Escolar Documentos
Profissional Documentos
Cultura Documentos
Question 1
The Owner of Jusco Puchong Branch is planning to modernize and expands the current
facilities. The project is expected to provide room for 8 to 10 new business. The activities
and the predecessors are as follows:
Question 2
To complete the wing assembly for an experimental aircraft, Asiacraft Company has laid
out the major steps and seven activities involved. These activities have been labeled A
through G in the following table, which also shows their estimated completion times (in
weeks) and immediate predecessors.
Activity a m b Immediate
predecessors
A 1 2 3 -
B 2 3 4 -
C 4 5 6 A
D 8 9 10 B
E 2 5 8 C,D
F 4 5 6 B
G 1 2 3 E
CRASH COST
1. Determine the least cost of reducing the project completion date by 3 months
based on the following information
A C
Finish
Start ACT Normal Crash time Normal Crash cost
time (months) cost (RM)
B D E (month)
A 6 4 2000 2400
B 7 5 3000 3500
C 7 6 1000 1300
D 6 4 2000 2600
E 9 8 8800 9000
Act. Normal time Crash time Normal cost Crash cost Immediate
(weeks) (weeks) (RM) (RM) predecessor(s)
A 4 3 2,000 2,600 -
B 2 1 2,200 2,800 -
C 3 3 500 500 -
D 8 4 2,300 2,600 A
E 6 3 900 1,200 B
F 3 2 3,000 4,200 C
G 4 2 1,400 2,000 D,E
3. The following table contains information about a project. Shorten the project three
weeks by finding the minimum-cost schedule. Assume that project indirect costs and
Dr. Azmawani Abd Rahman (MGM3161)
penalty costs are negligible. Identify activities to crash while minimizing the
additional crash costs.
START
E END
C D 2
6 3