CHHATTISGARH STATE ROAD SECTOR DEVELOPMENT PROJECT ( PHASE 2)

REHABILITATION AND UPGRADING OF NAGARI TO DHAMTARI PACKAGE - 10

BOQ( Km.34+000 to 44+000)


S.N. Description Unit Qty Rate Amount
1.01 Clearing, Grubbing including rank vegitation grass bushes,
shrubs, spelling of trees of girth upto 300 mm, removal of
strumps, disposal of unserviceable material and stacking of
serviceable materials upto 1000 m from road boundary as
per clause 201.

a In a Hectare 12.00 9743.68 116924.16


1.02 Cutting and uprooting of trees to the required depths below
gound level including stacking of serviceable material within
a lead of 1000 m and the earth filling in the depression/pit
as per clause 201.

a Above 300 mm upto 600 mm Each 125.00 53.68 6710.00


b Above 600 mm upto 900 mm Each 85.00 113.68 9662.80
c Above 900 mm upto 1800 mm Each 1.00 198.95 198.95
d Above 1800 mm Each NIL 356.85 -
1.03

Dismantling of existing structures like culverts, bridges,


retaining walls and other structure comprising of
masonry,cement concrete,wood work,steel work, including
T&P and scaffolding wherever necessary, sorting the
I dismantled material disposal of unser Cum NIL - -
ii Dismantlinmg Brick / Tile work in lime mortar. Cum NIL - -
iii Rubble Stone masonry in cement mortar Cum NIL - -
iv Lime Concrete, cement concrete grade M-10 and below Cum NIL - -
v Cement Concrete Grade M-15 & M-20 Cum NIL - -
vi Dismantling stone mpitching / dry stone spalls Cum NIL - -
vii Dismantling of 5the Kilometre stone Each NIL - -
viii Kilometer stone Each 9.00 63.16 568.44
ix Hectometer stone Each 45.00 31.58 1421.10
Removing all types of Hume Pipes and stacking within a
lead of 1000 metres including earthwork and dismantling of
x masonry works.
a Upto 600 mm dia. Metre -
b Above 600 mm upto 900 mm dia Metre -
c Above 900 mm dia. Metre -

CONTRACTOR REPRESENTATIVE
T.C.I.L.
CHHATTISGARH STATE ROAD SECTOR DEVELOPMENT PROJECT ( PHASE 2)
REHABILITATION AND UPGRADING OF NAGARI TO DHAMTARI PACKAGE - 10

BOQ( Km.34+000 to 44+000)


S.N. Description Unit Qty Rate Amount
1.04
Dismantling /scrifying of flexible pavements and disposal of
dismantled materials upto a lead of 1000 metres stacking
serviceable and unserviceable materails seperately.

a Bituminous Surface Sqm 5000.00 5.05 25250.00


b Granular Surface Sqm 5000.00 5.05 25250.00
1.05
Making 50 mm x 50 mm furrows, 25mm /50mm deep, 450
to the center line of the road and at one metre interval in the
existing thin bituminous wearing coarse including sweeping
and disposal of excavated material within 1000 metres lead

a 25mm deep furrow cutt Sqm 26000.00 0.63 16380.00


b 50 mm deep furrow cutting Sqm 1200.00 0.63 756.00
2.01 Excavation of emankment, sub-grade and drain consisting
of excavation, removal and satisfactory disposal of all
excavated materials including handling and stacking of or
hauling to sides of embankment and sub grade
construction, spoil banks or stacking of suitable cut
materials as required, as also the disposal of unsuitable
materials in specified manner and the trimming and
finishing of the road to the specified dimensions or as
directed by the Engineer-in Charge including all lifts, lead
upto 1000 metres and dewatering complete as per clause
301,(excluding preparation of cut formation vide clause
301.6) and excluding dressing the bed and sides, of the
drains vide clause 309.4

a Ordinary / Hard Soil Cum 26000.00 56.84 1477840.00


b Ordinary rock (not requiring blasting) Cum 10.00 69.47 694.70
c Hard rock (requiring blasting) Cum 6.00 189.47 1136.82
2.02 Constrtuction of embankment as per specification with
approved material from borrow area I/c cleaning and
grubbing of borrow area I/c excavation with an average lead
of 1000 metres with all lifts laying in layers I/c dressing
watering and compaction to the desired density and
maintenance of surface during construction to ensure
shedding and prevent pounding of water shaping, dressing ,
and finishing complete in all respect but excluding scarifying
existing granular / bituminous road surface vide clause
305.6 Cum 30000.00 69.47 2084100.00

CONTRACTOR REPRESENTATIVE
T.C.I.L.
CHHATTISGARH STATE ROAD SECTOR DEVELOPMENT PROJECT ( PHASE 2)
REHABILITATION AND UPGRADING OF NAGARI TO DHAMTARI PACKAGE - 10

BOQ( Km.34+000 to 44+000)


S.N. Description Unit Qty Rate Amount
2.03
Laying spreading soil for construction of embankment , sub
grade, earthern shoulder inclusive of all operation
necessary as per specification with approved material
obtained from the excavation of a road construction, drains,
widening of road, with in a lead of 1000m (excluding the
cost of excavation)etc. I/c consoldating the original ground
by rolling as directed by the Engineer-in-charge but with a
minimum 6 passes of 8-10 tonne roller, I/c watering and
compaction upto desired density and preventing ponding of
water finishing etc. I/c all lifts exclusing scarifying existing
granular/bituminous road surface cide clause 305.6 Cum 10000.00 25.27 252700.00
2.04
Construction of subgrade as per clause 305 & its sub
clauses where required, but with approved materials having
minimum four day soaked CBR not less than 7% all leads
and lifts I.e. excavation, cost of watering compaction (clause
305.3.6) and maintenance of surface during construction to
ensure shedding and preventing ponding of water (clause
305.3.7) shaping and dressing, finishing (clause 305.3.9)
etc. complete but excluding scarifying existing granular
/bituminous road surface vide clause 305.6 Cum 56500.00 126.32 7137080.00
2.05 Preparation of sub-grade in cut formation as per clause
301.6 involving loosening and compaction in layers in
accordance with clause 305 I/c consolidating the surface
below loosened layer of 500 mm, with a maximum of 6
passes of 8 to 10 tonnes roller but not requiring removal of
unsuitable materials and replacement oin accorance with
clause 305 Cum 3500.00 69.47 243145.00
Total 11399817.97