Você está na página 1de 13

DESIGN OF RECEIVING CHAMBER

Receiving chamber is the structure to receive the raw sewage collected through Under Ground Sewage
System. It is a rectangular-shaped tank constructed at the entrance of the sewage treatment plant. The
main sewer pipe is directly connected with this tank.

Design flow = 0.005 mᶟ/sec

Volume of receiving chamber (V) = flow x detention time

Assume the detention time = 180sec

= 0.005 (180)

= 0.9 mᶟ

Area of receiving chamber (A)

Assume depth d = 1.0m

𝑉𝑜𝑙𝑢𝑚𝑒
A= 𝐷𝑒𝑝𝑡ℎ

0.9𝑚ᶟ
= 1𝑚

A = 0.9m²

Let L = 2*B, so A = 2B²

0.9 = 2B²
B = 0.671m, take B = 0.7m

L = 2*0.671 = 1.342 m, take L = 1.3m


DESIGN OF COARSE SCREEN

Design Criteria Used:


a. Velocity through rack at max flow = 0.9 m/s
b. Bar spacing (clear) = 2.5 cm
c. Provide two identical barracks, each capable of handling max flow conditions and each
equipped with mechanical cleaning device , 𝜃 = 60° from horizontal
d. Average discharge of sewage = 0.005 mᶟ/s
e. Peak discharge of sewage = Qave x PF
= 0.005 x 2
= 0.01 mᶟ/s

The velocity at average flow is not allowed to exceed 0.9 m/s


𝑄
Vertical projected area of screen, A = 𝑉
0.01
=
0.9

= 0.011 m²
Vertical projected gross area of screen
Thickness = 10mm
Width = 25mm
Clear spacing = 30mm

25 + 10
Therefore, 𝐴 = 0.011( 25 ) = 0.0154 m²
The screen is inclined @ 45°
𝑎𝑟𝑒𝑎
Horizontal gross sectional area of screen = 𝑠𝑖𝑛 45°

0.0154
=
𝑠𝑖𝑛 45°

= 0.0218 m²

If 20 no of bars are provided, then no of openings = 21.


Width of screen= (no. of bars x thickness) + (no. of opening x spacing)
= (20 x 0.01) + (21 x 0.025)
= 0.725 m
Assuming depth as 0.9m including free board
Coarse screen channel is designed for the size of 0.725m x 0.9m
DESIGN OF EQUALIZATION TANK

Assumptions:

 The number of equalization used is 3.


 Detention time is 2-5 hours (Yung-Tse Hung et al., 2012). A typical detention time of 3 h is
chosen as the detention time needs to be long enough so as to effectively balance fluctuating
flows and to assist self-neutralization.
 A safety factor of 15% is considered to make sure that there is no overflow of wastewater
(Water Environment Federation, 2008).
 A freeboard of 0.5 m is considered (Karia. G.L et al., 2006).
 A depth of 2.7 m is considered with a 0.3 m of freeboard with a total of 3 m.

Volume = Flow rate (m3/h) × detention time (h)

= 18 × 2= 36 m3

Total volume = volume of tank + 15 % volume of tank

= 36 + (0.15 × 36) = 41.4 m3

41.4 𝑚3
Surface area/ tank = 3
= 13.8 m²

Assuming Length to Breadth ratio is 2:1

2× Breadth2 = 13.8 m2

Breadth = 2.63 m ‫ ﱠ‬3m


Length = 3m × 2 = 6 m
Dimension: 6 x 3 x 3

Inlet velocity = = = 1.73 m/h


Secondary Treatment:
3.2 Design Calculations

Flow Rate Calculations

Bulk of the wastewater from the condominium will be coming from residential units. The
residents are profiled to be mostly working in Makati. Business hours in Makati is 24 hours. Some of the
residents work in graveyard shifts, while some work during the day. Since the building is currently under
construction and there is no actual data, typical domestic wastewater parameters are used to determine
its flow dynamics and parameters pertinent to the design.

1. 𝑄𝑎𝑣𝑒 = 𝑄 ÷ 𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑜𝑛 ℎ𝑜𝑢𝑟𝑠

𝑚3
432
𝑑𝑎𝑦
𝑄𝑎𝑣𝑒 =
ℎ𝑟
24
𝑑𝑎𝑦
3
𝑄𝑎𝑣𝑒 = 18 𝑚 ⁄ℎ𝑟

2. 𝑄𝑝𝑒𝑎𝑘 = 𝑄𝑎𝑣𝑒 ∙ 𝑃𝑒𝑎𝑘 𝐹𝑎𝑐𝑡𝑜𝑟

3
𝑄𝑝𝑒𝑎𝑘 = (18 𝑚 ⁄ℎ𝑟) 2

3
𝑄𝑝𝑒𝑎𝑘 = 36 𝑚 ⁄ℎ𝑟

3. 𝑄𝑚𝑖𝑛 = 𝑄𝑎𝑣𝑒 ∙ 𝐹𝑎𝑐𝑡𝑜𝑟

3 1
𝑄𝑚𝑖𝑛 = (18 𝑚 ⁄ℎ𝑟)
2
3
𝑄𝑚𝑖𝑛 = 9 𝑚 ⁄ℎ𝑟
Table Error! No text of specified style in document.-1 Flow Rate
Flowrate, Q: 432 m³/day
Average, Qave: 18 m³/hr
Peak, Qpeak 36 m³/hr
Minimum, Qmin 9 m³/hr

Table Error! No text of specified style in document.-2 Typical Domestic Wastewater Characteristics vs.
Effluent target for the Design
Typical Domestic
Parameter Effluent Target
Wastewater
BOD5 300 mg/L 30 mg/L
COD 600 mg/L 60 mg/L
TSS 400 mg/L 40 mg/L
Oil & Grease 50 mg/L 3 mg/L

Total BOD Loading

𝐵𝑂𝐷 𝐿𝑜𝑎𝑑𝑖𝑛𝑔 = 𝐹𝑙𝑜𝑤 𝑅𝑎𝑡𝑒 𝑥 𝐵𝑂𝐷5

𝑚3 𝑚𝑔 1 𝑘𝑔 1,000 𝐿
𝐵𝑂𝐷 𝐿𝑜𝑎𝑑𝑖𝑛𝑔 = (432 𝑑𝑎𝑦) (300 𝐿
) (1,000,000 𝑚𝑔) ( 1 𝑚3
)

𝑘𝑔 𝑘𝑔
𝐵𝑂𝐷 𝐿𝑜𝑎𝑑𝑖𝑛𝑔 = 129.6 ⁄𝑑𝑎𝑦 = 130 ⁄𝑑𝑎𝑦

Total TSS Loading

𝑇𝑆𝑆 𝐿𝑜𝑎𝑑𝑖𝑛𝑔 = 𝐹𝑙𝑜𝑤 𝑅𝑎𝑡𝑒 𝑥 𝑇𝑆𝑆𝑖𝑛𝑓𝑙𝑢𝑒𝑛𝑡

𝑚3 𝑚𝑔 1 𝑘𝑔 1,000 𝐿
𝑇𝑆𝑆 𝐿𝑜𝑎𝑑𝑖𝑛𝑔 = (432 𝑑𝑎𝑦) (400 𝐿
) (1,000,000 𝑚𝑔) ( 1 𝑚3
)

𝑘𝑔 𝑘𝑔
𝑇𝑆𝑆 𝐿𝑜𝑎𝑑𝑖𝑛𝑔 = 172.8 ⁄𝑑𝑎𝑦 = 173 ⁄𝑑𝑎𝑦
3.4.1 Screening and Equalization Tank

The entry point of all wastewater generated by the condominium into the treatment facility is
the equalization tank through a fabricated stainless steel bar screen. It is a physical unit operation that
removes large particles, such as paper, plastics, rags, that contribute to the clogging of pipes. It also
helps in preventing damage to the equipment, piping, and other appurtenances downstream. The bar
screen will block solids with diameter greater than 1.0 cm from entering the EQT. The removal rate of
the screen basket will be the basis for the calculation of BOD and TSS entering the equalization tank.
During screening, about 15% and 25% of BOD and TSS is removed respectively.

BOD Removal:

𝐵𝑂𝐷𝑟𝑒𝑚𝑜𝑣𝑒𝑑 = (𝐵𝑂𝐷𝑙𝑜𝑎𝑑𝑖𝑛𝑔 ) (15% 𝑟𝑒𝑚𝑜𝑣𝑒𝑑)

𝐵𝑂𝐷𝑟𝑒𝑚𝑜𝑣𝑒𝑑 = (130) (0.15)


𝑘𝑔
𝐵𝑂𝐷𝑟𝑒𝑚𝑜𝑣𝑒𝑑 = 19.5 𝑖𝑠 𝑟𝑒𝑚𝑜𝑣𝑒𝑑 𝑖𝑛 𝑠𝑐𝑟𝑒𝑒𝑛𝑖𝑛𝑔
𝑑𝑎𝑦

TSS Removal:

𝑇𝑆𝑆𝑟𝑒𝑚𝑜𝑣𝑒𝑑 = (𝑇𝑆𝑆𝑙𝑜𝑎𝑑𝑖𝑛𝑔 ) (25% 𝑟𝑒𝑚𝑜𝑣𝑒𝑑)

𝑇𝑆𝑆𝑟𝑒𝑚𝑜𝑣𝑒𝑑 = (173) (0.25)


𝑘𝑔
𝑇𝑆𝑆𝑟𝑒𝑚𝑜𝑣𝑒𝑑 = 43.25 𝑑𝑎𝑦
𝑖𝑠 𝑟𝑒𝑚𝑜𝑣𝑒𝑑 𝑖𝑛 𝑠𝑐𝑟𝑒𝑒𝑛𝑖𝑛𝑔

The EQT dampens the flowrate variations so that it is nearly constant for the next steps in the
treatment process. According to the Water and Wastewater Calculations Manual, 30% of BOD and
55% of the COD entering the equalization tank is retained. The other percentage of these values
passes through and enters the next process.
𝑉𝐸𝑄𝑇 = (𝑎𝑣𝑒𝑟𝑎𝑔𝑒 ℎ𝑜𝑢𝑟𝑙𝑦 𝑓𝑙𝑜𝑤𝑟𝑎𝑡𝑒) 𝑥 (𝑝𝑒𝑎𝑘 𝑓𝑙𝑜𝑤)

𝑚3
𝑉𝐸𝑄𝑇 = 18 𝑥 2 ℎ𝑟 = 36 𝑚3
ℎ𝑟

𝑉𝐸𝑄𝑇
𝐴𝐸𝑄𝑇 =
𝑤𝑒𝑡 𝑑𝑒𝑝𝑡ℎ

173.36 𝑚3
𝐴𝐸𝑄𝑇 = = 𝑚2
3𝑚

USED THE FIRST CALC.

The equalization tank requires mixing and air. To maintain an aerobic condition for the EQT,
the air supplied should be 0.01 to 0.015 m³/m³·min (Metcalfp. 344).

3
𝑂2(𝐴𝐼𝑅−𝐸𝑄𝑇) = 0.015 𝑚 ⁄ 3 𝑥 𝑉𝐸𝑄𝑇
𝑚 ∙ 𝑚𝑖𝑛
3 3
𝑂2(𝐴𝐼𝑅−𝐸𝑄𝑇) = 0.015 𝑚 ⁄ 3 𝑥 41.4 𝑚3 = 0.621 𝑚 ⁄𝑚𝑖𝑛
𝑚 ∙ 𝑚𝑖𝑛

BOD Removal

𝐵𝑂𝐷𝑟𝑒𝑚𝑜𝑣𝑒𝑑 = (130) (30%)

𝐵𝑂𝐷𝑟𝑒𝑚𝑜𝑣𝑒𝑑 = 39

𝐵𝑂𝐷𝑟𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 = 𝐵𝑂𝐷𝑙𝑜𝑎𝑑𝑖𝑛𝑔 – 𝐵𝑂𝐷𝑟𝑒𝑚𝑜𝑣𝑒𝑑

𝐵𝑂𝐷𝑟𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 = 130 – 39

𝑘𝑔
𝐵𝑂𝐷𝑟𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 = 91 𝑑𝑎𝑦
TSS Removal

𝑇𝑆𝑆𝑟𝑒𝑚𝑜𝑣𝑒𝑑 = (173) (55%)

𝑇𝑆𝑆𝑟𝑒𝑚𝑜𝑣𝑒𝑑 = 95.15

𝑇𝑆𝑆𝑟𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 = 𝑇𝑆𝑆𝑙𝑜𝑎𝑑𝑖𝑛𝑔 – 𝑇𝑆𝑆𝑟𝑒𝑚𝑜𝑣𝑒𝑑

𝑇𝑆𝑆𝑟𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 = 173 − 95.15

𝑘𝑔
𝑇𝑆𝑆𝑟𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 = 77.85 𝑑𝑎𝑦

3.4.2 Sequential Batch Reactor Sizing

For this design, two (2) SBR basins will be used. This is to draw water out of the EQT more
frequent, making the process appear almost continuous.
𝐷𝑒𝑐𝑎𝑛𝑡𝑎𝑏𝑙𝑒 𝐻𝑒𝑖𝑔ℎ𝑡 2𝑚
= = 40 %
𝑊𝑒𝑡 𝐷𝑒𝑝𝑡ℎ 5𝑚

𝐹𝑙𝑜𝑤 𝑅𝑎𝑡𝑒 432 𝑚3 3


𝐷𝑒𝑐𝑎𝑛𝑡𝑎𝑏𝑙𝑒 𝑉𝑜𝑙𝑢𝑚𝑒 = = = 54 𝑚 ⁄𝑐𝑦𝑐𝑙𝑒
𝑇𝑜𝑡𝑎𝑙 𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝐶𝑦𝑐𝑙𝑒𝑠 8 𝑐𝑦𝑐𝑙𝑒𝑠

SBR REACTOR VOLUME (PER TANK)

3
𝐷𝑒𝑐𝑎𝑛𝑡𝑎𝑏𝑙𝑒 𝑉𝑜𝑙𝑢𝑚𝑒 54 𝑚 ⁄𝑐𝑦𝑐𝑙𝑒
𝑉𝑆𝐵𝑅 = = = 135 𝑚3 𝑝𝑒𝑟 𝑆𝐵𝑅 𝑇𝑎𝑛𝑘 𝑥 2 𝑇𝑎𝑛𝑘𝑠
% 𝐷𝑒𝑐𝑎𝑛𝑡𝑎𝑏𝑙𝑒 𝐻𝑒𝑖𝑔ℎ𝑡 40%

𝑉𝑆𝐵𝑅 135 𝑚3
𝐴𝑆𝐵𝑅 = = = 27 𝑚2 𝑝𝑒𝑟 𝑆𝐵𝑅 𝑇𝑎𝑛𝑘 𝑥 2 𝑇𝑎𝑛𝑘𝑠
𝑤𝑒𝑡 𝑑𝑒𝑝𝑡ℎ 5𝑚

Overall hydraulic Retention Time

ℎ𝑟
(# 𝑜𝑓 𝑆𝐵𝑅 𝑇𝑎𝑛𝑘𝑠)(𝑉𝑆𝐵𝑅 ) (24 )
𝐻𝑅𝑇 = 𝑑
𝑄

ℎ𝑟
2(135 𝑚3 ) (24 )
𝑑𝑎𝑦
𝐻𝑅𝑇 = = 15 ℎ𝑟
𝑚3
432
𝑑𝑎𝑦

In Metcalf and Eddy’s Wastewater Engineering, Treatment and reuse, typical kinetic coefficients
for an activated sludge process are as follows:
Table Error! No text of specified style in document.-3 Typical Kinetic Coefficients for Activated Sludge
Process
Substrate utilization rate, k k = 5 gCOD/gVSS·day
Half velocity constant, KS KS = 60 mg/L BOD
Yield coefficient, Y Y = 0.6 mg VSS/mg BOD
Decay coefficient, kd kd = 0.1 g VSS/g VSS·day
Mixed Liquor Suspended Solid, MLSS MLSS = 3,500 mg/L = 3,500 g/m³
Mixed Liquor Volatile Suspended Solid, MLVSS MLVSS = 0.8MLSS = 2,830 g/m³

(𝑉𝑇𝑆𝐵𝑅 )(𝑀𝐿𝑆𝑆)
𝑃𝑋,𝑇𝑆𝑆 =
𝑆𝑅𝑇

𝑃𝑋,𝑇𝑆𝑆 (𝑆𝑅𝑇) = (𝑉𝑇𝑆𝐵𝑅 )(𝑋𝑀𝐿𝑆𝑆 )

𝑔
𝑃𝑋,𝑇𝑆𝑆 (𝑆𝑅𝑇) = (292.44 𝑚3 ) (3,500 )
𝑚3

𝑃𝑋,𝑇𝑆𝑆 (𝑆𝑅𝑇) = 1,023,540 𝑔

𝑄𝑌(𝑆𝑂 −𝑆)(𝑆𝑅𝑇) 𝑄𝑌𝑛 (𝑁𝑂𝑋 )(𝑆𝑅𝑇) (𝑓 )(𝑘𝑑 )𝑄𝑌(𝑆𝑂 −𝑆)(𝑆𝑅𝑇 2 )


𝑃𝑋,𝑇𝑆𝑆 (𝑆𝑅𝑇) = [1+𝑘 + 𝑄(𝑛𝑏𝑉𝑆𝑆)(𝑆𝑅𝑇) + + 𝑑 [1+𝑘 +
𝑑 (𝑆𝑅𝑇)](0.85) [1+𝑘𝑑𝑛 (𝑆𝑅𝑇)](0.85) 𝑑 (𝑆𝑅𝑇)](0.85)
𝑄(𝑇𝑆𝑆𝑂 − 𝑉𝑆𝑆𝑂 )(𝑆𝑅𝑇)

3 𝑔 𝑔 𝑔
(520 𝑚 ⁄𝑑𝑎𝑦)(0.6 ⁄𝑔)(178.5 ⁄ 3 −30 ⁄ 3 )(𝑆𝑅𝑇) 3 𝑔
1,023,540 𝑔 = 𝑚 𝑚
+ (520 𝑚 ⁄𝑑𝑎𝑦) (68 ⁄ 3 ) (𝑆𝑅𝑇) +
[1+0.1(𝑆𝑅𝑇)](0.85) 𝑚
𝑚 3 𝑔 𝑔 𝑔 𝑔 𝑚 3 𝑔 𝑔 𝑔
(520 ⁄𝑑𝑎𝑦)(0.18 ⁄𝑔)(28 ⁄ 3 )(𝑆𝑅𝑇) (0.15 ⁄𝑔)(0.10 ⁄𝑔 )(520 ⁄𝑑𝑎𝑦)(0.6 ⁄𝑔)(178.5 ⁄ 3 −30 ⁄ 3 )(𝑆𝑅𝑇 2 )
𝑚 𝑚 𝑚
𝑔 + 𝑔 +
[1+(0.068 ⁄𝑔 )(𝑆𝑅𝑇)](0.85) [1+(0.10 ⁄𝑔 )(𝑆𝑅𝑇)](0.85)
3 𝑔 𝑔
(520 𝑚 ⁄𝑑𝑎𝑦) (300 ⁄ 3 − 220 ⁄ 3 )(𝑆𝑅𝑇)
𝑚 𝑚

𝑆𝑅𝑇 = 9.205 𝑑𝑎𝑦𝑠

3 𝑔
𝐹 𝑄𝑆𝑂 (520 𝑚 ⁄𝑑𝑎𝑦)(178.5 ⁄ 3 ) 𝑔
𝑚
𝑀
= 𝑉𝑋
= 𝑔 = 0.0907 ⁄𝑔 ∙ 𝑑𝑎𝑦
(292.44 𝑚3 )(3,500 )
𝑚3

For checking, a food to microorganism ratio of 0.0907 for an SBR process is ideal for a
suspended growth activated sludge process. This level ensures that nutrients are consumed by the
microorganisms, nutrients such as nitrates and phosphates.
3.4.3 Oxygen Requirement for each SBR Tank

For every kg of BOD of wastewater, 1.2 kg. of oxygen is required and for kilogram of total
Kjedahl Nitrogen in the wastewater, 4.6 kg. of oxygen is needed to attain a complete reaction.

Oxygen Requirement, OR

𝑘𝑔 𝐵𝑂𝐷 𝑘𝑔 𝑇𝐾𝑁
𝑂𝑅 = [(1.2 𝑘𝑔 𝑂2 ) ( ⁄𝑑𝑎𝑦 ∙ 𝑡𝑎𝑛𝑘 )] + [(4.6 𝑘𝑔 𝑂2 ) ( ⁄𝑑𝑎𝑦 ∙ 𝑡𝑎𝑛𝑘 )]

78.00 𝑘𝑔 𝐵𝑂𝐷 9.1 𝑘𝑔 𝑇𝐾𝑁


𝑂𝑅 = [(1.2 𝑘𝑔 𝑂2 ) ( ⁄𝑑𝑎𝑦 ∙ 𝑡𝑎𝑛𝑘 )] + [(4.6 𝑘𝑔 𝑂2 ) ( ⁄𝑑𝑎𝑦 ∙ 𝑡𝑎𝑛𝑘 )]

𝑘𝑔 𝑂2 𝑘𝑔 𝑂2
𝑂𝑅 = 93.6 + 41.86
𝑑𝑎𝑦 ∙ 𝑡𝑎𝑛𝑘 𝑑𝑎𝑦 ∙ 𝑡𝑎𝑛𝑘

𝑘𝑔 𝑂2
𝑂𝑅 = 135.46 ( )
𝑑𝑎𝑦 ∙ 𝑡𝑎𝑛𝑘

𝑘𝑔 𝑂2
135.46 ( )
𝑑𝑎𝑦 ∙ 𝑡𝑎𝑛𝑘
𝑂𝑅𝐴𝐼𝑅 =
𝜌𝑎𝑖𝑟 ∙ 𝜔𝑂2

𝑘𝑔⁄
𝐴𝑖𝑟 𝑑𝑒𝑛𝑠𝑖𝑡𝑦, 𝜌𝑎𝑖𝑟 = 1.225 ; 𝑂 𝑤𝑒𝑖𝑔ℎ𝑡 𝑓𝑟𝑎𝑐𝑡𝑖𝑜𝑛, 𝜔𝑂2 = 0.232
𝑚3 2
𝑘𝑔 𝑂2
135.46 ( )
𝑑𝑎𝑦 ∙ 𝑡𝑎𝑛𝑘
𝑂𝑅𝐴𝐼𝑅 =
𝑘𝑔
(1.225 ⁄ 3 ) (0.232)
𝑚

𝑚3 𝑎𝑖𝑟
𝑂𝑅𝐴𝐼𝑅 = 476.636172
𝑑𝑎𝑦 ∙ 𝑡𝑎𝑛𝑘

𝑚3
476.636172 3 ℎ𝑟𝑠 𝑎𝑒𝑟𝑎𝑡𝑖𝑜𝑛 6 𝑐𝑦𝑐𝑙𝑒𝑠 ℎ𝑟
𝑑𝑎𝑦 ∙ 𝑡𝑎𝑛𝑘
𝑂𝑅(min) = ; 𝑓𝑜𝑟 ( ) = 18
18 ℎ𝑟 60 𝑚𝑖𝑛 𝑐𝑦𝑐𝑙𝑒 𝑑𝑎𝑦 𝑑𝑎𝑦
( )( )
𝑑𝑎𝑦 ℎ𝑟

𝑚3
𝑂𝑅(min) = 0.441330
𝑚𝑖𝑛
Standard Oxygen Requirement, SOR

𝑂𝑅𝑚𝑖𝑛
𝑆𝑂𝑅 = ; 𝑒 = 0.56
𝐶𝑜𝑟𝑟𝑒𝑐𝑡𝑖𝑜𝑛 𝐹𝑎𝑐𝑡𝑜𝑟

𝑚3
0.441330 𝑚𝑖𝑛
𝑆𝑂𝑅 =
0.56

𝑚3
𝑆𝑂𝑅 = 0.788089
𝑚𝑖𝑛

Theoretical Oxygen Requirement, TOR

𝑆𝑂𝑅𝑚𝑖𝑛
𝑇𝑂𝑅 = ;
𝐷𝑖𝑓𝑓𝑢𝑠𝑒𝑟 𝑇𝑟𝑎𝑛𝑠𝑓𝑒𝑟 𝐸𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦

𝐹𝑖𝑛𝑒 𝐵𝑢𝑏𝑏𝑙𝑒 𝐷𝑖𝑓𝑓𝑢𝑠𝑒𝑟 𝑇𝑟𝑎𝑛𝑠𝑓𝑒𝑟 𝐸𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 = 0.35

𝑚3
0.788089 𝑚𝑖𝑛
𝑇𝑂𝑅 =
0.35

𝑚3
𝑇𝑂𝑅 = 2.251683 𝑚𝑖𝑛⁄𝑏𝑎𝑠𝑖𝑛

Number of Diffusers per SBR Tank, FBD

𝑇𝑂𝑅
𝐹𝐵𝐷 =
𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑜𝑓 𝐷𝑖𝑓𝑓𝑢𝑠𝑒𝑟

Kamair FBD (ø = 25 cm) = 0.085 m³/min

𝑚3
2.251683 𝑚𝑖𝑛
𝐹𝐵𝐷 =
𝑚3
0.08495 𝑚𝑖𝑛

𝐹𝐵𝐷 = 26.0506 𝑢𝑛𝑖𝑡𝑠 𝑝𝑒𝑟 𝑏𝑎𝑠𝑖𝑛 ≈ 27 𝑢𝑛𝑖𝑡𝑠 𝑝𝑒𝑟 𝑏𝑎𝑠𝑖𝑛

Você também pode gostar