Piping unit rate 2019

Unit Rate for piping and structure CCK

Item Description Unit Price/unit


I001 Welding carbon steel pipe sch 40 DB 396.00
I002 Welding carbon steel pipe sch >= 80 DB 424.00
I003 Welding carbon steel pipe sch 160 DB 450.00
I004 Welding pipe SS 304 or 304L sch < = 40S DB 453.00
I005 Welding pipe SS 304 or 304L sch 80S DB 478.00
I006 Welding pipe SS 316 or 316L sch < = 40S DB 480.00
I007 Welding pipe SS 316 or 316L sch 80S DB 500.00
I008 Welding pipe SS 316Ti sch < = 40S DB 847.00
I009 Welding pipe SS 316Ti sch 80S DB 880.00
I010 Welding pipe SS 904L Alloy sch.160S DB 1,500.00
I011 Welding pipe SS 904L Alloy sch 80S DB 1,300.00
I012 Nickel pipe Ni ASTM B161 (N02200) sch.10S DB 1,300.00
I013 Nickel pipe Ni ASTM B161 (N02200) sch.40S DB 1,500.00
I014 Welding pipe SS C-22 Hastelloy sch < = 40S DB 1,500.00
I015 Welding pipe SS C-22 Hastelloy sch 80S DB 2,300.00
I016 Welding pipe Titanium B337 Gr.7 sch. 40S DB 3,250.00
I017 Welding pipe Titanium B337 Gr.7 sch. 10S DB 3,500.00
I018 Welding pipe 321H sch.80S DB 1,300.00
I019 Welding pipe Duplex A790 S31803, (2205) sch.40S DB 1,500.00
I020 Welding pipe Duplex A790 S31803, (2205) sch.80S DB 2,000.00
I021 Welding pipe Duplex A790 S31803, (2205) sch.160S DB 2,300.00
I022 Welding pipe Monel ASTM B165 (N04400) sch.40S DB 1,500.00
I023 Repair leak by Patching DB 3,500.00
I024 Thread joint for CS / Galv. Types with threading DB 350.00
I025 Thread joint for SS with threading DB 350.00
I026 Thread joint for all types and SS without threading DB 350.00
I027 Plastic pipe connect by glue DB.M 190.00
I028 Plastic pipe connect by welding DB.M 280.00
I029 Demolish pipe connection by flange DB.M 120.00
I030 Install pipe connection by flange DB.M 168.00
I031 Demolish existing pipe by Hot work cutting DB 190.00
I032 Demolish existing pipe by Cold work cutting DB 121.00
I033 Demolish flange and thread connection DB 121.00
I034 Demolish or install blind flange DB 121.00
I035 Install flange joint of Valve, Control Valve, etc. EA 300.00
I036 Conveying pipe SS 316L sch. < = 10S DB 650.00
I037 Welding all of U/G CS pipe (Exclude wrapping) DB 600.00
I038 Install tube pipe bending for steam tracing M 700.00
I039 CS Fab Blind Plate thick 10 mm size 1-4" PC 600.00
I040 CS Fab Blind Plate thick 10 mm size 6-10" PC 2,000.00
I041 CS Fab Blind Plate thick 10 mm size above 10-24" PC 2,000.00
I042 SS Fab Blind Plate thick 10 mm size 1-4" PC 1,200.00
I043 SS Fab Blind Plate thick 10 mm size 6-10" PC 3,500.00
I044 SS Fab Blind Plate thick 10 mm size above 10-24" PC 3,500.00
I045 CS Fab Spade Blind Plate thick 3 mm size 1-4" PC 300.00
I046 CS Fab Spade Blind Plate thick 3 mm size 6-10" PC 500.00
I047 CS Fab Spade Blind Plate thick 3 mm size above 10-24" PC 800.00
I048 SS Fab Spade Blind Plate thick 3 mm size 1-4" PC 600.00
I049 SS Fab Spade Blind Plate thick 3 mm size 6-10" PC 1,000.00
I050 SS Fab Spade Blind Plate thick 3 mm size above 10-24" PC 1,600.00
I051 CS welding plate or large diameter tank think 3 mm - 6 mm M 650.00
I052 CS welding plate or large diameter tank think 7 mm - 12 mm M 850.00
I053 CS welding plate or large diameter tank think 13 mm - 20 mm M 950.00
I054 SS welding plate or large diameter tank think 3 mm - 6 mm M 950.00
I055 SS welding plate or large diameter tank think 7 mm - 12 mm M 1,150.00
I056 SS welding plate or large diameter tank think 13 mm - 20 mm M 1,350.00
I057 Steel structure and platform Fab & install (mat by contractor) kg 130.00
I058 Steel structure and platform Fab only (mat by contractor) kg 90.00
I059 Steel structure and platform Fab & install (mat by VNT) kg 90.00
I060 Steel structure and platform Fab only (mat by VNT) kg 60.00
I061 Galvanized platform and pipe support kg 150.00
I062 Support of stainless steel (SS304) kg 323.00
Piping unit rate 2019

Unit Rate for piping and structure CCK

Item Description Unit Price/unit


I063 Support of stainless steel (SS316) kg 423.00
I064 Carbon Steel handrail of platform M 1,800.00
I065 Carbon Steel ladder M 2,000.00
I066 Carbon Steel ladder with cage side step M 2,500.00
I067 Swing door of ladder or platform EA 1,000.00
I068 Stair treaded EA 1,800.00
I069 New grating for platform kg 15.00
I070 Modify grating for platform kg 30.00
I071 Checker plate for platform CS kg 120.00
I072 Checker plate for platform SS kg 350.00
I073 Demolish steel structure for scrap(include transport) kg 20.00
I074 Demolish steel structure for re-use(include transport) kg 25.00
I075 Light weight CS structure Thk. <= 4.0mm kg 130.00
I076 Install and alignment for rotating equipment kg 28.00
I077 Demolish and move rotating equipment kg 15.00
I078 Install and Alignment static equipment < = 2,000 kg kg 28.00
I079 Install and Alignment static equipment 2,001 - 5,000 kg kg 25.00
I080 Install and Alignment static equipment > = 5,001 kg kg 20.00
I081 Demolish and move static equipment < = 2,000 kg kg 15.00
I082 Demolish and move static equipment 2,001- 5,000 kg kg 13.00
I083 Demolish and move static equipment > = 5,001 kg kg 12.00
I084 Hydro test pressure 0- 50 barg time 3,550.00
I085 Sand Blasting SA 2.5 M2 170.00
I086 Primer + Intermediate +Top Coat (250 micron) M 2
350.00
I087 Touch up&Top coat M2 90.00
I088 Sketch & Create ISO dwg for A3 size Sheet 800.00
I089 Sketch & Create details drawing of platform.,etc Sheet 600.00
I090 Sketch & Create ISO dwg for A3 size (correct existing ACAD file) Sheet 400.00
I091 Sketch & Create details drawing of platform.,etc (correct existing ACAD file) Sheet 300.00
I092 Rental hieb Truck 6 Wheels (Service in Rayong) Day 7,000.00
I093 Rental hieb Truck 6 Wheels (Service in Rayong) Haft Day 3,500.00
I094 Rental Generator (45 KVA) Day 2,000.00
I095 Rental Generator (125 KVA) Day 3,000.00
I096 Rental Generator (220 KVA) Day 5,500.00
I097 Rental Generator (250 KVA) Day 7,500.00
I098 SUPERVISOR NORMAL TIME H 250.00
I099 SUPERVISOR OVERTIME (NORMAL DAY AFTER 18:00 AFTER 18:00) H 375.00
I100 SUPERVISOR OVERTIME (SAT-SUN-HOLIDAY) H 500.00
I101 SUPERVISOR OVERTIME (SAT-SUN-HOLIDAY AFTER 8 HR.) H 750.00
I102 FOREMAN/QC NORMAL TIME H 190.00
I103 FOREMAN/QC OVERTIME (NORMAL DAY AFTER 18:00) H 285.00
I104 FOREMAN/QC OVERTIME (SAT-SUN-HOLIDAY) H 380.00
I105 FOREMAN/QC OVERTIME (SAT-SUN-HOLIDAY AFTER 8 HR.) H 570.00
I106 WELDER NORMAL TIME H 230.00
I107 WELDER OVERTIME (NORMAL DAY AFTER 18:00) H 345.00
I108 WELDER OVERTIME (SAT-SUN-HOLIDAY) H 460.00
I109 WELDER OVERTIME (SAT-SUN-HOLIDAY AFTER 8 HR.) H 690.00
I110 FITTER NORMAL TIME H 145.00
I111 FITTER OVERTIME (NORMAL DAY AFTER 18:00) H 217.50
I112 FITTER OVERTIME (SAT-SUN-HOLIDAY) H 290.00
I113 FITTER OVERTIME (SAT-SUN-HOLIDAY AFTER 8 HR.) H 435.00
I114 HELPER NORMAL TIME H 120.00
I115 HELPER OVERTIME NORMAL DAY AFTER 18:00) H 180.00
I116 HELPER OVERTIME (SAT-SUN-HOLIDAY) H 240.00
I117 HELPER OVERTIME (SAT-SUN-HOLIDAY AFTER 8 HR.) H 360.00
I118 FREE AMOUNT (confined space Add cost from unit rate 30%) PRT 1.00
I119 FREE AMOUNT (Material Procurement On top from actual price 15%) PRT 1.00
I120 FREE AMOUNT (Special item On top from actual price 15%) PRT 1.00
I121 FREE AMOUNT for minimum charge PRT 1.00
I122 FREE AMOUNT PRT 1.00