Você está na página 1de 6

ZL SWITCHGEAR SDN BHD

NO.2, JALAN ONE INDUSTRIAL PARK 1, ONE INDUSTRIAL PARK, 43300 SERI KEMBANGAN, SELANGOR.

FACTORY ACCEPTANCE TEST PROCEDURES

FACTORY ACCEPTANCE TESTING PROCEDURES

1. Visual Inspection

1.1 General arrangements of components’ layout.


1.2 Brands/ models of components.
1.3 Dimensions of switchboards.
1.4 Feeder’s termination (top or bottom / cable or busduct).
1.5 BAS termination compartment, if any.

2. Mechanical Operation

2.1 Air circuit breakers.


2.2 Moulded case circuit breakers.
2.3 Mechanical interlocking for feeders and coupling system.
2.4 Mechanical interlocking for transfer switches (auto / manual)

3. Electrical Tests

3.1 Insulation Resistance Test.


To verify that the insulation level for all busbars of the switchboard is able to withstand 1000V DC
insulation resistance value shall not be less than 10 megaohms.

3.2 Dielectric test and insulation test.


To verify that the insulation level for all busbars of the switchboard is able to withstand a test

voltages of 2.5KV AC for withstand time of 1 minute. Acceptable leakage value not more than 100mA
3.3 Primary current injection tests to verify CTs’ polarity & ratio, spill current and all Overcurrent /
Earth Fault Relay setting.

4. Factory Inspection Feedback and Comment Form

To rectify comments made during inspection and rectification works before delivery.

Printed Date : 26/02/2019 Page 1 of 6


ZL SWITCHGEAR SDN BHD
NO.2, JALAN ONE INDUSTRIAL PARK 1, ONE INDUSTRIAL PARK, 43300 SERI KEMBANGAN, SELANGOR.

ZL/QC/FO.02

ATTENDANCE FOR FACTORY ACCEPTANCE TEST

Job Ref. No :
Date :
Job Title :

1. Project Owner
Company :

a. Name :
Designation : Signature :

b. Name :
Designation : Signature :

2. Consultant
Company :

a. Name :
Designation : Signature :

b. Name :
Designation : Signature :

3. Main Contractor
Company :

a. Name :
Designation : Signature :

b. Name :
Designation : Signature :

4. Sub Contractor
Company :

a. Name :
Designation : Signature :

b. Name :
Designation : Signature :

5. ZL SWITCHGEAR SDN BHD


a. Name :
Designation : Signature :

b. Name :
Designation : Signature :

Printed Date : 26/02/2019 Page 2 of 6


ZL SWITCHGEAR SDN BHD
NO.2, JALAN ONE INDUSTRIAL PARK 1, ONE INDUSTRIAL PARK, 43300 SERI KEMBANGAN, SELANGOR.

Doc No. ZL/FO/QC.03


INSPECTION RESULT
LV PANEL Rev No. 0
Rev. Date N/A
Client Drawing No
Project Name Panel Description
Q. Ref Panel Serial No.

IN-HOUSE FAT

Inspection Results
Clause Description
(Pass / Fail)
1 Visual Inspection Prior to Covering
1.1 Panel Construction
1.2 Components layout corresponds with drawing
1.3 Wiring Layout corresponds with drawing
1.4 Marking Inside Panel
1.5 Earth Bonding to Compartment Panel
1.6 Protection
1.7 Cleanliness

2 Visual Inspection After Covering


2.1 Correct Covering
2.2 No Scratches / Dented
2.3 Degree of Protection
2.4 Name Plate / Signs
2.5 Cleanliness

3 Mechanical Inspection
3.1 Hand Operated Apparatus
3.2 Mechanical Interlocks
3.3 Fuses Supplied with panel
3.4 Creepage Distance /Clearances
3.5 Wiring to door - using Star Washer
3.6 Protective Conductor - bars / wires
3.7 Terminal for Protective Conductor
3.8 Tightening of Cable - pull wire test

4 Electrical Inspection
4.1 Protection against electric shock from doors, if any
4.2 Mega Test / Insulation Test (1)
4.3 Pressure / High Voltage Test
4.4 Mega Test / Insulation Test (2)
4.5 Functioning test of control circuits
4.6 MCCB - Functioning Test
4.7 Indicating Light / Push Button - Functioning Test
4.8 Voltmeter - Functioning Test
4.9 Ammeter - Functioning Test
4.10 KWH Meter - Functioning Test

Printed Date : 26/02/2019 Page 3 of 6


ZL SWITCHGEAR SDN BHD
NO.2, JALAN ONE INDUSTRIAL PARK 1, ONE INDUSTRIAL PARK, 43300 SERI KEMBANGAN, SELANGOR.

Clause Description Inspection Results


4.11 KW Meter - Functioning Test
4.12 Maximum Demand Meter - Functioning Test
4.13 Frequency Meter - Functioning Test
4.14 Earth Leakage Relay - Functioning Test
4.15 Power Factor Regulator (CAP BANK) - Functioning Test
4.16 Under Voltage Relay - Functioning Test
4.17 Heater / Thermostat - Functioning Test
4.18 Timer - Functioning Test
4.19 Relay - Functioning Test
4.20 Auto Transfer Switch (ATS) - Functioning Test

5 AMF Board - Functioning Test


5.1 Hot Water Temperature
5.2 Low Oil Pressure
5.3 Over Speed
5.4 Fail To Start

6 ACB Inspection
6.1 Draw out type functioning test - Rack in/out
6.2 Functioning Test of Mechanical & Electrical Charging
6.3 Functioning Test of Under Voltage trip and Shunt Trip

7 Visual Control Before Dispatch


7.1 Documentation
7.2 Parts for transport division

Printed Date : 26/02/2019 Page 4 of 6


ZL SWITCHGEAR SDN BHD
NO.2, JALAN ONE INDUSTRIAL PARK 1, ONE INDUSTRIAL PARK, 43300 SERI KEMBANGAN, SELANGOR.

Client :
Project Title :
Consultant :
Date :
Equipment :

FACTORY INSPECTION FEEDBACK FORM

S/No Switchboard Designation Client's Comment Action By

Client's Representative : ___________________________________ Date : ___________________


(Name & Signature)

Printed Date : 26/02/2019 Page 5 of 6


ZL SWITCHGEAR SDN BHD
NO.2, JALAN ONE INDUSTRIAL PARK 1, ONE INDUSTRIAL PARK, 43300 SERI KEMBANGAN, SELANGOR.

Doc No. ZL/FO/QC.03


INSPECTION RESULT
Rev No. 0
LV PANEL
Rev. Date N/A
Client Drawing No
Project Name Panel Description
Q. Ref Panel Serial No.

1.0 DC Insulation Resistance Test


i. CB in Close Position
ii. Test with 1000V / 2000MΏ Insulation Tester
iii. Test Equipment : a) Model / Type : _____________________________ b) Serial Number : _______________________

TEST R-Y B-Y B-R R-N Y-N B-N Acceptable Value


Before Pressure
Test
After Pressure Test FAIL < 50 MΏ < PASS
Results (Pass/Fail)

2.0 Pressure Test


i. Applied voltage : 2.5 kVAC FOR 1 minute
ii. Test Equipment : a) Model / Type : _____________________________ b) Serial Number : _______________________

TEST POINT R - YBNE Y - RBNE B - RYNE N - RYBE Acceptable Value


Leakage
PASS < 11 mA < FAIL
Results (Pass/Fail)

Tested By Verified By
Signature : ________________________ Signature : ________________________
Name : ________________________ Name : ________________________
Date : ________________________ Date : ________________________

FOR FACTORY ACCEPTANCE TEST


Witnessed By
Prod. Manager (ZL) Witnessed By
Signature : ________________________ Signature : ________________________
Name : ________________________ Name : ________________________
Date : ________________________ Date : ________________________
Company : ________________________

Printed Date : 26/02/2019 Page 6 of 6