EIL/OWNER ID :

INSPECTION TEST PLAN


FOR
HV/LV SWITCHGEAR CONTRACTOR IDENTIFICATION

PROJECT: GGSR UNIT: LOCATION: BHATINDA PAGE 1 OF 1 REV :


VOLTAS

Accepted Stds : Applicable Specification, Codes, Contract Documents & Approved Drawing

INSPECTION AGENCY TYPE OF


S.NO. INSPECTION ACTIVITY LEGEND
VOLTAS EIL HMEL RECORD
1 Check the layout of base channels, levels, centre line
matching of base frames/ channels & ensure correct A WC S S
provision for grouting
2 Ensure proper handling of panels B WC S S
3 Check sequence wise (Starting from centre of bus duct
panel) Installation final levelling & bolting up of C WC S S
shipping section
4 Check main bus bar tightness with torque wrench,
cleaning, shrouding & box up, inter panel control D WC S S
wiring, fixing of loose accessories & wiring
5 Ensure the level of flooring for smooth opening of
E WC S S
panel doors & drawing out operation of breaker trolley
6 Check interchange abilities of CB, Relays & Modules F WC S S
7 Check continuity of earth bus & equipment earthing G WC H H
8 Check sealing of all spare entries H WC Rm Rm
9 Verify the correctness in accordance with the drawing
of all type of relays, control switches, meters & I WC S S
instruments, motor starters, fuses, space heaters etc.
10 TESTS
10.a Test CTs & PTs for polarity & ratio test (Wherever FORMAT
J WC Rw Rw NO
applicable)
10.b IR value of the power & control bus for LT switchgears, FORMAT
K WC Rw Rw NO
high pot test (For HT)
10.c Test protection relays & thermal overload relays with Shall be
developed at
secondary injection L WC Rm Rm site during
testing
VOLTAS EIL HMEL

Sign

Name
Date
EIL/OWNER ID :

INSPECTION TEST PLAN


FOR
HV/LV SWITCHGEAR CONTRACTOR IDENTIFICATION

PROJECT: GGSR UNIT: LOCATION: BHATINDA PAGE 1 OF 2 REV :


VOLTAS

INSPECTION AGENCY TYPE OF


S.NO. INSPECTION ACTIVITY LEGEND
EIL HMEL RECORD
10.d Test the functional schematics & interlocks M WC W W
10.e Test bus bar tightness with mV drop N WC W W
10.f Check breaker tripping , ammeter indications through
O WC W W
protective relays by primary injection
10.g Check the stability for REF & Diff protection schemes FORMET NO
P WC W W
by primary injection
10.h Check the phase sequence between bus sections &
Q WC W W
incomers
11 Set the relay parameters & settings R WC W W
12 Review of test & inspection documents S WC Rw Rw FORMAT NO
13 Activity completion report T WC HP HP