DETAILED CONSTRUCTION SCHEDULE Page

CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 1 of 33


Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J

CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 1089 03-Mar-18 02-Jul-20 -108 -88


PRELIMINARIES 1089 03-Mar-18 02-Jul-20 -88 -88

MILESTONE DATES 1089 03-Mar-18 02-Jul-20 -88 -88


CLX-Lag000 1 Delivery of ROW (First 7km) 0 0 0 Delivery of ROW (First 7km)
CLX-Lag000 2 Project Start 0 0 0 Project Start
CLX-Lag000 3 Delivery of ROW (Remaining 11km) 0 03-Mar-18 0 -61 Delivery of ROW (Remaining 11km)
CLX-Lag000 4 Project Finish 0 02-Jul-20 0 -88 Project Finish
GENERAL REQUIREMENTS 1089 03-Mar-18 02-Jul-20 -88 -88
FACILITIES FOR THE ENGINEER 1000 03-Mar-18 05-Apr-2 0 0 0
CLX-Lag000 5 Facili0es for the Engineers (Field Office, others) 1000 03-Mar-18 05-Apr-2 0 0 0 CLX-Lag000 5
CLX-Lag000 6 Facili0es for the Engineers (Purchase of Vehicles) 7 0 0
OTHER GENERAL REQUIREMENTS 1089 03-Mar-18 02-Jul-20 -88 -88
CLX-Lag000 7 Mobiliza0on 28 0 0
CLX-Lag000 8 Construc0on Health and Safety Requirements 1000 03-Mar-18 05-Apr-2 0 0 0 CLX-Lag000 8
CLX-Lag000 9 Environmental and Monitoring 1000 03-Mar-18 05-Apr-2 0 0 0 CLX-Lag000 9
CLX-Lag001 0 Traffic Management During Construc0on 1000 03-Mar-18 05-Apr-2 0 0 0 CLX-Lag001 0
CLX-Lag001 1 Temporary Detour Road Construc0on 1000 03-Mar-18 05-Apr-2 0 0 0 CLX-Lag001 1
CLX-Lag001 2 Project Billboards 1000 03-Mar-18 05-Apr-2 0 0 0 CLX-Lag001 2
CLX-Lag001 3 Demobiliza0on 44 20-May-2 0 02-Jul-20 0 -88 CLX-Lag001 3
CONSTRUCTION PHASE 821 03-Mar-18 19-May-2 0 -111 -88

STA 27+900.000 TO STA. 37+930.525 (10.03KM) 809 03-Mar-18 19-May-2 0 -27 -88
EARTHWORKS 642 03-Mar-18 04-Dec-19 -27 -88
Sta. 27 + 900.000 to Sta. 29 + 439.852 (WB16) 492 03-Mar-18 07-Jul-19 -27 -88
CLX-Lag001 4 Clearing & Grubbing 67 03-Mar-18 08-May-1 8 0 -61 CLX-Lag001 4
CLX-Lag001 5 Excava0on 98 01-Aug-18 06-Nov-18 0 -61 CLX-Lag001 5
CLX-Lag001 6 Subgrade Prepara0on 69 30-Apr-1 9 07-Jul-19 0 -88 CLX-Lag001 6
Sta. 29 + 509.852 (WB16) to Sta. 30 + 115.000 (WB17) 452 09-May-1 8 03-Aug-19 -27 -88
CLX-Lag001 7 Clearing & Grubbing 26 09-May-1 8 03-Jun-18 0 -61 CLX-Lag001 7
CLX-Lag001 8 Excava0on 30 07-Nov-18 06-Dec-18 0 -61 CLX-Lag001 8
CLX-Lag001 9 Subgrade Prepara0on 27 08-Jul-19 03-Aug-19 0 -88 CLX-Lag001 9
Sta. 30 + 140.000 (WB17) to Sta. 31 + 036.510 (EB9) 466 04-Jun-18 12-Sep-19 -27 -88
CLX-Lag002 0 Clearing & Grubbing 39 04-Jun-18 12-Jul-18 0 -61 CLX-Lag002 0
CLX-Lag002 1 Excava0on 42 07-Dec-18 17-Jan-19 0 -61 CLX-Lag002 1
CLX-Lag002 2 Subgrade Prepara0on 40 04-Aug-19 12-Sep-19 0 -88 CLX-Lag002 2
Sta. 31 + 071.510 (EB9) to Sta. 31 + 430.450 (WB18) 443 13-Jul-18 28-Sep-19 -27 -88
CLX-Lag002 3 Clearing & Grubbing 16 13-Jul-18 28-Jul-18 0 -61 CLX-Lag002 3
CLX-Lag002 4 Excava0on 21 18-Jan-19 07-Feb-19 0 -61 CLX-Lag002 4
CLX-Lag002 5 Subgrade Prepara0on 16 13-Sep-19 28-Sep-19 0 -88 CLX-Lag002 5
Sta. 31 + 491.550 (WB18) to Sta. 31+ 828.000 (WB19) 442 29-Jul-18 13-Oct-1 9 -27 -88
CLX-Lag002 6 Clearing & Grubbing 15 29-Jul-18 12-Aug-18 0 -61 CLX-Lag002 6

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 2 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag002 7 Excava0on 7 08-Feb-19 14-Feb-19 0 -61 CLX-Lag002 7
CLX-Lag002 8 Subgrade Prepara0on 15 29-Sep-19 13-Oct-1 9 0 -88 CLX-Lag002 8
Sta. 31 + 903.000 (WB19) to Sta. 33 + 025.279 (WB20) 479 13-Aug-18 04-Dec-19 -27 -88
CLX-Lag002 9 Clearing & Grubbing 49 13-Aug-18 30-Sep-18 0 -61 CLX-Lag002 9
CLX-Lag003 0 Excava0on 47 15-Feb-19 02-Apr-1 9 0 -61 CLX-Lag003 0
CLX-Lag003 1 Subgrade Prepara0on 52 14-Oct-1 9 04-Dec-19 0 -88 CLX-Lag003 1
Sta. 33 + 144.363 (WB20) to Sta. 33 + 608.000 (WB21) 214 30-May-1 8 29-Dec-18 -27 -88
CLX-Lag003 2 Clearing & Grubbing 20 30-May-1 8 18-Jun-18 0 -61 CLX-Lag003 2
CLX-Lag003 3 Excava0on 56 01-Sep-18 26-Oct-1 8 0 -61 CLX-Lag003 3
CLX-Lag003 4 Subgrade Prepara0on 22 08-Dec-18 29-Dec-18 0 -88 CLX-Lag003 4
Sta. 33 + 698.000 (WB21) to Sta. 33 + 924.000 (WB22) 202 20-May-1 8 07-Dec-18 -27 -88
CLX-Lag003 5 Clearing & Grubbing 10 20-May-1 8 29-May-1 8 0 -61 CLX-Lag003 5
CLX-Lag003 6 Excava0on 7 25-Aug-18 31-Aug-18 0 -61 CLX-Lag003 6
CLX-Lag003 7 Subgrade Prepara0on 11 27-Nov-18 07-Dec-18 0 -88 CLX-Lag003 7
Sta. 34 + 014.000 (WB22) to Sta. 34 + 782.833 (WB23) 224 17-Apr-1 8 26-Nov-18 -27 -88
CLX-Lag003 8 Clearing & Grubbing 33 17-Apr-1 8 19-May-1 8 0 -61 CLX-Lag003 8
CLX-Lag003 9 Excava0on 84 02-Jun-18 24-Aug-18 0 -61 CLX-Lag003 9
CLX-Lag004 0 Subgrade Prepara0on 38 20-Oct-1 8 26-Nov-18 0 -88 CLX-Lag004 0
Sta. 34 + 921.525 (WB23) to Sta. 35 + 118.380 (WB24) 194 09-Apr-1 8 19-Oct-1 8 -27 -88
CLX-Lag004 1 Clearing & Grubbing 8 09-Apr-1 8 16-Apr-1 8 0 -61 CLX-Lag004 1
CLX-Lag004 2 Excava0on 21 12-May-1 8 01-Jun-18 0 -61 CLX-Lag004 2
CLX-Lag004 3 Subgrade Prepara0on 10 10-Oct-1 8 19-Oct-1 8 0 -88 CLX-Lag004 3
Sta. 35 + 338.280 (WB24) to Sta. 35 + 625.480 (WB25) 196 28-Mar-18 09-Oct-1 8 -27 -88
CLX-Lag004 4 Clearing & Grubbing 12 28-Mar-18 08-Apr-1 8 0 -61 CLX-Lag004 4
CLX-Lag004 5 Excava0on 28 14-Apr-1 8 11-May-1 8 0 -61 CLX-Lag004 5
CLX-Lag004 6 Subgrade Prepara0on 14 26-Sep-18 09-Oct-1 8 0 -88 CLX-Lag004 6
Sta. 35 + 664.320 (WB25) to Sta. 37 + 053.562 (WB28) 207 03-Mar-18 25-Sep-18 -27 -88
CLX-Lag004 7 Clearing & Grubbing 25 03-Mar-18 27-Mar-18 0 -61 CLX-Lag004 7
CLX-Lag004 8 Excava0on 35 10-Mar-18 13-Apr-1 8 0 -61 CLX-Lag004 8
CLX-Lag004 9 Subgrade Prepara0on 29 28-Aug-18 25-Sep-18 0 -88 CLX-Lag004 9
Sta. 36 + 282.748 (EB10) to Sta. 37 + 053.562 (WB28) 281 23-Jul-18 29-Apr-1 9 -27 -88
CLX-Lag005 0 Clearing & Grubbing 70 23-Jul-18 30-Sep-18 0 -61 CLX-Lag005 0
CLX-Lag005 1 Subgrade Prepara0on 81 08-Feb-19 29-Apr-1 9 0 -88 CLX-Lag005 1
CLX-Lag005 2 Embankment 7 15-Feb-19 21-Feb-19 0 -88 CLX-Lag005 2
Sta. 36 + 282.748 (EB10) to Sta. 37 + 933.890 (WB26) 234 19-Jun-18 07-Feb-19 -27 -88
CLX-Lag005 3 Clearing & Grubbing 34 19-Jun-18 22-Jul-18 0 -61 CLX-Lag005 3
CLX-Lag005 4 Subgrade Prepara0on 40 30-Dec-18 07-Feb-19 0 -88 CLX-Lag005 4
CLX-Lag005 5 Embankment 14 06-Jan-19 19-Jan-19 0 -88 CLX-Lag005 5
SUB-BASE AND BASE COURSE 449 05-Nov-18 27-Jan-20 -1 -88
Sta. 27 + 900.000 to Sta. 29 + 439.852 (WB16) 73 08-Jul-19 18-Sep-19 0 -88
CLX-Lag005 6 Crushed Aggregate Base Course 38 08-Jul-19 14-Aug-19 0 -88 CLX-Lag005 6

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 3 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag005 7 Portland Cement Treated Mix Base Course 35 15-Aug-19 18-Sep-19 0 -88 CLX-Lag005 7
Sta. 29 + 509.852 (WB16) to Sta. 30 + 115.000 (WB17) 49 15-Aug-19 02-Oct-1 9 0 -88
CLX-Lag005 8 Crushed Aggregate Base Course 15 15-Aug-19 29-Aug-19 0 -88 CLX-Lag005 8
CLX-Lag005 9 Portland Cement Treated Mix Base Course 14 19-Sep-19 02-Oct-1 9 0 -88 CLX-Lag005 9
Sta. 30 + 140.000 (WB17) to Sta. 31 + 036.510 (EB9) 43 13-Sep-19 25-Oct-1 9 0 -88
CLX-Lag006 0 Crushed Aggregate Base Course 22 13-Sep-19 04-Oct-1 9 0 -88 CLX-Lag006 0
CLX-Lag006 1 Portland Cement Treated Mix Base Course 21 05-Oct-1 9 25-Oct-1 9 0 -88 CLX-Lag006 1
Sta. 31 + 071.510 (EB9) to Sta. 31 + 430.450 (WB18) 29 05-Oct-1 9 02-Nov-19 0 -88
CLX-Lag006 2 Crushed Aggregate Base Course 9 05-Oct-1 9 13-Oct-1 9 0 -88 CLX-Lag006 2
CLX-Lag006 3 Portland Cement Treated Mix Base Course 8 26-Oct-1 9 02-Nov-19 0 -88 CLX-Lag006 3
Sta. 31 + 491.550 (WB18) to Sta. 31+ 828.000 (WB19) 28 14-Oct-1 9 10-Nov-19 0 -88
CLX-Lag006 4 Crushed Aggregate Base Course 8 14-Oct-1 9 21-Oct-1 9 0 -88 CLX-Lag006 4
CLX-Lag006 5 Portland Cement Treated Mix Base Course 8 03-Nov-19 10-Nov-19 0 -88 CLX-Lag006 5
Sta. 31 + 903.000 (WB19) to Sta. 33 + 025.279 (WB20) 54 05-Dec-19 27-Jan-20 0 -88
CLX-Lag006 6 Crushed Aggregate Base Course 28 05-Dec-19 01-Jan-20 0 -88 CLX-Lag006 6
CLX-Lag006 7 Portland Cement Treated Mix Base Course 26 02-Jan-20 27-Jan-20 0 -88 CLX-Lag006 7
Sta. 33 + 144.363 (WB20) to Sta. 33 + 608.000 (WB21) 35 09-Jan-19 12-Feb-19 0 -87
CLX-Lag006 8 Crushed Aggregate Base Course 14 09-Jan-19 22-Jan-19 0 -87 CLX-Lag006 8
CLX-Lag006 9 Portland Cement Treated Mix Base Course 14 30-Jan-19 12-Feb-19 0 -87 CLX-Lag006 9
Sta. 33 + 698.000 (WB21) to Sta. 33 + 924.000 (WB22) 31 30-Dec-18 29-Jan-19 0 -87
CLX-Lag007 0 Crushed Aggregate Base Course 10 30-Dec-18 08-Jan-19 0 -87 CLX-Lag007 0
CLX-Lag007 1 Portland Cement Treated Mix Base Course 10 20-Jan-19 29-Jan-19 0 -87 CLX-Lag007 1
Sta. 34 + 014.000 (WB22) to Sta. 34 + 782.833 (WB23) 42 09-Dec-18 19-Jan-19 0 -87
CLX-Lag007 2 Crushed Aggregate Base Course 21 09-Dec-18 29-Dec-18 0 -87 CLX-Lag007 2
CLX-Lag007 3 Portland Cement Treated Mix Base Course 21 30-Dec-18 19-Jan-19 0 -87 CLX-Lag007 3
Sta. 34 + 921.525 (WB23) to Sta. 35 + 118.380 (WB24) 24 29-Nov-18 22-Dec-18 0 -87
CLX-Lag007 4 Crushed Aggregate Base Course 10 29-Nov-18 08-Dec-18 0 -87 CLX-Lag007 4
CLX-Lag007 5 Portland Cement Treated Mix Base Course 10 13-Dec-18 22-Dec-18 0 -87 CLX-Lag007 5
Sta. 35 + 338.280 (WB24) to Sta. 35 + 625.480 (WB25) 24 19-Nov-18 12-Dec-18 0 -87
CLX-Lag007 6 Crushed Aggregate Base Course 10 19-Nov-18 28-Nov-18 0 -87 CLX-Lag007 6
CLX-Lag007 7 Asphalt Treated Base Course 7 03-Dec-18 09-Dec-18 0 -87 CLX-Lag007 7
CLX-Lag007 8 Portland Cement Treated Mix Base Course 10 03-Dec-18 12-Dec-18 0 -87 CLX-Lag007 8
Sta. 35 + 664.320 (WB25) to Sta. 37 + 053.562 (WB28) 28 05-Nov-18 02-Dec-18 0 -87
CLX-Lag007 9 Crushed Aggregate Base Course 14 05-Nov-18 18-Nov-18 0 -87 CLX-Lag007 9
CLX-Lag008 0 Portland Cement Treated Mix Base Course 14 19-Nov-18 02-Dec-18 0 -87 CLX-Lag008 0
Sta. 36 + 282.748 (EB10) to Sta. 37 + 053.562 (WB28) 84 22-Feb-19 16-May-1 9 0 -88
CLX-Lag008 1 Crushed Aggregate Base Course 42 22-Feb-19 04-Apr-1 9 0 -88 CLX-Lag008 1
CLX-Lag008 2 Portland Cement Treated Mix Base Course 42 05-Apr-1 9 16-May-1 9 0 -88 CLX-Lag008 2
Sta. 36 + 282.748 (EB10) to Sta. 37 + 933.890 (WB26) 42 23-Jan-19 05-Mar-19 0 -87
CLX-Lag008 3 Crushed Aggregate Base Course 21 23-Jan-19 12-Feb-19 0 -87 CLX-Lag008 3
CLX-Lag008 4 Portland Cement Treated Mix Base Course 21 13-Feb-19 05-Mar-19 0 -87 CLX-Lag008 4

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 4 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
SURFACE COURSE 453 09-Dec-18 05-Mar-20 -18 -88
Sta. 27 + 900.000 to Sta. 29 + 439.852 (WB16) 54 19-Sep-19 11-Nov-19 0 -88
CLX-Lag008 5 Portland Cement Concrete Pavement 54 19-Sep-19 11-Nov-19 0 -88 CLX-Lag008 5
Sta. 29 + 509.852 (WB16) to Sta. 30 + 115.000 (WB17) 21 12-Nov-19 02-Dec-19 0 -88
CLX-Lag008 6 Portland Cement Concrete Pavement 21 12-Nov-19 02-Dec-19 0 -88 CLX-Lag008 6
Sta. 30 + 140.000 (WB17) to Sta. 31 + 036.510 (EB9) 32 03-Dec-19 03-Jan-20 0 -88
CLX-Lag008 7 Portland Cement Concrete Pavement 32 03-Dec-19 03-Jan-20 0 -88 CLX-Lag008 7
Sta. 31 + 071.510 (EB9) to Sta. 31 + 430.450 (WB18) 12 04-Jan-20 15-Jan-20 0 -88
CLX-Lag008 8 Portland Cement Concrete Pavement 12 04-Jan-20 15-Jan-20 0 -88 CLX-Lag008 8
Sta. 31 + 491.550 (WB18) to Sta. 31+ 828.000 (WB19) 12 16-Jan-20 27-Jan-20 0 -88
CLX-Lag008 9 Portland Cement Concrete Pavement 12 16-Jan-20 27-Jan-20 0 -88 CLX-Lag008 9
Sta. 31 + 903.000 (WB19) to Sta. 33 + 025.279 (WB20) 38 28-Jan-20 05-Mar-20 0 -88
CLX-Lag009 0 Portland Cement Concrete Pavement 38 28-Jan-20 05-Mar-20 0 -88 CLX-Lag009 0
Sta. 33 + 144.363 (WB20) to Sta. 33 + 608.000 (WB21) 23 20-Mar-19 11-Apr-1 9 0 -70
CLX-Lag009 1 Portland Cement Concrete Pavement 23 20-Mar-19 11-Apr-1 9 0 -70 CLX-Lag009 1
Sta. 33 + 698.000 (WB21) to Sta. 33 + 924.000 (WB22) 12 08-Mar-19 19-Mar-19 0 -70
CLX-Lag009 2 Portland Cement Concrete Pavement 12 08-Mar-19 19-Mar-19 0 -70 CLX-Lag009 2
Sta. 34 + 014.000 (WB22) to Sta. 34 + 782.833 (WB23) 37 30-Jan-19 07-Mar-19 0 -70
CLX-Lag009 3 Portland Cement Concrete Pavement 37 30-Jan-19 07-Mar-19 0 -70 CLX-Lag009 3
Sta. 34 + 921.525 (WB23) to Sta. 35 + 118.380 (WB24) 10 20-Jan-19 29-Jan-19 0 -70
CLX-Lag009 4 Portland Cement Concrete Pavement 10 20-Jan-19 29-Jan-19 0 -70 CLX-Lag009 4
Sta. 35 + 338.280 (WB24) to Sta. 35 + 625.480 (WB25) 14 06-Jan-19 19-Jan-19 0 -70
CLX-Lag009 5 Bituminous Concrete Surface Course 7 06-Jan-19 12-Jan-19 0 -70 CLX-Lag009 5
CLX-Lag009 6 Portland Cement Concrete Pavement 14 06-Jan-19 19-Jan-19 0 -70 CLX-Lag009 6
Sta. 35 + 664.320 (WB25) to Sta. 37 + 053.562 (WB28) 28 09-Dec-18 05-Jan-19 0 -70
CLX-Lag009 7 Portland Cement Concrete Pavement 28 09-Dec-18 05-Jan-19 0 -70 CLX-Lag009 7
Sta. 36 + 282.748 (EB10) to Sta. 37 + 053.562 (WB28) 80 22-May-1 9 09-Aug-19 0 -70
CLX-Lag009 8 Portland Cement Concrete Pavement 80 22-May-1 9 09-Aug-19 0 -70 CLX-Lag009 8
Sta. 36 + 282.748 (EB10) to Sta. 37 + 933.890 (WB26) 40 12-Apr-1 9 21-May-1 9 0 -70
CLX-Lag009 9 Portland Cement Concrete Pavement 40 12-Apr-1 9 21-May-1 9 0 -70 CLX-Lag009 9
BRIDGE CONSTRUCTION 629 03-Mar-18 21-Nov-19 0 -61
Nyogan Road Crossing Overpass (OB8) @ STA. 28+369.733 168 03-Mar-18 17-Aug-18 0 -61
CLX-Lag010 0 Bored Pile 35 03-Mar-18 06-Apr-1 8 0 -61 CLX-Lag010 0
CLX-Lag010 1 Pile Cap 42 17-Mar-18 27-Apr-1 8 0 -61 CLX-Lag010 1
CLX-Lag010 2 Column 42 07-Apr-1 8 18-May-1 8 0 -61 CLX-Lag010 2
CLX-Lag010 3 Coping Beam 42 28-Apr-1 8 08-Jun-18 0 -61 CLX-Lag010 3
CLX-Lag010 4 Pre-cast Girder 7 30-Jun-18 06-Jul-18 0 -61 CLX-Lag010 4
CLX-Lag010 5 Diap/Deck Slab/Railing/Barr ier 42 07-Jul-18 17-Aug-18 0 -61 CLX-Lag010 5
Gma-Silang Crossroad Underpass (UB1) @ STA. 29+295.621 54 28-Apr-1 8 20-Jun-18 0 -61
CLX-Lag010 6 Structure Excava0on 7 28-Apr-1 8 04-May-1 8 0 -61 CLX-Lag010 6
CLX-Lag010 7 Reinforcing Steel 42 28-Apr-1 8 08-Jun-18 0 -61 CLX-Lag010 7

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 5 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag010 8 Structural Concrete 42 03-May-1 8 13-Jun-18 0 -61 CLX-Lag010 8
CLX-Lag010 9 Lean Concrete 5 05-May-1 8 09-May-1 8 0 -61 CLX-Lag010 9
CLX-Lag011 0 Structural Backfilling 7 10-May-1 8 16-May-1 8 0 -61 CLX-Lag011 0
CLX-Lag011 1 Preformed Expansion Joint Cork Filler 7 14-Jun-18 20-Jun-18 0 -61 CLX-Lag011 1
Sabutan Kaong Waterway Bridge (WB16) STA. 29+439.852 to STA. 29+509.852 259 03-Mar-18 16-Nov-18 0 -61
CLX-Lag011 2 Access Road/Excava0on 28 03-Mar-18 30-Mar-18 0 -61 CLX-Lag011 2
CLX-Lag011 3 Bored Pile 56 07-Apr-1 8 01-Jun-18 0 -61 CLX-Lag011 3
CLX-Lag011 4 Column 56 19-May-1 8 13-Jul-18 0 -61 CLX-Lag011 4
CLX-Lag011 5 Coping Beam 56 16-Jun-18 10-Aug-18 0 -61 CLX-Lag011 5
CLX-Lag011 6 Pe-cast Concrete Girder 7 25-Aug-18 31-Aug-18 0 -61 CLX-Lag011 6
CLX-Lag011 7 Diap/Deck Slab/Railing/Barr ier 56 01-Sep-18 26-Oct-1 8 0 -61 CLX-Lag011 7
CLX-Lag011 8 Grouted Riprap 42 06-Oct-1 8 16-Nov-18 0 -61 CLX-Lag011 8
Kaong Farm Road Crossing Overpass (OB9) @ STA. 29+869.38 168 02-Jun-18 16-Nov-18 0 -61
CLX-Lag011 9 Bored Pile 21 02-Jun-18 22-Jun-18 0 -61 CLX-Lag011 9
CLX-Lag012 0 Pile Cap 7 23-Jun-18 29-Jun-18 0 -61 CLX-Lag012 0
CLX-Lag012 1 Column 28 30-Jun-18 27-Jul-18 0 -61 CLX-Lag012 1
CLX-Lag012 2 Coping Beam 42 28-Jul-18 07-Sep-18 0 -61 CLX-Lag012 2
CLX-Lag012 3 Pe-cast Concrete Girder 7 29-Sep-18 05-Oct-1 8 0 -61 CLX-Lag012 3
CLX-Lag012 4 Diaphragm/Deck Slab/Railing/Barrier/Parapet 42 06-Oct-1 8 16-Nov-18 0 -61 CLX-Lag012 4
Kaong Waterway Bridge (WB17) STA. 30+115 TO STA. 30+140 238 31-Mar-18 23-Nov-18 0 -61
CLX-Lag012 5 Access Road/Excava0on 28 31-Mar-18 27-Apr-1 8 0 -61 CLX-Lag012 5
CLX-Lag012 6 Bored Pile 21 23-Jun-18 13-Jul-18 0 -61 CLX-Lag012 6
CLX-Lag012 7 Coping Beam 42 14-Jul-18 24-Aug-18 0 -61 CLX-Lag012 7
CLX-Lag012 8 Pe-cast Concrete Girder 7 08-Sep-18 14-Sep-18 0 -61 CLX-Lag012 8
CLX-Lag012 9 Diap/Deck Slab/Railing/Barr ier 42 15-Sep-18 26-Oct-1 8 0 -61 CLX-Lag012 9
CLX-Lag013 0 Grouted Riprap 49 06-Oct-1 8 23-Nov-18 0 -61 CLX-Lag013 0
Silang Interchange Expressway Bridge (EB9) STA. 31+036.51 to STA. 31+071.51 224 14-Jul-18 22-Feb-19 0 -61
CLX-Lag013 1 Bored Pile 28 14-Jul-18 10-Aug-18 0 -61 CLX-Lag013 1
CLX-Lag013 2 Coping Beam 42 11-Aug-18 21-Sep-18 0 -61 CLX-Lag013 2
CLX-Lag013 3 Pe-cast Concrete Girder 7 13-Oct-1 8 19-Oct-1 8 0 -61 CLX-Lag013 3
CLX-Lag013 4 Diaphragm/Deck Slab/Railing/Barrier/Parapet 42 20-Oct-1 8 30-Nov-18 0 -61 CLX-Lag013 4
CLX-Lag013 5 Drain Piping 28 01-Dec-18 28-Dec-18 0 -61 CLX-Lag013 5
CLX-Lag013 6 Grouted Riprap 56 29-Dec-18 22-Feb-19 0 -61 CLX-Lag013 6
Tibig Waterway Bridge 1 (WB18) STA. 31+430.45 to STA. 31+491.55 343 28-Apr-1 8 05-Apr-1 9 0 -61
CLX-Lag013 7 Access Road/Excava0on 28 28-Apr-1 8 25-May-1 8 0 -61 CLX-Lag013 7
CLX-Lag013 8 Bored Pile 56 11-Aug-18 05-Oct-1 8 0 -61 CLX-Lag013 8
CLX-Lag013 9 Column 56 08-Sep-18 02-Nov-18 0 -61 CLX-Lag013 9
CLX-Lag014 0 Coping Beam 42 03-Nov-18 14-Dec-18 0 -61 CLX-Lag014 0
CLX-Lag014 1 Pe-cast Concrete Girder 7 05-Jan-19 11-Jan-19 0 -61 CLX-Lag014 1
CLX-Lag014 2 Diaphragm/Deck Slab/Railing/Barrier 56 12-Jan-19 08-Mar-19 0 -61 CLX-Lag014 2
CLX-Lag014 3 Grouted Riprap 56 09-Feb-19 05-Apr-1 9 0 -61 CLX-Lag014 3
Tibig Farm Crossroad Underpass Bridge (UB2) @ STA 31+620.373 68 06-Oct-1 8 12-Dec-18 0 -61

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 6 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag014 4 Structure Excava0on 7 06-Oct-1 8 12-Oct-1 8 0 -61 CLX-Lag014 4
CLX-Lag014 5 Reinforcing Steel 56 06-Oct-1 8 30-Nov-18 0 -61 CLX-Lag014 5
CLX-Lag014 6 Structural Concrete 56 11-Oct-1 8 05-Dec-18 0 -61 CLX-Lag014 6
CLX-Lag014 7 Lean Concrete 5 13-Oct-1 8 17-Oct-1 8 0 -61 CLX-Lag014 7
CLX-Lag014 8 Structural Backfilling 7 18-Oct-1 8 24-Oct-1 8 0 -61 CLX-Lag014 8
CLX-Lag014 9 Preformed Expansion Joint Cork Filler 7 06-Dec-18 12-Dec-18 0 -61 CLX-Lag014 9
Tibig Waterway Bridge 2 (WB19) STA. 31+828 to STA. 31+903 418 26-May-1 8 17-Jul-19 0 -61
CLX-Lag015 0 Access Road/Excava0on 28 26-May-1 8 22-Jun-18 0 -61 CLX-Lag015 0
CLX-Lag015 1 Bored Pile 56 13-Dec-18 06-Feb-19 0 -61 CLX-Lag015 1
CLX-Lag015 2 Column 63 03-Jan-19 06-Mar-19 0 -61 CLX-Lag015 2
CLX-Lag015 3 Coping Beam 42 14-Feb-19 27-Mar-19 0 -61 CLX-Lag015 3
CLX-Lag015 4 Pe-cast Concrete Girder 7 18-Apr-1 9 24-Apr-1 9 0 -61 CLX-Lag015 4
CLX-Lag015 5 Diaphragm/Deck Slab/Railing/Barrier 56 25-Apr-1 9 19-Jun-19 0 -61 CLX-Lag015 5
CLX-Lag015 6 Grouted Riprap 56 23-May-1 9 17-Jul-19 0 -61 CLX-Lag015 6
Alkalde Road Crossing Overpass (OB10) @ STA. 32+304.517 196 07-Feb-19 21-Aug-19 0 -61
CLX-Lag015 7 Bored Pile 35 07-Feb-19 13-Mar-19 0 -61 CLX-Lag015 7
CLX-Lag015 8 Pile Cap 28 28-Feb-19 27-Mar-19 0 -61 CLX-Lag015 8
CLX-Lag015 9 Column 42 28-Mar-19 08-May-1 9 0 -61 CLX-Lag015 9
CLX-Lag016 0 Coping Beam 42 18-Apr-1 9 29-May-1 9 0 -61 CLX-Lag016 0
CLX-Lag016 1 Pre-cast Girder 7 20-Jun-19 26-Jun-19 0 -61 CLX-Lag016 1
CLX-Lag016 2 Diap/Deck Slab/Railing/Barr ier 56 27-Jun-19 21-Aug-19 0 -61 CLX-Lag016 2
Tibig-Munting Ilog Waterway Bridge (WB20) STA. 33+025.279 to STA. 33+144.363 489 23-Jun-18 24-Oct-1 9 0 -61
CLX-Lag016 3 Access Road/Excava0on 28 23-Jun-18 20-Jul-18 0 -61 CLX-Lag016 3
CLX-Lag016 4 Bored Pile 56 14-Mar-19 08-May-1 9 0 -61 CLX-Lag016 4
CLX-Lag016 5 Column 56 18-Apr-1 9 12-Jun-19 0 -61 CLX-Lag016 5
CLX-Lag016 6 Coping Beam 42 23-May-1 9 03-Jul-19 0 -61 CLX-Lag016 6
CLX-Lag016 7 Pe-cast Concrete Girder 7 25-Jul-19 31-Jul-19 0 -61 CLX-Lag016 7
CLX-Lag016 8 Diaphragm/Deck Slab/Railing/Barrier 56 01-Aug-19 25-Sep-19 0 -61 CLX-Lag016 8
CLX-Lag016 9 Grouted Riprap 57 29-Aug-19 24-Oct-1 9 0 -61 CLX-Lag016 9
Munting Ilog Waterway Bridge 1 (WB21) STA. 33+608 to STA. 33+698 378 09-Nov-18 21-Nov-19 0 -61
CLX-Lag017 0 Access Road/Excava0on 28 09-Nov-18 06-Dec-18 0 -61 CLX-Lag017 0
CLX-Lag017 1 Bored Pile 56 12-Apr-1 9 06-Jun-19 0 -61 CLX-Lag017 1
CLX-Lag017 2 Column 49 17-May-1 9 04-Jul-19 0 -61 CLX-Lag017 2
CLX-Lag017 3 Coping Beam 49 14-Jun-19 01-Aug-19 0 -61 CLX-Lag017 3
CLX-Lag017 4 Pe-cast Concrete Girder 7 23-Aug-19 29-Aug-19 0 -61 CLX-Lag017 4
CLX-Lag017 5 Diaphragm/Deck Slab/Railing/Barrier 56 30-Aug-19 24-Oct-1 9 0 -61 CLX-Lag017 5
CLX-Lag017 6 Grouted Riprap 56 27-Sep-19 21-Nov-19 0 -61 CLX-Lag017 6
Munting Ilog Waterway Bridge 2(WB22) STA. 33+924 to STA. 34+014 350 12-Oct-1 8 26-Sep-19 0 -61
CLX-Lag017 7 Access Road/Excava0on 28 12-Oct-1 8 08-Nov-18 0 -61 CLX-Lag017 7
CLX-Lag017 8 Bored Pile 56 15-Feb-19 11-Apr-1 9 0 -61 CLX-Lag017 8
CLX-Lag017 9 Column 49 22-Mar-19 09-May-1 9 0 -61 CLX-Lag017 9
CLX-Lag018 0 Coping Beam 49 19-Apr-1 9 06-Jun-19 0 -61 CLX-Lag018 0

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 7 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag018 1 Pe-cast Concrete Girder 7 28-Jun-19 04-Jul-19 0 -61 CLX-Lag018 1
CLX-Lag018 2 Diaphragm/Deck Slab/Railing/Barrier 56 05-Jul-19 29-Aug-19 0 -61 CLX-Lag018 2
CLX-Lag018 3 Grouted Riprap 56 02-Aug-19 26-Sep-19 0 -61 CLX-Lag018 3
Munting Ilog-Carmen Waterway Bridge (WB23) STA. 34+782.833 to STA. 34+921.525 329 14-Sep-18 08-Aug-19 0 -61
CLX-Lag018 4 Access Road/Excava0on 28 14-Sep-18 11-Oct-1 8 0 -61 CLX-Lag018 4
CLX-Lag018 5 Bored Pile 70 07-Dec-18 14-Feb-19 0 -61 CLX-Lag018 5
CLX-Lag018 6 Column 77 04-Jan-19 21-Mar-19 0 -61 CLX-Lag018 6
CLX-Lag018 7 Coping Beam 56 22-Feb-19 18-Apr-1 9 0 -61 CLX-Lag018 7
CLX-Lag018 8 Pe-cast Concrete Girder 14 10-May-1 9 23-May-1 9 0 -61 CLX-Lag018 8
CLX-Lag018 9 Diaphragm/Deck Slab/Railing/Barrier 49 24-May-1 9 11-Jul-19 0 -61 CLX-Lag018 9
CLX-Lag019 0 Grouted Riprap & MSE Wall 56 14-Jun-19 08-Aug-19 0 -61 CLX-Lag019 0
Carmen Waterway Bridge 1 (WB24) STA. 35+118.38 to STA. 35+338.28 294 17-Aug-18 06-Jun-19 0 -61
CLX-Lag019 1 Access Road/Excava0on 28 17-Aug-18 13-Sep-18 0 -61 CLX-Lag019 1
CLX-Lag019 2 Bored Pile 70 28-Sep-18 06-Dec-18 0 -61 CLX-Lag019 2
CLX-Lag019 3 Column 70 02-Nov-18 10-Jan-19 0 -61 CLX-Lag019 3
CLX-Lag019 4 Coping Beam 70 07-Dec-18 14-Feb-19 0 -61 CLX-Lag019 4
CLX-Lag019 5 Pe-cast Concrete Girder 14 01-Mar-19 14-Mar-19 0 -61 CLX-Lag019 5
CLX-Lag019 6 Diaphragm/Deck Slab/Railing/Barrier 56 15-Mar-19 09-May-1 9 0 -61 CLX-Lag019 6
CLX-Lag019 7 Grouted Riprap & MSE Wall 56 12-Apr-1 9 06-Jun-19 0 -61 CLX-Lag019 7
Carmen Waterway Bridge 2 (WB25) STA. 35+625.48 to STA. 35+664.32 217 20-Jul-18 21-Feb-19 0 -61
CLX-Lag019 8 Access Road/Excava0on 28 20-Jul-18 16-Aug-18 0 -61 CLX-Lag019 8
CLX-Lag019 9 Bored Pile 42 17-Aug-18 27-Sep-18 0 -61 CLX-Lag019 9
CLX-Lag020 0 Coping Beam 42 28-Sep-18 08-Nov-18 0 -61 CLX-Lag020 0
CLX-Lag020 1 Pe-cast Concrete Girder 7 30-Nov-18 06-Dec-18 0 -61 CLX-Lag020 1
CLX-Lag020 2 Diaphragm/Deck Slab/Railing/Barrier 42 07-Dec-18 17-Jan-19 0 -61 CLX-Lag020 2
CLX-Lag020 3 Grouted Riprap & MSE Wall 56 28-Dec-18 21-Feb-19 0 -61 CLX-Lag020 3
Sta Rosa Interchange Expressway Bridge (EB10) STA. 36+247.748 to STA. 36+282.748 196 22-Jun-18 03-Jan-19 0 -61
CLX-Lag020 4 Bored Pile 28 22-Jun-18 19-Jul-18 0 -61 CLX-Lag020 4
CLX-Lag020 5 Coping Beam 42 20-Jul-18 30-Aug-18 0 -61 CLX-Lag020 5
CLX-Lag020 6 Pe-cast Concrete Girder 7 21-Sep-18 27-Sep-18 0 -61 CLX-Lag020 6
CLX-Lag020 7 Diaphragm/Deck Slab/Railing/Barrier 42 28-Sep-18 08-Nov-18 0 -61 CLX-Lag020 7
CLX-Lag020 8 Grouted Riprap & MSE Wall 56 09-Nov-18 03-Jan-19 0 -61 CLX-Lag020 8
CLX-Lag020 9 Drain Piping 28 09-Nov-18 06-Dec-18 0 -61 CLX-Lag020 9
Tagaytay Access Bridge (WB28) STA. 37+053.562 to STA. 37+092.562 196 22-Jun-18 03-Jan-19 0 -61
CLX-Lag021 0 Access Road/Excava0on 28 22-Jun-18 19-Jul-18 0 -61 CLX-Lag021 0
CLX-Lag021 1 Bored Pile 28 20-Jul-18 16-Aug-18 0 -61 CLX-Lag021 1
CLX-Lag021 2 Coping Beam 42 17-Aug-18 27-Sep-18 0 -61 CLX-Lag021 2
CLX-Lag021 3 Pe-cast Concrete Girder 7 19-Oct-1 8 25-Oct-1 8 0 -61 CLX-Lag021 3
CLX-Lag021 4 Diaphragm/Deck Slab/Railing/Barrier 42 26-Oct-1 8 06-Dec-18 0 -61 CLX-Lag021 4
CLX-Lag021 5 Grouted Riprap & MSE Wall 56 09-Nov-18 03-Jan-19 0 -61 CLX-Lag021 5
DRAINAGE AND SLOPE PROTECTION STRUCTURES 446 27-Oct-1 8 15-Jan-20 -66 -66
Sta. 27 + 900.000 to Sta. 29 + 439.852 (WB16) 114 12-May-1 9 02-Sep-19 -57 -57

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 8 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag021 6 Ditch 57 08-Jul-19 02-Sep-19 0 -57 CLX-Lag021 6
CLX-Lag021 7 RCPC 57 12-May-1 9 07-Jul-19 0 0 CLX-Lag021 7
CLX-Lag021 8 Drainage Canal & Stepp ed Canal 57 08-Jul-19 02-Sep-19 0 -57 CLX-Lag021 8
CLX-Lag021 9 RCBC 57 12-May-1 9 07-Jul-19 0 0 CLX-Lag021 9
CLX-Lag022 0 Retaining Wall 57 08-Jul-19 02-Sep-19 0 -57 CLX-Lag022 0
CLX-Lag022 1 Grouted Riprap 57 08-Jul-19 02-Sep-19 0 -57 CLX-Lag022 1
CLX-Lag022 2 Catch Basin 55 14-May-1 9 07-Jul-19 0 0 CLX-Lag022 2
CLX-Lag022 3 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 50 19-May-1 9 07-Jul-19 0 0 CLX-Lag022 3
CLX-Lag022 4 Headwall 49 19-May-1 9 06-Jul-19 0 0 CLX-Lag022 4
CLX-Lag022 5 OuCall 28 29-Jul-19 25-Aug-19 0 -55 CLX-Lag022 5
Sta. 29 + 509.852 (WB16) to Sta. 30 + 115.000 (WB17) 80 08-Jul-19 25-Sep-19 -57 -57
CLX-Lag022 6 Ditch 23 03-Sep-19 25-Sep-19 0 -57 CLX-Lag022 6
CLX-Lag022 7 RCPC 23 08-Jul-19 30-Jul-19 0 0 CLX-Lag022 7
CLX-Lag022 8 Drainage Canal & Stepp ed Canal 23 03-Sep-19 25-Sep-19 0 -57 CLX-Lag022 8
CLX-Lag022 9 RCBC 23 08-Jul-19 30-Jul-19 0 0 CLX-Lag022 9
CLX-Lag023 0 Retaining Wall 23 03-Sep-19 25-Sep-19 0 -57 CLX-Lag023 0
CLX-Lag023 1 Grouted Riprap 23 03-Sep-19 25-Sep-19 0 -57 CLX-Lag023 1
CLX-Lag023 2 Catch Basin 21 10-Jul-19 30-Jul-19 0 0 CLX-Lag023 2
CLX-Lag023 3 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 16 15-Jul-19 30-Jul-19 0 0 CLX-Lag023 3
CLX-Lag023 4 Headwall 14 15-Jul-19 28-Jul-19 0 0 CLX-Lag023 4
Sta. 30 + 140.000 (WB17) to Sta. 31 + 036.510 (EB9) 90 31-Jul-19 28-Oct-1 9 -57 -57
CLX-Lag023 5 Ditch 33 26-Sep-19 28-Oct-1 9 0 -57 CLX-Lag023 5
CLX-Lag023 6 RCPC 33 31-Jul-19 01-Sep-19 0 0 CLX-Lag023 6
CLX-Lag023 7 Drainage Canal & Stepp ed Canal 33 26-Sep-19 28-Oct-1 9 0 -57 CLX-Lag023 7
CLX-Lag023 8 RCBC 33 31-Jul-19 01-Sep-19 0 0 CLX-Lag023 8
CLX-Lag023 9 Retaining Wall 33 26-Sep-19 28-Oct-1 9 0 -57 CLX-Lag023 9
CLX-Lag024 0 Grouted Riprap 33 26-Sep-19 28-Oct-1 9 0 -57 CLX-Lag024 0
CLX-Lag024 1 Catch Basin 31 02-Aug-19 01-Sep-19 0 0 CLX-Lag024 1
CLX-Lag024 2 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 24 07-Aug-19 30-Aug-19 0 0 CLX-Lag024 2
CLX-Lag024 3 Headwall 21 07-Aug-19 27-Aug-19 0 0 CLX-Lag024 3
Sta. 31 + 071.510 (EB9) to Sta. 31 + 430.450 (WB18) 71 02-Sep-19 11-Nov-19 -57 -57
CLX-Lag024 4 Ditch 14 29-Oct-1 9 11-Nov-19 0 -57 CLX-Lag024 4
CLX-Lag024 5 RCPC 14 02-Sep-19 15-Sep-19 0 0 CLX-Lag024 5
CLX-Lag024 6 Drainage Canal & Stepp ed Canal 14 29-Oct-1 9 11-Nov-19 0 -57 CLX-Lag024 6
CLX-Lag024 7 RCBC 14 02-Sep-19 15-Sep-19 0 0 CLX-Lag024 7
CLX-Lag024 8 Retaining Wall 14 29-Oct-1 9 11-Nov-19 0 -57 CLX-Lag024 8
CLX-Lag024 9 Grouted Riprap 14 29-Oct-1 9 11-Nov-19 0 -57 CLX-Lag024 9
CLX-Lag025 0 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 12 04-Sep-19 15-Sep-19 0 0 CLX-Lag025 0
CLX-Lag025 1 Catch Basin 12 04-Sep-19 15-Sep-19 0 0 CLX-Lag025 1
CLX-Lag025 2 Headwall 7 04-Sep-19 10-Sep-19 0 0 CLX-Lag025 2
Sta. 31 + 491.550 (WB18) to Sta. 31+ 828.000 (WB19) 106 16-Sep-19 30-Dec-19 -55 -55
CLX-Lag025 3 Ditch 14 12-Nov-19 25-Nov-19 0 -57 CLX-Lag025 3

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 9 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag025 4 RCPC 14 16-Sep-19 29-Sep-19 0 0 CLX-Lag025 4
CLX-Lag025 5 Drainage Canal & Stepp ed Canal 14 12-Nov-19 25-Nov-19 0 -57 CLX-Lag025 5
CLX-Lag025 6 RCBC 14 16-Sep-19 29-Sep-19 0 0 CLX-Lag025 6
CLX-Lag025 7 Retaining Wall 14 12-Nov-19 25-Nov-19 0 -57 CLX-Lag025 7
CLX-Lag025 8 Grouted Riprap 14 12-Nov-19 25-Nov-19 0 -57 CLX-Lag025 8
CLX-Lag025 9 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 12 18-Sep-19 29-Sep-19 0 0 CLX-Lag025 9
CLX-Lag026 0 Catch Basin 12 18-Sep-19 29-Sep-19 0 0 CLX-Lag026 0
CLX-Lag026 1 Headwall 7 18-Sep-19 24-Sep-19 0 0 CLX-Lag026 1
CLX-Lag026 2 OuCall 28 03-Dec-19 30-Dec-19 0 -55 CLX-Lag026 2
Sta. 31 + 903.000 (WB19) to Sta. 33 + 025.279 (WB20) 108 30-Sep-19 15-Jan-20 -66 -66
CLX-Lag026 3 Ditch 42 05-Dec-19 15-Jan-20 0 -66 CLX-Lag026 3
CLX-Lag026 4 RCPC 42 30-Sep-19 10-Nov-19 0 0 CLX-Lag026 4
CLX-Lag026 5 Drainage Canal & Stepp ed Canal 42 05-Dec-19 15-Jan-20 0 -66 CLX-Lag026 5
CLX-Lag026 6 RCBC 42 30-Sep-19 10-Nov-19 0 0 CLX-Lag026 6
CLX-Lag026 7 Retaining Wall 42 05-Dec-19 15-Jan-20 0 -66 CLX-Lag026 7
CLX-Lag026 8 Grouted Riprap 42 05-Dec-19 15-Jan-20 0 -66 CLX-Lag026 8
CLX-Lag026 9 Catch Basin 40 02-Oct-1 9 10-Nov-19 0 0 CLX-Lag026 9
CLX-Lag027 0 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 35 07-Oct-1 9 10-Nov-19 0 0 CLX-Lag027 0
CLX-Lag027 1 Headwall 28 07-Oct-1 9 03-Nov-19 0 0 CLX-Lag027 1
Sta. 33 + 144.363 (WB20) to Sta. 33 + 608.000 (WB21) 74 17-Jan-19 31-Mar-19 -56 -56
CLX-Lag027 2 Ditch 18 14-Mar-19 31-Mar-19 0 -56 CLX-Lag027 2
CLX-Lag027 3 RCPC 18 17-Jan-19 03-Feb-19 0 0 CLX-Lag027 3
CLX-Lag027 4 Drainage Canal & Stepp ed Canal 18 14-Mar-19 31-Mar-19 0 -56 CLX-Lag027 4
CLX-Lag027 5 RCBC 18 17-Jan-19 03-Feb-19 0 0 CLX-Lag027 5
CLX-Lag027 6 Retaining Wall 18 14-Mar-19 31-Mar-19 0 -56 CLX-Lag027 6
CLX-Lag027 7 Grouted Riprap 18 14-Mar-19 31-Mar-19 0 -56 CLX-Lag027 7
CLX-Lag027 8 Catch Basin 16 19-Jan-19 03-Feb-19 0 0 CLX-Lag027 8
CLX-Lag027 9 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 11 24-Jan-19 03-Feb-19 0 0 CLX-Lag027 9
CLX-Lag028 0 Headwall 11 24-Jan-19 03-Feb-19 0 0 CLX-Lag028 0
Sta. 33 + 698.000 (WB21) to Sta. 33 + 924.000 (WB22) 65 08-Jan-19 13-Mar-19 -56 -56
CLX-Lag028 1 Ditch 9 05-Mar-19 13-Mar-19 0 -56 CLX-Lag028 1
CLX-Lag028 2 RCPC 9 08-Jan-19 16-Jan-19 0 0 CLX-Lag028 2
CLX-Lag028 3 Drainage Canal & Stepp ed Canal 9 05-Mar-19 13-Mar-19 0 -56 CLX-Lag028 3
CLX-Lag028 4 RCBC 9 08-Jan-19 16-Jan-19 0 0 CLX-Lag028 4
CLX-Lag028 5 Retaining Wall 9 05-Mar-19 13-Mar-19 0 -56 CLX-Lag028 5
CLX-Lag028 6 Grouted Riprap 9 05-Mar-19 13-Mar-19 0 -56 CLX-Lag028 6
CLX-Lag028 7 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 7 10-Jan-19 16-Jan-19 0 0 CLX-Lag028 7
CLX-Lag028 8 Catch Basin 7 10-Jan-19 16-Jan-19 0 0 CLX-Lag028 8
CLX-Lag028 9 Headwall 7 10-Jan-19 16-Jan-19 0 0 CLX-Lag028 9
Sta. 34 + 014.000 (WB22) to Sta. 34 + 782.833 (WB23) 86 09-Dec-18 04-Mar-19 -56 -56
CLX-Lag029 0 Ditch 30 03-Feb-19 04-Mar-19 0 -56 CLX-Lag029 0
CLX-Lag029 1 RCPC 30 09-Dec-18 07-Jan-19 0 0 CLX-Lag029 1

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 10 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag029 2 Drainage Canal & Stepp ed Canal 30 03-Feb-19 04-Mar-19 0 -56 CLX-Lag029 2
CLX-Lag029 3 RCBC 30 09-Dec-18 07-Jan-19 0 0 CLX-Lag029 3
CLX-Lag029 4 Retaining Wall 30 03-Feb-19 04-Mar-19 0 -56 CLX-Lag029 4
CLX-Lag029 5 Grouted Riprap 30 03-Feb-19 04-Mar-19 0 -56 CLX-Lag029 5
CLX-Lag029 6 Catch Basin 28 11-Dec-18 07-Jan-19 0 0 CLX-Lag029 6
CLX-Lag029 7 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 23 16-Dec-18 07-Jan-19 0 0 CLX-Lag029 7
CLX-Lag029 8 Headwall 21 16-Dec-18 05-Jan-19 0 0 CLX-Lag029 8
Sta. 34 + 921.525 (WB23) to Sta. 35 + 118.380 (WB24) 65 30-Nov-18 02-Feb-19 -56 -56
CLX-Lag029 9 Ditch 9 25-Jan-19 02-Feb-19 0 -56 CLX-Lag029 9
CLX-Lag030 0 RCPC 9 30-Nov-18 08-Dec-18 0 0 CLX-Lag030 0
CLX-Lag030 1 Drainage Canal & Stepp ed Canal 9 25-Jan-19 02-Feb-19 0 -56 CLX-Lag030 1
CLX-Lag030 2 RCBC 9 30-Nov-18 08-Dec-18 0 0 CLX-Lag030 2
CLX-Lag030 3 Retaining Wall 9 25-Jan-19 02-Feb-19 0 -56 CLX-Lag030 3
CLX-Lag030 4 Grouted Riprap 9 25-Jan-19 02-Feb-19 0 -56 CLX-Lag030 4
CLX-Lag030 5 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 7 02-Dec-18 08-Dec-18 0 0 CLX-Lag030 5
CLX-Lag030 6 Catch Basin 7 02-Dec-18 08-Dec-18 0 0 CLX-Lag030 6
CLX-Lag030 7 Headwall 7 02-Dec-18 08-Dec-18 0 0 CLX-Lag030 7
Sta. 35 + 338.280 (WB24) to Sta. 35 + 625.480 (WB25) 67 19-Nov-18 24-Jan-19 -56 -56
CLX-Lag030 8 Ditch 11 14-Jan-19 24-Jan-19 0 -56 CLX-Lag030 8
CLX-Lag030 9 RCPC 11 19-Nov-18 29-Nov-18 0 0 CLX-Lag030 9
CLX-Lag031 0 Drainage Canal & Stepp ed Canal 11 14-Jan-19 24-Jan-19 0 -56 CLX-Lag031 0
CLX-Lag031 1 RCBC 11 19-Nov-18 29-Nov-18 0 0 CLX-Lag031 1
CLX-Lag031 2 Retaining Wall 11 14-Jan-19 24-Jan-19 0 -56 CLX-Lag031 2
CLX-Lag031 3 Grouted Riprap 11 14-Jan-19 24-Jan-19 0 -56 CLX-Lag031 3
CLX-Lag031 4 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 9 21-Nov-18 29-Nov-18 0 0 CLX-Lag031 4
CLX-Lag031 5 Catch Basin 9 21-Nov-18 29-Nov-18 0 0 CLX-Lag031 5
CLX-Lag031 6 Headwall 9 21-Nov-18 29-Nov-18 0 0 CLX-Lag031 6
Sta. 35 + 664.320 (WB25) to Sta. 37 + 053.562 (WB28) 79 27-Oct-1 8 13-Jan-19 -56 -56
CLX-Lag031 7 Ditch 23 22-Dec-18 13-Jan-19 0 -56 CLX-Lag031 7
CLX-Lag031 8 RCPC 23 27-Oct-1 8 18-Nov-18 0 0 CLX-Lag031 8
CLX-Lag031 9 Drainage Canal & Stepp ed Canal 23 22-Dec-18 13-Jan-19 0 -56 CLX-Lag031 9
CLX-Lag032 0 RCBC 23 27-Oct-1 8 18-Nov-18 0 0 CLX-Lag032 0
CLX-Lag032 1 Retaining Wall 23 22-Dec-18 13-Jan-19 0 -56 CLX-Lag032 1
CLX-Lag032 2 Grouted Riprap 23 22-Dec-18 13-Jan-19 0 -56 CLX-Lag032 2
CLX-Lag032 3 Catch Basin 21 29-Oct-1 8 18-Nov-18 0 0 CLX-Lag032 3
CLX-Lag032 4 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 16 03-Nov-18 18-Nov-18 0 0 CLX-Lag032 4
CLX-Lag032 5 Headwall 14 03-Nov-18 16-Nov-18 0 0 CLX-Lag032 5
Sta. 36 + 282.748 (EB10) to Sta. 37 + 053.562 (WB28) 121 08-Mar-19 06-Jul-19 -56 -56
CLX-Lag032 6 Ditch 65 03-May-1 9 06-Jul-19 0 -56 CLX-Lag032 6
CLX-Lag032 7 RCPC 65 08-Mar-19 11-May-1 9 0 0 CLX-Lag032 7
CLX-Lag032 8 Drainage Canal & Stepp ed Canal 65 03-May-1 9 06-Jul-19 0 -56 CLX-Lag032 8
CLX-Lag032 9 RCBC 65 08-Mar-19 11-May-1 9 0 0 CLX-Lag032 9

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 11 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag033 0 Retaining Wall 65 03-May-1 9 06-Jul-19 0 -56 CLX-Lag033 0
CLX-Lag033 1 Grouted Riprap 65 03-May-1 9 06-Jul-19 0 -56 CLX-Lag033 1
CLX-Lag033 2 Catch Basin 63 10-Mar-19 11-May-1 9 0 0 CLX-Lag033 2
CLX-Lag033 3 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 58 15-Mar-19 11-May-1 9 0 0 CLX-Lag033 3
CLX-Lag033 4 Headwall 56 15-Mar-19 09-May-1 9 0 0 CLX-Lag033 4
Sta. 36 + 282.748 (EB10) to Sta. 37 + 933.890 (WB26) 88 04-Feb-19 02-May-1 9 -56 -56
CLX-Lag033 5 Ditch 32 01-Apr-1 9 02-May-1 9 0 -56 CLX-Lag033 5
CLX-Lag033 6 RCPC 32 04-Feb-19 07-Mar-19 0 0 CLX-Lag033 6
CLX-Lag033 7 Drainage Canal & Stepp ed Canal 32 01-Apr-1 9 02-May-1 9 0 -56 CLX-Lag033 7
CLX-Lag033 8 RCBC 32 04-Feb-19 07-Mar-19 0 0 CLX-Lag033 8
CLX-Lag033 9 Retaining Wall 32 01-Apr-1 9 02-May-1 9 0 -56 CLX-Lag033 9
CLX-Lag034 0 Grouted Riprap 32 01-Apr-1 9 02-May-1 9 0 -56 CLX-Lag034 0
CLX-Lag034 1 Catch Basin 29 06-Feb-19 06-Mar-19 0 0 CLX-Lag034 1
CLX-Lag034 2 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 25 11-Feb-19 07-Mar-19 0 0 CLX-Lag034 2
CLX-Lag034 3 Headwall 21 11-Feb-19 03-Mar-19 0 0 CLX-Lag034 3
MISCELLANEOUS STRUCTURES 486 20-Jan-19 19-May-2 0 -18 -88
Sta. 27 + 900.000 to Sta. 29 + 439.852 (WB16) 96 12-Nov-19 15-Feb-20 -10 -88
CLX-Lag034 4 Concrete Median Barrier 39 12-Nov-19 20-Dec-19 0 -78 CLX-Lag034 4
CLX-Lag034 5 Concrete Railing 26 26-Nov-19 21-Dec-19 0 -88 CLX-Lag034 5
CLX-Lag034 6 Concrete Curb 26 26-Nov-19 21-Dec-19 0 -88 CLX-Lag034 6
CLX-Lag034 7 Pre-Cast Fence 36 26-Nov-19 31-Dec-19 0 -88 CLX-Lag034 7
CLX-Lag034 8 Guardrail 40 10-Dec-19 18-Jan-20 0 -88 CLX-Lag034 8
CLX-Lag034 9 Chainlink Fence 40 10-Dec-19 18-Jan-20 0 -88 CLX-Lag034 9
CLX-Lag035 0 Sound Barrier 29 01-Jan-20 29-Jan-20 0 -88 CLX-Lag035 0
CLX-Lag035 1 Landscaping 35 01-Jan-20 04-Feb-20 0 -88 CLX-Lag035 1
CLX-Lag035 2 Lane Marking 24 04-Jan-20 27-Jan-20 0 -75 CLX-Lag035 2
CLX-Lag035 3 Signages 17 30-Jan-20 15-Feb-20 0 -88 CLX-Lag035 3
Sta. 29 + 509.852 (WB16) to Sta. 30 + 115.000 (WB17) 64 21-Dec-19 22-Feb-20 -1 -88
CLX-Lag035 4 Concrete Railing 10 22-Dec-19 31-Dec-19 0 -88 CLX-Lag035 4
CLX-Lag035 5 Concrete Curb 10 22-Dec-19 31-Dec-19 0 -88 CLX-Lag035 5
CLX-Lag035 6 Concrete Median Barrier 15 21-Dec-19 04-Jan-20 0 -78 CLX-Lag035 6
CLX-Lag035 7 Pre-Cast Fence 14 01-Jan-20 14-Jan-20 0 -88 CLX-Lag035 7
CLX-Lag035 8 Guardrail 16 19-Jan-20 03-Feb-20 0 -88 CLX-Lag035 8
CLX-Lag035 9 Chainlink Fence 16 19-Jan-20 03-Feb-20 0 -88 CLX-Lag035 9
CLX-Lag036 0 Sound Barrier 11 30-Jan-20 09-Feb-20 0 -88 CLX-Lag036 0
CLX-Lag036 1 Landscaping 14 05-Feb-20 18-Feb-20 0 -88 CLX-Lag036 1
CLX-Lag036 2 Lane Marking 9 28-Jan-20 05-Feb-20 0 -75 CLX-Lag036 2
CLX-Lag036 3 Signages 7 16-Feb-20 22-Feb-20 0 -88 CLX-Lag036 3
Sta. 30 + 140.000 (WB17) to Sta. 31 + 036.510 (EB9) 65 05-Jan-20 09-Mar-20 -10 -88
CLX-Lag036 4 Concrete Median Barrier 23 05-Jan-20 27-Jan-20 0 -78 CLX-Lag036 4
CLX-Lag036 5 Concrete Railing 15 18-Jan-20 01-Feb-20 0 -88 CLX-Lag036 5
CLX-Lag036 6 Concrete Curb 15 18-Jan-20 01-Feb-20 0 -88 CLX-Lag036 6

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 12 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag036 7 Pre-Cast Fence 21 18-Jan-20 07-Feb-20 0 -88 CLX-Lag036 7
CLX-Lag036 8 Guardrail 23 04-Feb-20 26-Feb-20 0 -88 CLX-Lag036 8
CLX-Lag036 9 Chainlink Fence 23 04-Feb-20 26-Feb-20 0 -88 CLX-Lag036 9
CLX-Lag037 0 Sound Barrier 17 10-Feb-20 26-Feb-20 0 -88 CLX-Lag037 0
CLX-Lag037 1 Landscaping 20 19-Feb-20 09-Mar-20 0 -88 CLX-Lag037 1
CLX-Lag037 2 Lane Marking 14 11-Feb-20 24-Feb-20 0 -78 CLX-Lag037 2
CLX-Lag037 3 Signages 10 27-Feb-20 07-Mar-20 0 -88 CLX-Lag037 3
Sta. 31 + 071.510 (EB9) to Sta. 31 + 430.450 (WB18) 50 28-Jan-20 17-Mar-20 -5 -88
CLX-Lag037 4 Concrete Railing 6 02-Feb-20 07-Feb-20 0 -88 CLX-Lag037 4
CLX-Lag037 5 Concrete Curb 6 02-Feb-20 07-Feb-20 0 -88 CLX-Lag037 5
CLX-Lag037 6 Concrete Median Barrier 9 28-Jan-20 05-Feb-20 0 -78 CLX-Lag037 6
CLX-Lag037 7 Pre-Cast Fence 8 08-Feb-20 15-Feb-20 0 -88 CLX-Lag037 7
CLX-Lag037 8 Guardrail 9 27-Feb-20 06-Mar-20 0 -88 CLX-Lag037 8
CLX-Lag037 9 Chainlink Fence 9 27-Feb-20 06-Mar-20 0 -88 CLX-Lag037 9
CLX-Lag038 0 Sound Barrier 7 27-Feb-20 04-Mar-20 0 -88 CLX-Lag038 0
CLX-Lag038 1 Lane Marking 6 25-Feb-20 01-Mar-20 0 -78 CLX-Lag038 1
CLX-Lag038 2 Signages 4 08-Mar-20 11-Mar-20 0 -88 CLX-Lag038 2
CLX-Lag038 3 Landscaping 8 10-Mar-20 17-Mar-20 0 -88 CLX-Lag038 3
Sta. 31 + 491.550 (WB18) to Sta. 31+ 828.000 (WB19) 49 06-Feb-20 25-Mar-20 -5 -88
CLX-Lag038 4 Concrete Railing 6 11-Feb-20 16-Feb-20 0 -88 CLX-Lag038 4
CLX-Lag038 5 Concrete Curb 6 11-Feb-20 16-Feb-20 0 -88 CLX-Lag038 5
CLX-Lag038 6 Concrete Median Barrier 8 06-Feb-20 13-Feb-20 0 -78 CLX-Lag038 6
CLX-Lag038 7 Pre-Cast Fence 8 16-Feb-20 23-Feb-20 0 -88 CLX-Lag038 7
CLX-Lag038 8 Sound Barrier 6 05-Mar-20 10-Mar-20 0 -88 CLX-Lag038 8
CLX-Lag038 9 Guardrail 9 07-Mar-20 15-Mar-20 0 -88 CLX-Lag038 9
CLX-Lag039 0 Chainlink Fence 9 07-Mar-20 15-Mar-20 0 -88 CLX-Lag039 0
CLX-Lag039 1 Lane Marking 5 02-Mar-20 06-Mar-20 0 -78 CLX-Lag039 1
CLX-Lag039 2 Signages 4 16-Mar-20 19-Mar-20 0 -88 CLX-Lag039 2
CLX-Lag039 3 Landscaping 8 18-Mar-20 25-Mar-20 0 -88 CLX-Lag039 3
Sta. 31 + 903.000 (WB19) to Sta. 33 + 025.279 (WB20) 75 06-Mar-20 19-May-2 0 0 -88
CLX-Lag039 4 Concrete Median Barrier 28 06-Mar-20 02-Apr-2 0 0 -88 CLX-Lag039 4
CLX-Lag039 5 Concrete Railing 19 20-Mar-20 07-Apr-2 0 0 -88 CLX-Lag039 5
CLX-Lag039 6 Concrete Curb 19 20-Mar-20 07-Apr-2 0 0 -88 CLX-Lag039 6
CLX-Lag039 7 Pre-Cast Fence 27 20-Mar-20 15-Apr-2 0 0 -88 CLX-Lag039 7
CLX-Lag039 8 Guardrail 29 03-Apr-2 0 01-May-2 0 0 -88 CLX-Lag039 8
CLX-Lag039 9 Chainlink Fence 29 03-Apr-2 0 01-May-2 0 0 -88 CLX-Lag039 9
CLX-Lag040 0 Sound Barrier 21 16-Apr-2 0 06-May-2 0 0 -88 CLX-Lag040 0
CLX-Lag040 1 Landscaping 26 16-Apr-2 0 11-May-2 0 0 -88 CLX-Lag040 1
CLX-Lag040 2 Lane Marking 18 17-Apr-2 0 04-May-2 0 0 -88 CLX-Lag040 2
CLX-Lag040 3 Signages 13 07-May-2 0 19-May-2 0 0 -88 CLX-Lag040 3
Sta. 33 + 144.363 (WB20) to Sta. 33 + 608.000 (WB21) 57 26-Apr-1 9 21-Jun-19 0 -70
CLX-Lag040 4 Concrete Railing 12 26-Apr-1 9 07-May-1 9 0 -70 CLX-Lag040 4

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 13 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag040 5 Concrete Curb 12 26-Apr-1 9 07-May-1 9 0 -70 CLX-Lag040 5
CLX-Lag040 6 Pre-Cast Fence 14 26-Apr-1 9 09-May-1 9 0 -70 CLX-Lag040 6
CLX-Lag040 7 Concrete Median Barrier 16 10-May-1 9 25-May-1 9 0 -70 CLX-Lag040 7
CLX-Lag040 8 Guardrail 16 10-May-1 9 25-May-1 9 0 -70 CLX-Lag040 8
CLX-Lag040 9 Chainlink Fence 16 10-May-1 9 25-May-1 9 0 -70 CLX-Lag040 9
CLX-Lag041 0 Sound Barrier 12 11-May-1 9 22-May-1 9 0 -70 CLX-Lag041 0
CLX-Lag041 1 Landscaping 15 16-May-1 9 30-May-1 9 0 -70 CLX-Lag041 1
CLX-Lag041 2 Signages 10 27-May-1 9 05-Jun-19 0 -70 CLX-Lag041 2
CLX-Lag041 3 Lane Marking 12 10-Jun-19 21-Jun-19 0 -70 CLX-Lag041 3
Sta. 33 + 698.000 (WB21) to Sta. 33 + 924.000 (WB22) 60 11-Apr-1 9 09-Jun-19 0 -70
CLX-Lag041 4 Concrete Railing 6 11-Apr-1 9 16-Apr-1 9 0 -70 CLX-Lag041 4
CLX-Lag041 5 Concrete Curb 6 11-Apr-1 9 16-Apr-1 9 0 -70 CLX-Lag041 5
CLX-Lag041 6 Pre-Cast Fence 7 14-Apr-1 9 20-Apr-1 9 0 -70 CLX-Lag041 6
CLX-Lag041 7 Concrete Median Barrier 8 02-May-1 9 09-May-1 9 0 -70 CLX-Lag041 7
CLX-Lag041 8 Guardrail 8 02-May-1 9 09-May-1 9 0 -70 CLX-Lag041 8
CLX-Lag041 9 Chainlink Fence 8 02-May-1 9 09-May-1 9 0 -70 CLX-Lag041 9
CLX-Lag042 0 Sound Barrier 6 05-May-1 9 10-May-1 9 0 -70 CLX-Lag042 0
CLX-Lag042 1 Landscaping 7 09-May-1 9 15-May-1 9 0 -70 CLX-Lag042 1
CLX-Lag042 2 Signages 5 22-May-1 9 26-May-1 9 0 -70 CLX-Lag042 2
CLX-Lag042 3 Lane Marking 6 04-Jun-19 09-Jun-19 0 -70 CLX-Lag042 3
Sta. 34 + 014.000 (WB22) to Sta. 34 + 782.833 (WB23) 74 22-Mar-19 03-Jun-19 0 -70
CLX-Lag042 4 Concrete Railing 20 22-Mar-19 10-Apr-1 9 0 -70 CLX-Lag042 4
CLX-Lag042 5 Concrete Curb 20 22-Mar-19 10-Apr-1 9 0 -70 CLX-Lag042 5
CLX-Lag042 6 Pre-Cast Fence 23 22-Mar-19 13-Apr-1 9 0 -70 CLX-Lag042 6
CLX-Lag042 7 Concrete Median Barrier 27 05-Apr-1 9 01-May-1 9 0 -70 CLX-Lag042 7
CLX-Lag042 8 Guardrail 27 05-Apr-1 9 01-May-1 9 0 -70 CLX-Lag042 8
CLX-Lag042 9 Chainlink Fence 27 05-Apr-1 9 01-May-1 9 0 -70 CLX-Lag042 9
CLX-Lag043 0 Sound Barrier 21 14-Apr-1 9 04-May-1 9 0 -70 CLX-Lag043 0
CLX-Lag043 1 Landscaping 25 14-Apr-1 9 08-May-1 9 0 -70 CLX-Lag043 1
CLX-Lag043 2 Signages 17 05-May-1 9 21-May-1 9 0 -70 CLX-Lag043 2
CLX-Lag043 3 Lane Marking 19 16-May-1 9 03-Jun-19 0 -70 CLX-Lag043 3
Sta. 34 + 921.525 (WB23) to Sta. 35 + 118.380 (WB24) 51 13-Feb-19 04-Apr-1 9 -1 -70
CLX-Lag043 4 Pre-Cast Fence 6 14-Feb-19 19-Feb-19 0 -70 CLX-Lag043 4
CLX-Lag043 5 Concrete Railing 5 13-Feb-19 17-Feb-19 0 -61 CLX-Lag043 5
CLX-Lag043 6 Concrete Curb 5 13-Feb-19 17-Feb-19 0 -61 CLX-Lag043 6
CLX-Lag043 7 Sound Barrier 5 02-Mar-19 06-Mar-19 0 -70 CLX-Lag043 7
CLX-Lag043 8 Concrete Median Barrier 7 05-Mar-19 11-Mar-19 0 -70 CLX-Lag043 8
CLX-Lag043 9 Guardrail 7 05-Mar-19 11-Mar-19 0 -70 CLX-Lag043 9
CLX-Lag044 0 Chainlink Fence 7 05-Mar-19 11-Mar-19 0 -70 CLX-Lag044 0
CLX-Lag044 1 Landscaping 6 06-Mar-19 11-Mar-19 0 -70 CLX-Lag044 1
CLX-Lag044 2 Signages 4 14-Mar-19 17-Mar-19 0 -70 CLX-Lag044 2
CLX-Lag044 3 Lane Marking 5 31-Mar-19 04-Apr-1 9 0 -70 CLX-Lag044 3

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 14 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
Sta. 35 + 338.280 (WB24) to Sta. 35 + 625.480 (WB25) 55 04-Feb-19 30-Mar-19 -2 -70
CLX-Lag044 4 Pre-Cast Fence 8 06-Feb-19 13-Feb-19 0 -70 CLX-Lag044 4
CLX-Lag044 5 Concrete Railing 8 04-Feb-19 11-Feb-19 0 -63 CLX-Lag044 5
CLX-Lag044 6 Concrete Curb 8 04-Feb-19 11-Feb-19 0 -63 CLX-Lag044 6
CLX-Lag044 7 Sound Barrier 8 22-Feb-19 01-Mar-19 0 -70 CLX-Lag044 7
CLX-Lag044 8 Concrete Median Barrier 10 23-Feb-19 04-Mar-19 0 -70 CLX-Lag044 8
CLX-Lag044 9 Guardrail 10 23-Feb-19 04-Mar-19 0 -70 CLX-Lag044 9
CLX-Lag045 0 Chainlink Fence 10 23-Feb-19 04-Mar-19 0 -70 CLX-Lag045 0
CLX-Lag045 1 Landscaping 9 25-Feb-19 05-Mar-19 0 -70 CLX-Lag045 1
CLX-Lag045 2 Signages 6 08-Mar-19 13-Mar-19 0 -70 CLX-Lag045 2
CLX-Lag045 3 Lane Marking 7 24-Mar-19 30-Mar-19 0 -70 CLX-Lag045 3
Sta. 35 + 664.320 (WB25) to Sta. 37 + 053.562 (WB28) 63 20-Jan-19 23-Mar-19 0 -70
CLX-Lag045 4 Concrete Railing 15 20-Jan-19 03-Feb-19 0 -70 CLX-Lag045 4
CLX-Lag045 5 Concrete Curb 15 20-Jan-19 03-Feb-19 0 -70 CLX-Lag045 5
CLX-Lag045 6 Pre-Cast Fence 17 20-Jan-19 05-Feb-19 0 -70 CLX-Lag045 6
CLX-Lag045 7 Concrete Median Barrier 20 03-Feb-19 22-Feb-19 0 -70 CLX-Lag045 7
CLX-Lag045 8 Guardrail 20 03-Feb-19 22-Feb-19 0 -70 CLX-Lag045 8
CLX-Lag045 9 Chainlink Fence 20 03-Feb-19 22-Feb-19 0 -70 CLX-Lag045 9
CLX-Lag046 0 Sound Barrier 16 06-Feb-19 21-Feb-19 0 -70 CLX-Lag046 0
CLX-Lag046 1 Landscaping 19 06-Feb-19 24-Feb-19 0 -70 CLX-Lag046 1
CLX-Lag046 2 Signages 13 23-Feb-19 07-Mar-19 0 -70 CLX-Lag046 2
CLX-Lag046 3 Lane Marking 15 09-Mar-19 23-Mar-19 0 -70 CLX-Lag046 3
Sta. 36 + 282.748 (EB10) to Sta. 37 + 053.562 (WB28) 129 24-Aug-19 30-Dec-19 0 -70
CLX-Lag046 4 Concrete Railing 44 24-Aug-19 06-Oct-1 9 0 -70 CLX-Lag046 4
CLX-Lag046 5 Concrete Curb 44 24-Aug-19 06-Oct-1 9 0 -70 CLX-Lag046 5
CLX-Lag046 6 Pre-Cast Fence 48 24-Aug-19 10-Oct-1 9 0 -70 CLX-Lag046 6
CLX-Lag046 7 Concrete Median Barrier 58 07-Sep-19 03-Nov-19 0 -70 CLX-Lag046 7
CLX-Lag046 8 Guardrail 58 07-Sep-19 03-Nov-19 0 -70 CLX-Lag046 8
CLX-Lag046 9 Chainlink Fence 58 07-Sep-19 03-Nov-19 0 -70 CLX-Lag046 9
CLX-Lag047 0 Sound Barrier 44 11-Oct-1 9 23-Nov-19 0 -70 CLX-Lag047 0
CLX-Lag047 1 Landscaping 53 11-Oct-1 9 02-Dec-19 0 -70 CLX-Lag047 1
CLX-Lag047 2 Lane Marking 42 18-Nov-19 29-Dec-19 0 -70 CLX-Lag047 2
CLX-Lag047 3 Signages 37 24-Nov-19 30-Dec-19 0 -70 CLX-Lag047 3
Sta. 36 + 282.748 (EB10) to Sta. 37 + 933.890 (WB26) 64 05-Jun-19 07-Aug-19 0 -70
CLX-Lag047 4 Concrete Railing 21 05-Jun-19 25-Jun-19 0 -70 CLX-Lag047 4
CLX-Lag047 5 Concrete Curb 21 05-Jun-19 25-Jun-19 0 -70 CLX-Lag047 5
CLX-Lag047 6 Pre-Cast Fence 24 05-Jun-19 28-Jun-19 0 -70 CLX-Lag047 6
CLX-Lag047 7 Concrete Median Barrier 28 19-Jun-19 16-Jul-19 0 -70 CLX-Lag047 7
CLX-Lag047 8 Guardrail 28 19-Jun-19 16-Jul-19 0 -70 CLX-Lag047 8
CLX-Lag047 9 Chainlink Fence 28 19-Jun-19 16-Jul-19 0 -70 CLX-Lag047 9
CLX-Lag048 0 Sound Barrier 22 29-Jun-19 20-Jul-19 0 -70 CLX-Lag048 0
CLX-Lag048 1 Landscaping 26 29-Jun-19 24-Jul-19 0 -70 CLX-Lag048 1

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 15 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag048 2 Lane Marking 20 17-Jul-19 05-Aug-19 0 -70 CLX-Lag048 2
CLX-Lag048 3 Signages 18 21-Jul-19 07-Aug-19 0 -70 CLX-Lag048 3
ROADWAY LIGHTING SYSTEM 368 06-Mar-19 07-Mar-20 -1 -88
Silang East Interchange 126 03-Nov-19 07-Mar-20 0 -88
CLX-Lag048 4 Ductbank 21 03-Nov-19 23-Nov-19 0 -88 CLX-Lag048 4
CLX-Lag048 5 Roughing-ins 35 10-Nov-19 14-Dec-19 0 -88 CLX-Lag048 5
CLX-Lag048 6 Roadway Light & Undercarriage Light 84 24-Nov-19 15-Feb-20 0 -88 CLX-Lag048 6
CLX-Lag048 7 Panel & Service Po le Entrance 21 16-Feb-20 07-Mar-20 0 -88 CLX-Lag048 7
Sta Rosa-Tagaytay Interchange 126 06-Mar-19 09-Jul-19 0 -87
CLX-Lag048 8 Ductbank 21 06-Mar-19 26-Mar-19 0 -87 CLX-Lag048 8
CLX-Lag048 9 Roughing-ins 28 13-Mar-19 09-Apr-1 9 0 -87 CLX-Lag048 9
CLX-Lag049 0 Roadway Light & Undercarriage Light 84 27-Mar-19 18-Jun-19 0 -87 CLX-Lag049 0
CLX-Lag049 1 Panel & Service Po le Entrance 21 19-Jun-19 09-Jul-19 0 -87 CLX-Lag049 1
BUILDINGS AND TOLL PLAZA 402 06-Mar-19 10-Apr-2 0 -1 -88
Silang East Interchange TP-1A (Entry Toll Plaza) 95 03-Nov-19 05-Feb-20 0 -88
Toll Plaza 95 03-Nov-19 05-Feb-20 0 -88
CLX-Lag049 2 Toll Canopy Structure 56 03-Nov-19 28-Dec-19 0 -88 CLX-Lag049 2
CLX-Lag049 3 Underground Power and Auxilliary 28 03-Nov-19 30-Nov-19 0 -88 CLX-Lag049 3
CLX-Lag049 4 Grounding System 12 05-Nov-19 16-Nov-19 0 -88 CLX-Lag049 4
CLX-Lag049 5 Storm Drainage and Sewerage System, and Water System 89 05-Nov-19 01-Feb-20 0 -88 CLX-Lag049 5
CLX-Lag049 6 Toll Island 76 17-Nov-19 31-Jan-20 0 -88 CLX-Lag049 6
CLX-Lag049 7 Metal Beam Guardrail 28 08-Dec-19 04-Jan-20 0 -88 CLX-Lag049 7
CLX-Lag049 8 Canopy Ligh0ng System 46 22-Dec-19 05-Feb-20 0 -88 CLX-Lag049 8
CLX-Lag049 9 Latrine with Bowl 18 29-Dec-19 15-Jan-20 0 -88 CLX-Lag049 9
CLX-Lag050 0 Lightning Protec0on System 14 29-Dec-19 11-Jan-20 0 -88 CLX-Lag050 0
CLX-Lag050 1 Protec 0on Bollards 21 05-Jan-20 25-Jan-20 0 -88 CLX-Lag050 1
CLX-Lag050 2 War ning / Flashing Light 27 05-Jan-20 31-Jan-20 0 -88 CLX-Lag050 2
CLX-Lag050 3 Protec 0on Bar riers 21 12-Jan-20 01-Feb-20 0 -88 CLX-Lag050 3
CLX-Lag050 4 Pedestrian Gates 14 19-Jan-20 01-Feb-20 0 -88 CLX-Lag050 4
Ground Reservoir And Water Tank 90 03-Nov-19 31-Jan-20 0 -88
CLX-Lag050 5 Ground Reservoir And Water Tank 90 03-Nov-19 31-Jan-20 0 -88 CLX-Lag050 5
Silang East Interchange TP-1B (Exit Toll Plaza) 139 17-Nov-19 03-Apr-2 0 0 -88
Toll Plaza 98 17-Nov-19 22-Feb-20 0 -88
CLX-Lag050 6 Toll Canopy Structure 56 17-Nov-19 11-Jan-20 0 -88 CLX-Lag050 6
CLX-Lag050 7 Underground Power and Auxilliary 28 17-Nov-19 14-Dec-19 0 -88 CLX-Lag050 7
CLX-Lag050 8 Grounding System 12 19-Nov-19 30-Nov-19 0 -88 CLX-Lag050 8
CLX-Lag050 9 Storm Drainage and Sewerage System, and Water System 88 19-Nov-19 14-Feb-20 0 -88 CLX-Lag050 9
CLX-Lag051 0 Toll Island 76 01-Dec-19 14-Feb-20 0 -88 CLX-Lag051 0
CLX-Lag051 1 Lightning Protec0on System 14 01-Dec-19 14-Dec-19 0 -88 CLX-Lag051 1
CLX-Lag051 2 Metal Beam Guardrail 28 22-Dec-19 18-Jan-20 0 -88 CLX-Lag051 2
CLX-Lag051 3 Canopy Ligh0ng System 46 05-Jan-20 19-Feb-20 0 -88 CLX-Lag051 3
CLX-Lag051 4 Toll Booth 46 05-Jan-20 19-Feb-20 0 -88 CLX-Lag051 4
Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 16 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag051 5 Protec 0on Bollards 18 19-Jan-20 05-Feb-20 0 -88 CLX-Lag051 5
CLX-Lag051 6 War ning / Flashing Light 28 19-Jan-20 15-Feb-20 0 -88 CLX-Lag051 6
CLX-Lag051 7 Protec 0on Bar riers (Toll Booth) 21 26-Jan-20 15-Feb-20 0 -88 CLX-Lag051 7
CLX-Lag051 8 Protec 0on Bar riers (Mini Building) 21 02-Feb-20 22-Feb-20 0 -88 CLX-Lag051 8
CLX-Lag051 9 Pedestrian Gates 14 09-Feb-20 22-Feb-20 0 -88 CLX-Lag051 9
Mini Building 118 08-Dec-19 03-Apr-2 0 0 -88
CLX-Lag052 0 Mini Building Structure including Ligh0ng and Power 56 08-Dec-19 01-Feb-20 0 -88 CLX-Lag052 0
CLX-Lag052 1 Grounding System 14 08-Dec-19 21-Dec-19 0 -88 CLX-Lag052 1
CLX-Lag052 2 Intercom and Communica0on System 62 15-Dec-19 14-Feb-20 0 -88 CLX-Lag052 2
CLX-Lag052 3 Video Surveilance System 62 02-Feb-20 03-Apr-2 0 0 -88 CLX-Lag052 3
CLX-Lag052 4 Access Control and Intrusion Detec0on System (ACID) 62 02-Feb-20 03-Apr-2 0 0 -88 CLX-Lag052 4
CLX-Lag052 5 Facili0es Control and Monitoring System 62 02-Feb-20 03-Apr-2 0 0 -88 CLX-Lag052 5
CLX-Lag052 6 Air Condi0oning and Ven0la0on System 62 02-Feb-20 03-Apr-2 0 0 -88 CLX-Lag052 6
CLX-Lag052 7 Fire Detec0ons and Alarm Sytems 62 02-Feb-20 03-Apr-2 0 0 -88 CLX-Lag052 7
CLX-Lag052 8 Lightning Protec0on System 14 02-Feb-20 15-Feb-20 0 -88 CLX-Lag052 8
Ground Reservoir And Water Tank 55 22-Dec-19 14-Feb-20 0 -88
CLX-Lag052 9 Ground Reservoir And Water Tank 55 22-Dec-19 14-Feb-20 0 -88 CLX-Lag052 9
Silang East Interchange TP-1C (Exit Toll Plaza) 132 01-Dec-19 10-Apr-2 0 0 -88
Toll Plaza 98 01-Dec-19 07-Mar-20 0 -88
CLX-Lag053 0 Toll Canopy Structure 56 01-Dec-19 25-Jan-20 0 -88 CLX-Lag053 0
CLX-Lag053 1 Underground Power and Auxilliary 28 01-Dec-19 28-Dec-19 0 -88 CLX-Lag053 1
CLX-Lag053 2 Grounding System 12 03-Dec-19 14-Dec-19 0 -88 CLX-Lag053 2
CLX-Lag053 3 Storm Drainage and Sewerage System, and Water System 88 03-Dec-19 28-Feb-20 0 -88 CLX-Lag053 3
CLX-Lag053 4 Toll Island 76 15-Dec-19 28-Feb-20 0 -88 CLX-Lag053 4
CLX-Lag053 5 Lightning Protec0on System 14 15-Dec-19 28-Dec-19 0 -88 CLX-Lag053 5
CLX-Lag053 6 Metal Beam Guardrail 28 05-Jan-20 01-Feb-20 0 -88 CLX-Lag053 6
CLX-Lag053 7 Canopy Ligh0ng System 46 19-Jan-20 04-Mar-20 0 -88 CLX-Lag053 7
CLX-Lag053 8 Toll Booth 46 19-Jan-20 04-Mar-20 0 -88 CLX-Lag053 8
CLX-Lag053 9 Protec 0on Bollards 18 02-Feb-20 19-Feb-20 0 -88 CLX-Lag053 9
CLX-Lag054 0 War ning / Flashing Light 28 02-Feb-20 29-Feb-20 0 -88 CLX-Lag054 0
CLX-Lag054 1 Protec 0on Bar riers (Toll Booth) 21 09-Feb-20 29-Feb-20 0 -88 CLX-Lag054 1
CLX-Lag054 2 Protec 0on Bar riers (Mini Building) 21 16-Feb-20 07-Mar-20 0 -88 CLX-Lag054 2
CLX-Lag054 3 Pedestrian Gates 14 23-Feb-20 07-Mar-20 0 -88 CLX-Lag054 3
Mini Building 118 15-Dec-19 10-Apr-2 0 0 -88
CLX-Lag054 4 Mini Building Structure including Ligh0ng and Power 56 15-Dec-19 08-Feb-20 0 -88 CLX-Lag054 4
CLX-Lag054 5 Grounding System 14 15-Dec-19 28-Dec-19 0 -88 CLX-Lag054 5
CLX-Lag054 6 Intercom and Communica0on System 62 22-Dec-19 21-Feb-20 0 -88 CLX-Lag054 6
CLX-Lag054 7 Video Surveilance System 62 09-Feb-20 10-Apr-2 0 0 -88 CLX-Lag054 7
CLX-Lag054 8 Access Control and Intrusion Detec0on System (ACID) 62 09-Feb-20 10-Apr-2 0 0 -88 CLX-Lag054 8
CLX-Lag054 9 Facili0es Control and Monitoring System 62 09-Feb-20 10-Apr-2 0 0 -88 CLX-Lag054 9
CLX-Lag055 0 Air Condi0oning and Ven0la0on System 62 09-Feb-20 10-Apr-2 0 0 -88 CLX-Lag055 0
CLX-Lag055 1 Fire Detec0ons and Alarm Sytems 62 09-Feb-20 10-Apr-2 0 0 -88 CLX-Lag055 1

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 17 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag055 2 Lightning Protec0on System 14 09-Feb-20 22-Feb-20 0 -88 CLX-Lag055 2
Ground Reservoir And Water Tank 55 26-Jan-20 20-Mar-20 0 -88
CLX-Lag055 3 Ground Reservoir And Water Tank 55 26-Jan-20 20-Mar-20 0 -88 CLX-Lag055 3
Silang East Interchange TP-1D (Entry Toll Plaza) 95 15-Dec-19 18-Mar-20 0 -88
Toll Plaza 95 15-Dec-19 18-Mar-20 0 -88
CLX-Lag055 4 Toll Canopy Structure 56 15-Dec-19 08-Feb-20 0 -88 CLX-Lag055 4
CLX-Lag055 5 Grounding System 12 17-Dec-19 28-Dec-19 0 -88 CLX-Lag055 5
CLX-Lag055 6 Storm Drainage and Sewerage System, and Water System 88 17-Dec-19 13-Mar-20 0 -88 CLX-Lag055 6
CLX-Lag055 7 Toll Island 76 29-Dec-19 13-Mar-20 0 -88 CLX-Lag055 7
CLX-Lag055 8 Lightning Protec0on System 14 29-Dec-19 11-Jan-20 0 -88 CLX-Lag055 8
CLX-Lag055 9 Metal Beam Guardrail 28 19-Jan-20 15-Feb-20 0 -88 CLX-Lag055 9
CLX-Lag056 0 Canopy Ligh0ng System 46 02-Feb-20 18-Mar-20 0 -88 CLX-Lag056 0
CLX-Lag056 1 Latrine with Bowl 18 09-Feb-20 26-Feb-20 0 -88 CLX-Lag056 1
CLX-Lag056 2 Underground Power and Auxilliary 28 09-Feb-20 07-Mar-20 0 -88 CLX-Lag056 2
CLX-Lag056 3 Protec 0on Bollards 18 16-Feb-20 04-Mar-20 0 -88 CLX-Lag056 3
CLX-Lag056 4 War ning / Flashing Light 28 16-Feb-20 14-Mar-20 0 -88 CLX-Lag056 4
CLX-Lag056 5 Protec 0on Bar riers 21 23-Feb-20 14-Mar-20 0 -88 CLX-Lag056 5
CLX-Lag056 6 Pedestrian Gates 14 01-Mar-20 14-Mar-20 0 -88 CLX-Lag056 6
Ground Reservoir And Water Tank 55 19-Jan-20 13-Mar-20 0 -88
CLX-Lag056 7 Ground Reservoir And Water Tank 55 19-Jan-20 13-Mar-20 0 -88 CLX-Lag056 7
Sta. Rosa-Tagaytay Interchange TP-2 132 06-Mar-19 15-Jul-19 0 -87
Toll Plaza 98 06-Mar-19 11-Jun-19 0 -87
CLX-Lag056 8 Toll Canopy Structure 56 06-Mar-19 30-Apr-1 9 0 -87 CLX-Lag056 8
CLX-Lag056 9 Underground Power and Auxilliary 28 06-Mar-19 02-Apr-1 9 0 -87 CLX-Lag056 9
CLX-Lag057 0 Grounding System 12 08-Mar-19 19-Mar-19 0 -87 CLX-Lag057 0
CLX-Lag057 1 Storm Drainage and Sewerage System, and Water System 88 08-Mar-19 03-Jun-19 0 -87 CLX-Lag057 1
CLX-Lag057 2 Toll Island 76 20-Mar-19 03-Jun-19 0 -87 CLX-Lag057 2
CLX-Lag057 3 Lightning Protec0on System 14 20-Mar-19 02-Apr-1 9 0 -87 CLX-Lag057 3
CLX-Lag057 4 Metal Beam Guardrail 28 10-Apr-1 9 07-May-1 9 0 -87 CLX-Lag057 4
CLX-Lag057 5 Canopy Ligh0ng System 46 24-Apr-1 9 08-Jun-19 0 -87 CLX-Lag057 5
CLX-Lag057 6 Toll Booth 46 24-Apr-1 9 08-Jun-19 0 -87 CLX-Lag057 6
CLX-Lag057 7 Catwalk and Access Stairs 18 01-May-1 9 18-May-1 9 0 -87 CLX-Lag057 7
CLX-Lag057 8 Protec 0on Bollards 18 08-May-1 9 25-May-1 9 0 -87 CLX-Lag057 8
CLX-Lag057 9 War ning / Flashing Light 28 08-May-1 9 04-Jun-19 0 -87 CLX-Lag057 9
CLX-Lag058 0 Protec 0on Bar riers (Toll Booth) 21 15-May-1 9 04-Jun-19 0 -87 CLX-Lag058 0
CLX-Lag058 1 Protec 0on Bar riers (Mini Building) 21 22-May-1 9 11-Jun-19 0 -87 CLX-Lag058 1
CLX-Lag058 2 Pedestrian Gates 14 29-May-1 9 11-Jun-19 0 -87 CLX-Lag058 2
Mini Building 118 20-Mar-19 15-Jul-19 0 -87
CLX-Lag058 3 Mini Building Structure including Ligh0ng and Power 56 20-Mar-19 14-May-1 9 0 -87 CLX-Lag058 3
CLX-Lag058 4 Grounding System 14 20-Mar-19 02-Apr-1 9 0 -87 CLX-Lag058 4
CLX-Lag058 5 Intercom and Communica0on System 62 27-Mar-19 27-May-1 9 0 -87 CLX-Lag058 5
CLX-Lag058 6 Video Surveilance System 62 15-May-1 9 15-Jul-19 0 -87 CLX-Lag058 6

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 18 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag058 7 Access Control and Intrusion Detec0on System (ACID) 62 15-May-1 9 15-Jul-19 0 -87 CLX-Lag058 7
CLX-Lag058 8 Facili0es Control and Monitoring System 62 15-May-1 9 15-Jul-19 0 -87 CLX-Lag058 8
CLX-Lag058 9 Air Condi0oning and Ven0la0on System 62 15-May-1 9 15-Jul-19 0 -87 CLX-Lag058 9
CLX-Lag059 0 Fire Detec0ons and Alarm Sytems 62 15-May-1 9 15-Jul-19 0 -87 CLX-Lag059 0
CLX-Lag059 1 Lightning Protec0on System 14 15-May-1 9 28-May-1 9 0 -87 CLX-Lag059 1
Ground Reservoir And Water Tank 55 10-Apr-1 9 03-Jun-19 0 -87
CLX-Lag059 2 Ground Reservoir And Water Tank 55 10-Apr-1 9 03-Jun-19 0 -87 CLX-Lag059 2
TELECOM DUCTING 474 03-Dec-18 20-Mar-20 -1 -88
Sta. 27 + 900.000 to Sta. 29 + 439.852 (WB16) 69 19-Sep-19 26-Nov-19 0 -88
CLX-Lag059 3 Ductbank 46 19-Sep-19 03-Nov-19 0 -88 CLX-Lag059 3
CLX-Lag059 4 Carriage Duc0ng 12 04-Nov-19 15-Nov-19 0 -88 CLX-Lag059 4
CLX-Lag059 5 Pullbox 4 16-Nov-19 19-Nov-19 0 -88 CLX-Lag059 5
CLX-Lag059 6 Telecom Manhole 7 20-Nov-19 26-Nov-19 0 -88 CLX-Lag059 6
Sta. 29 + 509.852 (WB16) to Sta. 30 + 115.000 (WB17) 32 04-Nov-19 05-Dec-19 0 -88
CLX-Lag059 7 Ductbank 18 04-Nov-19 21-Nov-19 0 -88 CLX-Lag059 7
CLX-Lag059 8 Carriage Duc0ng 5 22-Nov-19 26-Nov-19 0 -88 CLX-Lag059 8
CLX-Lag059 9 Pullbox 2 27-Nov-19 28-Nov-19 0 -88 CLX-Lag059 9
CLX-Lag060 0 Telecom Manhole 7 29-Nov-19 05-Dec-19 0 -88 CLX-Lag060 0
Sta. 30 + 140.000 (WB17) to Sta. 31 + 036.510 (EB9) 45 22-Nov-19 05-Jan-20 0 -88
CLX-Lag060 1 Ductbank 27 22-Nov-19 18-Dec-19 0 -88 CLX-Lag060 1
CLX-Lag060 2 Carriage Duc0ng 7 19-Dec-19 25-Dec-19 0 -88 CLX-Lag060 2
CLX-Lag060 3 Pullbox 4 26-Dec-19 29-Dec-19 0 -88 CLX-Lag060 3
CLX-Lag060 4 Telecom Manhole 7 30-Dec-19 05-Jan-20 0 -88 CLX-Lag060 4
Sta. 31 + 071.510 (EB9) to Sta. 31 + 430.450 (WB18) 25 19-Dec-19 12-Jan-20 0 -88
CLX-Lag060 5 Ductbank 11 19-Dec-19 29-Dec-19 0 -88 CLX-Lag060 5
CLX-Lag060 6 Carriage Duc0ng 3 30-Dec-19 01-Jan-20 0 -88 CLX-Lag060 6
CLX-Lag060 7 Pullbox 2 02-Jan-20 03-Jan-20 0 -88 CLX-Lag060 7
CLX-Lag060 8 Telecom Manhole 7 06-Jan-20 12-Jan-20 0 -88 CLX-Lag060 8
Sta. 31 + 491.550 (WB18) to Sta. 31+ 828.000 (WB19) 22 30-Dec-19 20-Jan-20 0 -88
CLX-Lag060 9 Ductbank 10 30-Dec-19 08-Jan-20 0 -88 CLX-Lag060 9
CLX-Lag061 0 Carriage Duc0ng 3 09-Jan-20 11-Jan-20 0 -88 CLX-Lag061 0
CLX-Lag061 1 Pullbox 2 12-Jan-20 13-Jan-20 0 -88 CLX-Lag061 1
CLX-Lag061 2 Telecom Manhole 7 14-Jan-20 20-Jan-20 0 -88 CLX-Lag061 2
Sta. 31 + 903.000 (WB19) to Sta. 33 + 025.279 (WB20) 53 28-Jan-20 20-Mar-20 0 -88
CLX-Lag061 3 Ductbank 34 28-Jan-20 01-Mar-20 0 -88 CLX-Lag061 3
CLX-Lag061 4 Carriage Duc0ng 9 02-Mar-20 10-Mar-20 0 -88 CLX-Lag061 4
CLX-Lag061 5 Pullbox 3 11-Mar-20 13-Mar-20 0 -88 CLX-Lag061 5
CLX-Lag061 6 Telecom Manhole 7 14-Mar-20 20-Mar-20 0 -88 CLX-Lag061 6
Sta. 33 + 144.363 (WB20) to Sta. 33 + 608.000 (WB21) 27 04-Mar-19 30-Mar-19 0 -87
CLX-Lag061 7 Ductbank 14 04-Mar-19 17-Mar-19 0 -87 CLX-Lag061 7
CLX-Lag061 8 Carriage Duc0ng 4 18-Mar-19 21-Mar-19 0 -87 CLX-Lag061 8
CLX-Lag061 9 Pullbox 2 22-Mar-19 23-Mar-19 0 -87 CLX-Lag061 9
Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 19 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag062 0 Telecom Manhole 7 24-Mar-19 30-Mar-19 0 -87 CLX-Lag062 0
Sta. 33 + 698.000 (WB21) to Sta. 33 + 924.000 (WB22) 26 22-Feb-19 19-Mar-19 0 -87
CLX-Lag062 1 Ductbank 10 22-Feb-19 03-Mar-19 0 -87 CLX-Lag062 1
CLX-Lag062 2 Carriage Duc0ng 3 04-Mar-19 06-Mar-19 0 -87 CLX-Lag062 2
CLX-Lag062 3 Pullbox 2 07-Mar-19 08-Mar-19 0 -87 CLX-Lag062 3
CLX-Lag062 4 Telecom Manhole 7 13-Mar-19 19-Mar-19 0 -87 CLX-Lag062 4
Sta. 34 + 014.000 (WB22) to Sta. 34 + 782.833 (WB23) 52 20-Jan-19 12-Mar-19 0 -87
CLX-Lag062 5 Ductbank 33 20-Jan-19 21-Feb-19 0 -87 CLX-Lag062 5
CLX-Lag062 6 Carriage Duc0ng 9 22-Feb-19 02-Mar-19 0 -87 CLX-Lag062 6
CLX-Lag062 7 Pullbox 3 03-Mar-19 05-Mar-19 0 -87 CLX-Lag062 7
CLX-Lag062 8 Telecom Manhole 7 06-Mar-19 12-Mar-19 0 -87 CLX-Lag062 8
Sta. 34 + 921.525 (WB23) to Sta. 35 + 118.380 (WB24) 33 09-Jan-19 10-Feb-19 0 -87
CLX-Lag062 9 Ductbank 9 09-Jan-19 17-Jan-19 0 -87 CLX-Lag062 9
CLX-Lag063 0 Carriage Duc0ng 2 18-Jan-19 19-Jan-19 0 -87 CLX-Lag063 0
CLX-Lag063 1 Pullbox 2 20-Jan-19 21-Jan-19 0 -87 CLX-Lag063 1
CLX-Lag063 2 Telecom Manhole 7 04-Feb-19 10-Feb-19 0 -87 CLX-Lag063 2
Sta. 35 + 338.280 (WB24) to Sta. 35 + 625.480 (WB25) 38 28-Dec-18 03-Feb-19 0 -87
CLX-Lag063 3 Ductbank 12 28-Dec-18 08-Jan-19 0 -87 CLX-Lag063 3
CLX-Lag063 4 Carriage Duc0ng 3 09-Jan-19 11-Jan-19 0 -87 CLX-Lag063 4
CLX-Lag063 5 Pullbox 2 12-Jan-19 13-Jan-19 0 -87 CLX-Lag063 5
CLX-Lag063 6 Telecom Manhole 7 28-Jan-19 03-Feb-19 0 -87 CLX-Lag063 6
Sta. 35 + 664.320 (WB25) to Sta. 37 + 053.562 (WB28) 56 03-Dec-18 27-Jan-19 0 -87
CLX-Lag063 7 Ductbank 25 03-Dec-18 27-Dec-18 0 -87 CLX-Lag063 7
CLX-Lag063 8 Carriage Duc0ng 7 28-Dec-18 03-Jan-19 0 -87 CLX-Lag063 8
CLX-Lag063 9 Pullbox 2 04-Jan-19 05-Jan-19 0 -87 CLX-Lag063 9
CLX-Lag064 0 Telecom Manhole 7 21-Jan-19 27-Jan-19 0 -87 CLX-Lag064 0
Sta. 36 + 282.748 (EB10) to Sta. 37 + 053.562 (WB28) 110 17-May-1 9 03-Sep-19 0 -88
CLX-Lag064 1 Ductbank 71 17-May-1 9 26-Jul-19 0 -88 CLX-Lag064 1
CLX-Lag064 2 Carriage Duc0ng 19 27-Jul-19 14-Aug-19 0 -88 CLX-Lag064 2
CLX-Lag064 3 Pullbox 6 15-Aug-19 20-Aug-19 0 -88 CLX-Lag064 3
CLX-Lag064 4 Telecom Manhole 14 21-Aug-19 03-Sep-19 0 -88 CLX-Lag064 4
Sta. 36 + 282.748 (EB10) to Sta. 37 + 933.890 (WB26) 54 18-Mar-19 10-May-1 9 0 -87
CLX-Lag064 5 Ductbank 35 18-Mar-19 21-Apr-1 9 0 -87 CLX-Lag064 5
CLX-Lag064 6 Carriage Duc0ng 9 22-Apr-1 9 30-Apr-1 9 0 -87 CLX-Lag064 6
CLX-Lag064 7 Pullbox 3 01-May-1 9 03-May-1 9 0 -87 CLX-Lag064 7
CLX-Lag064 8 Telecom Manhole 7 04-May-1 9 10-May-1 9 0 -87 CLX-Lag064 8
STA 37+930.525 TO STA. 45+311.016 (7.38KM) 368 03-Mar-18 21-Feb-19 -110 -87
EARTHWORKS 243 03-Mar-18 30-Oct-1 8 -110 -87
Sta. 37 + 983.890 (WB26) to Sta. 38 + 454.400 (V1) 217 03-Mar-18 30-Oct-1 8 -266 -87
CLX-Lag064 9 Clearing & Grubbing 12 03-Mar-18 08-Mar-18 -250 -71 CLX-Lag064 9
CLX-Lag065 0 Subgrade Prepara0on 11 17-Aug-18 27-Aug-18 0 -88 CLX-Lag065 0

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 20 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag065 1 Embankment 14 17-Oct-1 8 30-Oct-1 8 0 -87 CLX-Lag065 1
Sta. 38 + 835.400 (V1) to Sta. 39 + 203.680 (WB27) 213 03-Mar-18 16-Oct-1 8 -169 -87
CLX-Lag065 2 Clearing & Grubbing 10 03-Mar-18 07-Mar-18 -164 -82 CLX-Lag065 2
CLX-Lag065 3 Subgrade Prepara0on 10 07-Aug-18 16-Aug-18 0 -88 CLX-Lag065 3
CLX-Lag065 4 Embankment 14 03-Oct-1 8 16-Oct-1 8 0 -87 CLX-Lag065 4
Sta. 39 + 251.680 (WB27) to Sta. 40 + 473.823 (EB11) 112 03-Mar-18 02-Oct-1 8 -139 -87
CLX-Lag065 5 Clearing & Grubbing 32 03-Mar-18 18-Mar-18 -155 -103 CLX-Lag065 5
CLX-Lag065 6 Subgrade Prepara0on 29 09-Jul-18 06-Aug-18 0 -88 CLX-Lag065 6
CLX-Lag065 7 Embankment 7 26-Sep-18 02-Oct-1 8 0 -87 CLX-Lag065 7
Sta. 40 + 508.823 (EB11) to Sta. 41 + 112.330 (EB12) 121 25-Jun-18 25-Sep-18 -125 -87
CLX-Lag065 8 Clearing & Grubbing 16 -155 -117
CLX-Lag065 9 Subgrade Prepara0on 14 25-Jun-18 08-Jul-18 0 -88 CLX-Lag065 9
CLX-Lag066 0 Embankment 42 15-Aug-18 25-Sep-18 0 -87 CLX-Lag066 0
Sta. 41 + 146.330 (EB12) to Sta. 41 + 653.400 (V2) 82 13-Jun-18 14-Aug-18 -111 -87
CLX-Lag066 1 Clearing & Grubbing 14 -157 -133
CLX-Lag066 2 Subgrade Prepara0on 12 13-Jun-18 24-Jun-18 0 -88 CLX-Lag066 2
CLX-Lag066 3 Embankment 56 20-Jun-18 14-Aug-18 0 -87 CLX-Lag066 3
Sta. 42 + 072.300 (V2) to Sta. 43 + 347.500 (EB13) 69 10-Apr-1 8 17-Jun-18 136 -85
CLX-Lag066 4 Clearing & Grubbing 34 10-Apr-1 8 13-May-1 8 0 -221 CLX-Lag066 4
CLX-Lag066 5 Subgrade Prepara0on 30 14-May-1 8 12-Jun-18 0 -88 CLX-Lag066 5
CLX-Lag066 6 Embankment 28 21-May-1 8 17-Jun-18 0 -85 CLX-Lag066 6
Sta. 43 + 382.500 (EB13) to Sta. 44 + 809.998 (EB14) 75 03-Mar-18 16-May-1 8 140 -81
CLX-Lag066 7 Clearing & Grubbing 38 03-Mar-18 09-Apr-1 8 0 -221 CLX-Lag066 7
CLX-Lag066 8 Subgrade Prepara0on 34 10-Apr-1 8 13-May-1 8 0 -88 CLX-Lag066 8
CLX-Lag066 9 Embankment 30 17-Apr-1 8 16-May-1 8 0 -81 CLX-Lag066 9
Sta. 44 + 840.002 (EB14) to Sta. 45 + 311.016 26 03-Mar-18 27-Mar-18 30 -61
CLX-Lag067 0 Clearing & Grubbing 12 -109 -200
CLX-Lag067 1 Subgrade Prepara0on 11 03-Mar-18 13-Mar-18 0 -61 CLX-Lag067 1
CLX-Lag067 2 Embankment 11 17-Mar-18 27-Mar-18 0 -61 CLX-Lag067 2
SUB-BASE AND BASE COURSE 190 02-May-1 8 07-Nov-18 -26 -87
Sta. 37 + 983.890 (WB26) to Sta. 38 + 454.400 (V1) 8 31-Oct-1 8 07-Nov-18 0 -87
CLX-Lag067 3 Crushed Aggregate Base Course 5 31-Oct-1 8 04-Nov-18 0 -87 CLX-Lag067 3
CLX-Lag067 4 Portland Cement Treated Mix Base Course 5 03-Nov-18 07-Nov-18 0 -87 CLX-Lag067 4
Sta. 38 + 835.400 (V1) to Sta. 39 + 203.680 (WB27) 7 17-Oct-1 8 23-Oct-1 8 0 -87
CLX-Lag067 5 Crushed Aggregate Base Course 4 17-Oct-1 8 20-Oct-1 8 0 -87 CLX-Lag067 5
CLX-Lag067 6 Portland Cement Treated Mix Base Course 4 20-Oct-1 8 23-Oct-1 8 0 -87 CLX-Lag067 6
Sta. 39 + 251.680 (WB27) to Sta. 40 + 473.823 (EB11) 17 03-Oct-1 8 19-Oct-1 8 0 -87
CLX-Lag067 7 Crushed Aggregate Base Course 14 03-Oct-1 8 16-Oct-1 8 0 -87 CLX-Lag067 7
CLX-Lag067 8 Portland Cement Treated Mix Base Course 14 06-Oct-1 8 19-Oct-1 8 0 -87 CLX-Lag067 8
Sta. 40 + 508.823 (EB11) to Sta. 41 + 112.330 (EB12) 10 26-Sep-18 05-Oct-1 8 0 -87
CLX-Lag067 9 Crushed Aggregate Base Course 7 26-Sep-18 02-Oct-1 8 0 -87 CLX-Lag067 9

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 21 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag068 0 Portland Cement Treated Mix Base Course 7 29-Sep-18 05-Oct-1 8 0 -87 CLX-Lag068 0
Sta. 41 + 146.330 (EB12) to Sta. 41 + 653.400 (V2) 9 15-Aug-18 23-Aug-18 0 -87
CLX-Lag068 1 Crushed Aggregate Base Course 6 15-Aug-18 20-Aug-18 0 -87 CLX-Lag068 1
CLX-Lag068 2 Portland Cement Treated Mix Base Course 6 18-Aug-18 23-Aug-18 0 -87 CLX-Lag068 2
Sta. 42 + 072.300 (V2) to Sta. 43 + 347.500 (EB13) 17 18-Jun-18 04-Jul-18 0 -85
CLX-Lag068 3 Crushed Aggregate Base Course 14 18-Jun-18 01-Jul-18 0 -85 CLX-Lag068 3
CLX-Lag068 4 Portland Cement Treated Mix Base Course 14 21-Jun-18 04-Jul-18 0 -85 CLX-Lag068 4
Sta. 43 + 382.500 (EB13) to Sta. 44 + 809.998 (EB14) 19 17-May-1 8 04-Jun-18 0 -71
CLX-Lag068 5 Crushed Aggregate Base Course 16 17-May-1 8 01-Jun-18 0 -71 CLX-Lag068 5
CLX-Lag068 6 Portland Cement Treated Mix Base Course 16 20-May-1 8 04-Jun-18 0 -71 CLX-Lag068 6
Sta. 44 + 840.002 (EB14) to Sta. 45 + 311.016 8 02-May-1 8 09-May-1 8 0 -61
CLX-Lag068 7 Crushed Aggregate Base Course 5 02-May-1 8 06-May-1 8 0 -61 CLX-Lag068 7
CLX-Lag068 8 Portland Cement Treated Mix Base Course 5 05-May-1 8 09-May-1 8 0 -61 CLX-Lag068 8
SURFACE COURSE 161 01-Jul-18 08-Dec-18 -9 -70
Sta. 37 + 983.890 (WB26) to Sta. 38 + 454.400 (V1) 12 27-Nov-18 08-Dec-18 0 -70
CLX-Lag068 9 Portland Cement Concrete Pavement 12 27-Nov-18 08-Dec-18 0 -70 CLX-Lag068 9
Sta. 38 + 835.400 (V1) to Sta. 39 + 203.680 (WB27) 9 18-Nov-18 26-Nov-18 0 -70
CLX-Lag069 0 Portland Cement Concrete Pavement 9 18-Nov-18 26-Nov-18 0 -70 CLX-Lag069 0
Sta. 39 + 251.680 (WB27) to Sta. 40 + 473.823 (EB11) 29 20-Oct-1 8 17-Nov-18 0 -70
CLX-Lag069 1 Portland Cement Concrete Pavement 29 20-Oct-1 8 17-Nov-18 0 -70 CLX-Lag069 1
Sta. 40 + 508.823 (EB11) to Sta. 41 + 112.330 (EB12) 14 06-Oct-1 8 19-Oct-1 8 0 -70
CLX-Lag069 2 Portland Cement Concrete Pavement 14 06-Oct-1 8 19-Oct-1 8 0 -70 CLX-Lag069 2
Sta. 41 + 146.330 (EB12) to Sta. 41 + 653.400 (V2) 12 15-Sep-18 26-Sep-18 0 -61
CLX-Lag069 3 Portland Cement Concrete Pavement 12 15-Sep-18 26-Sep-18 0 -61 CLX-Lag069 3
Sta. 42 + 072.300 (V2) to Sta. 43 + 347.500 (EB13) 31 15-Aug-18 14-Sep-18 0 -61
CLX-Lag069 4 Portland Cement Concrete Pavement 31 15-Aug-18 14-Sep-18 0 -61 CLX-Lag069 4
Sta. 43 + 382.500 (EB13) to Sta. 44 + 809.998 (EB14) 34 12-Jul-18 14-Aug-18 0 -61
CLX-Lag069 5 Portland Cement Concrete Pavement 34 12-Jul-18 14-Aug-18 0 -61 CLX-Lag069 5
Sta. 44 + 840.002 (EB14) to Sta. 45 + 311.016 11 01-Jul-18 11-Jul-18 0 -61
CLX-Lag069 6 Portland Cement Concrete Pavement 11 01-Jul-18 11-Jul-18 0 -61 CLX-Lag069 6
BRIDGE CONSTRUCTION 293 03-Mar-18 08-Dec-18 -25 -35
Sta. Rosa Overpass Bridge (OB11) @ STA. 38+260 133 14-Apr-1 8 25-Aug-18 0 15
CLX-Lag069 7 Bored Pile 21 14-Apr-1 8 05-May-1 8 0 15 CLX-Lag069 7
CLX-Lag069 8 Coping Beam 42 28-Apr-1 8 09-Jun-18 0 15 CLX-Lag069 8
CLX-Lag069 9 Pre-cast Girder 7 23-Jun-18 30-Jun-18 0 15 CLX-Lag069 9
CLX-Lag070 0 Diaphragm/Deck Slab/Railing/Barrier 42 30-Jun-18 11-Aug-18 0 15 CLX-Lag070 0
CLX-Lag070 1 Grouted Riprap 42 14-Jul-18 25-Aug-18 0 15 CLX-Lag070 1
Carmen Nuvali Waterway Bridge (WB26) STA. 37+933.89 to STA. 37+983.89 217 03-Mar-18 05-Oct-1 8 16 22
CLX-Lag070 2 Access Road/Excava0on 28 03-Mar-18 21-Mar-18 -31 -25 CLX-Lag070 2
CLX-Lag070 3 Bored Pile 63 03-Mar-18 14-Apr-1 8 -11 15 CLX-Lag070 3
CLX-Lag070 4 Column 77 03-Mar-18 18-May-1 8 0 22 CLX-Lag070 4

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 22 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag070 5 Coping Beam 56 21-Apr-1 8 15-Jun-18 0 22 CLX-Lag070 5
CLX-Lag070 6 Pre-cast Girder 7 07-Jul-18 13-Jul-18 0 22 CLX-Lag070 6
CLX-Lag070 7 Diaphragm/Deck Slab/Railing/Barrier 56 14-Jul-18 07-Sep-18 0 22 CLX-Lag070 7
CLX-Lag070 8 Grouted Riprap 56 11-Aug-18 05-Oct-1 8 0 22 CLX-Lag070 8
Ayala Nuvali Blvd Viaduct (V1) STA. 38+454.40 to STA. 38+835.40 105 03-Mar-18 12-Jul-18 -9 -19
CLX-Lag070 9 Bored Pile 28 13 3
CLX-Lag071 0 Column 28 19 5
CLX-Lag071 1 Coping Beam 28 03-Mar-18 08-Mar-18 -14 -19 CLX-Lag071 1
CLX-Lag071 2 Pre-cast Girder 7 29-Mar-18 05-Apr-1 8 0 -19 CLX-Lag071 2
CLX-Lag071 3 Diaphragm/Deck Slab/Railing/Barrier 28 05-Apr-1 8 03-May-1 8 0 -19 CLX-Lag071 3
CLX-Lag071 4 MSE Wall 56 19-Apr-1 8 14-Jun-18 0 -19 CLX-Lag071 4
CLX-Lag071 5 Drain Piping 28 19-Apr-1 8 17-May-1 8 0 -19 CLX-Lag071 5
CLX-Lag071 6 Approach Slab 56 17-May-1 8 12-Jul-18 0 -19 CLX-Lag071 6
Ayala Nuvali Waterway Bridge (WB27) STA. 39+203.68 to STA. 39+251.68 144 03-Mar-18 25-Jul-18 23 -10
CLX-Lag071 7 Access Road/Excava0on 28 03-Mar-18 04-Mar-18 -37 -70 CLX-Lag071 7
CLX-Lag071 8 Bored Pile 56 03-Mar-18 07-Apr-1 8 -25 -49 CLX-Lag071 8
CLX-Lag071 9 Column 56 03-Mar-18 27-Apr-1 8 0 -41 CLX-Lag071 9
CLX-Lag072 0 Coping Beam 56 03-Mar-18 25-Apr-1 8 -9 -10 CLX-Lag072 0
CLX-Lag072 1 Pre-cast Girder 7 16-May-1 8 23-May-1 8 0 -10 CLX-Lag072 1
CLX-Lag072 2 Diaphragm/Deck Slab/Railing/Barrier 42 23-May-1 8 04-Jul-18 0 -10 CLX-Lag072 2
CLX-Lag072 3 Grouted Riprap 42 13-Jun-18 25-Jul-18 0 -10 CLX-Lag072 3
Ayala Laguna Expressway Bridge 1 (EB11) STA. 40+473.823 TO STA. 40+508.823 130 03-Mar-18 26-Jul-18 -43 -47
CLX-Lag072 4 Bored Pile 28 3 -1
CLX-Lag072 5 Column 28 17 11
CLX-Lag072 6 Coping Beam 28 03-Mar-18 08-Mar-18 -33 -47 CLX-Lag072 6
CLX-Lag072 7 Pre-cast Girder 7 29-Mar-18 05-Apr-1 8 0 -47 CLX-Lag072 7
CLX-Lag072 8 Diaphragm/Deck Slab/Railing/Barrier 28 05-Apr-1 8 03-May-1 8 0 -47 CLX-Lag072 8
CLX-Lag072 9 MSE Wall 56 03-May-1 8 28-Jun-18 0 -47 CLX-Lag072 9
CLX-Lag073 0 Drain Piping 28 03-May-1 8 31-May-1 8 0 -47 CLX-Lag073 0
CLX-Lag073 1 Approach Slab 56 31-May-1 8 26-Jul-18 0 -47 CLX-Lag073 1
Ayala Laguna Expressway Bridge 2 (EB12) STA. 41+112.33 to STA. 41+146.33 151 03-Mar-18 29-Jun-18 -38 -48
CLX-Lag073 2 Bored Pile 28 -8 -18
CLX-Lag073 3 Column 28 19 0
CLX-Lag073 4 Coping Beam 28 03-Mar-18 08-Mar-18 -50 -75 CLX-Lag073 4
CLX-Lag073 5 Pre-cast Girder 7 03-Mar-18 09-Mar-18 -16 -48 CLX-Lag073 5
CLX-Lag073 6 Diaphragm/Deck Slab/Railing/Barrier 28 09-Mar-18 06-Apr-1 8 0 -48 CLX-Lag073 6
CLX-Lag073 7 MSE Wall 56 03-Mar-18 27-Apr-1 8 -11 -12 CLX-Lag073 7
CLX-Lag073 8 Drain Piping 28 06-Apr-1 8 04-May-1 8 0 -48 CLX-Lag073 8
CLX-Lag073 9 Approach Slab 56 04-May-1 8 29-Jun-18 0 -48 CLX-Lag073 9
Ayala Laguna Blvd. Viaduct (V2) STA. 41+653.40 to STA. 42+072.30 293 03-Mar-18 08-Dec-18 1 -35
CLX-Lag074 0 Bored Pile 63 -12 -48
CLX-Lag074 1 Column 196 146 106

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 23 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag074 2 Coping Beam 196 03-Mar-18 10-Mar-18 140 105 CLX-Lag074 2
CLX-Lag074 3 Pre-cast Girder 140 01-Apr-1 8 18-Aug-18 0 -35 CLX-Lag074 3
CLX-Lag074 4 Diaphragm/Deck Slab/Railing/Barrier 175 08-Apr-1 8 29-Sep-18 0 -35 CLX-Lag074 4
CLX-Lag074 5 MSE Wall 112 17-Jun-18 06-Oct-1 8 0 -35 CLX-Lag074 5
CLX-Lag074 6 Drain Piping 56 24-Jun-18 18-Aug-18 0 -35 CLX-Lag074 6
CLX-Lag074 7 Approach Slab 105 26-Aug-18 08-Dec-18 0 -35 CLX-Lag074 7
Ayala Laguna Blvd Expressway Bridge 3 (EB13) STA. 43+347.50 to STA. 43+382.50 112 03-Mar-18 19-Jul-18 -7 -12
CLX-Lag074 8 Bored Pile 28 -1 -6
CLX-Lag074 9 Column 28 26 7
CLX-Lag075 0 Coping Beam 28 03-Mar-18 08-Mar-18 -6 -12 CLX-Lag075 0
CLX-Lag075 1 Pre-cast Girder 7 29-Mar-18 05-Apr-1 8 0 -12 CLX-Lag075 1
CLX-Lag075 2 Diaphragm/Deck Slab/Railing/Barrier 42 05-Apr-1 8 17-May-1 8 0 -12 CLX-Lag075 2
CLX-Lag075 3 MSE Wall 56 26-Apr-1 8 21-Jun-18 0 -12 CLX-Lag075 3
CLX-Lag075 4 Drain Piping 21 03-May-1 8 24-May-1 8 0 -12 CLX-Lag075 4
CLX-Lag075 5 Approach Slab 56 24-May-1 8 19-Jul-18 0 -12 CLX-Lag075 5
Greenfield Expressway Bridge 2 (EB14) STA. 44+809.998 to STA. 44+840.002 142 03-Mar-18 13-Jul-18 24 15
CLX-Lag075 6 Bored Pile 28 13 4
CLX-Lag075 7 Column 28 19 17
CLX-Lag075 8 Coping Beam 28 03-Mar-18 09-Mar-18 2 15 CLX-Lag075 8
CLX-Lag075 9 Pre-cast Girder 7 24-Mar-18 30-Mar-18 0 15 CLX-Lag075 9
CLX-Lag076 0 Diaphragm/Deck Slab/Railing/Barrier 42 31-Mar-18 11-May-1 8 0 15 CLX-Lag076 0
CLX-Lag076 1 MSE Wall 56 21-Apr-1 8 15-Jun-18 0 15 CLX-Lag076 1
CLX-Lag076 2 Drain Piping 21 28-Apr-1 8 18-May-1 8 0 15 CLX-Lag076 2
CLX-Lag076 3 Approach Slab 56 19-May-1 8 13-Jul-18 0 15 CLX-Lag076 3
DRAINAGE AND SLOPE PROTECTION STRUCTURES 265 01-Apr-1 8 21-Dec-18 -56 -56
Sta. 37 + 983.890 (WB26) to Sta. 38 + 454.400 (V1) 71 12-Oct-1 8 21-Dec-18 -56 -56
CLX-Lag076 4 Ditch 15 07-Dec-18 21-Dec-18 0 -56 CLX-Lag076 4
CLX-Lag076 5 RCPC 15 12-Oct-1 8 26-Oct-1 8 0 0 CLX-Lag076 5
CLX-Lag076 6 Drainage Canal & Stepp ed Canal 15 07-Dec-18 21-Dec-18 0 -56 CLX-Lag076 6
CLX-Lag076 7 RCBC 15 12-Oct-1 8 26-Oct-1 8 0 0 CLX-Lag076 7
CLX-Lag076 8 Retaining Wall 15 07-Dec-18 21-Dec-18 0 -56 CLX-Lag076 8
CLX-Lag076 9 Grouted Riprap 15 07-Dec-18 21-Dec-18 0 -56 CLX-Lag076 9
CLX-Lag077 0 Catch Basin 13 14-Oct-1 8 26-Oct-1 8 0 0 CLX-Lag077 0
CLX-Lag077 1 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 8 19-Oct-1 8 26-Oct-1 8 0 0 CLX-Lag077 1
CLX-Lag077 2 Headwall 7 19-Oct-1 8 25-Oct-1 8 0 0 CLX-Lag077 2
Sta. 38 + 835.400 (V1) to Sta. 39 + 203.680 (WB27) 68 30-Sep-18 06-Dec-18 -56 -56
CLX-Lag077 3 Ditch 12 25-Nov-18 06-Dec-18 0 -56 CLX-Lag077 3
CLX-Lag077 4 RCPC 12 30-Sep-18 11-Oct-1 8 0 0 CLX-Lag077 4
CLX-Lag077 5 Drainage Canal & Stepp ed Canal 12 25-Nov-18 06-Dec-18 0 -56 CLX-Lag077 5
CLX-Lag077 6 RCBC 12 30-Sep-18 11-Oct-1 8 0 0 CLX-Lag077 6
CLX-Lag077 7 Retaining Wall 12 25-Nov-18 06-Dec-18 0 -56 CLX-Lag077 7
CLX-Lag077 8 Grouted Riprap 12 25-Nov-18 06-Dec-18 0 -56 CLX-Lag077 8

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 24 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag077 9 Catch Basin 10 02-Oct-1 8 11-Oct-1 8 0 0 CLX-Lag077 9
CLX-Lag078 0 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 5 07-Oct-1 8 11-Oct-1 8 0 0 CLX-Lag078 0
CLX-Lag078 1 Headwall 5 07-Oct-1 8 11-Oct-1 8 0 0 CLX-Lag078 1
Sta. 39 + 251.680 (WB27) to Sta. 40 + 473.823 (EB11) 96 21-Aug-18 24-Nov-18 -56 -56
CLX-Lag078 2 Ditch 40 16-Oct-1 8 24-Nov-18 0 -56 CLX-Lag078 2
CLX-Lag078 3 RCPC 40 21-Aug-18 29-Sep-18 0 0 CLX-Lag078 3
CLX-Lag078 4 Drainage Canal & Stepp ed Canal 40 16-Oct-1 8 24-Nov-18 0 -56 CLX-Lag078 4
CLX-Lag078 5 RCBC 40 21-Aug-18 29-Sep-18 0 0 CLX-Lag078 5
CLX-Lag078 6 Retaining Wall 40 16-Oct-1 8 24-Nov-18 0 -56 CLX-Lag078 6
CLX-Lag078 7 Grouted Riprap 40 16-Oct-1 8 24-Nov-18 0 -56 CLX-Lag078 7
CLX-Lag078 8 Catch Basin 38 23-Aug-18 29-Sep-18 0 0 CLX-Lag078 8
CLX-Lag078 9 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 33 28-Aug-18 29-Sep-18 0 0 CLX-Lag078 9
CLX-Lag079 0 Headwall 28 28-Aug-18 24-Sep-18 0 0 CLX-Lag079 0
Sta. 40 + 508.823 (EB11) to Sta. 41 + 112.330 (EB12) 76 01-Aug-18 15-Oct-1 8 -56 -56
CLX-Lag079 1 Ditch 20 26-Sep-18 15-Oct-1 8 0 -56 CLX-Lag079 1
CLX-Lag079 2 RCPC 20 01-Aug-18 20-Aug-18 0 0 CLX-Lag079 2
CLX-Lag079 3 Drainage Canal & Stepp ed Canal 20 26-Sep-18 15-Oct-1 8 0 -56 CLX-Lag079 3
CLX-Lag079 4 RCBC 20 01-Aug-18 20-Aug-18 0 0 CLX-Lag079 4
CLX-Lag079 5 Retaining Wall 20 26-Sep-18 15-Oct-1 8 0 -56 CLX-Lag079 5
CLX-Lag079 6 Grouted Riprap 20 26-Sep-18 15-Oct-1 8 0 -56 CLX-Lag079 6
CLX-Lag079 7 Catch Basin 18 03-Aug-18 20-Aug-18 0 0 CLX-Lag079 7
CLX-Lag079 8 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 13 08-Aug-18 20-Aug-18 0 0 CLX-Lag079 8
CLX-Lag079 9 Headwall 7 08-Aug-18 14-Aug-18 0 0 CLX-Lag079 9
Sta. 41 + 146.330 (EB12) to Sta. 41 + 653.400 (V2) 48 15-Jul-18 31-Aug-18 -31 -31
CLX-Lag080 0 Ditch 17 15-Aug-18 31-Aug-18 0 -31 CLX-Lag080 0
CLX-Lag080 1 RCPC 17 15-Jul-18 31-Jul-18 0 0 CLX-Lag080 1
CLX-Lag080 2 Drainage Canal & Stepp ed Canal 17 15-Aug-18 31-Aug-18 0 -31 CLX-Lag080 2
CLX-Lag080 3 RCBC 17 15-Jul-18 31-Jul-18 0 0 CLX-Lag080 3
CLX-Lag080 4 Retaining Wall 17 15-Aug-18 31-Aug-18 0 -31 CLX-Lag080 4
CLX-Lag080 5 Grouted Riprap 17 15-Aug-18 31-Aug-18 0 -31 CLX-Lag080 5
CLX-Lag080 6 Catch Basin 15 17-Jul-18 31-Jul-18 0 0 CLX-Lag080 6
CLX-Lag080 7 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 10 22-Jul-18 31-Jul-18 0 0 CLX-Lag080 7
CLX-Lag080 8 Headwall & Wingwall 7 22-Jul-18 28-Jul-18 0 0 CLX-Lag080 8
Sta. 42 + 072.300 (V2) to Sta. 43 + 347.500 (EB13) 72 03-Jun-18 13-Aug-18 -30 -30
CLX-Lag080 9 Ditch 42 03-Jul-18 13-Aug-18 0 -30 CLX-Lag080 9
CLX-Lag081 0 RCPC 42 03-Jun-18 14-Jul-18 0 0 CLX-Lag081 0
CLX-Lag081 1 Drainage Canal & Stepp ed Canal 42 03-Jul-18 13-Aug-18 0 -30 CLX-Lag081 1
CLX-Lag081 2 RCBC 42 03-Jun-18 14-Jul-18 0 0 CLX-Lag081 2
CLX-Lag081 3 Retaining Wall 42 03-Jul-18 13-Aug-18 0 -30 CLX-Lag081 3
CLX-Lag081 4 Grouted Riprap 42 03-Jul-18 13-Aug-18 0 -30 CLX-Lag081 4
CLX-Lag081 5 Catch Basin 40 05-Jun-18 14-Jul-18 0 0 CLX-Lag081 5
CLX-Lag081 6 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 35 10-Jun-18 14-Jul-18 0 0 CLX-Lag081 6

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 25 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag081 7 Headwall 28 10-Jun-18 07-Jul-18 0 0 CLX-Lag081 7
Sta. 43 + 382.500 (EB13) to Sta. 44 + 809.998 (EB14) 77 17-Apr-1 8 02-Jul-18 -30 -30
CLX-Lag081 8 Ditch 47 17-May-1 8 02-Jul-18 0 -30 CLX-Lag081 8
CLX-Lag081 9 RCPC 47 17-Apr-1 8 02-Jun-18 0 0 CLX-Lag081 9
CLX-Lag082 0 Drainage Canal & Stepp ed Canal 47 17-May-1 8 02-Jul-18 0 -30 CLX-Lag082 0
CLX-Lag082 1 RCBC 47 17-Apr-1 8 02-Jun-18 0 0 CLX-Lag082 1
CLX-Lag082 2 Retaining Wall 47 17-May-1 8 02-Jul-18 0 -30 CLX-Lag082 2
CLX-Lag082 3 Grouted Riprap 47 17-May-1 8 02-Jul-18 0 -30 CLX-Lag082 3
CLX-Lag082 4 Catch Basin 45 19-Apr-1 8 02-Jun-18 0 0 CLX-Lag082 4
CLX-Lag082 5 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 40 24-Apr-1 8 02-Jun-18 0 0 CLX-Lag082 5
CLX-Lag082 6 Headwall 35 24-Apr-1 8 28-May-1 8 0 0 CLX-Lag082 6
Sta. 44 + 840.002 (EB14) to Sta. 45 + 311.016 16 01-Apr-1 8 16-Apr-1 8 0 0
CLX-Lag082 7 Ditch 16 01-Apr-1 8 16-Apr-1 8 0 0 CLX-Lag082 7
CLX-Lag082 8 RCPC 16 01-Apr-1 8 16-Apr-1 8 0 0 CLX-Lag082 8
CLX-Lag082 9 Drainage Canal & Stepp ed Canal 16 01-Apr-1 8 16-Apr-1 8 0 0 CLX-Lag082 9
CLX-Lag083 0 RCBC 16 01-Apr-1 8 16-Apr-1 8 0 0 CLX-Lag083 0
CLX-Lag083 1 Retaining Wall 16 01-Apr-1 8 16-Apr-1 8 0 0 CLX-Lag083 1
CLX-Lag083 2 Grouted Riprap 16 01-Apr-1 8 16-Apr-1 8 0 0 CLX-Lag083 2
CLX-Lag083 3 Catch Basin 14 03-Apr-1 8 16-Apr-1 8 0 0 CLX-Lag083 3
CLX-Lag083 4 Removal of Exis0ng RCBC & Stone Masonry Drainage Canal 9 08-Apr-1 8 16-Apr-1 8 0 0 CLX-Lag083 4
CLX-Lag083 5 Headwall 7 08-Apr-1 8 14-Apr-1 8 0 0 CLX-Lag083 5
MISCELLANEOUS STRUCTURES 191 12-Jul-18 18-Jan-19 -9 -70
Sta. 37 + 983.890 (WB26) to Sta. 38 + 454.400 (V1) 38 12-Dec-18 18-Jan-19 0 -70
CLX-Lag083 6 Concrete Median Barrier 7 12-Dec-18 18-Dec-18 0 -70 CLX-Lag083 6
CLX-Lag083 7 Pre-Cast Fence 5 27-Dec-18 31-Dec-18 0 -70 CLX-Lag083 7
CLX-Lag083 8 Concrete Railing 4 23-Dec-18 26-Dec-18 0 -58 CLX-Lag083 8
CLX-Lag083 9 Concrete Curb 4 23-Dec-18 26-Dec-18 0 -58 CLX-Lag083 9
CLX-Lag084 0 Sound Barrier 4 06-Jan-19 09-Jan-19 0 -70 CLX-Lag084 0
CLX-Lag084 1 Lane Marking 3 02-Jan-19 04-Jan-19 0 -64 CLX-Lag084 1
CLX-Lag084 2 Guardrail 7 10-Jan-19 16-Jan-19 0 -70 CLX-Lag084 2
CLX-Lag084 3 Chainlink Fence 7 10-Jan-19 16-Jan-19 0 -70 CLX-Lag084 3
CLX-Lag084 4 Landscaping 6 13-Jan-19 18-Jan-19 0 -70 CLX-Lag084 4
CLX-Lag084 5 Signages 2 17-Jan-19 18-Jan-19 0 -70 CLX-Lag084 5
Sta. 38 + 835.400 (V1) to Sta. 39 + 203.680 (WB27) 38 06-Dec-18 12-Jan-19 0 -70
CLX-Lag084 6 Concrete Median Barrier 6 06-Dec-18 11-Dec-18 0 -70 CLX-Lag084 6
CLX-Lag084 7 Concrete Railing 3 14-Dec-18 16-Dec-18 0 -61 CLX-Lag084 7
CLX-Lag084 8 Concrete Curb 3 14-Dec-18 16-Dec-18 0 -61 CLX-Lag084 8
CLX-Lag084 9 Pre-Cast Fence 4 23-Dec-18 26-Dec-18 0 -70 CLX-Lag084 9
CLX-Lag085 0 Lane Marking 2 27-Dec-18 28-Dec-18 0 -70 CLX-Lag085 0
CLX-Lag085 1 Sound Barrier 3 03-Jan-19 05-Jan-19 0 -70 CLX-Lag085 1
CLX-Lag085 2 Guardrail 6 04-Jan-19 09-Jan-19 0 -70 CLX-Lag085 2
CLX-Lag085 3 Chainlink Fence 6 04-Jan-19 09-Jan-19 0 -70 CLX-Lag085 3

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 26 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag085 4 Landscaping 5 08-Jan-19 12-Jan-19 0 -70 CLX-Lag085 4
CLX-Lag085 5 Signages 2 10-Jan-19 11-Jan-19 0 -70 CLX-Lag085 5
Sta. 39 + 251.680 (WB27) to Sta. 40 + 473.823 (EB11) 52 18-Nov-18 08-Jan-19 0 -70
CLX-Lag085 6 Concrete Median Barrier 18 18-Nov-18 05-Dec-18 0 -70 CLX-Lag085 6
CLX-Lag085 7 Concrete Railing 12 02-Dec-18 13-Dec-18 0 -70 CLX-Lag085 7
CLX-Lag085 8 Concrete Curb 12 02-Dec-18 13-Dec-18 0 -70 CLX-Lag085 8
CLX-Lag085 9 Pre-Cast Fence 21 02-Dec-18 22-Dec-18 0 -70 CLX-Lag085 9
CLX-Lag086 0 Guardrail 19 16-Dec-18 03-Jan-19 0 -70 CLX-Lag086 0
CLX-Lag086 1 Chainlink Fence 19 16-Dec-18 03-Jan-19 0 -70 CLX-Lag086 1
CLX-Lag086 2 Lane Marking 7 20-Dec-18 26-Dec-18 0 -70 CLX-Lag086 2
CLX-Lag086 3 Sound Barrier 11 23-Dec-18 02-Jan-19 0 -70 CLX-Lag086 3
CLX-Lag086 4 Landscaping 16 23-Dec-18 07-Jan-19 0 -70 CLX-Lag086 4
CLX-Lag086 5 Signages 5 04-Jan-19 08-Jan-19 0 -70 CLX-Lag086 5
Sta. 40 + 508.823 (EB11) to Sta. 41 + 112.330 (EB12) 46 20-Oct-1 8 04-Dec-18 8 -61
CLX-Lag086 6 Concrete Median Barrier 9 20-Oct-1 8 28-Oct-1 8 0 -69 CLX-Lag086 6
CLX-Lag086 7 Concrete Railing 6 03-Nov-18 08-Nov-18 0 -70 CLX-Lag086 7
CLX-Lag086 8 Concrete Curb 6 03-Nov-18 08-Nov-18 0 -70 CLX-Lag086 8
CLX-Lag086 9 Lane Marking 3 12-Nov-18 14-Nov-18 0 -69 CLX-Lag086 9
CLX-Lag087 0 Pre-Cast Fence 7 08-Nov-18 14-Nov-18 0 -61 CLX-Lag087 0
CLX-Lag087 1 Guardrail 9 17-Nov-18 25-Nov-18 0 -67 CLX-Lag087 1
CLX-Lag087 2 Chainlink Fence 9 17-Nov-18 25-Nov-18 0 -67 CLX-Lag087 2
CLX-Lag087 3 Sound Barrier 5 18-Nov-18 22-Nov-18 0 -61 CLX-Lag087 3
CLX-Lag087 4 Signages 3 26-Nov-18 28-Nov-18 0 -64 CLX-Lag087 4
CLX-Lag087 5 Landscaping 8 27-Nov-18 04-Dec-18 0 -61 CLX-Lag087 5
Sta. 41 + 146.330 (EB12) to Sta. 41 + 653.400 (V2) 54 04-Oct-1 8 26-Nov-18 0 -61
CLX-Lag087 6 Concrete Median Barrier 8 04-Oct-1 8 11-Oct-1 8 0 -61 CLX-Lag087 6
CLX-Lag087 7 Concrete Railing 5 11-Oct-1 8 15-Oct-1 8 0 -61 CLX-Lag087 7
CLX-Lag087 8 Concrete Curb 5 11-Oct-1 8 15-Oct-1 8 0 -61 CLX-Lag087 8
CLX-Lag087 9 Lane Marking 3 26-Oct-1 8 28-Oct-1 8 0 -61 CLX-Lag087 9
CLX-Lag088 0 Guardrail 8 03-Nov-18 10-Nov-18 0 -61 CLX-Lag088 0
CLX-Lag088 1 Chainlink Fence 8 03-Nov-18 10-Nov-18 0 -61 CLX-Lag088 1
CLX-Lag088 2 Pre-Cast Fence 5 03-Nov-18 07-Nov-18 0 -61 CLX-Lag088 2
CLX-Lag088 3 Sound Barrier 4 14-Nov-18 17-Nov-18 0 -61 CLX-Lag088 3
CLX-Lag088 4 Signages 2 19-Nov-18 20-Nov-18 0 -61 CLX-Lag088 4
CLX-Lag088 5 Landscaping 7 20-Nov-18 26-Nov-18 0 -61 CLX-Lag088 5
Sta. 42 + 072.300 (V2) to Sta. 43 + 347.500 (EB13) 66 15-Sep-18 19-Nov-18 0 -61
CLX-Lag088 6 Concrete Median Barrier 19 15-Sep-18 03-Oct-1 8 0 -61 CLX-Lag088 6
CLX-Lag088 7 Concrete Railing 12 29-Sep-18 10-Oct-1 8 0 -61 CLX-Lag088 7
CLX-Lag088 8 Concrete Curb 12 29-Sep-18 10-Oct-1 8 0 -61 CLX-Lag088 8
CLX-Lag088 9 Pre-Cast Fence 35 29-Sep-18 02-Nov-18 0 -61 CLX-Lag088 9
CLX-Lag089 0 Guardrail 21 13-Oct-1 8 02-Nov-18 0 -61 CLX-Lag089 0
CLX-Lag089 1 Chainlink Fence 21 13-Oct-1 8 02-Nov-18 0 -61 CLX-Lag089 1

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 27 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag089 2 Lane Marking 7 18-Oct-1 8 24-Oct-1 8 0 -61 CLX-Lag089 2
CLX-Lag089 3 Sound Barrier 11 03-Nov-18 13-Nov-18 0 -61 CLX-Lag089 3
CLX-Lag089 4 Landscaping 17 03-Nov-18 19-Nov-18 0 -61 CLX-Lag089 4
CLX-Lag089 5 Signages 5 14-Nov-18 18-Nov-18 0 -61 CLX-Lag089 5
Sta. 43 + 382.500 (EB13) to Sta. 44 + 809.998 (EB14) 56 15-Aug-18 09-Oct-1 8 0 -61
CLX-Lag089 6 Concrete Median Barrier 22 15-Aug-18 05-Sep-18 0 -61 CLX-Lag089 6
CLX-Lag089 7 Concrete Railing 13 29-Aug-18 10-Sep-18 0 -61 CLX-Lag089 7
CLX-Lag089 8 Concrete Curb 13 29-Aug-18 10-Sep-18 0 -61 CLX-Lag089 8
CLX-Lag089 9 Pre-Cast Fence 17 29-Aug-18 14-Sep-18 0 -61 CLX-Lag089 9
CLX-Lag090 0 Guardrail 22 12-Sep-18 03-Oct-1 8 0 -61 CLX-Lag090 0
CLX-Lag090 1 Chainlink Fence 22 12-Sep-18 03-Oct-1 8 0 -61 CLX-Lag090 1
CLX-Lag090 2 Sound Barrier 12 15-Sep-18 26-Sep-18 0 -61 CLX-Lag090 2
CLX-Lag090 3 Landscaping 19 15-Sep-18 03-Oct-1 8 0 -61 CLX-Lag090 3
CLX-Lag090 4 Lane Marking 8 20-Sep-18 27-Sep-18 0 -61 CLX-Lag090 4
CLX-Lag090 5 Signages 6 04-Oct-1 8 09-Oct-1 8 0 -61 CLX-Lag090 5
Sta. 44 + 840.002 (EB14) to Sta. 45 + 311.016 37 12-Jul-18 17-Aug-18 0 -61
CLX-Lag090 6 Concrete Median Barrier 7 12-Jul-18 18-Jul-18 0 -61 CLX-Lag090 6
CLX-Lag090 7 Concrete Railing 4 26-Jul-18 29-Jul-18 0 -61 CLX-Lag090 7
CLX-Lag090 8 Concrete Curb 4 26-Jul-18 29-Jul-18 0 -61 CLX-Lag090 8
CLX-Lag090 9 Pre-Cast Fence 5 26-Jul-18 30-Jul-18 0 -61 CLX-Lag090 9
CLX-Lag091 0 Sound Barrier 4 31-Jul-18 03-Aug-18 0 -61 CLX-Lag091 0
CLX-Lag091 1 Landscaping 6 31-Jul-18 05-Aug-18 0 -61 CLX-Lag091 1
CLX-Lag091 2 Lane Marking 3 02-Aug-18 04-Aug-18 0 -61 CLX-Lag091 2
CLX-Lag091 3 Guardrail 7 09-Aug-18 15-Aug-18 0 -61 CLX-Lag091 3
CLX-Lag091 4 Chainlink Fence 7 09-Aug-18 15-Aug-18 0 -61 CLX-Lag091 4
CLX-Lag091 5 Signages 2 16-Aug-18 17-Aug-18 0 -61 CLX-Lag091 5
ROADWAY LIGHTING SYSTEM 262 05-Jun-18 21-Feb-19 -16 -87
Laguna Boulevard Interchange 126 07-Sep-18 10-Jan-19 0 -87
CLX-Lag091 6 Ductbank 14 07-Sep-18 20-Sep-18 0 -87 CLX-Lag091 6
CLX-Lag091 7 Roughing-ins 21 28-Sep-18 18-Oct-1 8 0 -87 CLX-Lag091 7
CLX-Lag091 8 Roadway Light 42 09-Nov-18 20-Dec-18 0 -87 CLX-Lag091 8
CLX-Lag091 9 Panel & Service Po le Entrance 21 21-Dec-18 10-Jan-19 0 -87 CLX-Lag091 9
Laguna Boulevard (TP3C - TP3D) 154 21-Sep-18 21-Feb-19 0 -87
CLX-Lag092 0 Ductbank 14 21-Sep-18 04-Oct-1 8 0 -87 CLX-Lag092 0
CLX-Lag092 1 Roughing-ins 21 19-Oct-1 8 08-Nov-18 0 -87 CLX-Lag092 1
CLX-Lag092 2 Roadway Light 42 21-Dec-18 31-Jan-19 0 -87 CLX-Lag092 2
CLX-Lag092 3 Panel & Service Po le Entrance 21 01-Feb-19 21-Feb-19 0 -87 CLX-Lag092 3
Laguna Techno Park Interchange 105 24-Aug-18 06-Dec-18 0 -87
CLX-Lag092 4 Ductbank 14 24-Aug-18 06-Sep-18 0 -87 CLX-Lag092 4
CLX-Lag092 5 Roughing-ins 28 31-Aug-18 27-Sep-18 0 -87 CLX-Lag092 5
CLX-Lag092 6 Roadway Light 56 14-Sep-18 08-Nov-18 0 -87 CLX-Lag092 6
CLX-Lag092 7 Panel & Service Po le Entrance 28 09-Nov-18 06-Dec-18 0 -87 CLX-Lag092 7

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 28 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
Laguna Main Toll Barrier 105 05-Jun-18 17-Sep-18 0 -71
CLX-Lag092 8 Ductbank 14 05-Jun-18 18-Jun-18 0 -71 CLX-Lag092 8
CLX-Lag092 9 Roughing-ins 28 12-Jun-18 09-Jul-18 0 -71 CLX-Lag092 9
CLX-Lag093 0 Roadway Light 56 26-Jun-18 20-Aug-18 0 -71 CLX-Lag093 0
CLX-Lag093 1 High-Mast Electrical Pole 56 26-Jun-18 20-Aug-18 0 -71 CLX-Lag093 1
CLX-Lag093 2 Panel & Service Po le Entrance 28 21-Aug-18 17-Sep-18 0 -71 CLX-Lag093 2
BUILDINGS AND TOLL PLAZA 227 05-Jun-18 17-Jan-19 -4 -75
Laguna Blvd. Interchange TP-3A (Entry to Cavite) 95 31-Jul-18 02-Nov-18 0 -71
Toll Plaza 95 31-Jul-18 02-Nov-18 0 -71
CLX-Lag093 3 Toll Canopy Structure 56 31-Jul-18 24-Sep-18 0 -71 CLX-Lag093 3
CLX-Lag093 4 Underground Power and Auxilliary 28 31-Jul-18 27-Aug-18 0 -71 CLX-Lag093 4
CLX-Lag093 5 Grounding System 12 02-Aug-18 13-Aug-18 0 -71 CLX-Lag093 5
CLX-Lag093 6 Storm Drainage and Sewerage System, and Water System 89 02-Aug-18 29-Oct-1 8 0 -71 CLX-Lag093 6
CLX-Lag093 7 Toll Island 76 14-Aug-18 28-Oct-1 8 0 -71 CLX-Lag093 7
CLX-Lag093 8 Metal Beam Guardrail 28 04-Sep-18 01-Oct-1 8 0 -71 CLX-Lag093 8
CLX-Lag093 9 Canopy Ligh0ng System 46 18-Sep-18 02-Nov-18 0 -71 CLX-Lag093 9
CLX-Lag094 0 Latrine with Bowl 18 25-Sep-18 12-Oct-1 8 0 -71 CLX-Lag094 0
CLX-Lag094 1 Lightning Protec0on System 14 25-Sep-18 08-Oct-1 8 0 -71 CLX-Lag094 1
CLX-Lag094 2 Protec 0on Bollards 21 02-Oct-1 8 22-Oct-1 8 0 -71 CLX-Lag094 2
CLX-Lag094 3 War ning / Flashing Light 27 02-Oct-1 8 28-Oct-1 8 0 -71 CLX-Lag094 3
CLX-Lag094 4 Protec 0on Bar riers 21 09-Oct-1 8 29-Oct-1 8 0 -71 CLX-Lag094 4
CLX-Lag094 5 Pedestrian Gates 14 16-Oct-1 8 29-Oct-1 8 0 -71 CLX-Lag094 5
Ground Reservoir And Water Tank 55 04-Sep-18 28-Oct-1 8 0 -71
CLX-Lag094 6 Ground Reservoir And Water Tank 55 04-Sep-18 28-Oct-1 8 0 -71 CLX-Lag094 6
Laguna Blvd. Interchange TP-3B (Exit to Laguna) 139 14-Aug-18 30-Dec-18 0 -71
Toll Plaza 98 14-Aug-18 19-Nov-18 0 -71
CLX-Lag094 7 Toll Canopy Structure 56 14-Aug-18 08-Oct-1 8 0 -71 CLX-Lag094 7
CLX-Lag094 8 Underground Power and Auxilliary 28 14-Aug-18 10-Sep-18 0 -71 CLX-Lag094 8
CLX-Lag094 9 Grounding System 12 16-Aug-18 27-Aug-18 0 -71 CLX-Lag094 9
CLX-Lag095 0 Storm Drainage and Sewerage System, and Water System 89 16-Aug-18 12-Nov-18 0 -71 CLX-Lag095 0
CLX-Lag095 1 Toll Island 76 28-Aug-18 11-Nov-18 0 -71 CLX-Lag095 1
CLX-Lag095 2 Metal Beam Guardrail 28 18-Sep-18 15-Oct-1 8 0 -71 CLX-Lag095 2
CLX-Lag095 3 Canopy Ligh0ng System 46 02-Oct-1 8 16-Nov-18 0 -71 CLX-Lag095 3
CLX-Lag095 4 Toll Booth 46 02-Oct-1 8 16-Nov-18 0 -71 CLX-Lag095 4
CLX-Lag095 5 Catwalk and Access Stairs 18 09-Oct-1 8 26-Oct-1 8 0 -71 CLX-Lag095 5
CLX-Lag095 6 Lightning Protec0on System 14 09-Oct-1 8 22-Oct-1 8 0 -71 CLX-Lag095 6
CLX-Lag095 7 Protec 0on Bollards 18 16-Oct-1 8 02-Nov-18 0 -71 CLX-Lag095 7
CLX-Lag095 8 War ning / Flashing Light 28 16-Oct-1 8 12-Nov-18 0 -71 CLX-Lag095 8
CLX-Lag095 9 Protec 0on Bar riers (Toll Booth) 21 23-Oct-1 8 12-Nov-18 0 -71 CLX-Lag095 9
CLX-Lag096 0 Protec 0on Bar riers (Mini Building) 21 30-Oct-1 8 19-Nov-18 0 -71 CLX-Lag096 0
CLX-Lag096 1 Pedestrian Gates 14 06-Nov-18 19-Nov-18 0 -71 CLX-Lag096 1
Mini Building 118 04-Sep-18 30-Dec-18 0 -71

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 29 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag096 2 Mini Building Structure including Ligh0ng and Power 56 04-Sep-18 29-Oct-1 8 0 -71 CLX-Lag096 2
CLX-Lag096 3 Grounding System 14 04-Sep-18 17-Sep-18 0 -71 CLX-Lag096 3
CLX-Lag096 4 Intercom and Communica0on System 62 11-Sep-18 11-Nov-18 0 -71 CLX-Lag096 4
CLX-Lag096 5 Video Surveilance System 62 30-Oct-1 8 30-Dec-18 0 -71 CLX-Lag096 5
CLX-Lag096 6 Access Control and Intrusion Detec0on System (ACID) 62 30-Oct-1 8 30-Dec-18 0 -71 CLX-Lag096 6
CLX-Lag096 7 Facili0es Control and Monitoring System 62 30-Oct-1 8 30-Dec-18 0 -71 CLX-Lag096 7
CLX-Lag096 8 Air Condi0oning and Ven0la0on System 62 30-Oct-1 8 30-Dec-18 0 -71 CLX-Lag096 8
CLX-Lag096 9 Fire Detec0ons and Alarm Sytems 62 30-Oct-1 8 30-Dec-18 0 -71 CLX-Lag096 9
CLX-Lag097 0 Lightning Protec0on System 14 30-Oct-1 8 12-Nov-18 0 -71 CLX-Lag097 0
Ground Reservoir And Water Tank 55 18-Sep-18 11-Nov-18 0 -71
CLX-Lag097 1 Ground Reservoir And Water Tank 55 18-Sep-18 11-Nov-18 0 -71 CLX-Lag097 1
Laguna Blvd. Interchange TP-3C (1-Toll Plaza) Exit to Cavite 139 28-Aug-18 13-Jan-19 0 -71
Toll Plaza 98 28-Aug-18 03-Dec-18 0 -71
CLX-Lag097 2 Toll Canopy Structure 56 28-Aug-18 22-Oct-1 8 0 -71 CLX-Lag097 2
CLX-Lag097 3 Underground Power and Auxilliary (includes Roughing-ins for TCS) 28 28-Aug-18 24-Sep-18 0 -71 CLX-Lag097 3

CLX-Lag097 4 Grounding System 12 30-Aug-18 10-Sep-18 0 -71 CLX-Lag097 4


CLX-Lag097 5 Storm Drainage and Sewerage System, and Water System 89 30-Aug-18 26-Nov-18 0 -71 CLX-Lag097 5
CLX-Lag097 6 Toll Island 76 11-Sep-18 25-Nov-18 0 -71 CLX-Lag097 6
CLX-Lag097 7 Metal Beam Guardrail 28 02-Oct-1 8 29-Oct-1 8 0 -71 CLX-Lag097 7
CLX-Lag097 8 War ning / Flashing Light 28 16-Oct-1 8 12-Nov-18 0 -71 CLX-Lag097 8
CLX-Lag097 9 Toll Booth 46 16-Oct-1 8 30-Nov-18 0 -71 CLX-Lag097 9
CLX-Lag098 0 Catwalk and Access Stairs 18 23-Oct-1 8 09-Nov-18 0 -71 CLX-Lag098 0
CLX-Lag098 1 Protec 0on Bollards 21 30-Oct-1 8 19-Nov-18 0 -71 CLX-Lag098 1
CLX-Lag098 2 Lightning Protec0on System 14 30-Oct-1 8 12-Nov-18 0 -71 CLX-Lag098 2
CLX-Lag098 3 Protec 0on Bar riers (Toll Booth) 21 06-Nov-18 26-Nov-18 0 -71 CLX-Lag098 3
CLX-Lag098 4 Protec 0on Bar riers (Mini Building) 21 13-Nov-18 03-Dec-18 0 -71 CLX-Lag098 4
CLX-Lag098 5 Pedestrian Gates (Swing-in Barrier) 14 20-Nov-18 03-Dec-18 0 -71 CLX-Lag098 5
Mini Building 118 18-Sep-18 13-Jan-19 0 -71
CLX-Lag098 6 Mini Building Structure including Ligh0ng and Power 56 18-Sep-18 12-Nov-18 0 -71 CLX-Lag098 6
CLX-Lag098 7 Grounding System 14 18-Sep-18 01-Oct-1 8 0 -71 CLX-Lag098 7
CLX-Lag098 8 Intercom and Communica0on System 62 25-Sep-18 25-Nov-18 0 -71 CLX-Lag098 8
CLX-Lag098 9 Video Surveilance System 62 13-Nov-18 13-Jan-19 0 -71 CLX-Lag098 9
CLX-Lag099 0 Access Control and Intrusion Detec0on System (ACID) 62 13-Nov-18 13-Jan-19 0 -71 CLX-Lag099 0
CLX-Lag099 1 Facili0es Control and Monitoring System 62 13-Nov-18 13-Jan-19 0 -71 CLX-Lag099 1
CLX-Lag099 2 Air Condi0oning and Ven0la0on System 62 13-Nov-18 13-Jan-19 0 -71 CLX-Lag099 2
CLX-Lag099 3 Fire Detec0ons and Alarm Sytems 62 13-Nov-18 13-Jan-19 0 -71 CLX-Lag099 3
CLX-Lag099 4 Lightning Protec0on System 14 13-Nov-18 26-Nov-18 0 -71 CLX-Lag099 4
Ground Reservoir And Water Tank 55 02-Oct-1 8 25-Nov-18 0 -71
CLX-Lag099 5 Ground Reservoir And Water Tank 55 02-Oct-1 8 25-Nov-18 0 -71 CLX-Lag099 5
Laguna Blvd. Interchange TP-3D (1-Toll Plaza) Entry to Cavite 95 11-Sep-18 14-Dec-18 0 -71
Toll Plaza 95 11-Sep-18 14-Dec-18 0 -71

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 30 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag099 6 Toll Canopy Structure 56 11-Sep-18 05-Nov-18 0 -71 CLX-Lag099 6
CLX-Lag099 7 Underground Power and Auxilliary (includes Roughing-ins for TCS) 28 11-Sep-18 08-Oct-1 8 0 -71 CLX-Lag099 7

CLX-Lag099 8 Grounding System 12 13-Sep-18 24-Sep-18 0 -71 CLX-Lag099 8


CLX-Lag099 9 Storm Drainage and Sewerage System, and Water System 88 13-Sep-18 09-Dec-18 0 -71 CLX-Lag099 9
CLX-Lag100 0 Toll Island 76 25-Sep-18 09-Dec-18 0 -71 CLX-Lag100 0
CLX-Lag100 1 Metal Beam Guardrail 28 16-Oct-1 8 12-Nov-18 0 -71 CLX-Lag100 1
CLX-Lag100 2 Canopy Ligh0ng System 46 30-Oct-1 8 14-Dec-18 0 -71 CLX-Lag100 2
CLX-Lag100 3 Latrine with Bowl 18 06-Nov-18 23-Nov-18 0 -71 CLX-Lag100 3
CLX-Lag100 4 Lightning Protec0on System 14 06-Nov-18 19-Nov-18 0 -71 CLX-Lag100 4
CLX-Lag100 5 Protec 0on Bollards 18 13-Nov-18 30-Nov-18 0 -71 CLX-Lag100 5
CLX-Lag100 6 War ning / Flashing Light 28 13-Nov-18 10-Dec-18 0 -71 CLX-Lag100 6
CLX-Lag100 7 Protec 0on Bar riers (Toll Booth) 21 20-Nov-18 10-Dec-18 0 -71 CLX-Lag100 7
CLX-Lag100 8 Pedestrian Gates (Swing-in Barrier) 14 27-Nov-18 10-Dec-18 0 -71 CLX-Lag100 8
Ground Reservoir And Water Tank 55 16-Oct-1 8 09-Dec-18 0 -71
CLX-Lag100 9 Ground Reservoir And Water Tank 55 16-Oct-1 8 09-Dec-18 0 -71 CLX-Lag100 9
Technopark Interchange TP-4A (1-Toll Plaza) Exit to Laguna 139 24-Aug-18 09-Jan-19 0 -87
Toll Plaza 95 24-Aug-18 26-Nov-18 0 -87
CLX-Lag101 0 Toll Canopy Structure 56 24-Aug-18 18-Oct-1 8 0 -87 CLX-Lag101 0
CLX-Lag101 1 Underground Power and Auxilliary 28 24-Aug-18 20-Sep-18 0 -87 CLX-Lag101 1
CLX-Lag101 2 Grounding System 12 26-Aug-18 06-Sep-18 0 -87 CLX-Lag101 2
CLX-Lag101 3 Storm Drainage and Sewerage System, and Water System 88 26-Aug-18 21-Nov-18 0 -87 CLX-Lag101 3
CLX-Lag101 4 Toll Island 76 07-Sep-18 21-Nov-18 0 -87 CLX-Lag101 4
CLX-Lag101 5 Metal Beam Guardrail 28 28-Sep-18 25-Oct-1 8 0 -87 CLX-Lag101 5
CLX-Lag101 6 Canopy Ligh0ng System 46 12-Oct-1 8 26-Nov-18 0 -87 CLX-Lag101 6
CLX-Lag101 7 Toll Booth 46 12-Oct-1 8 26-Nov-18 0 -87 CLX-Lag101 7
CLX-Lag101 8 Protec 0on Bollards 18 19-Oct-1 8 05-Nov-18 0 -87 CLX-Lag101 8
CLX-Lag101 9 Catwalk and Access Stairs 18 19-Oct-1 8 05-Nov-18 0 -87 CLX-Lag101 9
CLX-Lag102 0 Lightning Protec0on System 14 19-Oct-1 8 01-Nov-18 0 -87 CLX-Lag102 0
CLX-Lag102 1 Protec 0on Bar riers (Toll Booth) 21 26-Oct-1 8 15-Nov-18 0 -87 CLX-Lag102 1
CLX-Lag102 2 War ning / Flashing Light 27 26-Oct-1 8 21-Nov-18 0 -87 CLX-Lag102 2
CLX-Lag102 3 Protec 0on Bar riers (Mini Building) 21 02-Nov-18 22-Nov-18 0 -87 CLX-Lag102 3
CLX-Lag102 4 Pedestrian Gates 14 09-Nov-18 22-Nov-18 0 -87 CLX-Lag102 4
Mini Building 118 14-Sep-18 09-Jan-19 0 -87
CLX-Lag102 5 Mini Building Structure including Ligh0ng and Power 56 14-Sep-18 08-Nov-18 0 -87 CLX-Lag102 5
CLX-Lag102 6 Grounding System 14 14-Sep-18 27-Sep-18 0 -87 CLX-Lag102 6
CLX-Lag102 7 Intercom and Communica0on System 62 21-Sep-18 21-Nov-18 0 -87 CLX-Lag102 7
CLX-Lag102 8 Video Surveilance System 62 09-Nov-18 09-Jan-19 0 -87 CLX-Lag102 8
CLX-Lag102 9 Access Control and Intrusion Detec0on System (ACID) 62 09-Nov-18 09-Jan-19 0 -87 CLX-Lag102 9
CLX-Lag103 0 Facili0es Control and Monitoring System 62 09-Nov-18 09-Jan-19 0 -87 CLX-Lag103 0
CLX-Lag103 1 Air Condi0oning and Ven0la0on System 62 09-Nov-18 09-Jan-19 0 -87 CLX-Lag103 1
CLX-Lag103 2 Fire Detec0ons and Alarm Sytems 62 09-Nov-18 09-Jan-19 0 -87 CLX-Lag103 2

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 31 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag103 3 Lightning Protec0on System 14 09-Nov-18 22-Nov-18 0 -87 CLX-Lag103 3
Technopark Interchange TP-4B (1-Toll Plaza) Entry to Cavite 133 07-Sep-18 17-Jan-19 0 -87
Toll Plaza 133 07-Sep-18 17-Jan-19 0 -87
CLX-Lag103 4 Toll Canopy Structure 56 07-Sep-18 01-Nov-18 0 -87 CLX-Lag103 4
CLX-Lag103 5 Underground Power and Auxilliary 28 07-Sep-18 04-Oct-1 8 0 -87 CLX-Lag103 5
CLX-Lag103 6 Grounding System 12 09-Sep-18 20-Sep-18 0 -87 CLX-Lag103 6
CLX-Lag103 7 Storm Drainage and Sewerage System, and Water System 89 09-Sep-18 06-Dec-18 0 -87 CLX-Lag103 7
CLX-Lag103 8 Canopy Ligh0ng System 46 26-Oct-1 8 10-Dec-18 0 -87 CLX-Lag103 8
CLX-Lag103 9 Toll Island 76 02-Nov-18 16-Jan-19 0 -87 CLX-Lag103 9
CLX-Lag104 0 Lightning Protec0on System 14 02-Nov-18 15-Nov-18 0 -87 CLX-Lag104 0
CLX-Lag104 1 War ning / Flashing Light 28 09-Nov-18 06-Dec-18 0 -87 CLX-Lag104 1
CLX-Lag104 2 Metal Beam Guardrail 28 23-Nov-18 20-Dec-18 0 -87 CLX-Lag104 2
CLX-Lag104 3 Latrine with Bowl 18 14-Dec-18 31-Dec-18 0 -87 CLX-Lag104 3
CLX-Lag104 4 Protec 0on Bollards 18 21-Dec-18 07-Jan-19 0 -87 CLX-Lag104 4
CLX-Lag104 5 Protec 0on Bar riers (Toll Booth) 21 28-Dec-18 17-Jan-19 0 -87 CLX-Lag104 5
CLX-Lag104 6 Pedestrian Gates 14 04-Jan-19 17-Jan-19 0 -87 CLX-Lag104 6
Ground Reservoir And Water Tank 55 23-Nov-18 16-Jan-19 0 -87
CLX-Lag104 7 Ground Reservoir And Water Tank 55 23-Nov-18 16-Jan-19 0 -87 CLX-Lag104 7
Main Toll Barrier Toll Plaza TP-5 210 05-Jun-18 31-Dec-18 0 -71
Toll Plaza 105 05-Jun-18 17-Sep-18 0 -71
CLX-Lag104 8 Toll Canopy Structure 56 05-Jun-18 30-Jul-18 0 -71 CLX-Lag104 8
CLX-Lag104 9 Underground Power and Auxilliary 28 05-Jun-18 02-Jul-18 0 -71 CLX-Lag104 9
CLX-Lag105 0 Grounding System 12 07-Jun-18 18-Jun-18 0 -71 CLX-Lag105 0
CLX-Lag105 1 Storm Drainage and Sewerage System, and Water System 88 07-Jun-18 02-Sep-18 0 -71 CLX-Lag105 1
CLX-Lag105 2 Toll Island 76 19-Jun-18 02-Sep-18 0 -71 CLX-Lag105 2
CLX-Lag105 3 Metal Beam Guardrail 28 10-Jul-18 06-Aug-18 0 -71 CLX-Lag105 3
CLX-Lag105 4 Canopy Ligh0ng System 46 24-Jul-18 07-Sep-18 0 -71 CLX-Lag105 4
CLX-Lag105 5 Toll Booth 46 24-Jul-18 07-Sep-18 0 -71 CLX-Lag105 5
CLX-Lag105 6 Catwalk and Access Stairs 18 31-Jul-18 17-Aug-18 0 -71 CLX-Lag105 6
CLX-Lag105 7 Lightning Protec0on System 14 31-Jul-18 13-Aug-18 0 -71 CLX-Lag105 7
CLX-Lag105 8 Protec 0on Bollards 18 07-Aug-18 24-Aug-18 0 -71 CLX-Lag105 8
CLX-Lag105 9 War ning / Flashing Light 28 07-Aug-18 03-Sep-18 0 -71 CLX-Lag105 9
CLX-Lag106 0 Protec 0on Bar riers (Toll Booth) 28 14-Aug-18 10-Sep-18 0 -71 CLX-Lag106 0
CLX-Lag106 1 Protec 0on Bar riers (Mini Building) 28 21-Aug-18 17-Sep-18 0 -71 CLX-Lag106 1
CLX-Lag106 2 Pedestrian Gates 14 28-Aug-18 10-Sep-18 0 -71 CLX-Lag106 2
Mini Building 118 26-Jun-18 21-Oct-1 8 0 -71
CLX-Lag106 3 Mini Building Structure including Ligh0ng and Power 56 26-Jun-18 20-Aug-18 0 -71 CLX-Lag106 3
CLX-Lag106 4 Grounding System 14 26-Jun-18 09-Jul-18 0 -71 CLX-Lag106 4
CLX-Lag106 5 Intercom and Communica0on System 62 03-Jul-18 02-Sep-18 0 -71 CLX-Lag106 5
CLX-Lag106 6 Video Surveilance System 62 21-Aug-18 21-Oct-1 8 0 -71 CLX-Lag106 6
CLX-Lag106 7 Access Control and Intrusion Detec0on System (ACID) 62 21-Aug-18 21-Oct-1 8 0 -71 CLX-Lag106 7
CLX-Lag106 8 Facili0es Control and Monitoring System 62 21-Aug-18 21-Oct-1 8 0 -71 CLX-Lag106 8

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 32 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
CLX-Lag106 9 Air Condi0oning and Ven0la0on System 62 21-Aug-18 21-Oct-1 8 0 -71 CLX-Lag106 9
CLX-Lag107 0 Fire Detec0ons and Alarm Sytems 62 21-Aug-18 21-Oct-1 8 0 -71 CLX-Lag107 0
CLX-Lag107 1 Lightning Protec0on System 14 21-Aug-18 03-Sep-18 0 -71 CLX-Lag107 1
Electrical Service Center 119 21-Aug-18 17-Dec-18 0 -71
CLX-Lag107 2 ESC Building Structure including ligh0ng and power system 77 21-Aug-18 05-Nov-18 0 -71 CLX-Lag107 2
CLX-Lag107 3 Grounding System 14 28-Aug-18 10-Sep-18 0 -71 CLX-Lag107 3
CLX-Lag107 4 Generator Set 21 06-Nov-18 26-Nov-18 0 -71 CLX-Lag107 4
CLX-Lag107 5 Fuel Tank and Ancilliaries 21 06-Nov-18 26-Nov-18 0 -71 CLX-Lag107 5
CLX-Lag107 6 Exhaust Fan 21 06-Nov-18 26-Nov-18 0 -71 CLX-Lag107 6
CLX-Lag107 7 Fire Detec0on and Alarm System 28 13-Nov-18 10-Dec-18 0 -71 CLX-Lag107 7
CLX-Lag107 8 Main Distribu0on Panel at Electrical Service Center 21 13-Nov-18 03-Dec-18 0 -71 CLX-Lag107 8
CLX-Lag107 9 Perimeter Ligh0ng 14 20-Nov-18 03-Dec-18 0 -71 CLX-Lag107 9
CLX-Lag108 0 Lightning Protec0on System 28 20-Nov-18 17-Dec-18 0 -71 CLX-Lag108 0
Ground Reservoir And Water Tank 55 10-Oct-1 8 03-Dec-18 0 -71
CLX-Lag108 1 Ground Reservoir And Water Tank 55 10-Oct-1 8 03-Dec-18 0 -71 CLX-Lag108 1
Technical Shelter 119 04-Sep-18 31-Dec-18 0 -71
CLX-Lag108 2 Technical Shelter Building Struc ture including ligh0ng and power supply system 56 04-Sep-18 29-Oct-1 8 0 -71 CLX-Lag108 2

CLX-Lag108 3 Grounding System 14 04-Sep-18 17-Sep-18 0 -71 CLX-Lag108 3


CLX-Lag108 4 Lightning Protec0on System 14 07-Oct-1 8 20-Oct-1 8 0 -71 CLX-Lag108 4
CLX-Lag108 5 Generator Set 21 30-Oct-1 8 19-Nov-18 0 -71 CLX-Lag108 5
CLX-Lag108 6 Fire Detec0on and Alarm System, Heat and Smoke Detector 28 30-Oct-1 8 26-Nov-18 0 -71 CLX-Lag108 6
CLX-Lag108 7 Intercom and Communica0on System 28 30-Oct-1 8 26-Nov-18 0 -71 CLX-Lag108 7
CLX-Lag108 8 Technical Shelter Air Co ndi0oning and Ven0la0on 28 06-Nov-18 03-Dec-18 0 -71 CLX-Lag108 8
CLX-Lag108 9 Main Distribu0on Panel 21 11-Dec-18 31-Dec-18 0 -71 CLX-Lag108 9
CLX-Lag109 0 Perimeter Ligh0ng 14 18-Dec-18 31-Dec-18 0 -71 CLX-Lag109 0
TELECOM DUCTING 256 10-May-1 8 20-Jan-19 -26 -87
Sta. 37 + 983.890 (WB26) to Sta. 38 + 454.400 (V1) 68 14-Nov-18 20-Jan-19 0 -87
CLX-Lag109 1 Ductbank 17 14-Nov-18 30-Nov-18 0 -87 CLX-Lag109 1
CLX-Lag109 2 Carriage Duc0ng 17 01-Dec-18 17-Dec-18 0 -87 CLX-Lag109 2
CLX-Lag109 3 Pullbox 17 18-Dec-18 03-Jan-19 0 -87 CLX-Lag109 3
CLX-Lag109 4 Telecom Manhole 17 04-Jan-19 20-Jan-19 0 -87 CLX-Lag109 4
Sta. 38 + 835.400 (V1) to Sta. 39 + 203.680 (WB27) 40 07-Nov-18 16-Dec-18 0 -87
CLX-Lag109 5 Ductbank 7 07-Nov-18 13-Nov-18 0 -87 CLX-Lag109 5
CLX-Lag109 6 Carriage Duc0ng 7 18-Nov-18 24-Nov-18 0 -87 CLX-Lag109 6
CLX-Lag109 7 Pullbox 7 29-Nov-18 05-Dec-18 0 -87 CLX-Lag109 7
CLX-Lag109 8 Telecom Manhole 7 10-Dec-18 16-Dec-18 0 -87 CLX-Lag109 8
Sta. 39 + 251.680 (WB27) to Sta. 40 + 473.823 (EB11) 51 20-Oct-1 8 09-Dec-18 0 -87
CLX-Lag109 9 Ductbank 18 20-Oct-1 8 06-Nov-18 0 -87 CLX-Lag109 9
CLX-Lag110 0 Carriage Duc0ng 11 07-Nov-18 17-Nov-18 0 -87 CLX-Lag110 0
CLX-Lag110 1 Pullbox 11 18-Nov-18 28-Nov-18 0 -87 CLX-Lag110 1
CLX-Lag110 2 Telecom Manhole 11 29-Nov-18 09-Dec-18 0 -87 CLX-Lag110 2

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative
DETAILED CONSTRUCTION SCHEDULE Page
CAVITE-LAGUNA EXPRESSWAY (Laguna Segment) 33 of 33
Activity ID Activity Name Duration Start Finish Variance - BL Variance - BL2017 2018 2019 2020
Project Duration Project Finish Date
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
Sta. 40 + 508.823 (EB11) to Sta. 41 + 112.330 (EB12) 24 06-Oct-1 8 29-Oct-1 8 0 -87
CLX-Lag110 3 Ductbank 9 06-Oct-1 8 14-Oct-1 8 0 -87 CLX-Lag110 3
CLX-Lag110 4 Carriage Duc0ng 4 15-Oct-1 8 18-Oct-1 8 0 -87 CLX-Lag110 4
CLX-Lag110 5 Pullbox 4 19-Oct-1 8 22-Oct-1 8 0 -87 CLX-Lag110 5
CLX-Lag110 6 Telecom Manhole 7 23-Oct-1 8 29-Oct-1 8 0 -87 CLX-Lag110 6
Sta. 41 + 146.330 (EB12) to Sta. 41 + 653.400 (V2) 22 24-Aug-18 14-Sep-18 3 -84
CLX-Lag110 7 Ductbank 7 24-Aug-18 30-Aug-18 0 -87 CLX-Lag110 7
CLX-Lag110 8 Carriage Duc0ng 4 31-Aug-18 03-Sep-18 0 -87 CLX-Lag110 8
CLX-Lag110 9 Pullbox 4 04-Sep-18 07-Sep-18 0 -87 CLX-Lag110 9
CLX-Lag111 0 Telecom Manhole 7 08-Sep-18 14-Sep-18 0 -84 CLX-Lag111 0
Sta. 42 + 072.300 (V2) to Sta. 43 + 347.500 (EB13) 61 05-Jul-18 03-Sep-18 0 -80
CLX-Lag111 1 Ductbank 19 05-Jul-18 23-Jul-18 0 -80 CLX-Lag111 1
CLX-Lag111 2 Carriage Duc0ng 14 24-Jul-18 06-Aug-18 0 -80 CLX-Lag111 2
CLX-Lag111 3 Pullbox 14 07-Aug-18 20-Aug-18 0 -80 CLX-Lag111 3
CLX-Lag111 4 Telecom Manhole 14 21-Aug-18 03-Sep-18 0 -80 CLX-Lag111 4
Sta. 43 + 382.500 (EB13) to Sta. 44 + 809.998 (EB14) 39 05-Jun-18 13-Jul-18 0 -71
CLX-Lag111 5 Ductbank 21 05-Jun-18 25-Jun-18 0 -71 CLX-Lag111 5
CLX-Lag111 6 Carriage Duc0ng 6 26-Jun-18 01-Jul-18 0 -71 CLX-Lag111 6
CLX-Lag111 7 Pullbox 5 02-Jul-18 06-Jul-18 0 -71 CLX-Lag111 7
CLX-Lag111 8 Telecom Manhole 7 07-Jul-18 13-Jul-18 0 -71 CLX-Lag111 8
Sta. 44 + 840.002 (EB14) to Sta. 45 + 311.016 20 10-May-1 8 29-May-1 8 0 -61
CLX-Lag111 9 Ductbank 7 10-May-1 8 16-May-1 8 0 -61 CLX-Lag111 9
CLX-Lag112 0 Carriage Duc0ng 4 17-May-1 8 20-May-1 8 0 -61 CLX-Lag112 0
CLX-Lag112 1 Pullbox 2 21-May-1 8 22-May-1 8 0 -61 CLX-Lag112 1
CLX-Lag112 2 Telecom Manhole 7 23-May-1 8 29-May-1 8 0 -61 CLX-Lag112 2

Primary Baseline
Remaining Work
Critical Remaining Work
Baseline Milestone
Submitted by: Approved by:
Milestone
Summary
EDGAR D. JOCSON JUSTINO B. DE GUZMAN
Project Manager, DMCI Employer's Representative