Rate Analysis- 4

Item No-14:- Pro. And fixing 50mmx50mmx6mm angle welded metal section with five horizontal lines G.I.
barbed wire fencing, weighting 9.38 kg per 100 mts including fixing concentrino razor blade
12 G wire loop of 610 mm dia on top of wall, applying priming coat and painting two coats
with necessary fixtures and hardware etc. complete as directed by Engineer-in-charge.
R.A.-4

For 3.0 m length of wall


(A) Angle section of 35mmx35mmx5mm (for 18.00 mt )
6 1.3 4.50 = 35.1 Kg
Kg/Rmt
5 % wastage = 1.76 Kg
36.86 Kg
36.86 Kg X 52.89 = 1949.26 Rs.
SOR-2015:16 Item No. 11.2A, Pg No. 125
For 3.0 mt = 324.88 Rs.
(B) Labour for welding ,febrication angle section and fixing barbed wire & Concentrino razor
blade wire at site complete
(M.R.) = 400.00 Rs.
© Two coats of oil painting etc complete

2 0.15 1.3 = 0.39 Smt

0.39 Smt X 55.18 = 21.52 Rs.


Sor 15-16 item no-19.7 Pno-158

(D) G.I. Barbed Wire


5 3.00 = 15.00 Rmt
For clamping L.S. = 0.50 Rmt
15.50 Rmt
5 % wastage = 0.78 Rmt
Total 16.28 Rmt
16.28 x 0.094 Kg/Rmt = 1.53 Kg
1.53 Kg x 68.00 = 104.03 Rs.
SOR, Basic Rate It.466, Pg 14
( E) Concentrino razor blade 12 g wire loop of 610mm dia
one loop (= 18' feet) wire cover 3.5 rmt of area at 3
3/3.5 = 0.857143 Rmt = 0.857 500 = 428.57 Rs
750.00 Rs/loop

Total = (A)+(B)+©+(D)+(E) = 1279.00 Rs.


Add for hardware pins etc L.S. (3 %) = 39.01 Rs.
Add for Electric charge (2 %) = 25.58 Rs.
Add 15% C.P. on (B), (D) ,(E) = 139.89 Rs.
(For 3.00 Mt) Total = 1483.48 Rs.
For 1 Rmt = 1483.48/3.0 = 494.49 Rs.
Say = 500.00 Rs/Rmt

Deputy Executive Engineer Executive Engineer