Você está na página 1de 10

MEP PROJECT STATUS

23rd August 2016
PROJECT OVER VIEW
Key Milestones
Aug 2016 Sep 2016 Oct 2016 Nov 2016 Dec 2016 Jan 2017 Feb 2017 Mar 2017 Apr 2017

PLANNED
1 2 3 4 5 6 7 8 9
Sept Oct Nov Nov Dec Dec Dec Feb Mar
6 3 14 30 7 11 27 14 30

ACTUAL/FORECASTED
1 2 5 3 4 6 7 8 9
Oct Nov Dec Dec Jan Jan Jan Feb Mar
8 1 7 15 1 10 26 14 30

1. Building BD – T&C Start 6. Building A – T&C Finish Date


2. Building A – T&C Start 7. Building A – Finish Date
3. Building BD – T&C Finish Date 8. Building C – T&C Finish Date
4. Building BD – Finish Date 9. Building C – Finish Date
5. Building C – T&C Start

Original Contract  Updated Contract  Updated HL 


Percentage progress
Programme programme Target programme
Building
Base line  Baseline  Projected  Projected  Planned
Duration Delay Delay Actual % Diff
start Finish completion completion %

OVERALL 27/08/2014 16/07/2016 690 29/06/2017 ‐348 30/03/2017 0 100% 57.95% ‐42.05%
Building A 27/08/2014 17/04/2016 600 06/06/2017 ‐415 26/01/2017 ‐30 100% 51.84% ‐48.16%
Building BD 27/08/2014 17/04/2016 600 26/04/2017 ‐374 01/01/2016 ‐32 100% 56.45% ‐43.55%
Building C 27/08/2014 16/07/2016 690 29/06/2017 ‐348 30/03/2017 0 100% 43.42% ‐56.58%
Key Milestone Legend: Gray Originally planned or completed activity Green On track; will complete as planned Yellow Planned delivery at risk Red Will miss planned delivery
MEP PROJECT SUMMARY
Recent Accomplishments Upcoming Key Activities
 FAHU Installation in Building A & BD  Chiller Installation in Building C
 VRF Outdoor Installations in Building A  Generator Installation.
 GRP Tank Installation in Building A  MDB & SMDB Installation
 VRF Outdoor Installation Building BD  FAHU Installation in Building C
 Fire Pump Room Piping and Valve Packages.  GRP Water Tank Installation in Building C
 HVAC Risers installation on going in 5th & 6th Floors.  Ventilation Fan Installation in Basements
 LPG Tank Installation.
 VRF Outdoor Unit Installation.
 Electrical Room Mockup.
PROJECT STATUS
Building : C – 1st & 2nd Fix High‐level Works
PROJECT STATUS
Building : C ‐ 1st & 2nd Fix High‐level Works
• Fire Fighting : 2nd Fix Installation Completed up to 5th floor, 6th, 7th, & 8th floor  in 
progress. 

• Electrical : Dry area completed up to 3rd floor progressing up to 7th floor. 

• Plumbing : 1st and 2nd floor Completed, 3rd floor to 10th floor in progress.

• HVAC : 1st floor ducting completed, 2nd to 6th floor in progress,


1st to 3rd floor chilled water piping completed, 4th to 11th floor in 
progress.

• Shafts : Ducting Riser – Up to 7th floor in progress, 78% work done.


Plumbing Riser – Up to 7th floor in progress, 67% work done.
Fire Fighting – Up to 6th floor in Progress, 83% work done.
PROJECT STATUS
Building : A ‐ 1st & 2nd Fix High‐level Works
PROJECT STATUS
Building : A ‐ 1st & 2nd Fix High‐level Works
• Fire Fighting : 2nd Fix Installation Completed up to 6th floor & 7th floor  in 
progress .
• Electrical : 1st floor, 2nd floor completed 3rd floor to 10th floor in progress.

• Plumbing : 1st and 2nd floor Completed, 3rd floor to 8th floor in progress,
water meter room mockup installation in progress.

• HVAC : 1st floor and 2nd floor ducting completed, 3rd to 4th floor in 
progress,
1st and 2nd floor refrigerant  piping completed, 3rd  to 5th floor in 
progress.
• Shafts : 2 HVAC duct riser completed up to 9th floor.

• Roof : FAHU installation, VRF outdoor units &  GRP tanks 
installations ongoing
PROJECT STATUS
Building : BD ‐ 1st & 2nd Fix High‐level Works
PROJECT STATUS
Building : BD ‐ 1st & 2nd Fix High‐level Works
• Fire Fighting : 2nd Fix Installation Completed up to 5th floor, 6th, 7th, & 8th floor  in 
progress 
• Electrical : 1st floor completed 2nd floor to 8th floor in progress.

• Plumbing : 1st floor Completed, 2nd floor to 7th floor in progress.

• HVAC : 1st floor ducting completed, 2nd to 5th floor in progress,
1st and 2nd floor refrigerant  piping completed, 3rd  to 5th floor in 
progress.
• Shafts : Duct ‐ 2 risers completed up to 8th floor, 
Garbage chute – 2 risers completed up to 6th floor 

• Roof : FAHU installation, VRF outdoor units &  GRP tanks installation ongoing