STANDARD MATERIAL CONSUMPTION FOR VARIOUS ITEMS

(A)
LOOSE
SR. NO. ITEMS IN PLINTH UNIT PER
SOIL
Excavation in black 100 cft 150 cft
1
cotton soil 1 cum 1.5 cum
100 cft
2 Compacted murum filling
1 cum
100 sft
3 Rubble soiling 23 cm (9”) thick
1 sqm

(B)
SR. NO. CONCRETE ITEMS UNIT PER CEMENT
100 cft 9 bags
1 P.C.C. (1 : 4 : 8)
1 cum 3.18 bags
100 cft 12 bags
2 P.C.C. (1 : 3 : 6)
1 cum 4.24 bags
100 cft 17 bags
3 R.C.C. (1 : 2 : 4)
1 cum 6.00 bags
100 cft 22 bags
4 R.C.C. (1 : 1½ : 3)
1 cum 7.77 bags

(C)
SR. NO. CONCRETE BLOCKS UNIT PER CEMENT
Solid cement concrete 35 Nos. 11 bags
1
block 30x15x20 cm (12” x 6” x 8”) 35 Nos. 1 bags
Solid cement concrete block 30x10x20 cm 50 Nos. 1 bags
2
(12” x 4” x 8”) 50 Nos. 1 bags
(D)

MASONRY ITEMS (excluding R.C.C.


SR. NO. UNIT PER CEMENT
band

U.C.R. masonry 100 cft 4.50 bags


1
in C.M. 1:6 1 cum 1.60 bags
100 sft 2.50 bags
2 23 cm (9”) B.B.M. in C.M. 1:6
1 sqm 0.27 bags
100 sft 1.50 bags
3 15 cm (6”) B.B.M. in C.M. 1:6
1 sqm 0.16 bags
100 sft 1.00 bags
4 10 cm (4”) B.B.M. in C.M. 1:4
1 sqm 0.11 bags
15 cm (6”) concrete block masonry in 100 sft 1.00 bags
5
C.M. 1:6 1 sqm 0.11 bags
10 cm (4”) concrete block masonry in 100 sft 1.00 bags
6
C.M. 1:4 1 sqm 0.11 bags

(E)
SR. NO. PLASTERING ITEMS UNIT PER CEMENT
Sanla finish plaster 12.5 mm (½”) thick 100 sft 1.50 bags
a) In C.M. 1 : 4 1 sqm 0.16 bag
100 sft 1.20 bags
1 b) In C.M. 1 : 5
1 sqm 0.13 bag
100 sft 1.00 bags
c) In C.M. 1 : 6
1 sqm 0.11 bag
Sanla finish plaster 20 mm (¾”) thick 100 sft 2.4 bags
a) In C.M. 1 : 4 1 sqm 0.26 bag
100 sft 1.90 bags
2 b) In C.M. 1 : 5
1 sqm 0.21 bag
100 sft 1.60 bags
c) In C.M. 1 : 6
1 sqm 0.17 bag
Sanla faced plaster
100 sft 2.25 bags
Single coat 15 to 20 mm thick
a) In C.M. 1 : 4 1 sqm 0.24 bag
3 100 sft 1.8 bags
b) In C.M. 1 : 5
1 sqm 0.19 bag
100 sft 1.5 bags
c) In C.M. 1 : 6
1 sqm 0.16 bag
Sanla faced plaster
100 sft 3.75 bags
Double coat 15 to 20 mm thick
a) In C.M. 1 : 4 1 sqm 0.41 bag
4 100 sft 3.0 bags
b) In C.M. 1 : 5
1 sqm 0.32 bag
100 sft 2.5 bags
c) In C.M. 1 : 6
1 sqm 0.27 bag

(F)
SR. NO. FLOORING & TILING UNIT PER CEMENT
Mosaie tile flooring 100 cft 1.0 bags
1
(25 cm x 25 cm) 1 cum 1.11 bags
Mosaie tile flooring 100 sft 2.0 bags
2
(25 cm x 12.5 cm) 1 sqm 0.65 bags
Stone flooring (marble, kotah, tandoor etc.
100 sft 2.0 bags
3 (45 cm x 60 cm uncut size)
(after cutting 40 cm x 55 cm) 1 sqm 0.22 bags
Rough shahabad stone flooring
100 sft 0.75 bags
4 (45 cm x 60 cm uncut size)
(after cutting 40 cm x 55 cm) 1 sqm 0.08 bags
Chequered tile flooring 100 sft 1.25 bags
5
(25 cm x 25 cm) 1 sqm 0.13 bags
100 sft 2.50 bags
6 Crazy (Tukda) mosaic flooring
1 sqm 0.27 bags
100 sft 3.5 bags
7 I.P.S. flooring
1 sqm 0.38 bags
Glazed tile dado 100 sft 3.5 bags
8
(15 cm x 15 cm) 1 sqm 0.38 bags

(G)
SR. NO. WATER PROOFING UNIT PER CEMENT
Brickbat coba W/P 100 sft 6.0 bags
1
in W.C. bath, toilet etc. 1 sqm 0.65 bags
Brickbat coba W/P 100 sft 4.0 bags
2
To terrace. 1 sqm 0.43 bags
Glazed china mosaie (Kavadi) type W/P to 100 sft 5.0 bags
3
terrace (including brick – bat coba) 1 sqm 0.50 bags

CALCULATIONS OF SHUTTERING MATERIAL REQUIREMENT BY QUICK METHOD ESTIMATION F

MULTIPLYI
NG
CONSTAN
SR. MATERIAL REQUIRED UNIT
T BY
THUMB
RULE
Plywood 12 m thick of
2500 sft 0.02
1 Size 2.44 x 1.22 m
(8’-0” x 4’-0”) 232 sqm 0.22
50 sheets
Silver oak battern of
2500 sft of plywood
Size 75 mm x 40 mm
x 65
2 50 sheets
(3” x 1 ½”) 232 sqm of plywood
x 19.82
2500 sft x
Beam bottom planks 2500 sft
0.24
3
232 sqm x
40 mm thick (1 ½”) 232 sqm
0.79
Wooden props 600 rft
beam
2500 sft
a) For beams bottom x
0.5
183 rft
beam
232 sqm
4 bottom x
1.65
2500 sft x
2500 sft
0.16
b) For slab
232 sqm x
232 sqm
1.72
Wooden batten for supporting
2500 sft 2500 x 0.4
5 Slab plates
75 mm x 75 mm (3” x 3”) 232 sqm 232 x 1.31
Steel plates of size 2500 x
2500 sft
6 60 mm x 90 cm 0.16
(2’-0” x 3’-0”) 232 sqm 232 x 1.72
2500 x
2500 sft
7 Wire nails 0.020
232 sqm 232 x 0.22
2500 x
2500 sft
8 Shuttering oil 0.006
232 x
232 sqm
0.065
M.S. clamps 2500 x
2500 sft
9 (Shikanja) 0.08
232 sqm 232 x 0.86
TION OF STEEL IN KG PER SQM OR SFT OF WORK

CONSUMPTION OF
SR. NO. ITEMS STEEL
on built-up area
0.55
1 Footing 0.05kg/sft
kg/sqm
2.15
2 Columns up to plinth 0.20kg/sft
kg/sqm
1.15
3 Tie beam 0.10kg/sft
kg/sqm
4.80
4 Column (super structure) 0.45kg/sft
kg/sqm
7.0
5 Slab 0.65kg/sft
kg/sqm
7.5
6 Beam 0.70kg/sft
kg/sqm
0.55
7 Chajja/loft/lintel 0.05kg/sft
kg/sqm
0.55
8 Over head water tank 0.05kg/sft
kg/sqm
24.25
TOTAL 2.25kg/sft
kg/sqm

OXIMATE QUANTITIES OF VARIOUS ITEMS PER SQ. M. / SQ. FT. OF BUILT-UP AREA.

APPROX. QTY.
PER
SR. NO. ITEM
SQ. M. SQ. FT.
1 Excavation 0.31 cum 1.00 cft
0.046
2 R.C.C. below plinth 0.15 cft
cum
0.290
3 R.C.C. above plinth 0.95 cft
cum
4 Internal Masonry 0.7 sqm 0.7 sft
5 External Masonry 0.9 sqm 0.9 sft
6 Internal Plaster/Paint 3.2 sqm 3.2 sft
7 External Plaster/Paint 2.5 sqm 2.5 sft
8 Oil Paint 0.62 sqm 0.62 sft
SUMPTION FOR VARIOUS ITEMS

LOOSE
RUBBLE
MURUM

150 cft
1.50 cum
90 cft
0.26 cum

METAL
METAL 25 METAL 20
SAND 12 mm
mm (1”) mm (¾”)
(½”)
60 cft 65 cft 20 cft
0.60 cum 0.65 cum 0.20 cum
60 cft 65 cft 20 cft
0.60 cum 0.65 cum 0.20 cum
60 cft 65 cft 20 cft
0.60 cum 0.65 cum 0.20 cum
60 cft 65 cft 20 cft
0.60 cum 0.65 cum 0.20 cum

METAL 12 STONE STONE


SAND SHINGLE
mm (½”) GRIT DUST
3.75 cft 2.50 cft 7.00 cft 5.50 cft 2.50 cft
0.11 cum 0.07 cum 0.20 cum 0.16 cum 0.07 cum
3.75 cft 2.50 cft 7.00 cft 5.50 cft 2.50 cft
0.11 cum 0.07 cum 0.20 cum 0.16 cum 0.07 cum

BRICKS BRICKS BRICKS


BRICKS
SAND RUBBLE 23X15X 23X10X 23X10X
23X10X7 cm
9 cm 7 cm 7 cm
40 cft 125 cft
0.40 cum 1.25 cum
20 cft 1000 Nos.
0.06 cum 110 Nos.
15 cft 400 Nos.
0.05 cum 45 Nos.
8 cft 475 Nos.
0.25 cum 50 Nos.
11 cft 145 Nos.
0.03 cum 16 Nos.
8 cft 145 Nos.
0.25 cum 16 Nos.

SANLA
SAND (30 Kg
bag)
11.0 cft 0.60 bag
0.03 cum 0.07 bag
11.0 cft 0.60 bag
0.03 cum 0.07 bag
11.0 cft 0.60 bag
0.03 cum 0.07 bag
18 cft 0.60 bag
0.06 cum 0.07 bag
18 cft 0.60 bag
0.06 cum 0.07 bag
18 cft 0.60 bag
0.06 cum 0.07 bag
17.0 cft
0.05 cum
17.0 cft
0.05 cum
17.0 cft
0.05 cum
28.0 cft
0.09 cum
28.0 cft
0.09 cum
28.0 cft
0.09 cum

LIME WHITE
SAND (30 TILES
CEMENT
kg/bag)
16 cft 2.0 bags 150 Nos. 5 kg
0.05 cum 0.2 bags 16 Nos. 0.55 kg
2 cft 125 Nos. 2 kg
0.01 cum 14 Nos. 0.65 kg
16 cft 43 Nos. 2 kg
0.05 cum 5 Nos. 0.221 kg
18 cft 2.0 bags 40 Nos.
0.06 cum 0.2 bags 4 Nos.
16 cft 2.0 bags 150 Nos.
0.05 cum 0.2 bags 16 Nos.
16 cft 2.0 bags required tukda
0.05 cum 0.2 bags required tukda
16 cft
0.05 cum
420 Nos. 2 kg
45 Nos. 0.22 kg

LIME KAVADI WHITE


SAND BRICKBAT
(30 kg/bag) (in kg) CEMENT
30 cft 30 cft
0.09 cum 0.09 cum
30 cft 30 cft
0.09 cum 0.09 cum
45 cft 30 cft 1.20 bags 125 kg 25 kg
0.14 cum 0.09 cum 0.13 bag 13.5 kg 2.07 kg

Y QUICK METHOD ESTIMATION FOR 232 sqm (2500 sft) OF SLAB AREA

APPROXIMAT
E QUANTITY
OF MATERIAL
REQUIRED

50 Nos. Sheets
50 Nos. Sheets
3250 rft

990 rm

600 rft

183 rm

300 Nos.

300 Nos.

400 Nos.

400 Nos.

1000 rft
305 rm
400 Nos.
400 Nos.
50 kg
50 kg
15 litres
15 litres
200 Nos.
200 Nos.
APPROX. QTY.
PER
SR. NO. ITEM

SQ. M. SQ. FT.


9 Flooring
a) MM tile 0.75 sqm 0.75 sft
b) skirting 0.82 rm 0.25 rft
c) W.C. /
0.05 sqm 0.05 sft
Bath
d) Dado 0.20 sqm 0.20 sft
Waterproofi
10 0.30 sqm 0.30 sft
ng
Door
11 0.17 sqm 0.17 sft
Frames
12 Windows 0.14 sqm 0.14 sft