Você está na página 1de 32

2018

SUMMARY REPORT

10‑Year
Transmission System
Assessment
Agility, flexibility needed to plan for

Long‑term transmission planning has In today’s marketplace, our customers


always been a complex undertaking, expect us to respond quickly. In fall
but it was relatively consistent in the 2017, Foxconn selected Wisconsin for its
days of steady load growth and a stable first U.S.‑based manufacturing facility
generation mix. But conditions in the early for flat‑screen technology. The Mount
21st century are no longer as predictable Pleasant Tech Interconnection Project
as they were in the past, adding new was developed to respond to the needs
challenges to the process. of a facility that would constitute the
largest load at a single substation in ATC’s
As a transmission‑only electric utility,
service territory. We filed an application
we collaborate with our customers
in January to build a new substation and
to determine needed replacements,
associated transmission lines with the
expansions and connections to the grid.
Recent changes in generation and the Public Service Commission of Wisconsin,
energy marketplace have required us to which approved the project in July.
be flexible and agile in our planning to Construction will start this fall and the
accommodate customer needs. project will be in service in late 2019.

Transmission investments
Projections from past and current Transmission System Assessments

2014 2015 2016 2017 2018

Specific
Network $1.4B $1.4B $1.3B $0.7B / $1.0B* $0.5B
Projects

Regional
Multi‑Value $0.5B $0.5B $0.5B $0.4B $0.3B
Projects

Asset
Maintenance $1.2B $1.4B $1.4B $1.4B $1.5B

Other Capital
Categories $0.2B / $0.8B $0.4B / $1.2B $0.4B / $1.2B $0.3B / $0.8B $0.5B / $1.1B

Total 10‑Year
Capital Cost $3.3B / $3.9B $3.7B / $4.5B $3.6B / $4.4B $2.8B / $3.6B $2.8B / $3.4B

*The Specific Network Projects range in 2017 reflects the fact that Northern Area Reliability Assessment
projects in the 10‑Year Assessment project list and in the MISO Transmission Expansion Plan database may be
replaced by generation being considered in the Midcontinent Independent System Operator generation queue.

2 A M E R I C A N T R A N S M I S S I O N C O.
Minnesota

Kingsford Michigan

Wisconsin

changing energy marketplace De Pere

Madison Pewaukee
Headquarters
Cottage
Grove
ATC Offices

Illinois

Upper Michigan Energy Resources Corp., We also work with our customers to
a subsidiary of WEC Energy Group, evaluate cost‑effective non‑transmission
proposed in early 2017 to add 180 solutions when examining the condition
megawatts of generation at two sites in of our aging assets. Recently, we made
the Upper Peninsula. The project was the decision to retire a 69‑kV line in
approved later that year, and construction northeastern Wisconsin that was in poor
began immediately. This allowed us condition when we determined, with
to scale back projects identified in our Wisconsin Public Service, that the local
Northern Area Reliability Assessment. distribution company’s two substations
UMERC’s two plants are located near served by the line could be tied into a
existing transmission infrastructure and nearby rebuilt 138‑kV line for about half
will require two new substations and only the cost.
a short segment of transmission line to
connect the facilities. These examples demonstrate the
dynamic nature of the electric industry
Generation retirements have a large today. That’s why it’s prudent to conduct
impact on the transmission grid. We an annual review of market conditions
anticipate that more than 30 percent of and transmission needs. Our 10‑year
the coal‑fired generation in our service forecast calls for a slight decrease in
territory will be retired by the end of 2019. capital expenditures from last year,
With the retirement of the Kewaunee with $2.8 to $3.4 billion in system
Nuclear Station in 2013, we canceled a improvements. This document contains
pair of 50‑mile, 138‑ and 345‑kV lines a summary of ATC’s planning initiatives,
that had been in the planning stages for and an overview of asset renewal and
several years – the change in generation network‑driven projects in each of our
allowed the need to be satisfied instead planning zones.
with a new substation that went into
service this year. The announced closing For more detailed information, please
of the Pleasant Prairie Power Plant in visit www.atc10yearplan.com.
southeastern Wisconsin meant that
another transmission connection into
northern Illinois was no longer needed,
and the Wisconsin‑Illinois Electric Jim Vespalec
Reliability Project was canceled. Director, Asset Planning & Engineering

Ron Snead
Vice President, System Planning

2 018 | 10 -Y E A R AS S E S S M E N T 3
Regional and economic planning

ATC is an active participant in a variety of efforts to address regional and inter‑regional planning initiatives
to maintain a reliable grid and capture economic benefits in a dynamic energy marketplace. Policy
initiatives to curb greenhouse gas emissions and expand the use of renewable energy continue to evolve,
and we work closely with our customers to plan for an electric transmission system that will serve their
needs well into the future.

MIDCONTINENT INDEPENDENT MARKET CONSTRAINTS


SYSTEM OPERATOR Two of the five narrowly constrained
TRANSMISSION EXPANSION areas identified in the MISO region are
PLANNING associated with ATC, and we continue to
MISO planning studies address long‑ and track these as well as other constraints.
short‑term issues as well as targeted Such tracking assists in planning projects
needs. Long‑term studies primarily look that alleviate congestion within the MISO
at value‑based options that provide market.
economic benefits in the 10‑ to 20‑year
horizon. Short‑term planning is primarily OTHER MISO PLANNING
driven by transmission owners’ reliability ACTIVITIES
and North American Electric Reliability
Our planning staff participates in various
Corporation compliance needs in a
technical and policy discussions and
five‑ to 10‑year period.
provides future direction for Midwest
ATC staff participates in the MISO Transmission Expansion Plan activities.
short‑term reliability and economic We also are involved in joint planning
studies in a variety of ways: ensuring studies with neighboring regional
accurate project information is included transmission organizations, including
in the MISO database, building and PJM and SPP.
reviewing models, correlating needs
MISO and PJM coordinate, conduct and
identified by MISO analyses with specific
analyze several market efficiency project
ATC projects and participating in various
studies. This analysis is reviewed by
studies and stakeholder forums.
an inter‑regional planning stakeholder
advisory committee, which typically
examines economic projects that could
benefit both Regional Transmission
Organizations and qualify for cross‑border
cost‑sharing.

4 A M E R I C A N T R A N S M I S S I O N C O.
Major projects update
BADGER COULEE BAY LAKE
This fall, we expect to energize the 180‑mile, The Bay Lake Project is a package of proposals
345‑kV Badger Coulee transmission line, one that address the delicate, shifting balance
of MISO’s 17 Multi-Value Projects designed between generation, load and transmission in
to deliver significant benefits to electric the northern portion of our service area.
consumers throughout the Upper Midwest. The North Appleton‑Morgan project was
A portion of the project from the Cardinal placed in service in September 2018, ahead of
Substation to the North Madison Substation schedule and under budget. It includes 345‑kV
was placed in service in fall 2017. Developed and 138‑kV lines from our North Appleton
jointly with Xcel Energy, the line will: Substation in Outagamie County to the
n offset the need for about $190 million Morgan Substation in Oconto County, Wis.
in lower-voltage upgrades in western Both substations have been expanded and
Wisconsin, additional work was required at 11 other
substations. A new substation, Benson Lake in
n increase access to the wholesale
Marinette County, was placed into service in
energy market and provide between
July 2017. It includes a large voltage‑control
$118 million and $700 million in net
device. North Appleton‑Morgan was
economic benefits over the life of the
approved by the Public Service Commission
line, and
of Wisconsin in May 2015, with an authorized
n establish another pathway for renewable cost of $328 million.
energy into Wisconsin with a connection
to key load centers.

(continued on page 6)

2 018 | 10 -Y E A R AS S E S S M E N T 5
Major projects update continued

The Mount CARDINAL – HICKORY CREEK SPRING VALLEY – NORTH LAKE


ATC, ITC Midwest LLC and Dairyland
GENEVA
Pleasant Tech Power Cooperative filed an application in Construction is underway on the $71 million
April with the Public Service Commission Spring Valley‑North Lake Geneva Project,
Interconnection of Wisconsin for a 102- to 120‑mile, 345‑kV which was approved by the Public Service
Project will serve transmission line connecting Dubuque Commission of Wisconsin in spring 2016.
County, Iowa, to Dane County, Wis. This project is needed to meet an increase in
up to 230 MW of electric demand in Walworth and Kenosha
The Cardinal-Hickory Creek Project is counties in Wisconsin.
load, the largest another MISO Multi-Value Project. Studies
indicate that it will deliver benefits to local The project involves:
load connected to communities and the Midwest region by: n construction of a new 138‑kV transmission
line of approximately 23 miles, stretching
a single substation n improving electric system reliability
from the North Lake Geneva Substation in
locally and regionally,
southern Walworth County to the Spring
on our system. delivering $23.5 million to
n
Valley Substation in western Kenosha
$350.1 million in net economic County,
benefits, and
n construction of a new 138‑kV and 69‑kV
n connecting to other 345‑kV substation on an ATC‑owned parcel along
transmission lines in the Upper Highway 50 in the Town of Wheatland,
Midwest and helping to enable 25
gigawatts of cost‑effective renewable
n construction of a new 69‑kV transmission
energy to be delivered to communities line to connect the new substation to the
in the region. existing Twin Lakes Substation in Twin
Lakes, and
If approved by Wisconsin and Iowa
regulators, the project is estimated to be
n other power line modifications.
in service in 2023. The project is expected to be placed into
service in 2019.

6 A M E R I C A N T R A N S M I S S I O N C O.
FINGER ROAD – CANAL n reconfiguring the Racine Substation
345‑kV bus,
The rebuild of a 69‑kV line in northeastern
Wisconsin, along with associated substation n rerouting the Pleasant Prairie and Bain
work, was approved by the Wisconsin Public 345‑kV line,
Service Commission in spring 2017 at a cost n uprating the Elm Road – Racine
of $60.7 million. About 55 miles of line on 345‑kV line, and
1950s‑vintage wood poles between Finger
Road Substation and Canal Substation will n constructing four new 138‑kV
be rebuilt. The line serves seven distribution underground lines (~400 feet) from the
substations in northern Kewaunee County Mount Pleasant Substation to serve a
and Door County. customer‑owned substation.

The project includes: ATC submitted the CPCN application in late


January 2018 to the Wisconsin Public Service
n the replacement of 834 wood pole Commission, which approved the project in
structures, July. Construction is underway. All electrical
n the replacement of line conductor and infrastructure has an expected in‑service date
addition of a fiber optic shield wire, of late 2019.
n the update at terminal‑end substations MACKINAC – MCGULPIN 138‑kV
of jumpers, selective bus conductor, and SUBMARINE CABLE REPLACEMENT
disconnect switches.
ATC has plans to replace the two 4‑mile,
Construction is scheduled to complete in 138‑kV submarine transmission lines
January 2021. connecting the Upper Peninsula of Michigan
to lower Michigan at an estimated cost of
MOUNT PLEASANT
$105 million.
TECH INTERCONNECTION
The Mackinac – McGulpin 138‑kV submarine
This project is designed to support Foxconn,
cable replacement project was submitted for
which upon completion will be one of the
MISO review in the MTEP18 planning cycle.
largest manufacturing facilities in the nation
The project was developed for the following
with a campus build‑out anticipated to be
reasons:
approximately 22‑million square feet. The
initial projected electric usage would be n Two 138‑kV submarine circuits were
200 megawatts at this manufacturing facility, damaged by an anchor strike on
with an additional 30 MW of expected April 1, 2018.
economic growth in the surrounding area. n Three working cables have been
The electric load required for Foxconn’s reconfigured to form one 138‑kV circuit.
operations will be the largest connected
to ATC’s transmission system at a single n The project will restore the eastern UP
substation. to the level of reliability it had before the
April 1 event.
The project cost is estimated to be about
$117 million and includes: n The integrity of the remaining cables is of
concern.
n constructing a new 345‑/138‑kV Mount
Pleasant Substation, n The remaining cables contain a
mineral‑oil based dielectric fluid; a
n looping the Racine – Pleasant Prairie submarine cable failure could result
345‑kV line into the new substation, in a fluid leak into Lake Michigan and
n stringing a new Racine – Pleasant Prairie Lake Huron.
345‑kV circuit in the vacant position on As proposed, the project is estimated to be in
existing structures and looping this new service in 2021.
circuit into the new substation,
(continued on page 8)

2 018 | 10 -Y E A R AS S E S S M E N T 7
Major projects update continued

BAYPORT – PIONEER JUNEAUTOWN


The rebuild of a 69‑kV transmission
INTERCONNECTION
line in northeastern Wisconsin, along The Juneautown Interconnection Project
with associated substation work, will be is a 138‑kV distribution‑transmission
submitted to the Wisconsin Public Service interconnection needed to meet
Commission in spring 2019 at a cost of We Energies’ growing reliability and
$51.7 million. Approximately 22 miles of economic needs.
line on 1910s‑vintage wood poles running
between Bayport Substation and Pioneer The cost of the project is estimated to be
Substation will be rebuilt. The line will $34.1 million and includes:
serve three distribution substations in a new Juneautown 138 / 13.2‑kV
n

Brown County and Oconto County. gas‑insulated substation,


The Bayport‑Pioneer asset renewal project looping the 138‑kV line between
n

consists of the following: Haymarket and Harbor substations to


n rebuilding the line between Bayport feed the new substation, and
and Pioneer substations with routing the new line segments through
n

double‑circuit structures, new underground corridors.


n stringing both Bayport‑Pioneer lines, An application for a Certificate of
combine, and operate as one line at Authority was filed with the Public Service
138‑kV, Commission of Wisconsin in January
n converting Suamico and Sobieski 2018 and was approved in August.
substations to 138‑kV operation, and Construction is scheduled to begin in fall
2019. The facilities are scheduled to be
n de‑energizing the Pulliam‑Bayport in service approximately 12 months after
69‑kV section of line. construction begins.
The project is scheduled to be in service in
December 2021.

8 A M E R I C A N T R A N S M I S S I O N C O.
By focusing on
life-cycle cost, our
asset management
program helps us
efficiently maintain
and upgrade our
older transmission
assets.

Our progress

One of ATC’s top priorities has always been electric Our single‑focus, transmission‑only business model has
reliability. With that focus, ATC has strengthened the produced significant results for our customers over the
grid to enable our customers to participate in and reap years.
the benefits of the wholesale energy market.
Over the past ten years, we have:
As we continue to use our system‑wide planning n upgraded more than 895 miles of transmission line,
process to effectively and economically improve
reliability, more emphasis is being placed on the need n improved 105 electric substations,
to efficiently maintain and upgrade our older assets. n built 25 new transmission lines (367 miles)
Our asset management program is focused on the
n connected 1,980 MW of new generation at 12 sites,
life‑cycle management of transmission assets. The
objective is to ensure assets perform the required – Includes 430 MW of renewable generation at
function in a sustainable manner while managing 6 sites
life‑cycle cost. Coordination of design, commissioning, n s aved customers millions in reduced energy costs
operation and maintenance is crucial to developing the with access to the marketplace and lower line
replacement strategy of the assets. Asset renewal is losses,
mainly driven by public and worker safety, regulatory
compliance, reliability, condition and operational
n increased import and export capability, and
performance. n improved transmission reliability.

Due in large part to our asset management efforts, ATC


consistently achieves better reliability performance
than our industry peers in all voltage classes.

2 018 | 10 -Y E A R AS S E S S M E N T 9
What drives the need for
transmission system improvements?
Early in our operational existence we COMMON NEEDS THAT DRIVE
focused on creating a smooth‑flowing SYSTEM IMPROVEMENTS
electrical highway to more reliably serve INCLUDE:
our customers. This involved finding

nNew or retiring generation – changes
the logical places in our service area to
in the generation impact on the
develop transmission projects. Major,
transmission system, the location and
network‑driven projects accounted for
amount of power flowing as well as
significant investment in our 345‑kV
system stability
system. As we were making our network
more interconnected and reliable, we also 
nEconomics – greater access to the
analyzed the life‑cycle maintenance of wholesale energy marketplace provides
our existing assets, focusing on an asset economic opportunities to utility
management strategy to complement customers
and create synergies with our network 
nEnhanced NERC reliability standards –
additions. require a greater degree of redundancy
and analysis to assure reliable, resilient
Today, our effective management of operation
transmission assets complements our

nPublic policy – renewable energy
planning strategy for electric reliability
mandates and pending air quality
and economic benefits.
regulations will affect how the
In a collaborative process, our asset transmission system will be built and
management and planning teams used
work with other functional groups 
nAsset renewal – maintaining the
and stakeholders to achieve the best system in good operating condition
solutions to transmission system needs. extends its life and improves safety and
Asset management staff monitor the performance
system through maintenance and Interconnections – changes in how
n

inspection programs to identify issues our customers distribute electricity to


related to equipment performance or consumers require new or modified
condition. Equipment needing attention is transmission facilities
discussed internally and with customers

nLoad changes – while overall load
to determine if replacement in kind is
growth is low, loads are appearing and
required and if other reliability needs
disappearing, changing power flows on
exist within the geographic area. Needs
the system
are evaluated using various options to
determine the best means of maintaining 
nNew technologies – synchronized
reliability. These discussions with phasor measurements, demand‑side
customers occur at 10-Year Assessment management and distributed energy
stakeholder meetings and MISO System resources affect how the grid is planned
Planning Meetings. and operated to maintain reliability

nCommunications – improvements
in communication technology, such
as fiber optics, are incorporated to
support an ever‑increasing need to see
and control what is happening on the
transmission system in real time

10 A M E R I C A N T R A N S M I S S I O N C O.
Plans and proposals
for the transmission system
For planning purposes, ATC’s service area is divided into five zones representing distinct geographic or
usage areas. Within each zone, we compile and assess transmission system needs.

PROJECT CLASSIFICATIONS
Network and asset renewal projects have targeted in‑service dates that are designed to address system
limitations and condition needs. The network projects are classified into one of three possible categories –
Planned, Proposed or Provisional, depending upon the stage of the project.

Planned Proposed Provisional

Status of ATC Studies complete Studies not complete Studies not complete
planning activities

Application for Application pending None None


regulatory approval or order issued

Project status Project in construction Project identified Project is not


planning phase or under as preferred necessarily the preferred
construction alternative alternative

Asset renewal projects generally fall into the Provisional or Planned categories.

Project is not necessarily


the preferred project
alternative

2 018 | 10 -Y E A R AS S E S S M E N T 11
NORTH CENTRAL WISCONSIN

Zone 1
Transmission system characteristics ELECTRIC SYSTEM OVERVIEW
in Zone 1
Small increases expected
ATC delivers power in Zone 1 with various
ONEIDA

LINCOLN
in population, employment
transmission facilities including:
LANGLADE

MARATHON
SHAWANO
Population in Zone 1 is projected to grow
WOOD
PORTAGE
WAUPACA
n East‑west 345‑kV line from the at 0.5 percent annually between now and
JUNEAU
ADAMS
WAUSHARA

MARQUETTE GREEN
LAKE
Village of Arpin through Stevens Point 2027. Employment is projected to grow
extending to the Appleton area, at 0.9 percent annually between now and
n 345‑kV line extending from Stevens 2027. Marathon County is projected to
Point, north to Wausau, and east realize the largest increase in population
toward Shawano County, and employment, while Adams County is
projected to have the highest growth rate
n 345‑kV line extending from Wausau
in population and employment.
to northeastern Minnesota,
n 115‑kV network in the northern Electricity usage
portion of the zone and
Peak electric demand typically occurs
n 138‑kV and 69‑kV network in the during the summer months, with some
southern portion of the zone. winter peaks appearing in the northern
portion of the zone. Primary electricity
Transmission system limitations in Zone 1 users in Zone 1 include several large
Zone 1 has a few key system performance paper mills and food processing plants.
issues. Low voltages that are a result of
potential multiple contingency events will Electric load is forecasted to grow
continue to be monitored, high voltages in approximately 0.4 percent annually
the northern portion of the zone, and other through 2028.
studies have identified thermal limitations
in the northern portion of the zone. The
most severe limitations occur during both
peak and off‑peak periods.

COUNTIES INCLUDED IN ZONE 1 – NORTH CENTRAL WISCONSIN


Adams | Forest (southwestern portion) | Fond du Lac (northwestern portion) | Green Lake | Juneau | Langlade
Lincoln | Marathon | Marquette | Monroe (eastern portion) | Oneida | Portage | Shawano (western portion) Vernon
(eastern portion) | Vilas (southern portion) | Waupaca | Waushara | Winnebago (western portion) | Wood

12 A M E R I C A N T R A N S M I S S I O N C O.
2 018 | 10 -Y E A R AS S E S S M E N T 13
NORTH CENTRAL WISCONSIN LINCOLN
ONEIDA

LANGLADE

MARATHON
SHAWANO

WOOD WAUPACA
PORTAGE

WAUSHARA
ADAMS

Zone 1
JUNEAU MARQUETTE GREEN
LAKE

TRANSMISSION PROJECTS IN ZONE 1


The most notable planned, proposed and provisional network projects and asset renewal projects in Zone 1, along
with their projected year of completion and the factors driving the need for the projects, are listed below.

PROJECT DESCRIPTION IN‑SERVICE YEAR NEED DRIVER

Planned Projects
1 Wild Rose – Harrison 69‑kV line (Y‑19) partial rebuild 2020 Condition and performance

Chaffee Creek – Lincoln Pump Station 69‑kV line


2 (Y‑18) rebuild 2021 Condition and performance

3 Wautoma – Chaffee Creek 69‑kV line (Y‑49) rebuild 2021 Condition and performance

Additional projects may be found in the full 10‑Year Assessment at atc10yearplan.com.

SYS T E M S O L U T I O N S K E Y
SUBSTATION KEY TRANSMISSION LINE KEY EXISTING TRANSMISSION LINES KEY

New substation 345-kV transmission line


Supports transmission system expansion
69 kV 161 kV
115-, 138- or 161-kV transmission line
Substation modifications
Upgrades equipment ratings to avert facility overloads 69-kV transmission line
115 kV 230 kV
Transformer Rebuilt 115- or 138-kV transmission line
Supports local growth and improves voltage levels
Rebuilt 69-kV transmission line 138 kV 345 kV
Capacitor bank or reactor
Relieves low voltages or high voltages 115- or 138-kV transmission line rating upgrade
T-D interconnection 69-kV transmission line rating upgrade
Supports local growth

Lines of proposed projects on the map are for illustrative purposes only and do not reflect actual routes.
For information on project status and routes, see atc‑projects.com.

SUBSTATION KEY
New substation
Supports transmission system expansion
Substation modifications
Upgrades equipment ratings to avert facility overloads

Transformer
Supports local growth and improves voltage levels

Capacitor bank
Relieves low voltages or high voltages

14 A M E R I C A N T R A N S M I S S I O N C O. T-D interconnection
Supports local growth
*
#

Venus
Metonga Forest
*
# *
#

#
* #
* #
* 2 018 | 10 ‑ Y E A R AS S E S S M E N T 15
Ashland Golden Sands Harrison Iron
Waupaca
#
*
Wautoma
#
*
AreaHartman Creek #* 69kV #* # *
k
Harrison Eastom
#
* Saratoga
ACEC Grant
# Portage North 138kV Tomahawk - #* Skanawan Vilas
!
*
Waupaca
11
ATC 115kV SW STR
Wood
Silver Cli
*
#
Woodmin *
# Eagle River *
#
ACEC
Plainfield #
* Tomahawk St Germain #
*
ACEC (ALTE) #
* Cranberry Hills
Arrowhead
# #* ACEC Wildrose Clear Lake Summit
Florence
#
* Plainfield * S
#
* ACEC Sherwood Springwater (WPS) Lake (WPS)
#
* #
* #
* *
#
Lincoln
ACEC Sand Lake
ACEC Wild Wild
Cottonville #
* #
* Fountain
Sawyer Rose Pump Rose
#
* Hancock Valley Grandfather
Three Lakes
#
*
ACEC Wautoma #
* Waushara #
* Falls
#
* #
*

!
ACEC
*
# Adams
Pershing
ACEC Coloma
Coloma
Hancock
#
*
33 #
*
Wautoma #
*
#
*
Red Granite
#
*
Grandfather
Falls Hydro
Langlade
#
* Silver
Oconto
!
#
*
2 Lake ACEC
Friendship ACEC Richford
#
Oneida
Lincoln Pump *
Taylor (ALTE) Spring Mountain
#
*#* ACEC STA Chaffee Creek Lake
* Friendship #
# * Price
ACEC Pine (WPS)
Rhinelander
Polar Forest
*
#
Adams Line 61 Turtle *
# Antigo *
#
#
*
Grand Marsh Westfield Lake Ackley
Paper *
# Aurora St
Mckenna ##
* *
#
#
*
#
* ACEC Brooks #
* #
* Highway Eight **
# Hodag

ACEC Chateau Marquette Green Lake #


*

ACEC #
* Montello Roeder #
* Metonga
Winnebago
ACEC Glen Neenah Creek #
* Montello Green Lake Venus #
* #
*
#
* #
* SW STA
#
* Oxford #
* Maine
Markesan *
# Deer Trail Menominee
Rusk #
* *
#
#
* #
* Eastom
Hilltop (WPS)
#
*# Skanawan
* ShermanSWSt
Cassel Sunnyvale #Tomahawk - STR Brooks Middle Vlg
Wien SW STA * *
#
*
# * ATC 115kV #
# * Birnamwood
Corners *
#
*
# *
#
T Corners
Kelly
*
#
*
#
Marathon *
# Summit
Lake (WPS)
Weston SW YD Morrison Ave #
*
Lincoln
*
#
#
* Wittenberg
Gardner Park #
* Cedar Creek ##
** CWEC
Stratford Grandfather Grandfather
Mosinee Wittenberg

Shawano
*
# Falls Hydro * Falls
# Paper Mill Whitcomb
White Cla
East Shawano *
#
#
* *
# *
# *
# *
#
Pershing # Kronen
*
Langlade
*
#
CWEC Tigerton West Shawano
Oconto
Clark Rozellville Guenther *
# Badger
*
#
*
#
Highway 22

Taylor Caroline *
# *
# Cloverleaf
*
# *
#
McMillan Groenier Marion Belle Plaine
*
# Pine (WPS)
CWEC Dewey *
# Polar
Wildwood *
#
#
* #
* Rosholt Antigo #
*
(MEWD) Ackley #
* Aurora St
* *
# # Mill Creek #
* Clintonville
Auburndale #
* Rosholt CWEC #
* *
#
*
#
Hume
*
#
Richfield
*
#
Arpin Northpoint
Portage
*
# CWEC Iola
*
# Lawn
*
# *
#
Maine
Rudolph
*
# #
*Rocky Run Hoover
*
#
Iola
Deer Trail Menominee
* #
# *
#
*
#
Pittsville Vesper
##
**
Sigel
Hilltop (WPS)
*
Whiting Ave Arnott
Amherst Jct
*
# *
# CWEC Sannes Waupaca
#
*
*
#
Manawa

Wood Lakehead
Consulated
CasselWater Power
#
* Sherman St #* Okray
* Plover
#
*
#
Brooks Middle Vlg
#
#
Outagamie
Wien SW Vesper
STA West * * Werner West
#
* (rrn) Birnamwood
Sheridan Corners #
*#
#
* Wisconsin Sunnyvale * Werner
T Corners
*
# Rapids #
* Coyne St #
* (ALTE) #
*
Harrison Hintz
Kelly
#
* *#
# * Marathon
*
#
#
*
*
# North * Ellington
#
Wisconsin Rapids Golden Sands 138kV

Jackson Port Edwards


*
#
Baker StWeston SW YD #
*
#
*
Morrison Ave *
# Hartman Creek *
#
Wittenberg
#
CWEC
*
#
* #
Harrison
* Waupaca White
Lake (WE)
Vulcan Chem *
#
#
* Gardner Park #
* Cedar Creek Wittenberg
69kV *
#
#
*#
* Apple Hills
*
# *
# ACEC Grant
Shawano
Stratford Hollywood

!
Saratoga Mosinee
*
# Casaloma
#
*
1
Paper Mill Whitcomb *
#
West Shawano
#
* #
* #
* # Butte Des
*
#
* Kronen CWEC Tigerton Morts
East Shawano #
ACEC * *
#
Plainfield #
*
Clark
ACEC
Arrowhead
(ALTE) * ACEC Wildrose
# Badger Highway 22 Northside #
* # *
Rozellville #
* Plainfield
Guenther #
* #
* #
*
* * #
# * M
Neevin #
* Cloverleaf
Winnebago
* ACEC Sherwood
# Caroline #
* # * Tayco Melis
#
* #
* Wild Rose
* #
# *
McMillan Groenier Marion Belle Plaine
#
* Badger West #
*
CWEC Dewey Sand Lake Springwater
Wildwood #
* *
#
*
# ACEC #
* *
# *Rosholt
(MEWD) Cottonville Rosholt CWEC
ACEC *#
Wild# Fountain Clintonville Woodenshoe
#
* #
* Mill Creek
Warrens *
# #
*
Hume
#
*
Auburndale *
#
*
#
Hancock Rose Pump
ACEC Wautoma # *
Waushara *
#
Valley *Winneconne
#
*
# *
#
Mears Corners

!
ACEC

3
Richfield Hancock ACEC Sunset Point
#
*
Big Pond *
#
#
* Arpin Adams Northpoint Coloma
* Wautoma Spring
#
*
# Lake
Red Granite Omro
Pearl Ave
*
#
*
#
Bowen St

#
* ACEC Coloma *
# * CWEC Iola
# * #
# *
* Necedah
# *
##
* Silver *
# #
* Omro
*
# Oshkosh
*
#

!
Tunnel City #
* Cardinal *
# Lake Ellinwood #

2
Rudolph River Run Industrial **
#
North Tomah *
# Glass Tomah ACEC Dellwood Hoover ACEC Richford (ALTE) Iola *
#
#
* Lincoln Rocky Run *
# Park
##
** #
* Friendship *
#
#
* #
* *
#
Pump #
* # Berlin
Waupaca#*
Council Creek Pittsville Vesper Sigel *#
# * * Chaffee Creek Amherst Jct Fox River #
Juneau
* Tomah
# Whiting Ave CWEC Sannes * Fitzgerald *
#
#
* *#
#* ACEC STA Arnott #
* * Manawa
#
Monroe County
*
# Monroe
# Industrial Pk
*
Timberwolf Wood Lakehead
* Friendship #
Houghton RockConsulated
# *
Adams Line 61 #
* Okray #
*
#
*
ACEC
Outagamie
Aviation
Camp Douglas #
West Water Power * Plover
se *
# Vesper Turtle Werner West
Wisconsin *
#
(rrn) Sheridan
#
* Werner
#
* Rapids #* MckennaCoyne St Grand Marsh Westfield Lake (ALTE) Ripon Hintz
*
# Harrison Ellington
* ACEC Brooks # *
*
# *
# #
* Dartford
DPC Buckhorn #
*# * # * # Ind Park #
Marquette
*
# North *
# *
Green Lake
DPC New *#
# * * #
# *
Portage Fond Du Lac
Dorset Wisconsin
ACEC Rapids
Quincy Golden Sands 138kV
Lisbon Castle Rock Northwest # North
Corners #
* #
* Hartman Creek #
* #
* #
* Waupaca White
* Ripon Fond Du
to La Crosse *
# Hilltop Port Edwards Baker St ACEC Chateau Ripon
Harrison
Roeder Lake (WE) Metomen Lac Sadoff

!1
area (ALTE)Vulcan Chem * #
* *
# Montello Rosendale Forest Co Eas
West Mauston
*#
# ACEC *
# 69kV #
* *
# *
# *
#
*# *
Hollywood #
* #
*Winnebago ACEC Grant
Neenah Creek
*
# *
# *
# *#
#*
Jackson Mauston Green Lake
* Saratoga ACEC
# #
* Glen #
* Montello SW STA Mercury *
#
* Oxford
# * #
##
* *#
*
*
# Brandon Marine
Mackford *
# *
# # * #
* # * Mar
Lyndon
Station Markesan Prairie Fairwater South Fond
*
# ACEC ACEC Koch Oil Du Lac
Plainfield Plainfield *
# *
# *
# *
# Wind G
Union Center
Arrowhead
(ALTE) #
#
* ACEC Wildrose Alto SW YD
DPC Lyndon #
* *
Endeavor ACEC Roslin Oakfield
* Wonewoc
# * #
# * ACEC
StationSherwood
Wisconsin *
# *
# *
# Creek
Winnebago
Wild Rose
* Hillsboro *
# # Dells * #
# *
Waupun Forward #*
BadgerWisconsin
West Muni 1 Sand Lake Springwater *
# Energy
Lakehead Westside #*# *
*Dells Muni 2 #
# *ACEC
*#
# * Platt # Portage #
*
Center Buttern
Finnegan Cottonville
* ACEC Wild # * Fountain *
#
Dell Creek Kilbourn * Rose Pump
#
Vernon Warrens #
*
*
# *
# #
*
*
# Loch Mirror ACEC Lewiston
*
# #
Hancock
* Hamilton St Wautoma #
ACEC Cambria
ACEC
Friesland North
#
*
Valley
Waushara #
*
Winneconne
Mears Corners
#*
Reedsburg Zobel ACEC * Fox Lake
Birchwood
Trienda *#
# * *#
# * Randolph
Nishan #* * ACEC
# * #
# * (ALTE) Sunset

!3
*
# Hancock
*
# StaffACEC
*#
# *
# Point
* *
#
Adams Portage Ind Pardeeville *
# Didion
Reedsburg #
* *#
# Artesian
Fox Hills #* Park
Portage *#
# Sanborn
* Wautoma Cambria
Spring
Red Randolph
Granite North
#
*Mayville
Big Pond
* Lake Delton ACEC Coloma
Coloma Manley #
* Lake Omro # * # * Pearl Ave#*
Rock Springs #
* Sand Wyocena Silver # * #
* Beaver Dam *#
# *
# Spring Brook
Tunnel City #
* Cardinal #
* Necedah *
# Island
*
Caledonia #
* *
# *
# *
# Lake Beaver Dam *
# Omro Ellinwood #
Horicon ** #
# *
*
# Baraboo ACEC Richford
Rio Pumping River3rd
RunSt *
# Industrial #
*

!2
Ind Park
North Tomah #* Glass Tomah ACEC Dellwood Kirkwood # * #
* *# * (ALTE) #* Columbia * (ALTE)
# Station #
*Center St # * Beaver
# Park #
*
Hubbard
#*#
* Loganville#
* Friendship# Lincoln #
* SW YD * Dam East Juneau #
** #
# *#*
Council Creek Skillet# #
*Creek
* Pump Fox River
ACEC Calamus Berlin
Chaffee Creek
Juneau
#
* Tomah *
# (ALTE) ACEC #
*# Fitzgerald
Northside Horicon #
*South # * *
Monroe County
Timberwolf #
* Industrial Pk
Houghton Rock # Sauk
ACEC
* Friendship #
STA
*
Merrimac Doylestown *
#
Columbia
*
# Aviation
#
*
Monroe Richland *
# Poynette ACEC
*
# Beaver Dam #
*
#
* Juneau Downtown
Dodge
Camp Douglas Adams Line 61 Fountain Prairie
*
# Fall River #
*# Juneau
#
* #
* Turtle * Industrial
Richland Mckenna Grand Marsh
Lodi
OkeeWestfield Lake Academy # * Columbus
Muni 1 Ripon
Hustisford
Ha
#
*
Arlington *
#
Crawford Center #
* DPC Buckhorn
#
#*
* ACEC Industrial
*
# #
* Maple Street #* * Columbus
# Dartford
Ind Park Butler Ridge #*
Marquette
#
* Brooks *
# #
*
#
Green Lake
Gays Mills Dorset *
# Richland
DPC New #
* * Dam Heights Park # * Lodi Hampden (ALTE) #* #
* *
#
Brewer #* Lisbon Castle Rock
ACEC Quincy
*
# Columbus # *
Seneca *
# Corners *
# *
#*
# *
# Northwest # * Ripon * Rubicon
#
Pine South
*
# DPC Bell #
* Hilltop
*#
#* Ninth Street ACEC Chateau
*
# Ripon
# Center
* River * Sauk City
# North Madison
#
* Roeder Metomen
Montello Rosendale
Dane
(ALTE) West Mauston (ALTE) Troy Sauk City Phillips 345/138 kV North Madison #
* #
*
# ACECSt #
*# *#* * Oak St #
* #
*
Mauston
*
# Winnebago Neenah
Dane #*Creek # *
#
* * Deforest
# *
# Green Lake
#
*
Fond Du Lac
Zone 1
ACEC Glen # * Montello
#
* SW STA
#
* Oxford #
* Brandon
Mackford # * #
*
Markesan Prairie Fairwater Koch Oil
#
* DPC Lyndon #
*
Lyndon 2 018 | 10 -Y E A R AS S E S S M E#
#
* NT
* #
* 15
Union Center Station Endeavor ACEC Roslin Alto
Station
#
* Wonewoc #* Wisconsin #
* #
* #
*
* Hillsboro #
# *
MICHIGAN’S UPPER PENINSULA
AND NORTHERN WISCONSIN

Zone 2
Transmission system characteristics ELECTRIC SYSTEM OVERVIEW
in Zone 2
Small increases expected
ATC delivers power in Zone 2 with various in population, employment
transmission facilities including:
Population in Zone 2 is projected to grow
n Morgan‑Plains, Plains‑Arnold, and
about 0.2 percent annually between now
Arnold‑Dead River 345‑kV lines,
and 2027, and employment is expected
n Plains‑Stiles 138‑kV double‑circuit to grow about 0.8 percent each year
line, in the same time period. Marquette
n Lakota Road‑Plains 138‑kV line, County (Michigan) is projected to realize
the largest increase in population and
n Holmes‑Old Mead Rd 138‑kV line, and employment. Florence County (Wisconsin)
n 138‑kV facilities tying the Upper is projected to have the highest growth
Peninsula of Michigan to lower rate in population while Keweenaw
Michigan. County (Michigan) is projected to have the
highest growth rate in employment.
Transmission system limitations in Zone 2
Electricity usage
There are a number of transmission
system performance issues in Zone 2, Zone 2 typically experiences peak electric
including limited ability to import or demand during the winter months. Ore
export power, generator instability, mining and paper mills are the largest
overloaded lines and equipment, low electricity users in the zone.
and high system voltages and chronic
limitations to transmission service. In the recent past, there have been some
Primary drivers of these issues include load reductions in Zone 2. From these
a mismatch of load to generation in the reduced levels, electric load is forecasted
Upper Peninsula and aging facilities in to increase by 0.4 percent annually
poor or deteriorated condition. In addition, through 2028. Also, locally generated
other ongoing studies, including northern electricity is declining in the area with
area studies performed by ATC and smaller, coal‑fired generators most at
MISO, have identified several voltage risk. This includes generation owned by
and thermal limitations. The most severe industry, municipalities and utilities.
limitations occur during both peak and
off‑peak periods.

COUNTIES INCLUDED IN ZONE 2 – MICHIGAN’S UPPER PENINSULA AND NORTHERN WISCONSIN


Alger, Mich. | Baraga, Mich. | Chippewa, Mich. | Delta, Mich. | Dickinson, Mich. | Florence, Wis.
Forest, Wis. (northern portion) | Gogebic, Mich. (eastern portion) | Houghton, Mich. | Iron, Mich.
Keweenaw, Mich. | Luce, Mich. | Mackinac, Mich. | Marinette, Wis. (northern portion) | Marquette, Mich.
Menominee, Mich. (northern portion) | Ontonagon, Mich. (eastern portion) | Schoolcraft, Mich. | Vilas, Wis. (northern portion)

16 A M E R I C A N T R A N S M I S S I O N C O.
2 018 | 10 -Y E A R AS S E S S M E N T 17
MICHIGAN’S UPPER PENINSULA
A N D N O R T H E R N CookW I S C O N S I N

Zone 2
L a k e S u p erior Keweenaw
*
#
Keweenaw

TRANSMISSION LINE KEY EXISTING TRANSMISSION LINES KEY


TRANSMISSION PROJECTS
345-kV transmission line
IN ZONE 2 69 kV 161 kV *
#
Osceola

115-, 138- or 161-kV transmission line Boston

overloads The most notable planned, proposed and


69-kV transmission line
*
#
Elevation St

provisional network projects and asset 115 kV 230 kV


Atlantic
# MTU
*
* #*#
*
Rebuilt 115- or 138-kV transmission line # Henry St.
levels renewal projects in Zone 2, along with 138 kV Portage
*
# (UPPCO)
Rebuilt 69-kV transmission line 345 kV (UPPCO)
their projected year of completion and the
115- or 138-kV transmission line rating upgrade Toivola
factors driving the need for the projects, are Donken *
#
69-kV transmission line rating upgrade
#
*
Houghton
listed on page 19. UPSCO
##
* Winona
* Ontonagon *
#
White Lake Mine
Pine Mine Mass
*
# JH Warden
White Rockland *
# M-38
Pine Vlg
*
# (UPP) *
# *
# * L'anse
#
#
*
3
*
# Baraga Vlg
Victoria Hy

2
*
#
SYS T E M S O L U T I O N S K E Y Ontonagon Baraga Dead
River Presq

5 Marquette (WE) Isle S

Big Bay Marqu


*
#
##
**
*
#
SUBSTATION KEY North Diese
* Bruce
# Greenstone Lake *#
# *
New substation Crossing Humboldt Mine #
* * #
# * Barnum Huron
Supports transmission system expansion *
# National Empire Mine
*
# * #
# *
Tilden
Substation modifications *
#
Upgrades equipment ratings to avert facility overloads
6
Perch Lake

Gogebic # Mich
*
Sawyer Lumber
##
**
KI
Transformer Transmitter
Facility
Supports local growth and improves voltage levels
Watersmeet Gwinn #
*
* Forsyt
#
Capacitor bank *
#
Relieves low voltages or high voltages Iron
Way Plant
Land O Lakes
T-D interconnection *
#
Lakehead *
#
Supports local growth Homer Road
Iron River
#
* Crystal Falls
Dickinson
*
# Arnold
Iron Grove ##
**
Sagola *
#
Vilas
Lakota Rd Watso
TRANSMISSION LINE KEY Twin Lake
Conover #
*
*
# Peavy
*
# Felch *
#
345-kV transmission line Falls Hy Randville Nordic Mountain
Watson
*
# *
# *
# *
#
Brule SW STA
115-, 138- or 161-kV transmission line Eagle * Michigamme
##
*
Aspen #
* Falls Hy
Woodmin River *
#
69-kV transmission line St Germain Twin Falls

4
*
# *
# Florence SW STA
*
# Cranberry *
#
Florence
Clear Lake
Transmission line voltage conversion # (WPS)
* Pine Hy Bass Lake #
*
*
# Armory Plains
Norway
Rebuilt 115- or 138-kV transmission line Three Lakes Grede Foundries *
#
*#
#* *
##
*#
#*#* Aragon
*
# Kingsford * Champion
Bluff
Rebuilt 69-kV transmission line Metals View Niagra
Oneida Paper Of Powers
*
# *
#
115- or 138-kV transmission line rating upgrade Wisconsin
Rhinelander Forest
69-kV transmission line rating upgrade Paper Goodman
** Hodag
## *
#
Highway Eight #
* Nathan
Metonga *
#
EXISTING TRANSMISSION LINES KEY *
# *
#
Venus
Amberg
White * Chalk Hill Hy
# Menomin
69 kV 161 kV Eastom
Benson Lake ##
** Rapids Hy #
*
Tomahawk - Holmes
115 kV 230 kV
ATC 115kV
*
#
*
#
* Skanawan
#
Silver Cliff
* #
# * Marinette
SW STR
Summit Fox Hills SW
138 kV 345 kV Lincoln Lake (WPS)
*
#
STA
*
#
Grand
Rapids Hy #
*
*
#
Ingalls

Grandfather Caldron
Falls Falls Hy
#
* High Falls Hy ##
** Sandstone
Grandfather
Falls Hydro Langlade Thunder Rapids Hy
*
#
Mountain Crivitz Bay De Noc
Pine (WPS) Polar *
# *
# *
#
*
# Antigo 30th
Ackley
*#
# Aurora St *
# *
#
*
# Ave #*
*
**#
# *#
*
# *#
# *# *
#
*
Pound
#
*
* Sherwood
#
Marathon
Maine Peshtigo
*
#
Menominee
Deer Trail
Hilltop (WPS)
*
# Oconto
Cassel * Sherman St
# Brooks Middle Vlg Lena
*
#
*#
# * Birnamwood Corners
*
# *
# *
# Oconto
Sunnyvale *
# *
#
* Kelly
# Falls Sawye
*
# # # Stiles SW STA
* *
Pioneer (WPS) SW STA
Weston SW YD #* Morrison Ave Wittenberg
Gardner Park #
* Cedar Creek
CWEC Wittenberg
##
** Shawano *
# Redwood
Industria
White Clay
Whitcomb West Shawano Brusbay *
#
* Mosinee
# *
# * #
# * *
#
Kronen # Paper Mill
* CWEC Tigerton East Shawano
*
# Badger Sobieski
* #
# *
Guenther * Caroline #
#
*
# Groenier Marion
*#
*
* Cloverleaf
# Rosiere
CWEC Dewey *
# Rosholt *
# Belle Plaine *
#
18 A M E R I C A N T R A N S M I S S I O N C O. Suamico Dyckesville
Portage
*
#
Kewaunee
Clintonville *
#
#
*
Rosholt CWEC Waupaca *
# Brown
*
# #
*
*
#
Al

Algoma South *A
#
PROJECT DESCRIPTION IN‑SERVICE YEAR NEED DRIVER

Planned Projects
1 Munising‑Blaney Park 69‑kV line (Inland) rebuild 2019 Condition and performance

2 J703: Huron Substation, new G‑T interconnection 2019 G‑T interconnection

3 J704: Silver River Substation, new G‑T interconnection 2019 G‑T interconnection

4 Plains – Arnold 138‑kV uprate 2019 Network integration transmission service request

Proposed Project
5 J711‑Silver River Substation, network upgrades 2020 G‑T interconnection

Provisional Projects
6 Lakota – Winona 138‑kV conversion 2021 Overloads and low voltages

Mackinac – McGulpin 138‑kV submarine cables


7 2021 Condition
(9901, 9903), replacement

Additional projects may be found in the full 10 ‑Year Assessment at atc10yearplan.com.

Magazine Portage St Hy
que
SW YD
##
**
3 Mile Sault
##
* *
uette
el Luce * Pine Grove
#
Brimley Dafter 9 Mile SW STA

1 Raco *
# ##
**
Timber Eckerman *
#
Munising #
* Newberry Vlg Hulbert *
#
Products
# Lou Pac
Chippewa
*
# *
# Seney (UPPCO) * *
#
Chatham Alger *
# #
* Newberry *#
#*
*
# Hulbert Tone
Forest Lake Seney *
# Newberry *
# *
#
I Sawyer *
# *
# *
# Shingleton Kincheloe
(AD-REA) Correctional
Hiawatha SW STA
Alger (AD-REA)
Facility Trout
Lake (CEC)
* Rudyard
# *
#
Pickford

*
# #
* Pickford
th Pine
Schoolcraft *
# River
Rockview
Frank
Lakehead
Gould City
Engadine
#
* *
#
Rexton
Mackinac *
#
Limeston
Talentino
#
* SW STA Goetzville
Hiawatha * Frank
#
*
# Curtis * *
# #
(ESE)
Lakehead
Mich *
# Detour
Gould City Naubinway Brevort Talentino
Blaney Limestone *
#
Park
SW STA *
# Quarry * Mich Limestone
#
SW STA Loading Dock
on
Indian Lake
Delta
Lakehead Valley (ESE)
Perkins ##
*
*
#
Rapid
River
** #
# * Evergreen
Garden Manistique Glen Jenks Mackinac #* St Ignace
*
# Corners *#
# *
Cornell-UP Mackinac Converter #
*
Masonville *
# Straits
*
# *
# (UPPCO)

7
Chandler
* McGulpin
#
*
# *#
# * Gladstone
Old Mead Road
Mead Paper #* North Bluff
#
*#* Mead Pump
*
#
Delta (UPPCO) *
# * Escanaba
#
# Steam Plant
*
Harris West Side
*
#

Emmet
Cheboygan
nee
Presque Isle

g an
h i Charlevoix
i c
M Alpena
Sister Bay
*
#
Lines of proposed projects on the
Montmorency
Otsego
e map are for illustrative purposes

ak
Egg Harbor
Antrim
*
#
only and do not reflect actual routes.
For information on project status
Door
Dunn Rd
L Leelanau and routes, see atc‑projects.com.
*
#
er
Michigan St
A
*#
#
#
* *
* Canal
Alcona
#
al *
# Oscoda
Kalkaska Crawford
Grand
Benzie Traverse
2 018 | 10 -Y E A R AS S E S S M E N T 19
lgoma
Algoma City Ogemaw Iosco
SOUTH CENTRAL/SOUTHWEST WISCONSIN
AND NORTH CENTRAL ILLINOIS

Zone 3
Transmission system ELECTRIC SYSTEM OVERVIEW
characteristics in Zone 3
Increases expected in population,
ATC delivers power in Zone 3 with various employment
transmission facilities including:
Population in Zone 3 is projected to grow
n Columbia‑North Madison 345‑kV lines, about 0.8 percent annually between now
n Columbia‑Rockdale 345‑kV line, and 2027, and employment is projected
to grow about 1.3 percent each year for
n Paddock‑Rockdale 345‑kV line,
the same time period. Dane County is
n Paddock‑Wempletown 345‑kV line, projected to realize the largest increase
n Rockdale‑Wempletown 345‑kV line, in population and employment. Dane
County is also projected to have the
n Rockdale‑Cardinal 345‑kV line, and highest growth rate in population and
n 138‑kV facilities from Nelson Dewey, employment.
around the Madison area, and in the
northwest and southeast portions of Electricity usage
Zone 3. Electric load is forecasted to grow
Transmission system approximately 0.7 percent annually
limitations in Zone 3 through 2028 in Zone 3.

In our analysis of Zone 3, we identified


a number of transmission facility
overloads. These overloads are due to
new generation in the Janesville and
Darlington areas. In addition, other
emerging issues resulting in facility
overloads include steady growth in certain
areas and different generation dispatches.
The most severe limitations occur during
both peak and off‑peak periods.

COUNTIES INCLUDED IN ZONE 3 – SOUTH CENTRAL/SOUTHWEST WISCONSIN


AND NORTH CENTRAL ILLINOIS
Columbia | Crawford (southern portion) | Dane | Dodge | Grant | Green | Iowa | Lafayette
Jefferson | Richland | Rock | Sauk | Walworth | Winnebago, Ill. (northern portion)

20 A M E R I C A N T R A N S M I S S I O N C O.
2 018 | 10 ‑ Y E A R AS S E S S M E N T 21
SOUTH CENTRAL/SOUTHWEST WISCONSIN
AND NORTH CENTRAL ILLINOIS
Tunnel City Cardinal
Glass

Zone 3
North Tomah Tomah
Council Creek
Tomah
Timberwolf Industrial Pk
Briggs Road Monroe County
Camp Douglas
Monroe
La Crosse
DPC New
Dorset Lisbon
Corners

Sauk Madison Area


Sun Prairie
* Vienna
#
Waunakee Business Park West Mau
Mazomanie Division Street Industrial Token Creek #
*
Park Yahara River # * #
* Colorado # * Bird St
Jun
Industrial Mazomanie *#
*#
Centennial # *#
*
# Highway 151 # *
* South#
*
Wick Drive #
* #
* Park *
Waunakee SW # Sun
STA #
* American # * # *
TRANSMISSION PROJEC
TRANSMISSION LINE KEY T S TRANSMISSION LINES KEY
EXISTING
#
*
Black Earth
Dane Westport #
*
Pheasant
Huiskamp
Sycamore
Burke #
Prairie
* Reiner Rd
SW YD # *
IN ZONE 3
345-kV transmission line

!
Stage Coach West Branch Mendota Gaston Rd
#
* Ruskin # #* East Towne #
*
9
SW STA Middleton *
69 kV 161 kV Cross Plains #
** #* Walnut Walnut Gateway # * Royster Sprecher
115-, 138- or 161-kV transmission line Iowa * Cardinal # Blackhawk # *
(MGE) GIS
* Blount #
# * #
* Cottage Grove
Union Center
The most notable planned, proposed and # #
* # #

!
* (MGE) * AGA Gas *
Pflaum *#
# *

1 0
Timberlane Pleasant View East Campus
overloads
10
# Hillsboro Wonewoc
69-kV transmission line * #
*
#
Wingra Femrite #
*
provisional network projects and asset115 kV 230 kV West Towne Tokay *
East Wally Road
#* Femrite McFarland
Syene Nine 138/69 kV #*
Fitchburg
Rebuilt 115- or 138-kV transmission line Lincoln St #
* #
* #
* #
* Springs
evels renewal projects in Zone 3, along with #
** Mount Horeb
# Cross Country Oak Ridge
Colladay

!
Point Kegonsa
Rebuilt 69-kV transmission line 138 kV 345 kV #
8
Verona * #
* #*
their projected year of completion and the Vernon #
*
North
115- or 138-kV transmission line rating upgrade Stoughton
factors driving the need for the projects, are Sun Valley
#
* #
*
Oregon #
*

69-kV transmission line rating upgrade #


* #
*
listed on page 23.

Lines of proposed projects on the


map are for illustrative purposes
SYS T E M S O L U T I O N S K E Y
only and do not reflect actual routes. Richland
SUBSTATION KEY For information on project status Richland
Center
New substation and routes, see atc‑projects.com.
Gays Mills Brewer Richland
Supports transmission system expansion
Seneca Pine
DPC Bell River
Substation modifications Center (ALTE)
Upgrades equipment ratings to avert facility overloads
Allamakee
Transformer
Supports local growth and improves voltage levels
Crawford Lone Rock
Capacitor bank Blue River Muscoda
Avoca
Relieves low voltages or high voltages Muscoda
Industrial
T-D interconnection Boscobel Muni Boscobel
Supports local growth Boscobel
Boscobel Muni
4 Sub

Wauzeka Eastside
TRANSMISSION LINE KEY
Brisbois
345-kV transmission line
Hillside DPC Gran Grae
115-, 138- or 161-kV transmission line La Pointe Prairie
Gran Grae

69-kV transmission line


Du Chien
9 Iowa
Rebuilt 115- or 138-kV transmission line
Eden
Rebuilt 69-kV transmission line Hill Valley Lands End

115- or 138-kV transmission line rating upgrade


69-kV transmission line rating upgrade
Bloomington
Bloomington

Lancaster
EXISTING TRANSMISSION LINES KEY Grant Distribution Rewey
Mineral Point

69 kV 161 kV
Clayton Lancaster

115 kV 230 kV Glen Haven

138 kV 345 kV Nelson


Dewey Belmont
SW YD Cassville Pioneer(ALTE)
Potosi
Hillman
DPC
Stoneman Falcon
Elmo
Red Bird

Cuba City
Kieler DPC
Cuba City
South Benton Shullsburg
Shullsburg

to Dubuque County area Miners

Delaware Dubuque

Jo Daviess
22 A M E R I C A N T R A N S M I S S I O N C O.
PROJECT DESCRIPTION IN‑SERVICE YEAR NEED DRIVER

Planned Projects
Badger Coulee: Briggs Rd – North Madison – Cardinal
1 2018 Reliability, Omro
economics and public policy
345‑kV line construction Industrial
Sunset Point
Big Pond Wautoma
Waushara Omro Park
Bowen St Gravesville

2 J390: Kittyhawk Substation, new G‑T interconnection


ACEC Coloma
Coloma Red Granite
2019 G‑T interconnection
Pearl Ave

Necedah
Silver Lake
(ALTE) ACEC
Ellinwood
Oshkosh
Calumet
3 J395: Darlington – North Monroe 138‑kV
ACEC Dellwood
ACECline
Richford(X‑49), Uprate
Spring 2019
River Run
G‑TWinnebago
interconnection
Fitzgerald Ford
Friendship Lake Drive
Berlin Tecumseh Rd
4 Lone ACEC
Rock – Boscobel
Friendship Pump STA
Lincoln
69‑kV lineChaffee
(Y‑124)Creek
rebuild 2019
Fox River
Condition and performance
Aviation
New
Holstein SW
Houghton Rock
5 Spring Valley – NorthAdams
Lake Geneva 138‑kV line ACEC
Line 61
construction
Turtle
2019 Overloads and low voltages, provide network serviceSTA
Cypress SW YD
Lake Esker View
6 Portage – Staff – North
Mckenna
RandolphWestfield
Grand Marsh
138‑kV lines (X‑6), (X‑98), rebuild 2020
Dartford
Condition
Ripon and performance
Fond Du Lac
Castle Rock
DPC Buckhorn
Adams ACEC Brooks Ind Park
Green Lake 2021 Northwest
7 Sheepskin
ACEC Quincy
– Stoughton 69‑kV line (Y‑12) rebuild Condition
Ripon and performance
North
ACEC Chateau Ripon Fond Du
Hilltop
Roeder Metomen Lac Sadoff
uston (ALTE) Proposed Projects
ACEC
Montello Rosendale Forest Co East Scott St

new T‑DMarquette
Neenah Creek Ledgeview Kettle
neau 8
Mauston Northern Lights Substation,
Winnebago
ACEC Glen interconnection 2020
Green Lake
SW STA
T‑D interconnection Mercury Marine
Macy St
Ohmstead
Morraine
(ALTE)
Oxford Rienzi Road
Brandon Willow Lawn
9 Cardinal – Hickory Creek 345‑kV line construction 2023
Mackford
Reliability, economics and publicMartin
policy
Rd
Cedar
Prairie Fairwater South Fond
Markesan Koch Oil Oakfield Ridge Wind
Du Lac SW YD
Provisional
Lyndon
Station
Project Alto
Forward
Generation

Endeavor Creekview
10 Cardinal
DPC Lyndon – Blount 138‑kV line construction ACEC Roslin
Wisconsin
Station
2029 Overloads and low voltages Energy
Center
Dells Waupun
Wisconsin
Muni 1
Additional
Dells Muni projects
2 Platt may be found in the full
Lakehead
Portage
10 ‑Year Assessment at atc10yearplan.com.
Waupun Butternut
Finnegan Kilbourn Westside
Dell Creek
Loch Mirror ACEC Lewiston ACEC
ACEC Cambria Friesland
Reedsburg Zobel Birchwood Hamilton St Staff Fox Lake Auburn
North
Trienda (ALTE)
Nishan Randolph
Portage Ind Pardeeville Sanborn Cambria
Didion Randolph
Reedsburg Artesian Fox Hills Park
Portage
6 North Mayville

1
Lake Delton
Manley Sand Beaver Dam
Rock Springs Horicon Spring Brook
Rio Pumping Beaver Dam Beaver
Island Caledonia Dam East Ind
Baraboo Wyocena Station 3rd St
(ALTE) Columbia Park
Kirkwood Hubbard Barton
SW YD Center St
Loganville Skillet Creek (ALTE) Columbia ACEC
ACEC Calamus
Juneau
Northside Horicon
Glacier
Merrimac Doylestown South
Sauk Poynette Fall River
Beaver Dam
Juneau Downtown Pleasant
Juneau
Fountain Prairie Valley
Industrial
Academy Arthur Road
Okee Columbus Hustisford
Hartford
Lodi
Industrial
Arlington Maple Street (ALTE) Dodge Butler Ridge
St Lawrence

Dam Heights Park Lodi Hampden Columbus


South
Columbus
Muni 1 Rubicon Washington
Maple (WE)
Ninth Street
North Madison
Troy Sauk City 345/138 kV Deforest Vinburn
Sauk City
Oak St
Phillips St
Dane North
Vienna Sun Prairie Germantown
Madison
Business Park SW YD
Division Yahara River
Mazomanie Street
Spring Green Industrial Centennial Park Bird St Lakehead
Mazomanie Concord SW YD
Token Creek South Stony Brook Bark River
Arena Waterloo
Wick Drive Waunakee SW Burke Sun Prairie
Wyoming Highway 151 Sussex
STA American Tamarack
Valley Black Earth Westport Lakehead Boxelder
Stage Sycamore Reiner Rd Waterloo 2 Cottonwood
Pheasant SW YD
Coach West East Towne Cooney (WE) Mill Rd
Branch Ruskin
SW STA Middleton Gaston Rd
Walnut Royster Tyranena Summit Duplainville
Cross Plains Cardinal Sprecher
(MGE)
Timberlane
Blount AGA Gas

Jefferson
Pleasant View Walnut Wingra Cottage Grove London
Pflaum Femrite Waukesha
West Towne GIS Crawfish

Hooterville
East
Lincoln St
Wally Road
Cross 10
Tokay
Syene Nine Springs
McFarland

Cambridge
River
Merrill Hills
Mount Horeb Country Fitchburg Colladay Jefferson
Waukesha
Kegonsa Lakehead
Point
Verona Christiana Cambridge
Dodgeville
Dane Oak Ridge North
Rockdale
Fort Atkinson

8 Sun Valley Oregon


Stoughton
West
Stoughton

Stoughton 23
Stoughton East Edgewood
Forward
New Stoughton Edgerton
University Mukwonago
Hollandale Brooklyn South Business Mukwonago
Belleville (WE)
Rock Branch Park

7
Dana Corp
Whitewater
Blanchardville Saunders
Sheepskin
New Glarus Creek Lakehead
Evansville Delavan T2 Lakehead Bluff Creek
Delavan Tichigan
Muni LaMar
Union REC Fulton
Monticello Townline REC Red Hawk
(ALTE)
Russell
REC Harmony
Walworth Racine
Lafayette
McCue Sugar Creek
REC Center Milton Lawns

3 Green Viking
Traxler
Burlington

Rock
Albany (ALTE) Footville
North Monroe Sunrise Bristol
Elkhorn Air Liquide

5
REC Janesville General SW YD (ALTE)
Darlington Bass Creek Delavan
Brodhead Orfordville
Jennings Venture REC Bradford North Lake
Idle Hour North Orfordville Tripp Rd
DPC Gratiot Wiota Rd SW STA REC LaPrairie Geneva
Monroe
Central
Brodhead Brodhead
Central Southwest Lake Balsam Kenosha
2
Browntown South Monroe Rock River
Brodhead West Delavan Williams Geneva
Blacksmith South Turtle Scot Darien Bay South Lake
Marine Forge 1 Zenda Geneva
Brick Church Walworth
Spring Grove REC Newark Twin
Paddock Scot Forge 2 Tiger Katzenberg Lakes (ALTE)
Sharon Lakehead Cobblestone
Brodhead Pipeline Richmond Road
SW STA Colley Rd
REC Clinton
East Beloit
I L L I NOIS Shirland
Ave
Park Ave
REC East Rockton
Shaw

Stephenson Winnebago Boone Mchenry Lake


2 018 | 10 ‑-Y
Y E A R AS S E S S M E N T 23
NORTHEAST WISCONSIN

Zone 4
Transmission system characteristics ELECTRIC SYSTEM OVERVIEW
in Zone 4
Increases expected in population,
ATC delivers power in Zone 4 with various employment
transmission facilities including: Population in Zone 4 is projected to grow
n four 345‑kV lines extending from the at 0.6 percent annually between now and
Point Beach Nuclear Plant, 2027. Employment is projected to grow
at 1.0 percent annually between now and
n two 345‑kV lines extending from the
2027. Brown County is projected to realize
Edgewater Power Plant to South
the largest increase in population and
Fond du Lac and Cedarsauk,
employment. Calumet County is projected to
n two additional 345‑kV lines connecting have the highest growth rate in population
the South Fond du Lac Power Plant to and Sheboygan County is projected to have
Columbia and Fitzgerald, the highest growth rate in employment.
n four 345‑kV lines connecting the
Electricity usage
Gardner Park, Werner West, Morgan,
and Plains Substations, Peak electric demand typically occurs during
the summer months, although the northern
n four 345‑kV lines from North Appleton
portion of Zone 4 typically experiences nearly
to Kewaunee, Fox River, Werner West
equal summer and winter peaks. Paper mills
and Fitzgerald, and
and foundries in and around the Green Bay
n a 138‑kV network throughout the zone. and Appleton metropolitan areas are some of
the largest electricity users in the zone.
Transmission system limitations in Zone 4
In our analysis of Zone 4, we found high Electric load is forecasted to grow at
voltages in Calumet County and impending approximately 0.3 percent annually through
low voltages in Brown County. In addition, 2028. Also, locally generated electricity
other ongoing studies have identified is declining in the area with smaller,
several voltage and thermal limitations. coal‑fired generators most at risk. This
The most severe limitations occur during includes generation owned by industries,
both peak and off‑peak periods. municipalities and utilities.

Several area projects are related to the


underlying condition and performance of
assets in Zone 4.

CO U N T I E S I N C L U D E D I N Z O N E 4 – N O R T H E AST W I S CO N S I N
Brown | Calumet | Dodge (northeastern corner) | Door | Fond du Lac (eastern portion) | Kewaunee
Manitowoc | Marinette (southern portion) | Menominee, Mich. (southern portion) | Menominee, Wis.
Oconto | Outagamie | Shawano (eastern portion) | Sheboygan | Winnebago (eastern portion)

24 A M E R I C A N T R A N S M I S S I O N C O.
2 018 | 10 -Y E A R AS S E S S M E N T 25
NORTHEAST WISCONSIN

Zone 4
TRANSMISSION PROJECTS IN ZONE 4
The most notable planned, proposed and provisional network projects and asset renewal projects in Zone 4,
along with their projected year of completion and the factors driving the need for the projects, are listed below.

PROJECT DESCRIPTION IN‑SERVICE YEAR NEED DRIVER

Planned Projects
Bay Lake: North Appleton – Morgan 345‑kV and 2018 Overloads and low voltages
1
138‑kV line construction
2 Cedar Ridge Wind – Mullet River 138‑kV line (X‑97) rebuild 2020 Condition and performance
3 Edgewater SS, 345‑kV bus reconfiguration 2020 Condition and performance
4 Goodman – Caldron Falls 69‑kV line (J‑88) rebuild 2020 Condition and performance
Butte des Morts – Sunset Point 138‑kV lines 2021 Condition and performance
5
(40321), (80952), (A‑79), (MCRG21) rebuild
6 Finger Rd – Canal 69‑kV line (J‑10) rebuild 2021 Condition and performance
7 Ogden St. – Bayshore 69‑kV line construction 2021 Provide network service

8 Hwy V – Oak St 69‑kV line (Z‑26) rebuild 2022 Condition and performance

Proposed Projects
9 Bayport area – Pioneer, rebuild as double‑circuit 138‑kV
2021 Condition, performance
and provide network service
Pioneer – Crivitz (E‑83/B‑2), retire 69‑kV and 2022 Condition, performance,
10
reconfigure load to 138‑kV and provide network service
Additional projects may be found in the full 10‑Year Assessment at atc10yearplan.com.

SYS T E M S O L U T I O N S K E Y
SUBSTATION KEY TRANSMISSION LINE KEY EXISTING TRANSMISSION LINES KEY

New substation 345-kV transmission line


Supports transmission system expansion
69 kV 161 kV
115-, 138- or 161-kV transmission line
Substation modifications
Upgrades equipment ratings to avert facility overloads 69-kV transmission line
115 kV 230 kV
Transformer Transmission line voltage conversion
Supports local growth and improves voltage levels
Rebuilt 115- or 138-kV transmission line 138 kV 345 kV
Capacitor bank or reactor
Relieves low voltages or high voltages Rebuilt 69-kV transmission line
T-D interconnection 115- or 138-kV transmission line rating upgrade
Supports local growth
69-kV transmission line rating upgrade

26 A M E R I C A N T R A N S M I S S I O N C O.
#
*
Metonga
#
*

Forest
Chalk Hill Hy
#
*
Amberg White
Benson Lake *#
* Rapids Hy
#
#
* Holmes
* Menominee
Fox Hills
Silver Cliff SW STA
#
* #
*

4 #
*
#
Grand
Rapids Hy
*#
*
Ingalls
Caldron
Falls Hy

High Falls Hy
Thunder Marinette
* #
# *
High Sandstone
Falls Hy
Langlade #
*
Rapids Hy

Mountain Bay De Noc Sister Bay


Crivitz #
*
#
* #
*
#
*
Polar Menominee
#
* #
*
30th Ave
Wells #
*
Scott Paper Co St
#
* *#
#**#
#
*
*
#
*
Pound #
* * #
# *
Ogden St
West Egg Harbor
#
*

7
Marinette
Peshtigo #
**
# SW YD
Sherwood

Deer Trail Menominee Oconto


10

n
#
*

ga
Lena
#
*
Middle Vlg Door

hi
Brooks #
*
Corners Oconto Dunn Rd
#
* #
* #
*

ic
Pioneer
Stiles SW STA
(W PS)
Falls
#
*
#
*
#
* Sawyer

M
Michigan St
SW STA
Morgan
*#* # *
#
* Redwood # First Ave
#
*

9 * Canal
Industrial #

e
Shawano Brusbay

k
White Clay
West Shawano #
* #
*
#
* #
* East Shawano

a
Little
CWEC Tigerton Suamico

L
#
* #*
Highway 22 #
*
#
* Badger #
*
* Sobieski
Cloverleaf
Caroline #
* #
*
Belle Plaine Rosiere
#
1
Marion *
#
*
#
* Dyckesville
Clintonville Suamico #
* Algoma
#
* #
*#
*
Algoma City
#
*
Bayport Algoma South

Kewaunee
Maplewood SW STA
#
* #
*
Howard
#
* #
* Pulliam SW YD
WEC Iola # *

6
Lawn Rd Velp Ave
#
*
#* Luxemburg
Lawn Rd #
* Mason St #
* #
*# #
* #
*
7th St * #
*
#
*# Preble #
*
Liberty St *#
* * Finger Rd SW Barnett
*#
# #
*
#
* #
* STA Ontario
Highway V#
* #
* Booster
Ashland Ave #
* Beardsley St
Manawa #
*
#
* Outagamie Glory Rd #
#
*
*
#
Oak St #
#
*
** East Krok
Waupaca De Pere # * #
*
Werner West
# * Red Maple
#
* Hintz
8
*
Werner
* Rockland
#
Ellington (W PS)
Harrison
#
* #
*
Kewaunee
North Appleton Lost Dauphin
North 138kV #
* SW YD
Wesmark
#
* Greenleaf
Brown #
*

Green Bay Area


#
* Waupaca White Fox River #
* #
*
arrison
SW YRD
#
*
69kV Lake (WE) Bayport
#
* #
* #
* SW STA
Apple Hills * Kaukauna North
# Apollo
#
* #
* Point Beach Howard
Casaloma Maes Kaukauna Velp Ave
#
* #
* Central SW YD #
* #
*
#
* #
* Mishicot #
*
Butte Des City Combined Pulliam SW YD
Locks #
* Tower Dr
Morts Limits Kellnersville Danz
#
* #
* # * Lake Park Branch River #
* James St
#
* Ave SW
Mason St Van Buren St STA
#
* #
* # #
*
*#
* *
Northside #
* #
* Meadows Eastman Ave # #
*
Neevin #
*
* #
# *
Tayco Melissa
Forest Ryan St Brown 7th St
Henry St
(WPS)
Junction
Glenview #
* Iron F oundry
* #
*#
* Columbus St #
* #
* #
*
Liberty St Preble
Winnebago Brillion
Iron Works Shoto
#
* #
* * #
# * South
Broadway

5
Mirro Finger Rd
#
*
Woodenshoe Manitowoc Northeast
#
*
#
* #
* Potts Avenue
#
*
SW STA

Fountain Highway V
Rapids Revere Dr

!
Valley Winneconne
#
* Manrap #
* #* Lakefront #
* #
*

Waushara
#
* #
*
Mears Corners
Calumet #
*
Custer #
*
Dewey
#
* SW YD
Mpu Plant
Glory Rd
Glory
Road
North #
*
Ashland Ave
8 Bluestone #
*
Omro Sunset Point #
* De
Industrial #
* Gravesville St Nazianz Pere
Bowen St Oak St #
ed Granite Omro Park #
* #
* *#*#
*
* #
# * Pearl Ave #
* De Pere Nicolet
#
* Oshkosh Paper Co Mystery Hills
#
*
Ellinwood *#
# *12th#
*
River Run
Progress #
* Ford
#
* Fitzgerald
Fox River
#
* Tecumseh Rd
Drive
#
* #
* Berlin
# Aviation #
*
* New Holstein
#
* Roosevelt
#
* New
Holstein SW
STA

* Esker View
#
Cypress SW YD
#
*
Dartford Ripon
Ind Park Howards Grove
#
*
#
* #
*
Northwest #
*
Ripon #
* Ripon North Fond Du Lac #
*
Elkhart Lake
Plymouth
Fond

Green Lake Du Lac Sadoff


er Metomen Sub 4 Erdman North
#
*
#
*
Rosendale Forest
#
*
* Co
#
** #
# *
East Scott St

# Macy St # * Ledgeview
#
*
Northside
#
* Gate
#
*
Lines of proposed projects
Hickory St # Kettle Plymouth Plymouth Sub 3 (sfm) 32nd St #
*
Green Lake
SW STA
#
*
Mercury Marine #
*
**
#
#
* * Ohmstead Cedar Ridge
#
Rienzi Wind Generation
Morraine
(ALTE)
Muncipal
#*
Mullet River #
#
*
#
*
Sheboygan Bemis #
*
(ALTE)
#
*
20th St #
*
#
* Riverside (ALTE) on the map are for illustrative
Brandon Willow Lawn
* Nicolet #
Fairwater # #
* * *
* # *
* #
purposes only and do not
# * Road Falls Energy #* #*#
#
* * # Martin Rd North #* #
*#
*
Edgewater SW YD
Center SW YD
Mackford * Monroe St #
2
South Mullet River # *
Markesan Prairie Fond Du Lac
Oakfield
reflect actual routes.
Koch Oil South
#
* #
*
#
* #
* SW YD Sheboygan
Forward Falls
Alto Lyndon
Creekview
#
* Energy
#
* Sheboygan #
*
For information on project
3
Center
Waupun
Waupun #
*
Westside # #
*
* #
*
Butternut
Holland status and routes, see
#
*

ACEC
#
*
atc‑projects.com.
North
Friesland
Dodge
Randolph Fox Lake Auburn
#
* #
* #
*
(ALTE)
ia Randolph
Didion #
*
# #
Washington
* *
umbia Mayville
Ozaukee
#
*
#
*
Fredonia
#
Zone 4
*

2 018 | 10 ‑ Y E A R AS S E S S M E N T 27
SOUTHEAST WISCONSIN

Zone 5
Transmission system ELECTRIC SYSTEM OVERVIEW
characteristics in Zone 5
Increases expected in
ATC delivers power in Zone 5 with various population, employment
transmission facilities including:
Population in Zone 5 is projected to grow
n the southern portion of 345‑kV lines 0.5 percent annually between now and
from Point Beach and Edgewater, 2027, and employment is projected to
n the Saukville, Arcadian, Granville, grow 1.1 percent in the same time period.
Oak Creek, and Racine 345‑/138‑kV Waukesha County is projected to realize
substations, the largest increase in both population
and employment. Waukesha County is
n the transmission lines emanating
also projected to have the highest growth
from the Oak Creek power plant,
rate in employment while Ozaukee County
n 230‑kV facilities near Milwaukee, and is projected to have the highest growth
n a significant 138‑kV network in the rate in population.
Milwaukee area, a portion of which
is underground. Electricity usage
Peak electric demand typically occurs
Transmission system during the summer months. Large
limitations in Zone 5 industrial loads in the Milwaukee
metropolitan area are among the largest
Transmission system performance issues
electricity users in the zone.
in Zone 5 include heavy market flows
to and from the south, resulting in high Electric load is forecasted to grow
345‑kV and 138‑kV line loadings and approximately 0.7 percent annually
the need to monitor potential multiple through 2028.
contingency conditions.

COUNTIES INCLUDED IN ZONE 5 – SOUTHEAST WISCONSIN


Kenosha | Milwaukee | Ozaukee | Racine | Washington | Waukesha

28 A M E R I C A N T R A N S M I S S I O N C O.
A M E R I C A N T R A N S M I S S I O N C O. 2 016 10 ‑ Y E A R AS S E S S M E NT

2 018 | 10 -Y E A R AS S E S S M E N T 29
SOUTHEAST WISCONSIN

Zone 5
TRANSMISSION PROJECTS IN ZONE 5
The most notable planned, proposed and provisional network projects and asset renewal projects in Zone 5, along
with their projected year of completion and the factors driving the need for the projects, are listed below.

PROJECT DESCRIPTION IN‑SERVICE YEAR NEED DRIVER

Planned Projects
1 Mount Pleasant Tech Interconnection Project 2019 T‑D interconnection

Mukwonago‑Edgewood‑St. Martins 138‑kV lines 2019 Condition and performance


2
(3013), (671K61), rebuild

3 Spring Valley‑North Lake Geneva 138‑kV line construction 2019 Overloads and low voltages,
provide network service

4 Paris‑Burlington 138‑kV line (8962) rebuild 2021 Condition and performance

St. Lawrence‑Barton‑Auburn 138‑kV lines 2022 Condition and performance


5
(8032), (9752), rebuild

Proposed Projects
6 Juneautown Substation, new T‑D interconnection 2020 T‑D interconnection

Port Washington‑Saukville 138‑kV rebuild line 762


7 2021 Overloads
to a double circuit

Additional projects may be found in the full 10‑Year Assessment at atc10yearplan.com.

SYS T E M S O L U T I O N S K E Y
SUBSTATION KEY TRANSMISSION LINE KEY EXISTING TRANSMISSION LINES KEY

New substation 345-kV transmission line


Supports transmission system expansion
69 kV 161 kV
115-, 138- or 161-kV transmission line
Substation modifications
Upgrades equipment ratings to avert facility overloads 69-kV transmission line
115 kV 230 kV
Transformer Rebuilt 115- or 138-kV transmission line
Supports local growth and improves voltage levels
Rebuilt 69-kV transmission line 138 kV 345 kV
Capacitor bank or reactor
Relieves low voltages or high voltages 115- or 138-kV transmission line rating upgrade
T-D interconnection 69-kV transmission line rating upgrade
Supports local growth
230-kV transmission line rating upgrade

30 A M E R I C A N T R A N S M I S S I O N C O.
#
*

Mayville
#
*
m Fredonia
er Spring Brook #
*
East #
*

Horicon Ozaukee
Ind Park
#
* Hubbard
#
*
#
* Barton
#
5
Horicon *
Juneau * Glacier
#
Northside
#
* Dodge Charter Steel
* Juneau
# #
* Port
Downtown Washington
Juneau
#
*
SW YD
Industrial #
*
Pleasant
Cedarsauk #
#
*
Valley Saukville
Arthur Road #
*

7
#
#
*
*
Hustisford St Lawrence
#
* Hartford
#
*
Butler Ridge
#
Washington
*
River Bend
Rubicon #
*
#
*
Cedarburg
South
Maple (WE)
#
* #
*
Mequon
#
*

Germantown
SW YD 68th St
#
* #
*
Swan
#
*
Concord SW YD
Parkland
#
* Bark River #
*
#
* Range
Line
Sussex Dist
#
* Range Line SW
Mill Rd Tamarack
* #
# * Douglas # *
#
*
* #
# *
Granville #
* Glendale
Sidney Term # *
Cottonwood Cornell -
Cooney (WE) Butler Milwaukee
#
* #
* #
* #
*
Fiebrantz #
* #
* Shorewood

Lak
Humbolt #
*
Summit Duplainville
#
* Tosa Term
#
* #
* Center
#
*
Milwaukee Haymarket

6
CTY SW YD Square
#
* Park #
*
28th St
O Connor Hill #
* *
Waukesha Bluemound
#
* #
* # *#
* #* * #
# Juneautown
#
* #
*

e M
96th St #
* Valley #
*
Jefferson Waukesha Arcadian
Moorland Walker (WE) Harbor (WE)
#
* #
* #
*
West Junction Russel Term
Merrill Hills Lincoln #
* Montana
#
* #
* #
*
#
*
Plainfield Dewey (WE)
Norwich
(WE) 43rd St Term Kansas
Brookdale #
* *#* Terminal
#
* #
#
* #
* 51st St Term Norwich

ich
Allerton
Milwaukee
Barland Ramsey
* #
# *
Branch
Nicholson

2 #
* (WE)
#
*

iga
St Martin
St. Martins Branch
#
*
Edgewood
#
*
Pennsylvania
#
*
University
Mukwonago
(WE)
*#
* Root River Oak Creek
#
* # #
* Oakview SW YD
Oak Creek (COMS
#
* 230kV) SW YD
*#
#*
Oak Elm Road
Creek (COMS 138kV) 345 Sws Yd
Whitewater SW YD
#
*
kehead
lavan
Bluff Creek St Rita
# Raymond
* #
*
Tichigan #
*
#
*
Racine

Walworth Hayes
Sugar Creek #
* #
*
#
* Racine

Burlington

Air Liquide
#
*
4 Paris
Mt. Pleasant
#
*
Elkhorn #
*
#
*
#
* Somers
Bristol #
*
(ALTE)
#
*
Delavan Berryville #
*
#
*
adford Southwest North Lake
* Delavan
3
# Geneva #
*
Albers

1
West Darien Lake Geneva
#
* #
*
#
* Balsam
#
* #
*
Kenosha
Williams Bay
Lines of proposed projects #
*
South Lake Kenosha
Geneva #
*
on the map are for illustrativeZenda Spring #
*
Bain

Brick Church Valley


purposes only #* and
#
* do not reflect
Walworth #
*
# Tw in
* Lakes
(ALTE)
(WE)
#
* Pleasant
#
*
Lakehead Cobblestone
actual routes. For information
Pipeline #
* Katzenberg
#
*
#
* Richmond Road Prairie
SW YD
Sharon State Line Sub
on
#*
project status and routes, #
* #
*
Lakeview

see atc‑projects.com.
I L L I NOIS Zion Energy
Center
#
*

2 018 | 10 -Y E A R AS S E S S M E N T 31
ne Mchenry Lake
P.O. Box 47
Waukesha, WI 53187‑0047

Helping to keep the lights on, businesses running and communities strong
®

ATC AT A GLANCE
n Formed in 2001 as the first multi‑state, transmission‑only utility
n Owner and operator of approximately 9,600 miles
of transmission line and more than 560 substations
n Meeting electric needs of more than five million people
in 72 counties in four states: Wisconsin, Michigan,
Minnesota and Illinois
n $4.7 billion in total assets

CONTACT

Mail P.O. Box 47 n Waukesha, WI 53187‑0047


Toll‑free (866) 899‑3204
Email info@atcllc.com

More detailed information is available at atc10yearplan.com

atcllc.com

Would you like a speaker from ATC to address your group?


Give us a call, toll‑free, at (866) 899‑3204, ext. 8679.

Você também pode gostar