Civil front
Sl No Description Qty Duration Start Date End Date Handing Over
(days) (R0) (R0) Dates
Civil activity schedule tantative
Transformer Foundation
1 Dismentalling of existing building 1 30 5.10.17 05.11.17
2 Trial trench of Transformer foundation 1 30 05.11.17 05.12.17
3 Clearance from six party 1 4 06.12.17 10.12.17
4 Excavation of Transformer foundation 1 10 11.12.17 22.12.17
5 foundation Raf 1 10 23.12.17 03.12.18
6 construction of foundation with rail fixing 2 30 03.12.18 6.1.18
7 construction of transformer trench 2 30 7.1.18 7.2.18
8 6.6kV foundation modification at MRSS 1 lot 60 15.01.18 17.03 18
9 NGBS civil and Core cutting 1 lot 30 18.3.18 18.4.18
10 33 kV Gantry trial trench 1 lot 30 18.4.18 18.5.18
Gantry foundation Excavation 1 lot 10 19.5.18 30.5.18
11 Gantry foundation Casting 1 lot 30 1.06.18 30.6.18
12 Barrication of Ganntry and transformer area 1 lot 30 30.6.18 30.7.18
Remarks
Followed by Sl No. 35
Replacement of 13.2 and 13.6 kV Switchboards at Power House # 3
Package Description RFQ Issued TR Release
Package -1 : 20 MVA
33/13.2kV transformer Plan 24.10.17 27.04.18
Actual 24.10.17 27.04.18
Package -2 : 13.2kV Double
bus-bar GIS Plan 12.10.17 11.01.18
Actual 12.10.17 11.01.18
Package-3 : Brk pnl for Neutral
& Reactor, NGR Plan 13.07.18 24.08.18
Actual
Package -4 : Generator 03.11.17 20.03.18
control desk, 13.2 kV CRP, 13.2
kV remote control panel,
Synchronization bracket
Plan
Actual 03.11.17 20.03.18
Package -5 : PH#3 control
room SCADA, RTU for LDC
connectivity along with
software , Modification in LDC
RTU
Plan 27.07.18 24.08.18
Actual
Package -6 : 33 kV (U/E) and
22kV (U/E) power & control
cables and cabling accessories
Plan
Actual
Package -7 : Battery & battery
charger, DCDB Plan 20.07.18 10.08.18
Actual
Package -8 : HVAC Plan
Actual
Package -9 : Civil package Plan 31.08.18 14.09.18
Actual
Package -10 : Structural
package Plan 31.08.18 14.09.18
Actual
Package -11 : Erection
package Plan 27.07.18 17.08.18
Package Description QTY
S.NO Package -1 : 20 MVA 33/13.2kV transformer 1
Sl No Description Qty
tantative
6 05.05.18 12.05.18
4 14.05.18 17.05.18
12 18.05.18 31.05.18
4 01.06.18 05.06.18
2 06.06.18 07.06.18
2 8.06.18 9.06.18
Rainy Season wil
starts, ground
work finishing
2 11.06.18 12.06.18 earliar
10 13.06.18 22.06.18
10 23.06.18 2.07.18
3 04.07.18 06.07.18
4 07.07.18 11.07.18
4 12.07.18 16.07.18
4 17.07.18 20.07.18
4 21.07.18 23.07.18
5 24.07.18 30.07.18
4 01.08.18 04.08.18
(4 per
12 06.08.18 18.08.18 legx3phasex2 trf)
6 20.0818 25.08.18
2 27.08.18 28.0818
15 29.08.18 1509.18
Durga Puja
30 15.09.18 20.10.18 18.10.2018
10 22.10.18 03.11.18
05.11.2018
Sl No Description
1 3
1 2
2 4
10 6
1 2
1 2
1 2
1 1
4 10
4 10
1(lot) 30
1(lot) 8
1(lot) 8
1(lot) 20
1(lot) 15
1(lot) 5
6 4
12 8
1(lot) 6
1(lot) 2
1 7
1 8
1 6
1 2
no. of da date
5
3
5
2
8
8
5
8
60
8
5
6
8
8
8
5
no. of da date
20
6
5
5
30
6
15
15
15
10
no. of da date
6
5
5
30
6
15
15
15
10
no. of da date
5
5
6
6
7
3
5
5
5
5
5
2
2
3
5
2
5
5
no. of da date
15
5
5
30
6
15
15
15
10
25
15
no. of da date
10
5
5
30
6
15
15
30
30
15
10
10