14.12.2016.

Method Statement For Installation of Electrical Water Heaters

Method Statement For Installation of Electrical Water
Heaters
1. PURPOSE

The  purpose  of  generating  this  Method  Statement  is  to  define  the  procedure  step  by  step  to  implement  the
correct practices for Installation of Electrical Water Heater through the guide line contained herein so as to
ensure that the job execution complies with the requirements and serves the intended function to satisfactory
level.

2. SCOPE

This  Method  Statement  refers  to  various  work


Advertisement procedures  contained  within  project
control  documents,  which  explains  and  covers  the
Installation of Electrical Water Heater

3. RESPONSIBILITIES

Plumbing  Engineer  In­charge  (Plumbing)  /  Site


Engineer (Plumbing).

4. TOOLS / EQUIPMENTS

4.1. Portable hand tools.
4.2. Spirit Level / Level Threads
4.3. Drill Machine / Hammering Machine
4.4. Step Ladder.

5. MATERIALS

Electrical Water Heater and accessories shall be in line with the approved material submittal.

6. HANDLING & STORAGE

6.1. On receipt of the Electrical Water Heater and accessories at site, shall be off­loaded carefully at site using
necessary manpower and required equipment to ensure that no damage is caused to the materials necessary
precautions shall be taken for unloading, shifting & storage.

6.2. All Packages for the Electrical Water Heater reaching to site shall be identified as per package list.

6.3.  The  Electric  Water  Heaters  shall  be  preferably  shifted  directly  to  its  location  for  installation.  In  case  the
House  Keeping  Pad  /  Foundation  is  not  ready  the  Electric  Water  Heaters  will  be  stored  in  site  stores  as  per
manufacturer instruction.

6.4. All Packages for the Electrical Water Heater reaching to site shall be identified as per package list.

6.5.  The  Electric  Water  Heaters  will  be  checked  to  ensure  that  it  complies  with  the  approved  material
submittals in terms of make, model, type, capacity etc.

6.6. Any discrepancies, damage etc., found will be notified and reported for further action.

6.7. Site Engineer (Plumbing) has to ensure that all Water Heater used at site are of free from any damage or
deformity  of  any  kind.  Material  found  not  suitable  for  site  use  will  be  removed  immediately  from  site  and  the
same will be replaced by correct item.

http://safeworkmethodofstatement.com/method­statement­for­installation­of­electrical­water­heaters/ 1/2
14.12.2016. Method Statement For Installation of Electrical Water Heaters

6.8.  All  packages  shall  be  stored  under  protected  dust  area,  till  the  Electrical  Water  Heater  is  shifted  for
installation

INSTALLATION PROCEDURE FOR ELECTRICAL WATER HEATER

7.1 Ensure all civil works are completed for the area of installation, and clearance is obtained from respective
authorities to proceed further.

7.2  Prior  to  start  the  installation,  refer  to  the  approved  shop  drawings  related  to  the  area  of  installation  and
ensure that required materials are available at site as per approved material submittals.

7.3 Ensure the materials are stored properly and there is no mark of damage or deformity of any kind before
issuing the material from site store.

7.4 Approved Electric Water Heaters shall be used for installation purpose.

7.5 Electric Water Heaters shall be installed as shown in the approved shop drawing.

7.6 Electric Water Heaters shall be installed on the House Keeping Pad / Foundation ensuring adequate space
is available for valves, piping and for future maintenance.

7.7 Installed Electric Water Heaters shall be offered for inspection.

8. INSPECTION
Inspection will be raised for installation of Electrical Water Heater.

9. ATTACHMENTS
9.1 Risk Assessment
9.2 Inspection and test plan
9.3 Quality control procedure
9.4 Check sheets