Escolar Documentos
Profissional Documentos
Cultura Documentos
Undertake Project
Work
Learning
Guide
Northern Sydney Institute
Northern Beaches
Learning Guide
Table of Contents
Project scope
One of the most difficult aspects of project management is defining the scope of a project. The
word ‘scope’ means extent or depth. When applied to project management, it refers to how much
work there is to do.
The scope is all work needed to fulfil the project goals. It includes all the resources and processes
used to do this.
The project scope must provide a clear and refined description of:
the project goal
what is to be achieved
how is it to be achieved
who will achieve it
when it will be achieved
with what resources it will be achieved.
Once these have been determined, they are written down in a scope document.
A scope document shows the scope, or extent, of a project. Let’s look at the key sections and an
example of a project scope document.
Section Details
Scope statement This clearly states the project goal, objectives and deliverables. If it is not
specified in the scope statement then it is outside the scope of the
project and is not relevant. Project tasks should only address work that is
relevant to the project goal and objectives.
Project constraints These are any limiting factors that prevent the project from moving in a
particular path. Examples include:
You have dependent tasks that impact on specific areas of the
project, for example, tasks that cannot begin unless another one has
The following is an example of a scope document, in this case for a project to install animal litter
bins in local parks.
This scope has been approved by: Bob Smith_____________________ Project Sponsor
Project sponsor
A good scope document will clearly define the project sponsor. The project sponsor is a key
stakeholder for the project. The sponsor is the person or organisation that has taken the idea for a
project and developed it into a structure, or who has identified the idea for the project and
initiated its further development.
The sponsor may be the manager, client, department or work team that has initiated the project.
The sponsor usually provides the resources and approvals for the project, and has the final say on
project deliverables, costs, schedules and risk.
Project stakeholders
Stakeholders are the individuals or organisations that are involved in, or may be affected by, the
project. These might include the project sponsor (company management, department head, client
etc), staff, contractors, suppliers, project team, external clients, government agencies and the
public. This group will vary greatly from one project to another.
There are always a number of stakeholders involved in workplace projects. For example,
stakeholders could include members of the following groups:
employees, contractors
unions and labour hire companies
managers
customers
Bsbpmg522 Learning Guide V1
Page 9 of 82 Revision Date: 11/04/2013
Learning Guide
suppliers.
Stakeholder Details
Sponsor The person or business unit that initiated the project and provides
funding for the project.
Project Team The project manager and team members who carry out all of the
tasks required to complete the project on time and within budget.
Senior Senior management obviously have an interest in projects
management undertaken by their organisation, and their approval will be
required.
Functional They become involved when they are directly affected by the project
Managers or offer their staff to take part in the project.
Shareholders As they usually provide the funding they have a vested interest in
the success of the project.
Project resources
Resource planning is a critical part of project cost management. To estimate budget and control
costs, project managers and their teams must determine what physical resources (people, money,
time, equipment and facilities) and in what quantity they are required to complete the project.
Expert judgement and the availability of alternatives are the only real tools available to assist in
resource planning, but to help with this process ask yourself some questions.
Will it be difficult to accomplish specific tasks in the project?
Is there anything unique about the project that might cause problems in the future?
Has your organisation done anything similar before? Who did the work?
Does your organisation have staff, equipment and resources that are capable of doing the
job?
Do you need to outsource some of the work?
Does your organisation have any policies that might affect obtaining resources?
If the resources are not available within the organisation or easily obtainable from outside, then it
may not be a good idea to pursue the project any further.
Topic 1 Activities
Questions
1. Who are the stakeholders for your project?
Answer:
Answer:
3. What are your responsibilities and level of authority as a member of your project team?
Answer:
Answer:
Answer:
Answer:
7. Does your organisation have the resources required to complete your project? If they are not
available from within your organisation, how can they be obtained from outside the
organisation?
Answer:
Question 1
Your list should include all those who are involved or affected by your project, including sponsors,
management, staff, contractors, suppliers, clients, etc. Think about the extent of your project so
you can identify all stakeholders.
Question 2
Think of the individual ways in which your project may affect these stakeholders and what
concerns they may raise. Consider issues such as:
Will client orders be delayed?
Will staff have to work additional hours?
Activity 3: Quiz
Use this quiz to check your knowledge of the project definition stage.
Question 1:
1. project mangers
2. project stakeholders
3. project steering committee
4. organisational employees
Question 3:
Which of the following characteristics are important for project managers to have? Select all
correct answers.
1. good communicator
2. strong negotiator
3. authoritative
4. able to set goals
5. works staff hard
Question 4:
A scoping document outlines the extent or depth of the project. True or false?
1. True
2. False
Question 5:
Question 6:
1. True
2. False
Question 7:
Why is it important to allocate project team responsibilities? Select all correct answers.
Question 8:
Which of the following are common project reporting techniques? Select all correct answers.
Question 9:
Projects should be designed to stand alone from other projects. True or false?
1. True
2. False
Question 10:
1. technical objectives
2. organisational objectives
3. staff development
4. business processes
Project objectives
To successfully complete a project, several major steps need to take place. These steps usually
represent the major parts of the project. These are the project objectives, sometimes called
milestones.
As the project manager you will work with stakeholders to identify the key project objectives for
the project goal.
Objectives are not actual work but are sub-goals that are used to focus work activities during the
life of the project. Objectives have outputs that are clearly defined in terms of results, goods, or
services produced during the project or at its completion.
These outputs are sometimes referred to as deliverables and may include reports, plans, products,
or even organisational changes.
It is extremely important to be precise about the project objectives because they are the
foundation from which the project plan is developed.
Project objectives can influence:
the selection of the project team
task definition
task schedule
resource allocation
budget.
Objectives are also compared against outcomes at the end of the project and continuously during
the life of the project, to make sure that expectations have been met and that the project is
moving in the right direction.
Tasks
Once you have defined project goals and objectives you can begin to focus on the actual work
required to complete the project. This work is divided into tasks.
Tasks must be:
clearly defined
Defining tasks
Task definition involves identifying all of the specific tasks and task activities for the project. A task
is an element of work that is contained in the work breakdown structure found in the scope
document.
Each task has:
an expected duration
an estimated cost
resource requirements.
Task definition usually results in a very detailed work breakdown structure from which the project
team has a complete understanding of the work that is required to achieve the project
deliverables.
Tasks must first be determined. Some guidelines for determining tasks are as follows:
Identify tasks as precisely as possible. Each task should be short compared to the overall
project duration. For example, if you plan to put up a frame house, you may want to break
up the “put up the frame” process into three or more tasks, one for each part of the house
(outer walls, inner walls, roof etc). This helps you make a more reliable estimate of the
time and resources required to complete a task.
Tasks must be significant enough to include in the project plan. Insignificant or
unscheduled tasks only clutter your project task list. For example, in the “pour the
concrete” task mixing the concrete may be important, but it may not be significant enough
to include as a separate step if it doesn’t affect how the task is scheduled.
The level of detail in your list of tasks should be appropriate for the amount of planning
and control you want. For example, if you are hiring outside consultants to do a study, you
are interested in when the consultant starts the study and when the study will be
completed but you are not interested in the detailed tasks performed by the consultants.
In your list of tasks, you would include one task for the study, showing the duration for the
whole, rather than many tasks indicating each step of the study. However, if you are doing
the study yourself, the separate steps would need to be included in your task list.
When you list your tasks, you must be aware of the scope of the tasks and the assumptions
on which the tasks are based. This helps you identify changes and measure progress.
Be comprehensive. Remember to include reports, reviews and coordination activities in
your list of tasks and remember to include tasks for anticipated rework or modifications
after a task has been completed, such as revising a manual or reworking and retesting a
new product.
Name a task using a verb and a noun, such as “pour the concrete”, “build the outer wall
frame” and “tile the roof”. Make the names as explicit as possible and keep the style of the
Task sequencing
At this point in the planning phase, our project is a list of tasks, what must be done in order to
complete it, deliverables, and milestones to measure its progress.
Now it’s time to work out the sequence in which the tasks can be done to achieve these
milestones and deliverables.
Obviously we could just put them in a logical order like a 'to do' list and then do them one after
the other. This is fine for small, simple projects but for a complex project with many tasks this has
the potential to be a long and inefficient path to completion.
Many activities in a project can be done simultaneously to increase efficiency, while other tasks
will be done sequentially because they are dependent on earlier tasks.
An example of a WBS chart for installation of animal litter bins and bag dispensers in all council
parks
Gantt charts
Gantt charts are the most common means for displaying project schedule information. Gantt
charts use a list of tasks or activities required to complete the project. The timing for each task is
represented as a series of horizontal lines or bars under a calendar scale.
Here is an example Gantt chart. Notice that task timings can overlap, be broken up or have gaps
between tasks.
1 day 6 days
Task A Task C Task G
3 days 2 days
6 days Task F
Task D
PERT analysis
PERT analysis is a technique that is used when there is a high degree of uncertainty about the
individual activity duration estimates. PERT calculates the critical path method but uses
statistically weighted average duration estimates.
PERT uses probabilistic estimates, which are activity duration estimates based on three criteria:
optimistic duration
most likely duration
pessimistic duration.
The three estimates are then statistically averaged using a formula called the weighted average
formula. Deriving this formula is outside the scope of this topic but an example is provided below.
Risk management
Risk management is a major issue in project management. Your project plan should include a risk
management plan.
A risk is something that may happen and if it does, it will have a negative impact on the project. A
risk must also have a probability of occurring that is something above 0% and less than 100%. If
there is no chance of it happening, then it is not a risk. If it has a 100% chance of occurring it is a
certainty rather than a risk and must be factored into the project planning.
Risk identification
In this stage, we identify and name the risks. The best way to do this is to run a workshop with the
project team. Use a combination of brainstorming specific project risks and reviewing standard
risk lists. There are different sorts of risks for each project and you need to decide on a project-by-
project basis what to do about each type of risk.
Business risks are ongoing risks that are best handled by the business. Consider Happy Pizza P/L. If
the project to install a new accounting system cannot meet the end of financial year deadline, the
business area may need to keep their existing accounting system for another year. Happy Pizza P/L
can respond by developing a contingency plan to use the existing system for another year.
Generic risks are risks to all projects, for example the risk that suppliers might not meet project
deadlines. Each organisation will develop standard responses to generic risks.
Risks should be defined in two parts:
the cause of the risk (such as suppliers not meeting deadlines, staff absences, contractors
not available, etc)
the impact of the risk occurring (such as exceeding the budget, milestones not achieved,
etc).
Risk quantification
Risks need to be quantified in two dimensions. You need to assess the probability of the risk
occurring as well as the likely impact on the project if the risk does occur. For simplicity, rate each
on a 1 to 4 scale using a matrix similar to the one below—the larger the number, the larger the
impact or probability.
Note that if probability is high and impact is low then this is a medium risk, whereas if the impact
of a risk is high and probability is low it is high risk. A remote chance of a project-destroying risk
warrants more attention than a high chance of a small problem.
Risk response
There are four things you can do about a risk:
1. Avoid the risk. Do something to remove it, for example, use another supplier if the current
supplier cannot deliver on time.
2. Transfer the risk. Make someone else responsible. Perhaps a vendor can be made
responsible for a particularly risky part of the project, or insurance can be obtained to
provide cover in the event of the risk occurring.
3. Mitigate the risk. Take action to lessen the impact or chance of the risk occurring. If the
risk relates to availability of resources, identify alternative suppliers and draw up
agreements to allow suppliers to be changed if deadlines are not met.
4. Accept the risk. The risk might be so small that the effort to do anything about it is not
worthwhile.
A risk response plan should include the strategy and action items to address each risk. The actions
should include what needs to be done, who is going to do it, and when it should be completed.
Below is a sample risk response plan.
Sample risk response plan for installation of animal litter bins and bag dispensers in council parks
Cost management
Cost management is and important area of project management especially in profit-focused
corporate contexts. Companies are always conscious of budget overruns and cost restrictions in
today’s competitive markets.
Project cost management includes all the processes required to make sure the project is
completed within the approved budget.
As the project manager, it is crucial for you to make sure that the scope document is as accurate
as possible, so that the approved budget is based on estimates that are as realistic as possible.
An accurate scope document also helps to make sure that the only work that is done on the
project is work that is defined in the scope. Remember—it is your job as the project manager to
constantly satisfy the needs of the stakeholders while keeping costs down and under control.
Project cost management processes include:
resource planning
estimating costs
estimated costs and budget.
Resource planning
To estimate, budget and control the costs of a project, you, as the project manager, must
determine what resources are required and in what quantities, to complete all the project tasks.
This includes people, equipment, facilities and materials.
When you have determined this, you will have a detailed list of resource requirements. To make
sure that resource estimates are as accurate as possible, draw upon the skills of people with
experience and expertise in similar projects.
Estimating cost
Costing a project is not an easy task. All projects are different and you may not have a previous
example to assist you in costing the current project. You can refer to audit reports and budgets
from previous projects, but these may only provide ideas, rather than real costs.
One of the key inputs to the costing process is the detailed WBS that you developed at the start of
the planning phase.
With very large projects this estimation process is usually undertaken in three stages.
Contingency allowances
When all task costs have been totalled and you have a final cost for the project, don’t forget to
add in a contingency allowance. In project management terms this is ‘padding’ to allow for errors
in estimating or unexpected cost occurrences.
Sample budget for installation of animal litter bins and bag dispensers in council parks
For medium to large projects, the project plan is definitely the key document in the project. If you
have a project like this you should consolidate all of your planning documents created so far into
one project plan document.
For smaller projects with established work teams, you may be able to use just the scope
document, along with budget, work schedules and the risk management plan as your total project
planning tools.
Answer:
2. What are the costs that relate to your project and how can you budget for them?
Answer:
3. Identify the risks associated with your project and fill out a plan.
Answer:
Question 1
The materials including the tiles to do the work will not be able to be delivered until 8am
Wednesday 19th March.
Easter is from Friday 21st – Monday 24th March inclusive.
Gary and Tim are paid $50 per hour each with double time after the first 8 hours and
double time on weekends and public holidays.
ACME want to maximize the profit from the renovation.
Mr and Mrs Smith want minimum inconvenience to their bathroom. Currently their
bathroom is not usable as the old tiles have been removed and their bathroom is not
waterproof.
Activity:
1) Produce a time line showing each day the work will be undertaken along with the resources,
cost and total cost. E.g.:
Total Cost =
$5000
________________________________________________________________________________
________________________________________________________________________________
__________________________________________________________________________
b) Risk:
________________________________________________________________________________
________________________________________________________________________________
__________________________________________________________________________
c) Costs:
________________________________________________________________________________
________________________________________________________________________________
__________________________________________________________________________
d) Procurement:
________________________________________________________________________________
________________________________________________________________________________
__________________________________________________________________________
Activity 3: Budgeting
You work for a global manufacturer of consumer electronics. There is an international tradeshow
in Brisbane to which seven of your sales team will be attending. This team comes from offices all
over the world.
Before attending the Brisbane tradeshow the sales team will be stopping off in Sydney to attend a
one day, new product training session.
You have been given the task of budgeting this project. The international offices are covering the
cost of flights to Sydney. However you must research the estimated costs for the following:
Activity 3: Quiz
Use this quiz to check your knowledge of the project planning stage.
Question 1:
Question 2:
Question 3:
Question 4:
1. resource list
2. Gantt chart
3. work break down structure
4. quality audit
Question 5:
Question 6:
Question 7:
Projects should be broken down into the following units from largest to smallest
A defined task should contain which of the following. Select all correct answers.
1. duration
2. cost
3. resources
4. staffing
Question 9:
Task duration is the number of hours required to complete the task. True or false.
1. True
2. False
Question 10:
A risk that is highly probable but will have a low impact represents what level of overall risk?
1. low
2. medium
3. high
4. critical
Recruiting personnel
As the project manager, you may not be solely responsible for determining who will be part of the
project team. Your organisation may have particular recruitment processes and human resources
staff that can assist you in finding the right people for the project. During the recruiting process
you must:
determine the skills required for each activity by developing a skills requirement list
determine where the people will come from—existing internal or new external staff or
contractors
select the right team members, either internally or externally
assign activities to each team member
establish an appropriate staff hierarchy and chain of responsibility for the project.
As you work through the skills requirements list, you list each activity required and then the skills
needed to complete that activity. You may need more than one person to provide the skills
Bsbpmg522 Learning Guide V1
Page 45 of 82 Revision Date: 11/04/2013
Learning Guide
required. In fact in many cases the skills might need to be provided by teams made up of a number
of people with the same skills, for example, a team of architects.
Date Date
Team member name Skills
entered departed
project management skills
George Williams 12/3 9/12
construction supervisor
Building quantity surveyor and
Beth Carillios 15/4 -
estimator
Construction foreman and
Alan Peters WorkCover OHS accredited 20/4 17/12
trainer
Employing external project staff in either permanent positions or as contractors is all part of the
process. Hiring or contracting staff is necessary when appropriate internal staff are not available.
Team leadership
There are many textbooks on the subject of team leadership and leaders. It is beyond the scope of
this topic to teach these skills, but it is important that you recognise the skill areas that you must
develop to succeed as a project manager. You can successfully do all of the management parts of
the project: planning, reporting, analysing and organising, but if you fail as a leader, then your
project is also in danger of failing.
Here are some useful tips.
As the team leader you can arrange discussions around the needs of the organisation for
innovative ideas.
You can introduce team members to techniques such as brainstorming that can help the
innovation process.
You can support team members when setbacks happen. If the team puts a proposal to
senior management and it is rejected, that can demoralise team members. Your role as a
team leader is to work with your team to find out why an idea was rejected, and discuss
what they will do in the future. Teams need feedback so that they can improve their skills.
Studies have found that successful project managers have several common characteristics that
make them successful. Successful project managers:
are leaders by example
are technically competent
are decisive
are good communicators
are team players
Leadership styles
There is a wide range of leadership styles that are effective across many situations, but we will
consider three basic styles that you can use to manage your projects:
People-oriented leaders develop rapport with team members and generate an open,
positive environment for the team.
Task-oriented leaders focus on getting the tasks decided on, organised and assigned, as
well as evaluating performance.
Reward-oriented leaders use meaningful rewards that correlate to the level of results and
the person's efforts. These rewards can range from money to simple support and
acknowledgment for work well done.
A successful project manager has the ability to vary the leadership style to suit to individuals and
teams.
Managing a project is an ongoing cycle involving monitoring, controlling and directing work
Change control
Change control gives control over the scope of the project. The three main focuses of change
control throughout the life cycle of the project are:
identifying that a change is necessary and making sure that the change is beneficial
determining that a change has taken place
managing the actual changes as they occur.
Change control is also called change management, and in a project it can use a formal
documented process called a change control system. The aim of change management is to:
maintain the integrity of the performance measurement baselines (all changes must be
reflected on the scope and time line)
ensure that changes required to the project scope are reflected in the scope definition.
A project change request form can be used for all requests for a change in the project. Such
requests might be submitted to the project manager for consideration and processing. The form
should include:
a request number (for tracking)
the name and contact details of the person making the request
Quality control
Quality control an important sub-part of the overall control mechanisms for a project. Quality
control is the means of consistently meeting the negotiated expectations of stakeholders in a
project. It is something that every organisation strives to achieve to give it a competitive edge in
industry. Quality objectives are often expressed in a policy document that reflects the standards
the organisation wishes to achieve and the responsibilities associated in meeting those objectives.
Project management needs to follow organisational policy in this regard.
Quality management is perhaps the most difficult area of expertise in project management to
define. It helps to remember that the customer ultimately decides if quality is acceptable, the
basis for quality exists in the original intentions of the project and that quality control a continuous
process of evaluation and improvement.
Project quality management has three main processes.
Quality planning includes identifying which quality standards are required and how to
measure and satisfy them.
Quality assurance involves the regular evaluation of overall project performance against
the quality standards.
Quality control involves monitoring specific project deliverables to ensure that they meet
the relevant standards and identifying ways to improve overall quality.
Quality assurance
For large projects, a quality assurance group may be formed, and for smaller projects quality
assurance may fall to one person. Quality assurance includes all of the activities related to
satisfying the relevant and agreed quality standards that have been set for the project. Another
goal of quality assurance is continual quality improvement.
Quality assurance is usually determined by ISO 9000 standards, which are a series of international
guidelines on quality management. If a company has ISO 9000 accreditation then these guidelines
are part of normal business.
Quality audits
Quality audits are a review of specific quality management activities and are one of the tools of
quality assurance. Project plans and design specifications are reviewed to ensure that all the steps
of the development process are being carried out correctly. As project activities are completed
they are usually formally documented. This documentation can become one measure of quality.
When you apply this process to project management, it’s important to remember:
track progress of the project to identify problems early
respond quickly to problems once they occur
identify the cause of the problem, not the symptoms that highlighted it
find the best solution to solve the problem quickly and efficiently, and involve relevant
team members
compromise if necessary to get back on track
consult stakeholders and gain their approval when required.
Small projects
Small projects usually do not need more than basic project reporting. If, as the project manager
you are doing hands-on work on the project, you probably have a very good idea of the overall
status. However, if you are not working on the project, you may need a formal status reporting
process. The following process would be typical:
Project team members send a status update to the project manager on a weekly basis. This
report covers common issues such as performance against timelines, likely need to change
schedule, tasks and budgets. If suppliers or contractors are working off-site then you may
request they provide project reports against their delivery schedules and budgets.
The project manager sends a status update to the project sponsor and stakeholders on a
bi-weekly or monthly basis. However, be careful about monthly reporting. If the project is
very small, the client may get no updates before the project is completed. This does not
give them an opportunity to respond if they see anything unusual. The project manager
should report the project status bi-weekly or weekly in these cases.
The entire project team should attend project status meetings. The meetings should focus
on the project status against the project work plan and try to uncover any current issues,
as well as scope change requests or potential risks. The client should be invited to attend,
but their attendance is not compulsory. The frequency of the meetings depends on the
timetable for the project and the need to get information in a timely manner. For instance,
if the project runs for three weeks, the team might want to meet twice a week. If the
project runs for eight weeks, weekly meetings are probably appropriate.
Larger projects
For larger projects the communication should include formal status meetings and project reports.
The team should attend project meetings on a weekly or bi-weekly basis. The client should
be represented at the project meeting. If the project manager prefers, there could be
project meetings for the project team and a separate meeting with the client. There should
be a standard agenda for the meetings and each meeting should be no longer than one
hour. In general, the purpose of these meetings is to communicate status, not solve
problems.
The project manager should send project reports to all stakeholders on a bi-weekly or
monthly basis. Depending on the financial reporting cycle, the monthly project report
should include a financial status.
Information to include
There are generally three types of information that may need to be included in project reports and
other forms of project communications.
Mandatory—this generally includes project status reports, legal requirements, financial
reporting, etc. This information is sent out to the required recipients such as key project
team members, sponsors/clients and management staff.
Informational—this is information people want to know or that they may need to know to
do their job. This information is usually made available for people to read, and may be sent
to all or to selected project team members, suppliers, contractors, sponsors or clients.
Project marketing—this may include project marketing communication, which is designed
to motivate and generate enthusiasm among staff to support the project and its
deliverables. This type of information is particularly important when you want to promote
a project that aims to implement a change in organisational culture or work habits.
Introduction
Research the answers to these questions in your own workplace or a workplace you are familiar
with. You can check your answers against the guidelines below, but naturally your answers will
vary depending on your workplace.
Questions
Answer:
2. What team development will you use with your project team?
Answer:
3. Have you worked in teams before? What made that experience successful or unsuccessful?
How much of that was due to the management of the team by the project manager or team
leader?
Answer:
4. What control mechanisms would you put in place for your project?
Answer:
5. Identify the kind of information that will be useful in your project reports.
Answer:
Research and create a mini-guide to effective project management. Focus on the skills and
personal attributes necessary for project success and developing good relationships with the
project team.
You work as a section manager for a large retail chain in their head office. The regional manager
has asked you to take on a project organising a series of promotional videos for five new
products. You have two months to launch the videos on the company website. Who should you
get involved? What tasks need to be performed? Who performs the tasks. How will you
documents if and when tasks are done? How will you know if the project is completed on time?
Planned start/finish
dates
Actual start/finish
dates
Remaining duration
For the following situations which traffic light would you use?
Activity 7: Quiz
Use this quiz to check your knowledge of administer and monitor project stage.
Question 1:
Question 2:
Question 3:
Question 4:
Question 5:
1. organising
2. communicating
3. leading
4. all of the above
Question 6:
The most important resource are the people in your project team. Without the right project team,
other materials and facilities are useless. True or false?
1. True
2. False
Question 7:
One of the goals of quality assurance is continual quality improvement. True or false?
1. True
2. False
Instructions
This activity asks you to focus on the key tasks that need to be undertaken when implementing a
project. Place them in order.
Complete the project accounts and hand over the project files
Financial accounts
At the end of the project there may be a large number of accounting functions that need to be
finalised. These might include:
Topic 4 Activities
Questions
1. What steps do you need to follow to close a project in your workplace?
Answer:
2. How will you go about identifying why cost differences occurred in your project?
Answer:
Answer:
4. What resources are left over from your project and what will you do with them?
5. How will you motivate your team to return to their normal duties?
Answer:
Answer:
Activity 2: Quiz
Use this quiz to check your knowledge of the project finalisation stage.
Repeat this quiz until you have answered all questions correctly.
Question 1:
Question 2:
At the close of a project the project deliverables and actual deliverables should be compared. True
or false?
1. True
2. False
Question 3:
All unused equipment from a project should be sold to fund further projects. True or false?
1. True
2. False
Question 4:
Question 5:
Unpaid contractor fees should be rolled over into the next project contract. True or false?
1. True
2. False
Question 6:
What should be done with staff on the project team when the project is completed? (Select all
correct answers.)
Question 7:
Which of the following items should be included in the projects closing report? (Select all correct
answers.)
Question 8:
You should obtain client/stakeholder signoff on which of the following documents? (Select all
correct answers.)
1. financial records
2. project team communications
3. service level agreements
4. client/stakeholder feedback
Topic 5 Activities
Answer:
Answer:
Answer:
Use this quiz to check your knowledge of the review project stage.
Repeat this quiz until you have answered all questions correctly.
Activity 2: Quiz
Question 1:
Which of the following methods would be the best way to collect feedback at the end of a project?
Question 2:
Question 3:
Question 4:
What is the main reason processes are reviewed at the end of a project?
Question 5:
Question 6:
1. all project goals were achieved and the project budget was exceeded by 10%
2. half of the project goals were achieved and the project expenditure was 35% under budget
3. the project team is happy with the result, the project expenditure is 20% under budget and
70% of the project goals were achieved
4. 90% of the project goals were achieved and the project expenditure was 30% over budget
Question 7:
It is important to decide up-front what criteria you will use to determine whether a project is a
success or a failure. True or false?
1. True
2. False
Question 8:
Why should the performance of project team members be evaluated? (Select all correct answers.)
When evaluating the project team’s performance both the individual and team should be
evaluated? True or false?
1. True
2. False
Question 10:
How can the project review process become a part of risk management? (Select all correct
answers.)
1. a more accurate budget history can be created to help future project improve their budget
estimations to prevent over-expenditure
2. the suitability of staff in various project roles can be better determined for use in future
projects
3. the project planning phase can be reused in future projects
4. future projects can use the lessons learnt from a completed project to help protect against
problems being repeated
References
Department of Education and Training 2008 Learning Guide from the BSBPGM510A Toolbox on
Equella.
H. Kerzner and F Saladis, “Project Management Workbook”, 2006.
Project Management Institute, “The Project Management Body of Knowledge”, 5th edition, 2013.