Escolar Documentos
Profissional Documentos
Cultura Documentos
Barracuda Virtual Reactor, Barracuda VR, Barracuda and CPFD are registered trademarks of CPFD Software, LLC
1
Presentation Outline
Acknowledgements
Recommendations
2
History: Planning for 2015 Turn-Around
3
Presenting Problems and Preliminary Diagnosis
4
Audience Poll
5
Formation of Team and Initial Finding
Shutdown scheduled to repair expected
damage
6
Primary Cause – Spent Catalyst Distributor
Significant maldistribution
• Different regenerator regions with differing
temperature, coke loadings, gas compositions, etc.
7
What Could be Modified if No Damage Found?
During shutdown could alter:
• Air grid orientation
• Dipleg discharge
direction
• Shortening secondary Aligned
dipleg lengths
1A
1B
2B
3A
2A
3B
8
Top: Half model Bottom: Distributor
view orientation Elevation slice
Mixing and Channeling
Can incremental
improvements be
obtained?
• Regions with highest
time-averaged gas
bypass shown
• Cases 2 and 3
dissipate gas jets at a
lower elevation Case 0 Current Case 1 Case 2 Case 3
9
0
10
Thermal and Gas Composition Profiles
Regenerator temperature
profiles dominated by
maldistribution
11
Flue Gas CO
12
Catalyst Losses and Secondary Dipleg Plugging
Density [pcf]
Catalyst losses may be correlated with 50
secondary dipleg plugging
1B 2B
2B 1B
Lower bed densities at secondary dipleg 3B
outlets were observed before the 2015 Pre-2015
3B Current
25
turn-around
• Dipleg 3B in the current configuration
shows a high likelihood of plugging
2B 2B
• Case 3 appears to have a greater likelihood
of dipleg plugging based on overall density 1B 1B
gradients
0 3B
• Raising the Case 2 dipleg discharge 3B
elevation by 1.5 feet reduces the concern Case 2 Case 3
13
Summary of Simulation Findings
The root cause of maldistribution is the spent catalyst distributor
• Some maldistribution expected to remain in all 5 cases
Case 2 shows significant improvement over the current configuration in terms of:
• Improved flow uniformity
• Reduced air jetting
• Increased thermal uniformity
• Improved oxygen utilization
• Reduced CO entering the cyclone inlets
• Reduced likelihood of secondary dipleg plugging
14
Outcome
During shutdown
• The air grid wasn’t broken
• Simulation gave the refiner confidence to implement the change
• The refiner opted for Case 2 with the secondary dipleg heights
shortened by 1.5 ft
Post-shutdown:
Case 2
• NOx & CO maintained below 365 day rolling average
• Dropped significantly after start-up
• Air rate optimization performed and NOx additive used
• Catalyst losses: complete elimination of the catalyst loss events
15
Recommendations
Use the “Team” approach
• Refinery process engineers, central engineering, recognized consultants, technology
suppliers, radioactive tracer studies, hardware vendors, catalyst suppliers, simulation
expertise, etc.
• Encourage transparency between parties
16