Solutions for Assignment- 1

1. Which of these is not one of the constraints of a project?


a. Scope
b. Resources
c. Team
d. Budget

2. Which of the following is not correct about initial phase of a project?


a. The cost associated at the beginning of the project is highest.
b. Stakeholders have maximum influence during this phase
c. The highest uncertainty is at this stage of the project.
d. All the above statements are correct.

3. Effective communication is one of the most important skills required by


a. The project team
b. The management
c. The project Manager
d. The project Contractor

4. Which of the following is not an objective of a project?


a. Scope
b.Schedule
c. Cost
d.Accurate

5. Which of the following is not a basic function of project manager?


a. Controlling
b. Programming
c. Scheduling
d. Directing

6. Project scope defines:

a. A project manager’s visibility to the end date.


b. The magnitude or size of the job.
C. How often a project has been changed.
d. The limits of a project manager’s authority.

7. Which of the following is the definition of a project?


a. A temporary endeavor undertaken to create a unique product, service, or result.
b. An ongoing activity that is a part of daily operations.
c. Neither A nor B
d. Both A and B
8. Which of the following conditions of a project is wrong?
a. A project is finite
b. Usually complex
c. Repetitive
d. It is unique

9. ___________________ is an organizational structure with specific mandated that that


can include an enterprise-wide perspective?

a. Project Management
b. Project Management Office
c. Functional department
d. None of the above

10. Which of the following does not constitute the role of a project manager?
a. Integrator and coordinator
b. Business case approval
c. Project delivery
d. Project planning and controlling