Você está na página 1de 3

1 Total Welder Quantity

Piping Welders – 53 psn : 53 Welders


Structural Welders – 26 psn : 26 Welders

2 Welder Qualification 1st Welder Qualification 2nd Welder Qualification 3rd


Welder Qualification Total
Target qualification date : Mid-March-2019 : 1st week April-2019 : 1st week May-2019
Qualification venue : Balaraja Workshop : Balaraja Workshop : Balaraja Workshop

Carbon Steel 10 10 10 30
Stainless Steel 6 6 7 19
Duplex 3 3
CUNI 1 1
Structure 2 6 18 26

Total 22 22 35 79
LIST OF MATERIALS REQUIRED FOR WELDER QUALIFICATION TEST

PIPING INSTALLATION PACKAGE


As of 25-Jan-2019
Material
No Description Size Unit Q'ty
grade
1 Pipe CS 1/2" SCH 80 A106 Gr. B M 6
2 Pipe CS 3/4" SCH 80 A106 Gr. B M 12
3 Pipe CS 2" SCH 80 A106 Gr. B M 12
4 Pipe CS 8" SCH 80 A106 Gr. B M 12
5 Pipe CS 3/4" SCH 80 A333 Gr. 6 M 6
6 Pipe CS 2" SCH 80 A333 Gr. 6 M 9
7 Pipe CS 8" SCH 80 A333 Gr. 6 M 9
8 Pipe SS 304L 3/4" SCH 40 TP 304L M 6
9 Pipe SS 304L 2" SCH 40 TP 304L M 9
10 Pipe SS 304L 8" SCH 80 TP 304L M 9
11 Pipe SS 316L 3/4" SCH 40 TP 316L M 6
12 Pipe SS 316L 2" SCH 40 TP 316L M 9
13 Pipe SS 316L 8" SCH 80 TP 316L M 9
14 CuNi 90/10 1" SCH 40 CuNi 90/10 M 4
15 SS Duplex 3/4" SCH 40 DSS 25 Cr M 6
16 SS Duplex 2" SCH 40 DSS 25 Cr M 9
17 SS Duplex 8" SCH 80 DSS 25 Cr M 9
Remark