€ CETHAR VESSELS UMITeED
~
TECHNICAL SPECIFICATION FOR REGENERATIVE AIRPREHEATER
(VERTICAL INVERTED)
SPEC. NO. 03: RAPH~ MBI 087
CLIENT : M/S. MEENAKSHI ENERGY PRIVATE LTD.
CONSULTANT : EVONIK ENERGY SERVICES INDIA PRIVATE LTD.
PROJECT i 2X 300 MW THERMAL POWER PLANT
o
as yh fe. 290 Le
‘dle. Page | of 18 v |
0 -burdose en LA fiom, mo€ CETHAR VESSELS LIMITED
CONTENTS
SECTION
DESCRIPTION
|__ No.
[1.0 | Scope of supply
2.0 | Fuel, Fue gas and Ash analysis data
3.0 | Tri sector Regenerative Airpreheater Selection data
4.0 Operational Requirement
5.0 | Specific Requirement
6.0 __ | Guarantees
7.0 | Documentation
8.0 | Painting
9.0 | Packing & Forwarding
40.0__| Inspection & Testing
14.0 | General
12.0 | interfaces & Terminal Points
13.0 [Information to be supplied.
ao)
Page 2 of 18€ CETHAR VESSELS LIMITED
144
14.2
1.2
124
122
1.2.3
124
125
1.26
1.2.7
128
1.29
1.2.10
4.2.11
1.2.12
0) PLY
This specification covers the technical requirement of regenerative
airpreheater_ (RAPH) to recover heat from flue gas and heat the combustion air in
coal based boiler within power plant.
Type: Tri-sector, Rotary regeneration with vertical axis rotation, enclosed
with air/gas tight casing.
No. of RAPH per boiler: Two
Each RAPH to include the following items,
Main rotor assembly.
Main drive motor shall be an electric motor and gear reducer assembly. The
motor shall be suitable for Low voltage (10%) power source specified elsewhere.
Rotor housing assembly including hot end and cold end centre section
assembly.
Pin Rack assembly.
Hot end heating elements.
Hot intermediate heating elements.
Cold end heat elements:
Seal assembly (Radial seals, Axial seals and Rotor post seal etc.)
‘An auxiliary air motor drive complete with over running clutch and
electromagnetic valve, lubricator and fiter.
Bearings
Hot end bearing oil circulation system with water cooler and stand by.(with
two pumps)
Cold end bearing oil circulation system with water cooler and stand by.(with
‘two pumps)
‘Two stationary water washing device.
Water washing device for deluge.
One soot blower is required (cold end arrangement only)
‘Two observation ports ~ one each hot and cold ends.
One vapor-proof inspection light assembly at cold end.
Page 3 of 18 ]