Current Audit Process Flow Chart

Revision 2 40 – 60 hrs
1 auditor
Post-Audit

Pre -Audit 1h (small) – 3h (large) Data record


2 – 3 people
Walkthrough Audit  Notes from audit
Initial Customer  Fill in “Existing
Meeting External Audit Summary table”
 Pitch the program 2 hrs  Walls, windows,
 Record the meeting doors, lightning
 Electrical devices Building model
connected to the a) Weather, location
meter b) Fuel rates
Historical Data
Analysis c) Schedules 1h – 5h
d) Heating Cooling
 Building data
e) Building envelope
 Weather data Interview Client
f) Lighting
 Occupation & g) Other equipment
schedule
 Areas of concern
Prepare Auditing
 Recent renovations
Materials Balance & review
30 min /  Upgrades of 15 min
 Floor plan metering Interest base case
 Utility data point
 Questions
Perform self-
Internal Audit 5 min
checklist
 Motors / pumps
Apply for the
 Water heaters
program through 30 min  HVAC equipment Balance the
NB power 1h -5 h
 Meters/transformer proposed case
 Lights
 Record all electrical
Book the audit devices Analyze cost
benefit 1h

Group Brainstorm
Send final model
10 min
for peer review

Fill in “Master File


Table” & 20 min
“Consumption – 1h
table”

Finish the Audit


report 4h – 8h

Apply to NB Power