MIVAN SYSTEM FORMWORK

Typical Four Day Construction Cycle

Location Activities Working Day Numbers


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Level 1 Walls Level 2 Walls Level 3 Walls Level 4 Walls
Level 2 Slab Level 3 Slab Level 4 Slab Level 5 Slab

Section 1 Setting Out / Surveys


Wall Steel / M&E
Strike Wall Formwork SWF SWF SWF
Erect wall Form
Strike Deck Form SDF SDF SDF
Erect Deck Form
Deck Steel / M&E
Concrete Wall & Slab
Strip and erect Propping P1 P2 P1 P2
Level 1 Walls Level 2 Walls Level 3 Walls Level 4 Walls
Level 2 Slab Level 3 Slab Level 4 Slab Level 5 Slab
Section 2 Setting Out / Surveys
Wall Steel / M&E
Strike Wall Formwork SWF SWF SWF
Erect wall Form
Strike Deck Form SDF SDF SDF
Erect Deck Form
Deck Steel / M&E
Concrete Wall & Slab
Strip and erect Propping P1 P2 P1 P2
Level 1 Walls Level 2 Walls Level 3 Walls Level 4 Walls
Level 2 Slab Level 3 Slab Level 4 Slab Level 5 Slab
Section 3 Setting Out / Surveys
Wall Steel / M&E
Strike Wall Formwork SWF SWF SWF
Erect wall Form
Strike Deck Form SDF SDF SDF
Erect Deck Form
Deck Steel / M&E
Concrete Wall & Slab
Strip and erect Propping P1 P2 P1 P2
Level 1 Walls Level 2 Walls Level 3 Walls
Level 2 Slab Level 3 Slab Level 4 Slab
Section 4 Setting Out / Surveys
Wall Steel / M&E
Strike Wall Formwork SWF SWF SWF
Erect wall Form
Strike Deck Form SDF SDF
Erect Deck Form
Deck Steel / M&E
Concrete Wall & Slab
Strip and erect Propping P1 P2 P1

Note: Cycle repeats on a daily basis.


Activity Section 1 Section 2 Section 3 Section 4
Each activity has a full day if necessary on each floor. Wall steel ? ton ? ton ? ton ? ton Section 3
Wall Formwork ? sqm ? sqm ? sqm ? sqm
There is minimal interference between activities. Beam, Slab Form? sqm ? sqm ? sqm ? sqm Section 4
Beam, Slab Steel? ton ? ton ? ton ? ton
Two levels of propping will accommodate propping until the sixth day. Concrete ? cum ? cum ? cum ? cum
Section 2

Section 1