18 04.05.18
2 Shifing of 6.6KV AIS from IM Section 10 6 05.05.18 12.05.18
3 Installation of 20 MVA Transformer Main Tank 2 4 14.05.18 17.05.18
4 Installation of Radiators for 20 MVA Transformer 20_ 12 18.05.18 31.05.18
5 Installation of Conservator Tank 2 4 01.06.18 05.06.18
6 Installation of MB for 20 MVA Transformer 2 2 06.06.18 07.06.18
7 Installation of NGR 2 2 8.06.18 9.06.18
8 Installation of Neutral Isolator/Knife switch 2 2 11.06.18 12.06.18
9 Making of Earthing Pit for Neutral Earthing 4 10 13.06.18 22.06.18
10 Making normal earth pits 4 10 23.06.18 2.07.18
Civil front
Duration Start Date End Date
Sl No Description Qty Handing Over
(days) (R0) (R0) Dates
11 Erection of Cable Trays for Trf Yard & Inside MRSS 1(lot) 3 04.07.18 06.07.18
12 Laying of Control Cable From GIS & AIS to 20 MVA Transformer 1(lot) 4 07.07.18 11.07.18
10 Laying of 33 KV Power Cable from GIS to 20MVA Trf 1(lot) 4 12.07.18 16.07.18
11 laying of 6.6 KV Power Cable from New AIS to 20 MVA trf 1(lot) 4 17.07.18 20.07.18
12 Laying of control cable from new AIS to MB 1(lot) 4 21.07.18 23.07.18
13 Laying of Neutral Cable from Earth stn to NGR & NGR To Trf 1(lot) 5 24.07.18 30.07.18
14 E/T of 33 KV cables at Trf End 12 4 01.08.18 04.08.18
15 E/T of 6.6 KV cables at Trf End 24 12 06.08.18 18.08.18
16 E/T of Control Cables at Trf End 1(lot) 6 20.0818 25.08.18
17 E/T of Neutral Cables 1(lot) 2 27.08.18 28.0818
18 Oil Filteration of 20 MVA Trf 2 15 29.08.18 1509.18
19 Installation/comissioning of N2/water spray system 2 30 15.09.18 20.10.18
21 Testing of 20 MVA Transformer 2 10 22.10.18 03.11.18
23 Readyness of Transformer 2 05.11.2018
Installation Testing & Commissioning of 6.6 KV AIS at MRSS
24 installation of base frame for 6.6 KV AIS 1set 15 10.03.18 25.03.18
25 Installation of 6.6 KV Switch Board at MRSS1 1set 30 26.03.18 30.04.18
26 Control cabling inside panel 1set 30 2.05.18 07.06.18
27 Installation of Remote control panel 1 set 7 08.06.18 15.06.18
28 Control cabling from RCP to AIS 1lot 7 16.06.18 23.06.18
29 Testing and comissioning of 6.6kV AIS 1lot 60 24.06.18 05.09.18
Integration testing of 33 kv GIS, Transformer and 6.6 kV AIS
30 Integration testing of 33 kv GIS, Transformer and 6.6 kV AIS 1set 15 05.11.18 21.12.18
Preparation of Report for submission to general testing,relay testing and 1set
31 S&T 7 22.11.18 29.11.18

32 Testing report Approval 1set 15 30.11.18 18.12.18


33 SSTG Approval 7 19.12.18 26.12.18
34 Charging of 33kv Cable and transformer#1 27.12.2017
35 Charging of 6.6kV board 28.12.18

Activity for NGBS feeder charging


installation of base frame for 6.6 KV AIS 1set 10 12.5.18 23.05.18
36 Installation of 6.6 KV Switch Board at MRSS1 1set 10 24.5.18 4.6.18
37 Control cabling inside panel 1set 5 5.6.18 10.5.18
38 Installation of Remote control panel 1 set 2 11.5.18 12.5.18
Civil front
Duration Start Date End Date
Sl No Description Qty Handing Over
(days) (R0) (R0) Dates
39 Control cabling from RCP to AIS 1lot 1 14.5.18
40 Testing and comissioning of 6.6kV AIS 1lot 3 15.05.18 17.5.18
41 tray fixing inside NGBS 1lot 15 18.5.18 5.06.18
42 Tray fixing in trench and gallery 1 lot 45 6.06.18 23.8.18
43 Cable laying/ clamping /dressing from MRSS to NGBS 1 lot 45 24.8.18 12.10.18
41 Shifing of LD#3 feeder at NGBS 1 6 14.10.18 20.6.18
ESS to MRSS load shifting and other works
1 the existing
Taking shutdown of one incomer to NGBS board from ESS, disconnecting 15 31.12.18
cable at both 14.1.19
ends and termination of newly laid cable from
charging of second incomer to the board in a similar manner. 15 15.01.19 31.1.19

Termination of old cables (Incomers to NGBS from ESS) to identified


41 outgoing breakers of NGBS board, taking shutdown of Ring plant 15 1.02.19 17.2.19
incoming feeders (one after another), jointing of said cables with
Ring plant cables (being laid during Augmentation scheme) in order
to energize Ring plant board from NGBS board
42 15 plant switchboard,
Rerouting of old cable (Incomer to Ring plant from ESS) for feeding Korf from Ring 17.2.19 5.3.19
termination of one end of the cable to identif
43 Taking shutdown of Jamipol feeder and termination of newly laid cable to the 3 5.3.19 8.3.19
Taking shutdown of MPDS-1 tie to 33kV ESS, disconnecting the
44 cable from 33kV switchboard at ESS and termination of the said 5 a 15.3.19
cable to the existing 33kV gantry at ESS for feeding PH #3
45 Taking shutdown of Golmuri line (L9/L10) 1 18.3.19 18.3.19
46 Erection of Gantry and dead End Tower 45 18.3.19 5.5.19
47 Laying of 33 kV power cable between 33kV gantry & 33kV GIS 5 18.3.19 23.3.19
48 Testing and comissioning L9/L10 5 5.5.19 10.5.19
Dismentalling of Existing l9/L10 tower from MRSS1 to ESS 90 11.5 19 11.8.19
vity Schedule for ESS-MRSS1 Relocation

Remarks

Transformer detail engg assignment required

on , Testing & Commissioning of 20 MVA Transformer


Delivery Expected date 25.04.2018

Rainy Season wil starts, ground work finishing earliar


Remarks

(4 per legx3phasex2 trf)

Durga Puja 18.10.2018

tion Testing & Commissioning of 6.6 KV AIS at MRSS


Followed by 6.6 kv civil job srl no 8
Delivery Expected date 26.03.2018

on testing of 33 kv GIS, Transformer and 6.6 kV AIS


Followed by Completion of transformer testing

Delivery Expected date 24.05.2018


Remarks

Followed by Sl No. 35
Replacement of 13.2 and 13.6 kV Switchboards at Power House # 3
Package Description RFQ Issued TR Release
Package -1 : 20 MVA
33/13.2kV transformer Plan 24.10.17 27.04.18
Actual 24.10.17 27.04.18
Package -2 : 13.2kV Double
bus-bar GIS Plan 12.10.17 11.01.18
Actual 12.10.17 11.01.18
Package-3 : Brk pnl for Neutral
& Reactor, NGR Plan 13.07.18 24.08.18
Actual
Package -4 : Generator 03.11.17 20.03.18
control desk, 13.2 kV CRP, 13.2
kV remote control panel,
Synchronization bracket

Plan
Actual 03.11.17 20.03.18
Package -5 : PH#3 control
room SCADA, RTU for LDC
connectivity along with
software , Modification in LDC
RTU
Plan 27.07.18 24.08.18
Actual
Package -6 : 33 kV (U/E) and
22kV (U/E) power & control
cables and cabling accessories

Plan
Actual
Package -7 : Battery & battery
charger, DCDB Plan 20.07.18 10.08.18
Actual
Package -8 : HVAC Plan
Actual
Package -9 : Civil package Plan 31.08.18 14.09.18
Actual
Package -10 : Structural
package Plan 31.08.18 14.09.18
Actual
Package -11 : Erection
package Plan 27.07.18 17.08.18
Package Description QTY
S.NO Package -1 : 20 MVA 33/13.2kV transformer 1

Sl No Description Qty

Civil activity schedule tantative


Transformer Foundation

1 Drawing release for civil 1

2 Trial trench of Transformer foundation 1


3 Clearance from six party 1
4 Excavation of Transformer foundation 1
5 foundation Raf 1
6 construction of foundation with rail fixing 2
7 construction of transformer trench 2
Installation , Testing & Commissioning of 20 MVA Transforme
Shifing of 20 MVA Transformer from IM Section 2
1

2 Shifing of 6.6KV AIS from IM Section 10


3 Installation of 20 MVA Transformer Main Tank 2
4 Installation of Radiators for 20 MVA Transformer 20_
5 Installation of Conservator Tank 2
6 Installation of MB for 20 MVA Transformer 2
7 Installation of NGR 2
Installation of Neutral Isolator/Knife switch 2

9 Making of Earthing Pit for Neutral Earthing 4


10 Making normal earth pits 4
Erection of Cable Trays for Trf Yard & Inside MRSS 1(lot
11 )
Laying of Control Cable From GIS & AIS to 20 MVA Transformer 1(lot
12 )
Laying of 33 KV Power Cable from GIS to 20MVA Trf 1(lot
10 )
laying of 6.6 KV Power Cable from New AIS to 20 MVA trf 1(lot
11 )
Laying of control cable from new AIS to MB 1(lot
12 )
Laying of Neutral Cable from Earth stn to NGR & NGR To Trf 1(lot
13 )
14 E/T of 33 KV cables at Trf End 12
E/T of 6.6 KV cables at Trf End 24
15

E/T of Control Cables at Trf End 1(lot


16 )
E/T of Neutral Cables 1(lot
17 )
18 Oil Filteration of 20 MVA Trf 2
Installation/comissioning of N2/water spray system 2
19

21 Testing of 20 MVA Transformer 2


23 Readyness of Transformer 2
RFQ Issued TR Release
24.10.17 27.04.18

Duration End Date Civil front Handing


Start Date (R0) Remarks
(days) (R0) Over Dates

tantative

trafo order date


30 10/1/2018 11/1/2018 in july
30 11/2/2018 12/2/2018
4 12/3/2018 12/7/2018
10 12/8/2018 12/18/2018
10 12/19/2018 12/29/2018
30 12/30/2018 1/29/2019
30 1/30/2019 3/1/2019
oning of 20 MVA Transformer
Delivery
6 26.04.18 04.05.18 Expected date
25.04.2018

6 05.05.18 12.05.18
4 14.05.18 17.05.18
12 18.05.18 31.05.18
4 01.06.18 05.06.18
2 06.06.18 07.06.18
2 8.06.18 9.06.18
Rainy Season wil
starts, ground
work finishing
2 11.06.18 12.06.18 earliar

10 13.06.18 22.06.18
10 23.06.18 2.07.18

3 04.07.18 06.07.18

4 07.07.18 11.07.18

4 12.07.18 16.07.18

4 17.07.18 20.07.18

4 21.07.18 23.07.18

5 24.07.18 30.07.18
4 01.08.18 04.08.18
(4 per
12 06.08.18 18.08.18 legx3phasex2 trf)

6 20.0818 25.08.18

2 27.08.18 28.0818

15 29.08.18 1509.18
Durga Puja
30 15.09.18 20.10.18 18.10.2018
10 22.10.18 03.11.18
05.11.2018
Sl No Description

Civil activity schedule tantative


A Transformer Foundation
1 Drawing release for civil
2 Trial trench of Transformer foundation
3 Clearance from six party
4 Excavation of Transformer foundation
5 foundation Raft
6 construction of foundation with rail fixing
7 construction of transformer trench
B Installation , Testing & Commissioning of 20 MVA Transformer
1 Shifting of 20 MVA Transformer from IM Section
2 Shifting of radiator, NGR ,MB ,  isolator etc
3 Installation of 20 MVA Transformer Main Tank
4 Installation of Radiators for 20 MVA Transformer
5 Installation of Conservator Tank
6 Installation of MB for 20 MVA Transformer
7 Installation of NGR
8 Installation of Neutral Isolator/Knife switch
9 Making of Earthing Pit for Neutral Earthing
10 Making normal earth pits
11 Erection of Cable Trays for Trf  
12 Laying of Control Cable From GIS & AIS to 20 MVA Transformer
13 Laying of 13.2  Power Cable from GIS to 20MVA Trf
14 laying of 33   KV Power Cable from trafo to 33 KV breaker
15 Laying of control cable related to trafo
16 Laying of Neutral Cable from Earth stn to NGR & NGR To Trf
17 E/T of 33 KV cables at Trf End
18 E/T of13.2  cables at Trf End
19 E/T of Control Cables at Trf End
20 E/T of Neutral Cables
21 Oil Filteration of 20 MVA Trf
22 Installation/comissioning of N2/water spray system
23 Testing of 20 MVA Transformer
24 Readyness of Transformer
C Erection ,testing & commissioing activities on 13.2 KV GIS panels
1 preparation & checking  of cut out for GIS
2 shifting of base frame for GIS
3 installtion of baseframe for GIS
4 shifting of GIS  panel at floor
5 position of all panels at baseframe 
6 physical connection of GIS bay
7 BOM checking 
8 interconnection of GIS bay
9 control & power cable laying & termination
10 CT's testing 
11 CB testing ­ 
12 Elect & Mech operations test on CB,Isolator & E/S
13 Elect scheme , various Interlocks functionality checking
14 main busbar contact resistance , Hi­pot test 
15 VT's testing ( line & bus VT's )
16 commissioning checks
D Erection ,testing & commissioing activities for generator control desk & Sync braket
1 Unloading from lorry  & shifting of Panels in C&R 
Removal of old unused panels
2 Panel Room
3 Removal of Packing,Physical inspection & Removal of gland plate & making hole for glanding 
4 Erection of CR Panel on foundation & & fixing 
5 cable laying & termination
6 Terminal Tightness
7 Control & Protectio circuit Checking
8 Relay testing secondary injection & Primary Injection
9 Relat Coordination
10 Pre commissioning checks
E Erection ,testing & commissioing activities for CRP panels
Unloading from lorry  & shifting of Panels in C&R 
1 Panel Room
2 Removal of Packing,Physical inspection & Removal of gland plate & making hole for glanding 
3 Erection of CR Panel on foundation & & fixing 
4 cable laying & termination
5 Terminal Tightness
6 Control & Protectio circuit Checking
7 Relay testing secondary injection & Primary Injection
8 Relat Coordination
9 Pre commissioning checks
F Erection ,testing & commissioing activities for battery bank & chrager
Battery bank
1 shifting of battery bank cell & mounting frame to fdn
2 erection of battery bank stand
3 erection of battery bank cell
4 interconnection of cell to form battery bank,terminal tightness & application of petrolium jelly
5 pre commissioning test
Battery charger
1 Unloading from lorry  & shifting of battery Charger in Panel Room.
2 Removal of Packing,Physical inspection & Removal of gland plate & making hole for glanding &
3 Erection of battery Charger on channel &  fixing. 
4 Terminal Tightness.
5 operational check & Load test of Charger
6 Pre commissioning checks
220V DC distribution board (DCDB)
1 Fixing & grouting of  Base Channel for DCDB  Mounting
Unloading from lorry  & shifting of DCDB
2 Panel Room.
3 Removal of Packing,Physical inspection & Removal of gland plate & making hole for glanding &
4 Erection of DCDB Panel on channel &  fixing. 
5 Earthing of  Panels at Two points.
6 Terminal Tightness.
7 Pre commissioning checks
G Erection ,testing & commissioing activities for scada & RTU
Unloading from lorry  & shifting of Panels in 
1 Panel Room
2 Removal of Packing,Physical inspection & Removal of gland plate & making hole for glanding 
3 Erection of Panel on foundation  & fixing 
4 cable laying & termination
5 Terminal Tightness
6 Control & Protectio circuit Checking
7 panel power up
8 FO cable checkinh
9 Pre commissioning checks
10 software development
11 software checking
H Erection ,testing & commissioing activities for HVAC
Unloading panel from lorry  & shifting of Panels in 
1 Panel Room
2 Removal of Packing,Physical inspection & Removal of gland plate & making hole for glanding 
3 Erection of Panel on foundation  & fixing 
4 cable laying & termination
5 Terminal Tightness
6 Control & Protectio circuit Checking
7 panel power up
8 AHU erection
9 duct erection
10 testing
11 Pre commissioning checks
12 charing
Duration
Qty (days)

1 30 trafo order date in july


1 30
1 4
1 10
1 10
2 30
2 30

1 3
1 2
2 4
10 6
1 2
1 2
1 2
1 1
4 10
4 10
1(lot) 30
1(lot) 8
1(lot) 8
1(lot) 20
1(lot) 15
1(lot) 5
6 4
12 8
1(lot) 6
1(lot) 2
1 7
1 8
1 6
1 2
no. of da date
5
3
5
2
8
8
5
8
60
8
5
6
8
8
8
5
no. of da date
20
6
5
5
30
6
15
15
15
10
no. of da date
6
5
5
30
6
15
15
15
10
no. of da date

5
5
6
6
7

3
5
5
5
5
5

2
2
3
5
2
5
5
no. of da date
15
5
5
30
6
15
15
15
10
25
15
no. of da date
10
5
5
30
6
15
15
30
30
15
10
10