Você está na página 1de 5

PRICE ADJUSTMENT FOR INFRASTRUCTURE PART-B

A= 0.38 (Fix Portion) b = 0.20 (Steel - FBS) c = 0.18 (Cement - FBS) d = 0.14 (Skilled Labour) e = 0.10 (HSD - PSO OGRA)
October, 2011 (Basic Rates) HSD = 94.15 Cement = 410.00 Steel = 70500.00 Skilled Labour = 700.00
MONTH OF WORK MONTH OF RATE DAYS WORK DONE WORK DONE HSD (PSO) SKILLED HSD (PSO) SKILLED
S.NO CEMENT STEEL LABOUR CEMENT STEEL
DONE APPLYING AMOUNT FOR MONTH LABOUR

October, 2011 (Basic Rates) 94.15 410 70500 700

December, 2012 November, 2012 #DIV/0! 94.15 410 70500 700 109.77 440 74500 775
IPC # 021March 19, 2013

January, 2013 December, 2012 #DIV/0! 94.15 410 70500 700 110.13 455 73500 775

February, 2013 January, 2013 #DIV/0! 94.15 410 70500 700 109.21 455 73500 800

March, 2013 February, 2013 #DIV/0! 94.15 410 70500 700 109.21 452.5 72500 800

Total Days 0
IPC # 02 May 07, 2013

March, 2013 February, 2013 #DIV/0! 94.15 410 70500 700 109.21 452.5 72500 800

April, 2013 March, 2013 #DIV/0! 94.15 410 70500 700 113.56 460 71500 800

May, 2013 April, 2013 #DIV/0! 94.15 410 70500 700 108.59 460 72500 800

Total Days 0

TOTAL AMOUNT OF PRICE ADJUSTMENT

PAID IN PREVIOUS IPCS

Pn= A + b(Ln/Lo) + c (Cn/Co) + d (Sn/So) + e (Dn/Do) PAYABLE IN THIS IPC

CWE............................ NESPAK...........................
P.A PRICE ADJUSTMENT
FACTOR AMOUNT

1.0561 #DIV/0!

1.0602 #DIV/0!

1.0643 #DIV/0!

1.0603 #DIV/0!

1.0603 #DIV/0!

1.0654 #DIV/0!

1.0630 #DIV/0!

RICE ADJUSTMENT #DIV/0!

IN PREVIOUS IPCS

AYABLE IN THIS IPC #DIV/0!

CWE............................ NESPAK...........................
CHINA INTERNATIONAL WATER & ELCTRIC CORP.(CWE)
Infrastructure Services, Bagh
Part-B (Drainage Systems)

MEASUREMENT SHEETS FOR DRAIN (AHMED BACKERY TO BYPASS ROAD) IPC-007


R.D MEASUREMENTS
S.NO DESCRIPTION OF ITEM NOS QUANTITY REQ.NO
FROM TO L B H

1 RCC (1:1:2) FOR SLAB

Top Slab -0+35 -0+45 1 10.15 1.60 0.20 3.248 6973

TOTAL QUANTITY OF RCC FOR SLAB 3.248

3 STEEL REINFORCEMENT

Top Slab -0+35 -0+45 0 10.15 439.04 KG/12.00 M 0.371 6973

TOTAL STEEL 0.371

CWE_____________ NESPAK_______________
CHINA INTERNATIONAL WATER & ELCTRIC CORP.(CWE)
Infrastructure Services, Bagh
Part-B (Drainage Systems)

IPC-006
SUMMARY OF QUANTITIES
DETAIL OF QUANTITIES
S.NO NAME OF DRAINS STEEL
EXCAVATION EXCAVATION STONE EXTRA PCC RCC(1:1:2) WATER RCC WALLS RCC WALLS
PCC (1:4:8) (Grade-
(SOIL) (HARD ROCK) SOLING (1:1:2) BASE SLAB STOPPER UPTO 9" 9" TO 18" 60)

1 D-1(Ahmed Backery to Bypass Road)

2 D-2(Khna Mohri to Haidry Chowk)

3 D-3(Banni Passari Drain)

4 D-4(Khan Mohalla Drain)

5 D-5(Grid Station Colony Drain)

6 D-6(Drain Near Bedori Shop)

7 D-7(Drain Along Pema Road)

8 D-8(Grid Station)

CWE................................ NESPAK................................
Drain From College Chowk to Khan
9 Chowk

CWE................................ NESPAK................................