Escolar Documentos
Profissional Documentos
Cultura Documentos
ONLY THE CLIENT OR ITS DESIGNATED REPRESENTATIVES MAY USE THIS DOCUMENT AND ONLY FOR THE
SPECIFIC PROJECT FOR WHICH THIS REPORT WAS PREPARED.
A Plan Prepared for:
Prepared by:
Jake Stelten, EI
Professional
Reviewed by:
John Wendelburg, PE
Principal Professional
KLEINFELDER
300 Westage Business Center Drive, Suite 407
Fishkill, NY, 12524
Phone: 845.231.2500
List of Appendices
Appendix A Notice of Intent
Appendix B Notice of Intent Acknowledgement Letter (to be included upon receipt)
Appendix C SPDES General Permit for Stormwater Discharges from Construction Activity
Appendix D MS4 SWPPP Acceptance Form
Appendix E Town of Bethlehem SWPPP Application Review Checklist
Appendix F SWPPP Preparer Certification Form
Appendix G Contractor Certification Statement Form
Appendix H Selkirk Solar Project Construction Plans
Appendix I Erosion and Sediment Control Component Cost Estimate
Appendix J SWPPP Inspection Reports
Appendix K NRCS Soils Report & Site Geotechnical Report
Appendix L FEMA floodplain Map
Appendix M Division of Historic Preservation Letters
Appendix N Pre & Post-Development Drainage Area Map
Appendix O Pre-Development Hydrologic Model and Results
Appendix P Pre-Development Hydrologic Model and Results
Appendix Q Impervious Area Calculations
Appendix R TR-55 Time of Concentration Calculations
Appendix S NYS DEC Runoff Reduction Worksheets
Appendix T National Oceanic and Atmospheric Administration Rainfall Data
Appendix U NYS DEC SMP Inspection Checklist
Appendix V Commercial Requirements
Appendix W Notice of Termination Form
This SWPPP document has been prepared by Kleinfelder, for DG Suny Solar 1, LLC (DG
Solar), for the construction of the Selkirk Solar Site.
DG Solar is proposing the construction of a photovoltaic solar energy farm within the Selkirk
Hamlet of the Town of Bethlehem, in Albany County, New York. The site, located at 93 Bridge
Street, Bethlehem, New York, 12158, is on a 72.26-acre parcel. Of the 72.26 acres, 41.5 acres
is within the limit of disturbance.
The vast majority of area proposed for the solar array and connector station currently consist of
agricultural farm fields. The farm field topography is generally flat to gently sloping (0.5% to 5%
average slopes). These fields predominantly drain via a combination of man‐made, non‐
jurisdictional ditches and four jurisdictional streams to a wetland located south of the site. The
wetland outlets towards the south into an existing vegetated swale, which flows northwest
towards Vloman Kill, a tributary of the Hudson River.
Tree clearing is proposed onsite for array installation and shade mitigation. Proposed tree
clearing is designated in 3 different capacities: tree clearing and grubbing, tree cutting, and tree
topping.
Tree clearing and grubbing (approximately 1.47 acres) consists of cutting trees and
clearing and grubbing all tree remains for array installation.
Tree cutting (approximately 2.19 acres) consists of cutting trees down to stump
elevation while avoiding ground disturbance, for shade reduction.
Tree topping (approximately 0.48 acres) consists of cutting tree tops down to elevation
205’ for shade reduction.
The solar array will consist of fixed-tilt solar panels mounted to a racking system, which will be
supported with driven H‐piles. There will be several string inverters which will be supported on
pile foundations at the end of each row of arrays. There will be 4 transformers placed on
concrete pads located within the site. Gravel access roads are proposed to serve as access to
each transformer pad. The array will be surrounded by a chain-link fence.
There are jurisdictional ditches present within the array area. These ditches will not be altered
or disturbed as part of the project. The use of composite timber mats will be used to cross
these ditches during construction. The timber mats will be removed following construction.
The entire limit of disturbance will be planted with a low‐maintenance grass seed mixture.
No mass grading is proposed as part of the project. See the Selkirk Solar Project
Construction Plans (Appendix H).
No mass grading is proposed as part of the project. See the Selkirk Solar Project
Construction Plans (Appendix H).
No steep slopes are being disturbed as part of this project. See the Selkirk Solar
Project Construction Plans (Appendix H).
The surface waters in vicinity of the site include two federally regulated wetlands:
one to the southwest of the site, and one to the southeast of the site. There is an
existing road adjacent-north of the southwestern wetland. The road is proposed
to be improved for site traffic. The existing road utilizes a culvert to cross an
existing ditch which feeds the southwestern wetland. In order to avoid new impact
to the ditch, the crossing will be utilized and improved for site traffic, and the
existing culvert left in place. Due to the proximity of the crossing to the
southwestern wetland and concern for direct runoff to the wetland, the road cross-
section will be sloped to drain runoff away from the wetland into the proposed dry
swale to the north of the road. The dry swale is designed to treat road runoff
before discharging into the ditch, which eventually crosses the road via the
culvert, and discharges into the southern wetland. This design helps to maintain
predevelopment runoff volumes and improves the water quality of runoff to the
No mass grading is proposed as part of the project. Only light duty construction
traffic used to drive the racking piles will be onsite, which minimizes soil compaction.
See the Selkirk Solar Project Construction Plans (Appendix H).
The only disturbance to topsoil will be in the form of light duty construction traffic.
See the Selkirk Solar Project Construction Plans (Appendix H) for temporary and
permanent seeding notes.
1.1.7 Dewatering
If uncontaminated excavation dewatering becomes necessary, dewatering
operations will be in conformance with the Selkirk Solar Project Construction
Plans (Appendix H).
This SWPPP has been prepared pursuant to GP-0-15-002 erosion and sediment control
requirements (Appendix C), and includes erosion and sediment control practices designed in
conformance with the technical standard, New York State Standards and Specifications for
Erosion and Sediment Control, dated August 2005. Please see Appendix E for the Town of
Bethlehem SWPPP Application Review Checklist.
1.1 Background information about the scope of the project, including the location, type
and size of project;
Please see the Selkirk Solar Project Construction Plans (Appendix H) for a comprehensive
site map.
1.3 Soils;
Terracon Consultants completed 12 test borings and four test pits throughout the site to
depths ranging from 8 to 17 feet below existing ground surface. Site is underlain by a
glaciolacustrine deposit with an upper stratum of medium stiff to very stiff lean clay over a
stratum of soft to medium stiff fat clay. Groundwater depths range from 5 – 15 feet below the
ground surface onsite. The Site Geotechnical Report is included in (Appendix K).
According to the NRCS Soils Report and Soils Map (Appendix K) the soils onsite are
predominantly a silt loam, and a silty clay loam type. Also, 92 percent of the soils onsite are
classified as Hydrologic Soil Group (HSG) C with infiltration rates of approximately 0.06 to
0.20 inches per hour. The remaining 8 percent of soils are classified as HSG B.
The NRCS Soils Report (Appendix K) also rates soils onsite by erosivity. The erosion factor,
K, indicates the susceptibility of a soil to sheet and rill erosion by water. The estimates are
based primarily on percentage of silt, sand, and organic matter and on soil structure and
DG Solar does not wish to limit construction to 5-acre portions of the site in any given time.
Because of this, they will meet the requirements in the CGP (Appendix C) Part II.C.3 as
follows:
a) DG Solar shall have a qualified inspector conduct at least two site inspections in
accordance with Part K of this SWPPP document.
b) In areas where soil disturbance activity has temporarily or permanently ceased, the
application of soil stabilization measures must be initiated by the end of the next
business day and completed within seven (7) days from the date the current soil
disturbance activity ceased. The soil stabilization measures selected shall be in
conformance with the technical standard, New York State Standards and
Specifications for Erosion and Sediment Control, dated August 2005.
d) Water quality will be protected due to the efforts set forth in the Erosion and
Sediment Control and Stormwater Management Practice design which can be
found in the Selkirk Solar Project Construction Plans (Appendix H).
The construction sequence can be found on the Construction Plans (Appendix H) sheet 2,
“Construction Sequence Notes” and shall be as follows:
1. Obtain land disturbing permit from Town of Bethlehem and schedule a
preconstruction meeting with Town of Bethlehem inspector.
2. Notify Town of Bethlehem one week prior to the pre-construction conference, one
week prior to the commencement of land disturbing activity, and one week prior to
the final inspection. The name of the responsible land disturber must be provided
to Town of Bethlehem prior to actual engagement in the land-disturbing activity
shown on the approved plan. If the name is not provided prior to engaging in the
land-disturbing activity, the plan's approval will be revoked.
4. Prior to land-disturbing activities, install all erosion and sediment control measures
and wetland protection fencing as shown on plans. Upon completion of installation,
seed, mulch, and anchor erosion and sediment control measures.
5. Begin installation of solar farm components including access roads with culvert
crossings, inverter stations, solar array, and underground electrical lines.
7. Stabilize site as areas are brought up to finished grade with vegetation, stone base
course, concrete, etc. see CIVIL DETAILS sheets for seeding schedule.
Please see the Selkirk Solar Project Construction Plans (Appendix H).
1.6 A temporary and permanent soil stabilization plan, covering initial land clearing and
grubbing to project completion and achievement of final stabilization.
Please see the Selkirk Solar Project Construction Plans (Appendix H).
1.7 A site map/construction drawing(s) showing the specific location(s), size(s), and
length(s) of each erosion and sediment control practice.
Please see the Selkirk Solar Project Construction Plans (Appendix H).
1.8 The dimensions, material specifications, installation details, and operation and
maintenance requirements for all erosion and sediment control practices. Include the
location and sizing of any temporary sediment basins and structural practices that will
be used to divert flows from exposed soils.
Please see the Selkirk Solar Project Construction Plans (Appendix H).
1.9 A maintenance inspection schedule for the contractor(s) identified in Part D of this
document, to ensure continuous and effective operation of the erosion and sediment
control practices.
1.10 A description of the pollution prevention measures that will be used to control litter,
construction chemicals and construction debris from becoming a pollutant source in
1.11 A description and location of any stormwater discharges associated with industrial
activity.
1.12 Identify elements of the design not in conformance with technical standard design
criteria.
All erosion and sediment control practices are designed to be in conformance with the criteria
in the NYS DEC Standards and Specifications for Erosion and Sediment Control Manual.
An important aspect of the solar array is that it functions as a pervious cover feature. The
rationale behind this consideration is that stormwater will infiltrate into the ground beneath the
solar array at a rate equal (or greater) to that of the infiltration rate prior to the placement of the
array. The project will utilize a fixed-tilt array, which will consist of racks of panels. Each array
rack will house several rectangular solar panels (6.5 feet x 3.25 feet +/‐) with spacing between
each panel to allow stormwater to pass through. The stormwater will then hit the ground below,
where it will infiltrate into the underlying earth. It is important to note that the existing cultivated
fields over which the panels will be seeded with a low‐maintenance seed mixture, which will
provide a full, year‐round, enhanced cover condition. The array itself will be mounted to the
ground surface by way of driven H-piles, which will represent a minimal amount of cross‐
sectional impervious area (approximately 0.026 square feet each).
As noted above, rain water will hit the panels and sheet flow a maximum distance of
approximately 6.5 feet before enter the spacing between the panels (which is typically 1 inch
to 1.5 inches) and/or the lower edge of the panel where it will then fall to the ground below.
Since the equivalent unsaturated pervious area is available below the array, the runoff will enter
the soils and infiltrate and/or runoff in a fashion substantially equivalent to if the panels were
not there. As demonstrated, an important feature of the solar array is that its construction does
not reduce the amount of pervious ground surface available for infiltration. Furthermore, the
It is important to note that from a practical perspective that the ground cover improvement due
to site seeding practices will enhance water quality, reduce erosive potential, and enhance the
infiltration opportunity for runoff. The proposed impervious area includes permanent access
roads, driven H-piles, and concrete transformer pads and will account for 2.02% of the site.
Impervious area calculations can be seen in Appendix Q.
The Water Quality Volume (denoted as the WQv) is intended to improve water quality by
capturing and treating runoff from small, frequent storm events that tend to contain higher
pollutant levels. New York has defined the WQv as the volume of runoff generated from the
entire 90th percentile rain event. Essentially what this means is that a practice sized using the
WQv will capture and treat 90% of all 24 hour rain events. The WQv is directly related to the
amount of impervious cover constructed at a site.
The only changes to existing ground cover to land outside of the proposed Limit of Disturbance
is tree cutting & topping for the purposes of eliminating future shading of solar panels. Tree
cutting & topping activities outside of the Limit of disturbance will not include any ground
disturbance. Stumps and other existing ground and existing hydrologic patterns will be
maintained. Since the ground cover will be unchanged outside of the LOD, this 31.26 is not
included in WQv calculations.
Within the LOD, approximately 0.91 acres of vegetation will be cleared and grubbed, stumps
and brush removed for the installation of solar panels. Area within the LOD, excluding 1.47
acres of proposed impervious area, will be planted with a low-maintenance grass seed.
Seeding practices will increase infiltration in areas that were previously cultivated. This
increased infiltration is the main proponent of runoff reduction on the site. Due to the pervious
nature of the solar panels and the increased infiltration rate due to proposed seeding practices
approximately 39.90 acres within the LOD will be considered grassed filter strips, and are
excluded from the WQv calculation. The remaining WQv-contributing area includes the
impervious features (1.47 acres) i.e. proposed gravel access roads, concrete transformer pads,
The WQv caluclations were done using the NYS DEC Runoff Reduction Worksheets
(Appendix S). The initial WQv was calculated to be 14,693 cubic feet. The area reduction
techniques as described above reduce the WQv to 4,552 cubic feet.
Predominant site soils are Hydrologic Soil Group (HSG) C and only allow for a 20% credit for
dry swale RRv reduction. Due to this decreased efficiency in calculations, the Dry Swales do
not meet the WQv requirements as calculated. However, due to the low infiltration rate of HSG
C soils, a minimum standard was developed for WQv requirements. Calculations in Appendix
S show the minimum requirements for site considering the limiting soil infiltration rates to be
1,901 cubic feet.
The total provided RRv, 12,259 cubic feet, meets approximately 80 percent of initial WQv
requirements, and surpasses the minim RRv requirements. The proposed Dry Swales
have been strategically placed alongside the site access road to efficiently treat runoff at
the source. It is anticipated that the improved grass cover over the Limit of Disturbance will
increase runoff infiltration, treating runoff for quality and controlling it for discharge
quantities. It is anticipated that this improved grass cover in combination with the proposed
Dry Swales will improve the quality of site runoff, increase groundwater recharge, and
control runoff discharge rates. For pre-development and post-development discharge rates
see Appendices O & P.
3. Stream Channel Protection (Cpv), Overbank Flood Control (Qp), and Extreme Flood Control
Criteria (Qf)
Due to the minimal added impervious area and the increased stormwater infiltration, discharges
from the site will be reduced for all rainfall events. HydroCAD Version 10.0, a computer
modeling software package, was used to calculate the pre and post-development peak
discharge rates for the 1, 2, 10, and 100-year Type II storm. Hydrology calculations were
performed using the NRCS SCS and TR-55 methods. Time of Concentration calculations can
be seen in Appendix R. Rainfall date was obtained from the NYS DEC Stormwater
Management Design Manual. Albany County lies within the SCS Type II rainfall distribution.
The site was divided into natural drainage areas as seen in the Drainage Area Maps in
DG Suny Solar 1, LLC (DG Solar) shall be responsible for operation and maintenance of the
stormwater facilities located at the Selkirk Solar Project.
This Operation and Management (O&M) Plan provides guidance on the long term
maintenance of the stormwater facilities that have been constructed. Long term maintenance
is the critical component of a successful stormwater management practice. Implementation
of the O&M Plan is important for permanent BMPs to continue to function as designed.
Regular maintenance also provides opportunities for potential problems to be identified and
addressed before system failure.
The stormwater drainage system for the Selkirk Solar Project utilizes improved grass
groundcover over pervious areas of the site and a single type of permanent structural BMP,
grass-lined dry swales (Dry Swales). The Dry Swales on site are used to treat and infiltrate
stormwater runoff.
An enclosed fence will serve to prevent public access to the site. Inspection and maintenance
activities should be completed with safety precautions. Mowing of grass on Dry Swale side
slopes or any steep slopes should be done with care. Removal and disposal of built-up
sediment should be done in a fashion to avoid danger hazards.
Annual maintenance costs are estimated to be in the amount of $4,000 for mowing, $4,000
for inspections, and $2,000 for sediment removal and disposal, totaling about $10,000. It is
anticipated that profits gained from site operation will act as the funding source for
maintenance costs.
1.1 Diesel Fuel, Oil Hydraulic Fluids, Petroleum Products, and Other Chemicals
All chemical and petroleum product containers stored on the Site (excluding those contained
within vehicles and equipment) shall be provided with impermeable containment which will
hold at least 110% of the volume of the largest container, or 10% of the total volume of all
containers in the area, whichever is larger, without overflow from the containment area. All
chemicals and their containers shall be stored under a roofed area except for those chemicals
stored in containers of 100 gallon capacity or more, in which case a roof is not required.
Double-walled tanks satisfy this requirement.
All waste materials shall be collected and stored in a manner that will prevent materials from
entering watercourses, wetlands, or other off site areas. Waste containers of sufficient size
and number to contain wastes shall be provided. Wastes shall be placed in designated waste
containers on a daily basis. Material shall be regularly collected and disposed of offsite in a
manner consistent with all federal, state and local regulations. Waste materials for this project
may consist of earthen materials, granular materials, and any surplus materials.
During construction, all sanitary waste shall be collected in portable sanitary units, which
shall be positioned so that they are secure and will not be tipped or knocked over. These
Vehicles shall be inspected for mud, dirt, or debris prior to exiting the site and precautions
shall be taken as necessary to prevent tracking of excess materials from the site. Vehicle
use shall be restricted to properly designated exit points. Anti-tracking pads or turf mats shall
be installed to provide sediment removal prior to vehicle exit. Additional controls to remove
sediment from vehicle tires, such as wheel washing, rumble strips, and rattle plates shall be
used when necessary.
Where sediment track out has occurred, the deposited sediment must be removed by the
end of the same work day by sweeping, shoveling, or vacuuming. Hosing or sweeping
sediment into any surface water, storm drain structure, or stormwater conveyance is
prohibited, unless the storm drain or stormwater conveyance is connected to a sediment
basin, sediment trap, or other sediment control.
Dump trucks hauling material to or from the construction site shall be covered with a tarpaulin.
Wet dust suppression shall be used for any construction activity that causes airborne
particulates. No discharge of dust control water shall contain or cause a visible oil sheen,
floating solids, visible discoloration, or foaming in the receiving water.
All waters of the U.S. (as defined at 40 CFR Section 122.2) located on site or adjacent shall
be protected from discharge of solid materials, except those as authorized by a permit issued
under Section 404 of the Clean Water Act. Solid materials may include solid waste, building
materials, fill, sewage, sediment, or any other solid substance. Structural BMPs located
upgradient of waters of the U.S., such as sediment logs and sediment basins, may act to trap
or block solid materials from entering waters of the U.S. Proper waste disposal and sanitary
waste collection, as described in Part E, Section 1.3 and 1.4 shall also minimize the discharge
of solid materials to waters of the U.S. The Operator is responsible for preventing any
discharge of solid materials to waters of the U.S.
Discharges of fuels, oils, or other chemicals used in vehicle equipment operation and
maintenance are prohibited.
Project #20174543.001A Page 16 of 30 April 11, 2017
© 2017 Kleinfelder
If vehicle fueling and maintenance activities are to be completed onsite, a designated area
shall be established in a controlled and covered area, when possible, and marked on the
Selkirk Solar Project Construction Plans (Appendix H) by the Contractor. The area shall be
located away from surface waters and stormwater inlets or conveyances, and/or secondary
containment shall be provided (e.g., spill berms, decks, spill containment pallets). Drip pans
and absorbents shall be placed under or around vehicles.
The fueling and maintenance area shall have a spill kit that is located in a visible and
accessible location. Examples of typical items which should be included in a spill kit are
provided in this document. Spills or contaminated surfaces shall be cleaned up immediately,
using dry clean up measures where possible, and the source of the spill shall be eliminated.
Surfaces shall not be cleaned by hosing the area down.
Recycle oil and oily wastes shall be disposed in accordance with all federal, state, tribal, and
local requirements. If applicable, the Contractor shall comply with the Spill Prevention Control
and Countermeasures (SPCC) requirements in 40 CFR 112 and Section 311 of the Clean
Water Act.
1.9 Concrete Truck Washout Area and Containers used for Paint and other materials
The discharge of wastewater from washout of concrete, and washout and cleanout of stucco,
paint, form release oils, curing compounds, and other construction materials is generally
prohibited. However, if appropriate options for water handling are implemented to keep these
materials from reaching any drainage system or outlet to a surface water, washout/cleanout
may be allowed onsite, in accordance with all applicable local, state, or federal regulations
and permits.
A leak-proof pit or container shall be established in the washout area(s), to which washings
shall be directed. This area shall be used for washout containment and dewatering by
evaporation only. The pit shall not allow infiltration to occur. Prefabricated washout containers
are the preferable choice, although the Contractor may construct their own unit in the
depressed area by establishing a frame and lining the washout pit with plastic sheeting of at
least 10-mil thickness with no holes, tears, or seams. The pit should be sized properly, with
freeboard included to account for precipitation or run-on to the pit. The immediate area
leading to the washout shall have a layer of crushed stone to stabilize the ground for concrete
Project #20174543.001A Page 18 of 30 April 11, 2017
© 2017 Kleinfelder
truck traffic. To prevent clean water from entering the pit, the washout area should be covered
during precipitation events.
The washout area should be inspected weekly and the contents removed when they reach
50% of the capacity of the washout pit. Liquids may be vacuumed and disposed of in
accordance with local, state, and federal requirements. Hardened solids shall be removed
from the washout either as a whole or after being broken up. These solids may be removed
from the site and properly recycled or disposed of, or may be used onsite as appropriate, in
accordance with all applicable regulations and the project plans and specifications. Wastes
shall be handled in accordance with Part A, Section 1.10. If a plastic lined pit is used, plastic
must be inspected for holes or tears after every cleanout, since the washwater removal
process is likely to damage the plastic. The plastic liner must be replaced upon discovery of
such damage. Records of all cleanouts and methods of waste materials disposal shall be
maintained with the SWPCP and mentioned in the weekly construction site inspection forms.
The Contractor is responsible for proper waste handling and disposal and for following all
applicable regulations associated with this activity. EPA maintains a fact sheet regarding this
practice on its website (www.epa.gov) under the NPDES Stormwater Menu of BMPs fact
sheets.
The locations of material storage areas (i.e., for chemicals and other liquids) shall be noted
on the Selkirk Solar Project Construction Plans (Appendix H) by the Contractor. The
following good housekeeping and material management practices shall be followed to reduce
the risk of spills or other accidental exposure of hazardous materials to storm water runoff:
If an emergency spill or release occurs, site personnel will report the spill or release to the
Contractor’s Site Health and Safety Officer (SHSO), the Resident Engineer, and/or site
management and evacuate the area. All employees shall receive Awareness Level training
as part of their hazard communication training. Only employees trained at the First
Responder Operations Level of 29 CFR 1910.120(q) will be authorized to respond in a
defensive manner to emergency spills or releases of fuel and other materials.
If a spill occurs, the SHSO and/or site management shall be contacted and the SHSO and/or
site management with assistance from appropriately trained personnel will contain the spill.
If necessary the SHSO and/or site management will contact an emergency response
contractor and will also notify the Engineer and all other authorities and agencies in
accordance with state and local regulations. Absorptive materials and other supplies will be
used as needed to clean up and prevent the spill from spreading. The source of the spill shall
be eliminated immediately. Water shall not be used to wash the spill down. Recycle oil and
Any discharge, spillage, uncontrolled loss, seepage or filtration of oil or petroleum or chemical
liquids or solid, liquid or gaseous products or hazardous wastes, shall be immediately
reported to the Department of Environmental Conservation (DEC), NYS Spill Hotline
(1.800.457.7362). Information that shall be reported includes:
The location;
The quantity and type of substance, material or waste;
The date and the cause of the incident;
The name and address of the owner; and
The name and address of the person making the report and his relationship to the
owner.
The National Response Center (NRC) must be notified at 800-424-8802 where a leak, spill,
or other release containing a hazardous substance or oil in an amount equal to or in excess
of a reportable quantity established under either 40 CFR Part 110, 40 CFR Part 117, or 40
CFR Part 302 occurs during a 24-hour period. A description of the release, the circumstances
leading to the release, and the date of the release must be provided within 7 calendar days
of the knowledge of the release.
Training of staff and subcontractors in the basics of erosion and sediment control, good
housekeeping and pollution prevention will reinforce proper implementation of the SWPCP.
It is the responsibility of the Contractor to ensure that site personnel understand the
requirements of the SWPCP and their specific responsibilities.
Any training conducted should be documented in the SWPCP. Include dates, number of
attendees, subjects covered, and length of training.
This site is not located within a watershed with enhanced phosphorus removal standards.
In accordance with the State Environmental Quality Review Act, the Division of Historic
Preservation was queried to review the Selkirk Solar Farm Phase I Archaeological Survey with
respect to Historic/Cultural resource protection. The Division of Historic Preservation issued a
letter (Appendix M), dated February 24, 2017, requesting a short-term and long-term
avoidance plan for 3 archaeological areas of concern. Kleinfelder issued an avoidance plan,
dated March 7, 2017, including short-term and long-term avoidance measures (Appendix M).
The Division of Historic Preservation approved the avoidance measures and responded with a
letter of approval (Appendix M), dated March 15, 2017. The areas of concern are shown on
the Construction Plans (Appendix H) as “ENVIRONMENTAL AREAS OF CONCERN” per
Division of Historic Preservation request. See Appendix M for the Division of Historic
Preservation letters and the short-term and long-term avoidance plan. This plan is to be
followed throughout the life of the project.
Project #20174543.001A Page 22 of 30 April 11, 2017
© 2017 Kleinfelder
Stormwater Pollution Prevention Plan - Part H: Amendments
Whenever there is a change in design, construction, or operation at the construction site that
has or could have an effect on the discharge of pollutants; and
All SWPPP revisions shall be documented in the table located in Part B.1.
DG Solar will maintain a copy of this document, including the General Permit (GP-0- 15-002)
(Appendix C), NOI (Appendix A), NOI Acknowledgment Letter (Appendix B), MS4 SWPPP
Acceptance form (Appendix D), inspection reports (Appendix J), and all documentation
necessary to demonstrate eligibility with the GP-0- 15-002 permit at the construction site until all
disturbed areas have achieved final stabilization and the Notice of Termination (NOT) (Appendix
T) has been submitted to the Department. The documents will be maintained in a secure location,
such as a job trailer, on-site construction office, or mailbox with lock. The secure location will be
accessible during normal business hours to an individual performing a compliance inspection.
DG Solar will ensure that the provisions of the SWPPP are implemented from the commencement
of construction activity until all areas of disturbance have achieved final stabilization and the NOT
(Appendix T) has been submitted to the Department in accordance with Part V of the GP-0-15-
002 permit (Appendix C). This includes any changes made to the SWPPP pursuant to Part B of
this permit.
Prior to the commencement of construction activity, DG Solar will identify the contractor(s) and
subcontractor(s) that will be responsible for installing, constructing, repairing, replacing, inspecting
and maintaining the erosion and sediment control practices included in the SWPPP. DG Solar will
have each of the contractors and subcontractors identify at least one person from their company
that will be responsible for implementation of the SWPPP. This person shall be known as the trained
DG Solar will have each of the contractors and subcontractors identified above complete and sign
a copy of the Contractor Certification Statement Form in Appendix F.
The table, below, will identify the contractor(s) that will implement and maintain each control
measure identified in the SWPPP. The SWPPP shall be amended to identify any new contractor
that will implement and maintain a control measure.
A trained contractor, listed in Part D.3, will inspect erosion and sediment control practices and
pollution prevention measures being implemented within the active work area daily to ensure that
they are being maintained in effective operating condition at all times. If deficiencies are identified,
the trained contractor will begin implementing corrective actions within one business day and
complete the corrective actions in a reasonable time frame.
The qualified inspector will be a licensed professional engineer, a certified professional in erosion
and sediment control (CPESC), a registered landscape architect, or someone working under the
direct supervision of, and at the same company as, the licensed Professional Engineer or
Registered Landscape Architect, provided they have received four (4) hours of Department
endorsed training in proper erosion and sediment control principles from a Soil and Water
Conservation District, or other Department endorsed entity. Qualified Inspectors should be listed
in Part E.2.1.
Name:
Title:
Cell:
Responsibilities:
Name:
Title:
Cell:
Responsibilities:
Name:
Title:
Cell:
Responsibilities:
Name:
Title:
Cell:
Responsibilities:
*Note that the current members of the stormwater pollution prevention team are listed here
as of the writing of this plan. The plan will not be updated for the sole purpose of changing
an individual’s name serving on the team. An individual with the same title or from the same
department will serve in that capacity if a team member changes. The names will be
updated upon subsequent revisions of the plan that is required for material purposes.
DG Solar plans on disturbing greater than five acres of land at any one time. Proper erosion
controls will be implemented according to the Selkirk Solar Project Construction Plans (Appendix
H) in order to stabilize the site at all times. Because of this, DG Solar will have a qualified inspector
conduct two site inspections in accordance with Part E of this document every seven calendar
days for as long as greater than five acres of soil remain disturbed. Each inspection will be
separated by a minimum of two full calendar days. Once site stabilization reduces the disturbed
acreage to less than five acres, site inspection frequency will reduce to once every seven calendar
days.
In areas where soil disturbance activity has temporarily or permanently ceased, the application of
soil stabilization measures will be initiated by the end of the next business day and completed
within seven (7) days from the date the current soil disturbance activity ceased. The soil
stabilization measures will be in the form of temporary or permanent seeding as shown in the
Selkirk Solar Project Construction Plans (Appendix H).
If soil disturbance activities are temporarily suspended and temporary stabilization measures have
been applied to all disturbed areas, a SWPPP inspection shall be conducted at least once every
thirty calendar days. The owner shall inform the Town of Bethlehem in writing before reducing the
frequency of inspections.
If soil disturbance activities have been shut down with partial project completion, the qualified
inspector can stop conducting inspections if all areas disturbed as of the project shutdown date
have achieved final stabilization. The owner shall inform the Town of Bethlehem in writing prior to
site shutdown. If soil disturbance activities are not resumed within 2 years from the date of
shutdown, the owner or operator shall have the qualified inspector perform a final inspection and
certify that all disturbed areas have achieved final stabilization, and all temporary, structural
erosion and sediment control measures have been removed by signing the “Final Stabilization”
certification statement on the NOT (Appendix T) and submitting the NOT to the address listed in
Part II.A.1 of the GP-0-15-002 (Appendix C).
4. Inspection Requirements
At a minimum, the qualified inspector shall inspect all erosion and sediment control practices and
pollution prevention measures to ensure integrity and effectiveness, all post-construction
stormwater management practices under construction to ensure that they are constructed in
Inspection reports shall be completed for each inspection and made available onsite in
accordance with Part C of this document. Inspection reports may be round in Appendix
J. Inspections shall include, at minimum, the following:
c. A description of the weather and soil conditions (e.g. dry, wet, saturated) at the time
of the inspection;
d. A description of the condition of the runoff at all points of discharge from the
construction site. This shall include identification of any discharges of sediment from
the construction site. Include discharges from conveyance systems (i.e. pipes,
culverts, ditches, etc.) and overland flow;
f. Identification of all erosion and sediment control practices and pollution prevention
measures that need repair or maintenance;
g. Identification of all erosion and sediment control practices and pollution prevention
measures that were not installed properly or are not functioning as designed and need
to be reinstalled or replaced;
h. Description and sketch of areas with active soil disturbance activity, areas that have
been disturbed but are inactive at the time of the inspection, and areas that have been
stabilized (temporary and/or final) since the last inspection;
j. Corrective action(s) that must be taken to install, repair, replace or maintain erosion
and sediment control practices and pollution prevention measures; and to correct
deficiencies identified with the construction of the post-construction stormwater
management practice(s);
k. Identification and status of all corrective actions that were required by previous
inspection; and
Project #20174543.001A Page 29 of 30 April 11, 2017
© 2017 Kleinfelder
l. Digital photographs, with date stamp, that clearly show the condition of all practices
that have been identified as needing corrective actions. The qualified inspector shall
attach paper color copies of the digital photographs to the inspection report being
maintained onsite within seven (7) calendar days of the date of the inspection. The
qualified inspector shall also take digital photographs, with date stamp, that clearly
show the condition of the practice(s) after the corrective action has been completed.
The qualified inspector shall attach paper color copies of the digital photographs to the
inspection report that documents the completion of the corrective action work within
seven (7) calendar days of that inspection.
Within one business day of the completion of an inspection, the qualified inspector shall
notify the owner or operator and appropriate contractor or subcontractor identified in Part
D.3 of this document of any corrective actions that need to be taken. The contractor or
subcontractor shall begin implementing the corrective actions within one business day of
this notification and shall complete the corrective actions in a reasonable time frame.
In accordance with statute, regulations, and the terms and conditions of this permit, the Department
may suspend or revoke an owner’s or operator’s coverage under this permit at any time if the
Department determines that the SWPPP does not meet the permit requirements. Upon a finding
of significant non-compliance with the practices described in the SWPPP or violation of this permit,
the Department may order an immediate stop to all activity at the site until the non-compliance is
remedied. The stop work order shall be in writing, describe the non-compliance in detail, and be
sent to the owner or operator.
NOTICE OF INTENT
________________________________________________________________________________
0644089821
NOTICE OF INTENT
New York State Department of Environmental Conservation
Division of Water
625 Broadway, 4th Floor NYR
(for DEC use only)
Albany, New York 12233-3505
Stormwater Discharges Associated with Construction Activity Under State
Pollutant Discharge Elimination System (SPDES) General Permit # GP-0-15-002
All sections must be completed unless otherwise noted. Failure to complete all items may
result in this form being returned to you, thereby delaying your coverage under this
General Permit. Applicants must read and understand the conditions of the permit and
prepare a Stormwater Pollution Prevention Plan prior to submitting this NOI. Applicants
are responsible for identifying and obtaining other DEC permits that may be required.
-IMPORTANT-
RETURN THIS FORM TO THE ADDRESS ABOVE
OWNER/OPERATOR MUST SIGN FORM
Owner/Operator Information
FED TAX ID
4 7 - 4 9 0 6 2 2 8 (not required for individuals)
Page 1 of 14
6401089828
Project/Site Name
S E L K I R K S O L A R F A R M
Side of Street
North South East West
1. Provide the Geographic Coordinates for the project site in NYTM Units. To do this you
must go to the NYSDEC Stormwater Interactive Map on the DEC website at:
www.dec.ny.gov/imsmaps/stormwater/viewer.htm
Zoom into your Project Location such that you can accurately click on the centroid of
your site. Once you have located your project site, go to the tool boxes on the top and
choose "i"(identify). Then click on the center of your site and a new window containing
the X, Y coordinates in UTM will pop up. Transcribe these coordinates into the boxes
below. For problems with the interactive map use the help function.
X Coordinates (Easting) Y Coordinates (Northing)
5 9 6 8 4 0 4 7 1 1 5 1 9
New Construction
Page 2 of 14
4107089829
3. Select the predominant land use for both pre and post development conditions.
SELECT ONLY ONE CHOICE FOR EACH
Pre-Development Post-Development
Existing Land Use Future Land Use
FOREST SINGLE FAMILY HOME Number of Lots
PASTURE/OPEN LAND SINGLE FAMILY SUBDIVISION
CULTIVATED LAND TOWN HOME RESIDENTIAL
SINGLE FAMILY HOME MULTIFAMILY RESIDENTIAL
SINGLE FAMILY SUBDIVISION INSTITUTIONAL/SCHOOL
TOWN HOME RESIDENTIAL INDUSTRIAL
MULTIFAMILY RESIDENTIAL COMMERCIAL
INSTITUTIONAL/SCHOOL MUNICIPAL
INDUSTRIAL ROAD/HIGHWAY
COMMERCIAL RECREATIONAL/SPORTS FIELD
ROAD/HIGHWAY BIKE PATH/TRAIL
RECREATIONAL/SPORTS FIELD LINEAR UTILITY (water, sewer, gas, etc.)
BIKE PATH/TRAIL PARKING LOT
LINEAR UTILITY CLEARING/GRADING ONLY
PARKING LOT DEMOLITION, NO REDEVELOPMENT
OTHER WELL DRILLING ACTIVITY *(Oil, Gas, etc.)
OTHER
S O L A R F A R M
*Note: for gas well drilling, non-high volume hydraulic fractured wells only
5. Do you plan to disturb more than 5 acres of soil at any one time? Yes No
Page 3 of 14
8600089821
9. Identify the nearest surface waterbody(ies) to which construction site runoff will
discharge.
Name
W E T L A N D
Page 4 of 14
6403089820
16. What is the name of the municipality/entity that owns the separate storm sewer
system?
17. Does any runoff from the site enter a sewer classified
Yes No Unknown
as a Combined Sewer?
21. Has the required Erosion and Sediment Control component of the
SWPPP been developed in conformance with the current NYS Yes No
Standards and Specifications for Erosion and Sediment Control
(aka Blue Book)?
Page 5 of 14
0251089825
24. The Stormwater Pollution Prevention Plan (SWPPP) was prepared by:
SWPPP Preparer
K L E I N F E L D E R
Contact Name (Last, Space, First)
W E N D E L B U R G , J O H N
Mailing Address
3 0 0 W E S T A G E B U S I N E S S C E N T E R D R I V E , # 4 0 7
City
F I S H K I L L
State Zip
N Y 1 2 5 2 4 -
Phone Fax
8 4 5 - 2 3 1 - 2 5 0 0 8 4 5 - 8 9 7 - 2 6 3 6
Email
J W E N D E L B U R G @ K L E I N F E L D E R .C O M
I hereby certify that the Stormwater Pollution Prevention Plan (SWPPP) for
this project has been prepared in accordance with the terms and conditions of
the GP-0-15-002. Furthermore, I understand that certifying false, incorrect
or inaccurate information is a violation of this permit and the laws of the
State of New York and could subject me to criminal, civil and/or
administrative proceedings.
First Name MI
J O H N
Last Name
W E N D E L B U R G
Signature
Date
0 4 / 1 1 / 2 0 1 7
Page 6 of 14
0005089822
26. Select all of the erosion and sediment control practices that will be
employed on the project site:
Page 7 of 14
0182089828
27. Identify all site planning practices that were used to prepare the final site
plan/layout for the project.
27a. Indicate which of the following soil restoration criteria was used to address the
requirements in Section 5.1.6("Soil Restoration") of the Design Manual
(2010 version).
All disturbed areas will be restored in accordance with the Soil
Restoration requirements in Table 5.3 of the Design Manual (see page 5-22).
28. Provide the total Water Quality Volume (WQv) required for this project (based on
final site plan/layout).
Total WQv Required
. 3 3 7 acre-feet
Also, provide in Table 1 the total impervious area that contributes runoff to each
technique/practice selected. For the Area Reduction Techniques, provide the total
contributing area (includes pervious area) and, if applicable, the total impervious
area that contributes runoff to the technique/practice.
Note: Redevelopment projects shall use Tables 1 and 2 to identify the SMPs used
to treat and/or reduce the WQv required. If runoff reduction techniques will not
be used to reduce the required WQv, skip to question 33a after identifying the
SMPs.
Page 8 of 14
7738089822 Table 1 - Runoff Reduction (RR) Techniques
and Standard Stormwater Management
Practices (SMPs)
Total Contributing Total Contributing
Area (acres) Impervious Area(acres)
RR Techniques (Area Reduction)
Conservation of Natural Areas (RR-1) ... . and/or
0 .
Sheetflow to Riparian
Buffers/Filters Strips (RR-2) .......... 3 9 . 9 0 and/or . 3 7
Standard SMPs
Hydrodynamic ............................................... .
Wet Vault .................................................. .
Media Filter ............................................... .
Other .................. .
Provide the name and manufacturer of the Alternative SMPs (i.e.
proprietary practice(s)) being used for WQv treatment.
Name
Manufacturer
Note: Redevelopment projects which do not use RR techniques, shall
use questions 28, 29, 33 and 33a to provide SMPs used, total
WQv required and total WQv provided for the project.
30. Indicate the Total RRv provided by the RR techniques (Area/Volume Reduction) and
Standard SMPs with RRv capacity identified in question 29.
. 2 8 1 acre-feet
31. Is the Total RRv provided (#30) greater than or equal to the
total WQv required (#28).
Yes No
If Yes, go to question 36.
If No, go to question 32.
. 0 4 4 acre-feet
32a. Is the Total RRv provided (#30) greater than or equal to the
Minimum RRv Required (#32)? Yes No
Page 10 of 14
1766089827
33. Identify the Standard SMPs in Table 1 and, if applicable, the Alternative SMPs in
Table 2 that were used to treat the remaining
total WQv(=Total WQv Required in 28 - Total RRv Provided in 30).
Also, provide in Table 1 and 2 the total impervious area that contributes runoff
to each practice selected.
Note: Use Tables 1 and 2 to identify the SMPs used on Redevelopment projects.
33a. Indicate the Total WQv provided (i.e. WQv treated) by the SMPs
identified in question #33 and Standard SMPs with RRv Capacity identified
in question 29.
WQv Provided
. 0 5 6 acre-feet
Note: For the standard SMPs with RRv capacity, the WQv provided by each practice
= the WQv calculated using the contributing drainage area to the practice
- RRv provided by the practice. (See Table 3.5 in Design Manual)
34. Provide the sum of the Total RRv provided (#30) and
the WQv provided (#33a). . 3 3 7
35. Is the sum of the RRv provided (#30) and the WQv provided
(#33a) greater than or equal to the total WQv required (#28)? Yes No
36. Provide the total Channel Protection Storage Volume (CPv) required and
provided or select waiver (36a), if applicable.
. acre-feet . acre-feet
36a. The need to provide channel protection has been waived because:
Site discharges directly to tidal waters
or a fifth order or larger stream.
Reduction of the total CPv is achieved on site
through runoff reduction techniques or infiltration systems.
37. Provide the Overbank Flood (Qp) and Extreme Flood (Qf) control criteria or
select waiver (37a), if applicable.
Total Overbank Flood Control Criteria (Qp)
Pre-Development Post-development
5 9 . 7 1 CFS 2 9 . 6 4 CFS
Page 11 of 14
1310089822
37a. The need to meet the Qp and Qf criteria has been waived because:
Site discharges directly to tidal waters
or a fifth order or larger stream.
Downstream analysis reveals that the Qp and Qf
controls are not required
38. Has a long term Operation and Maintenance Plan for the
post-construction stormwater management practice(s) been Yes No
developed?
If Yes, Identify the entity responsible for the long term
Operation and Maintenance
D G S U N Y S O L A R 1 , L L C
39. Use this space to summarize the specific site limitations and justification
for not reducing 100% of WQv required(#28). (See question 32a)
This space can also be used for other pertinent project information.
88 percent of the site is classified as Hydrologic Soil Group C. Due to the slow infiltration rate, a lower WQv
credit is given for the Dry Swale design. The existing cultivated land cover will be seeded and stabilized with
permanent grass cover. The grass cover increases infiltration improving water quality, increasing important
groundwater recharge volumes, and controlling runoff discharge quantities. Special consideration has been
given to the placement of the proposed Dry Swales. The swales will be located immediately adjacent the
proposed access road, which will be sloped to shed water towards them, providing the ideal runoff treatment, at
the source.
Despite not meeting the optimum RRv due to slow infiltration rates, it is anticipated that the combination of
improved grass cover and implemented Dry Swales will improve runoff quality and quantity from the
pre-development to the post-development phase. For water quantity calculations, please see the SWPPP,
Appendices O and P.
Page 12 of 14
4285089826
40. Identify other DEC permits, existing and new, that are required for this
project/facility.
Air Pollution Control
Coastal Erosion
Hazardous Waste
Solid Waste
Dam Safety
Water Supply
Freshwater Wetlands/Article 24
Tidal Wetlands
Individual SPDES
SPDES Multi-Sector GP
Other
None
43. Has the "MS4 SWPPP Acceptance" form been signed by the principal
executive officer or ranking elected official and submitted along Yes No
with this NOI?
44. If this NOI is being submitted for the purpose of continuing or transferring
coverage under a general permit for stormwater runoff from construction
activities, please indicate the former SPDES number assigned.
Page 13 of 14
3547089826
Owner/Operator Certification
I have read or been advised of the permit conditions and believe that I understand them. I also
understand that, under the terms of the permit, there may be reporting requirements. I hereby certify
that this document and the corresponding documents were prepared under my direction or supervision. I am
aware that there are significant penalties for submitting false information, including the possibility of
fine and imprisonment for knowing violations. I further understand that coverage under the general permit
will be identified in the acknowledgment that I will receive as a result of submitting this NOI and can
be as long as sixty (60) business days as provided for in the general permit. I also understand that, by
submitting this NOI, I am acknowledging that the SWPPP has been developed and will be implemented as the
first element of construction, and agreeing to comply with all the terms and conditions of the general
permit for which this NOI is being submitted.
Print First Name MI
M A T T H E W
Print Last Name
H A N D E L
Owner/Operator Signature
Date
/ /
Page 14 of 14
APPENDIX B
________________________________________________________________________________
APPENDIX C
________________________________________________________________________________
WYORK Department of.
TEOF
ORfUNITY Environmental
Conservation
From
CONSTRUCTION ACTIVITY
Effective Date: January 29, 2015 Expiration Date: January 28, 2020
Modification Date:
July 14, 2015 - Correction of typographical error in definition of "New Development",
Appendix A
John J. Ferguson
Chief Permit Administrator
~gd;J--
Address: NYS DEC
Division of Environmental Permits
625 Broadway, 4th Floor
Albany, N.Y. 12233-1750
PREFACE
Pursuant to Section 402 of the Clean Water Act (“CWA”), stormwater discharges
from certain construction activities are unlawful unless they are authorized by a National
Pollutant Discharge Elimination System (“NPDES”) permit or by a state permit program.
New York’s State Pollutant Discharge Elimination System (“SPDES”) is a NPDES-
approved program with permits issued in accordance with the Environmental
Conservation Law (“ECL”).
This general permit (“permit”) is issued pursuant to Article 17, Titles 7, 8 and
Article 70 of the ECL. An owner or operator may obtain coverage under this permit by
submitting a Notice of Intent ("NOI") to the Department. Copies of this permit and the NOI
for New York are available by calling (518) 402-8109 or at any New York State
Department of Environmental Conservation (“the Department”) regional office (see
Appendix G).They are also available on the Department’s website at:
http://www.dec.ny.gov/
*Note: The italicized words/phrases within this permit are defined in Appendix A.
I
NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION
SPDES GENERAL PERMIT FOR STORMWATER DISCHARGES
FROM CONSTRUCTION ACTIVITIES
II
Q. Penalties for Falsification of Forms and Reports ................................................. 36
R. Other Permits ...................................................................................................... 36
APPENDIX A .................................................................................................................... 37
APPENDIX B .................................................................................................................... 44
APPENDIX C ................................................................................................................... 46
APPENDIX D ................................................................................................................... 52
APPENDIX E .................................................................................................................... 53
APPENDIX F .................................................................................................................... 55
III
(Part I)
Part I. PERMIT COVERAGE AND LIMITATIONS
A. Permit Application
This permit authorizes stormwater discharges to surface waters of the State from
the following construction activities identified within 40 CFR Parts 122.26(b)(14)(x),
122.26(b)(15)(i) and 122.26(b)(15)(ii), provided all of the eligibility provisions of this
permit are met:
Construction activities involving soil disturbances of less than one (1) acre
where the Department has determined that a SPDES permit is required for
stormwater discharges based on the potential for contribution to a violation
of a water quality standard or for significant contribution of pollutants to
surface waters of the State.
(i) Minimize soil erosion through application of runoff control and soil
stabilization control measure to minimize pollutant discharges;
(vi) Provide and maintain natural buffers around surface waters, direct
stormwater to vegetated areas and maximize stormwater
infiltration to reduce pollutant discharges, unless infeasible;
(iii) Prevent the discharge of pollutants from spills and leaks and
implement chemical spill and leak prevention and response
procedures.
(i) Runoff Reduction Volume (“RRv”): Reduce the total Water Quality
Volume (“WQv”) by application of RR techniques and standard
SMPs with RRv capacity. The total WQv shall be calculated in
accordance with the criteria in Section 4.2 of the Design Manual.
(i) Runoff Reduction Volume (RRv): Reduce the total Water Quality
Volume (WQv) by application of RR techniques and standard
SMPs with RRv capacity. The total WQv is the runoff volume from
the 1-year, 24 hour design storm over the post-developed
watershed and shall be calculated in accordance with the criteria
in Section 10.3 of the Design Manual.
(iii) Overbank Flood Control Criteria (Qp): Not required if there are no
changes to hydrology that increase the discharge rate from the
project site.
7
(Part I.C.2.c.iv)
(iv) Extreme Flood Control Criteria (Qf): Not required if there are no
changes to hydrology that increase the discharge rate from the
project site.
There shall be no residue from oil and floating substances, nor visible oil
film, nor globules of grease.
If there is evidence indicating that despite compliance with the terms and conditions
of this general permit it is demonstrated that the stormwater discharges authorized
by this permit are causing or contributing to a violation of water quality standards, or
8
(Part I.D)
if the Department determines that a modification of the permit is necessary to
prevent a violation of water quality standards, the authorized discharges will no
longer be eligible for coverage under this permit. The Department may require the
owner or operator to obtain an individual SPDES permit to continue discharging.
F. Activities Which Are Ineligible for Coverage Under This General Permit
All of the following are not authorized by this permit:
9
(Part I.F)
Discharges after construction activities have been completed and the site
has undergone final stabilization;
Discharges that are mixed with sources of non-stormwater other than those
expressly authorized under subsection E.3. of this Part and identified in the
SWPPP required by this permit;
b. Which disturb one or more acres of land with no existing impervious cover;
and
c. Which are undertaken on land with a Soil Slope Phase that is identified as
an E or F, or the map unit name is inclusive of 25% or greater slope, on
the United States Department of Agriculture (“USDA”) Soil Survey for the
County where the disturbance will occur.
b. Which disturb two or more acres of land with no existing impervious cover;
and
c. Which are undertaken on land with a Soil Slope Phase that is identified as
an E or F, or the map unit name is inclusive of 25% or greater slope, on
the USDA Soil Survey for the County where the disturbance will occur.
10
(Part I.F.8)
b. DEC consultation form sent to OPRHP, and copied to the NYS DEC
Agency Historic Preservation Officer (APO), and
(i) the State Environmental Quality Review (SEQR) Environmental
Assessment Form (EAF) with a negative declaration or the
Findings Statement, with documentation of OPRHP’s agreement
with the resolution; or
(ii) documentation from OPRHP that the construction activity will
result in No Impact; or
(iii) documentation from OPRHP providing a determination of No
Adverse Impact; or
(iv) a Letter of Resolution signed by the owner/operator, OPRHP and
the DEC APO which allows for this construction activity to be
eligible for coverage under the general permit in terms of the State
Historic Preservation Act (SHPA); or
d. Documentation that:
(i) SHPA Section 14.09 has been completed by NYS DEC or another
state agency.
NOTICE OF INTENT
NYS DEC, Bureau of Water Permits
625 Broadway, 4th Floor
Albany, New York 12233-3505
The paper version of the NOI shall be signed in accordance with Part VII.H.
of this permit and submitted to the address in Part II.A.1.
12
(Part II.A.2)
The requirement for an owner or operator to have its SWPPP reviewed and
accepted by the MS4 prior to submitting the NOI to the Department does
not apply to an owner or operator that is obtaining permit coverage in
accordance with the requirements in Part II.E. (Change of Owner or
Operator) or where the owner or operator of the construction activity is the
regulated, traditional land use control MS4.
The owner or operator shall have the SWPPP preparer sign the “SWPPP
Preparer Certification” statement on the NOI prior to submitting the form to
the Department.
As of the date the NOI is submitted to the Department, the owner or operator
shall make the NOI and SWPPP available for review and copying in
accordance with the requirements in Part VII.F. of this permit.
B. Permit Authorization
Authorization to discharge under this permit will be effective when the owner
or operator has satisfied all of the following criteria:
An owner or operator that has satisfied the requirements of Part II.B.2 above
13
(Part II.B.3)
will be authorized to discharge stormwater from their construction activity in
accordance with the following schedule:
(i) Five (5) business days from the date the Department receives a
complete electronic version of the NOI (eNOI) for construction
activities with a SWPPP that has been prepared in conformance
with the design criteria in the technical standard referenced in Part
III.B.1 and the performance criteria in the technical standard
referenced in Parts III.B., 2 or 3, for construction activities that
require post-construction stormwater management practices
pursuant to Part III.C.; or
(ii) Sixty (60) business days from the date the Department receives a
complete NOI (electronic or paper version) for construction
activities with a SWPPP that has not been prepared in
conformance with the design criteria in technical standard
referenced in Part III.B.1. or, for construction activities that require
post-construction stormwater management practices pursuant to
Part III.C., the performance criteria in the technical standard
referenced in Parts III.B., 2 or 3, or;
(iii) Ten (10) business days from the date the Department receives a
complete paper version of the NOI for construction activities with
a SWPPP that has been prepared in conformance with the design
criteria in the technical standard referenced in Part III.B.1 and the
performance criteria in the technical standard referenced in Parts
III.B., 2 or 3, for construction activities that require post-
construction stormwater management practices pursuant to Part
III.C.
(i) Five (5) business days from the date the Department receives both
a complete electronic version of the NOI (eNOI) and signed “MS4
SWPPP Acceptance” form, or
(ii) Ten (10) business days from the date the Department receives
both a complete paper version of the NOI and signed “MS4
SWPPP Acceptance” form.
14
(Part II.B.4)
under this permit if the Department determines that the SWPPP does not
meet the permit requirements. In accordance with statute, regulation, and
the terms and conditions of this permit, the Department may deny coverage
under this permit and require submittal of an application for an individual
SPDES permit based on a review of the NOI or other information pursuant
to Part II.
The owner or operator shall ensure that the provisions of the SWPPP are
implemented from the commencement of construction activity until all areas
of disturbance have achieved final stabilization and the Notice of
Termination (“NOT”) has been submitted to the Department in accordance
with Part V. of this permit. This includes any changes made to the SWPPP
pursuant to Part III.A.4. of this permit.
The owner or operator shall maintain a copy of the General Permit (GP-0-
15-002), NOI, NOI Acknowledgment Letter, SWPPP, MS4 SWPPP
Acceptance form, inspection reports, and all documentation necessary to
demonstrate eligibility with this permit at the construction site until all
disturbed areas have achieved final stabilization and the NOT has been
submitted to the Department. The documents must be maintained in a
secure location, such as a job trailer, on-site construction office, or mailbox
with lock. The secure location must be accessible during normal business
hours to an individual performing a compliance inspection.
c. The owner or operator shall prepare a phasing plan that defines maximum
disturbed area per phase and shows required cuts and fills.
d. The owner or operator shall install any additional site specific practices
needed to protect water quality.
In accordance with statute, regulations, and the terms and conditions of this
permit, the Department may suspend or revoke an owner’s or operator’s
coverage under this permit at any time if the Department determines that
the SWPPP does not meet the permit requirements. Upon a finding of
significant non-compliance with the practices described in the SWPPP or
violation of this permit, the Department may order an immediate stop to all
activity at the site until the non-compliance is remedied. The stop work order
shall be in writing, describe the non-compliance in detail, and be sent to the
owner or operator.
16
(Part II.D)
D. Permit Coverage for Discharges Authorized Under GP-0-10-001
Permit coverage for the new owner or operator will be effective as of the date
the Department receives a complete NOI, provided the original owner or
operator was not subject to a sixty (60) business day authorization period that
has not expired as of the date the Department receives the NOI from the new
owner or operator.
17
(Part III)
Part III. STORMWATER POLLUTION PREVENTION PLAN (SWPPP)
The SWPPP shall describe the erosion and sediment control practices and
where required, post-construction stormwater management practices that
will be used and/or constructed to reduce the pollutants in stormwater
discharges and to assure compliance with the terms and conditions of this
permit. In addition, the SWPPP shall identify potential sources of pollution
which may reasonably be expected to affect the quality of stormwater
discharges.
The owner or operator must keep the SWPPP current so that it at all times
accurately documents the erosion and sediment controls practices that are
being used or will be used during construction, and all post-construction
stormwater management practices that will be constructed on the site. At a
minimum, the owner or operator shall amend the SWPPP:
The Department may notify the owner or operator at any time that the
18
(Part III.A.5)
SWPPP does not meet one or more of the minimum requirements of this
permit. The notification shall be in writing and identify the provisions of the
SWPPP that require modification. Within fourteen (14) calendar days of
such notification, or as otherwise indicated by the Department, the owner
or operator shall make the required changes to the SWPPP and submit
written notification to the Department that the changes have been made. If
the owner or operator does not respond to the Department’s comments in
the specified time frame, the Department may suspend the owner’s or
operator’s coverage under this permit or require the owner or operator to
obtain coverage under an individual SPDES permit in accordance with Part
II.C.4. of this permit.
"I hereby certify under penalty of law that I understand and agree to
comply with the terms and conditions of the SWPPP and agree to
implement any corrective actions identified by the qualified inspector
during a site inspection. I also understand that the owner or operator
must comply with the terms and conditions of the most current version
of the New York State Pollutant Discharge Elimination System
("SPDES") general permit for stormwater discharges from construction
activities and that it is unlawful for any person to cause or contribute
to a violation of water quality standards. Furthermore, I am aware that
there are significant penalties for submitting false information, that I do
not believe to be true, including the possibility of fine and imprisonment
for knowing violations"
(v) Identification of any sizing criteria that is not required based on the
requirements included in Part I.C. of this permit; and
23
(Part IV)
Part IV. INSPECTION AND MAINTENANCE REQUIREMENTS
The terms of this permit shall not be construed to prohibit the State of New
York from exercising any authority pursuant to the ECL, common law or
federal law, or prohibit New York State from taking any measures, whether
civil or criminal, to prevent violations of the laws of the State of New York,
or protect the public health and safety and/or the environment.
For construction sites where soil disturbance activities have been shut down
with partial project completion, the trained contractor can stop conducting
the maintenance inspections if all areas disturbed as of the project
shutdown date have achieved final stabilization and all post-construction
stormwater management practices required for the completed portion of the
project have been constructed in conformance with the SWPPP and are
operational.
24
(Part IV.C)
The owner or operator shall have a qualified inspector conduct site inspections in
conformance with the following requirements:
[Note: The trained contractor identified in Part III.A.6. and IV.B. of this permit
cannot conduct the qualified inspector site inspections unless they meet the
qualified inspector qualifications included in Appendix A. In order to perform these
inspections, the trained contractor would have to be a:
- licensed Professional Engineer,
- Certified Professional in Erosion and Sediment Control (CPESC),
- Registered Landscape Architect, or
- someone working under the direct supervision of, and at the same company
as, the licensed Professional Engineer or Registered Landscape Architect,
provided they have received four (4) hours of Department endorsed training
in proper erosion and sediment control principles from a Soil and Water
Conservation District, or other Department endorsed entity].
a. For construction sites where soil disturbance activities are on-going, the
qualified inspector shall conduct a site inspection at least once every
seven (7) calendar days.
b. For construction sites where soil disturbance activities are on-going and
25
(Part IV.C.2.b)
the owner or operator has received authorization in accordance with Part
II.C.3 to disturb greater than five (5) acres of soil at any one time, the
qualified inspector shall conduct at least two (2) site inspections every
seven (7) calendar days. The two (2) inspections shall be separated by a
minimum of two (2) full calendar days.
d. For construction sites where soil disturbance activities have been shut
down with partial project completion, the qualified inspector can stop
conducting inspections if all areas disturbed as of the project shutdown
date have achieved final stabilization and all post-construction stormwater
management practices required for the completed portion of the project
have been constructed in conformance with the SWPPP and are
operational. The owner or operator shall notify the DOW Water (SPDES)
Program contact at the Regional Office (see contact information in
Appendix F) or, in areas under the jurisdiction of a regulated, traditional
land use control MS4, the regulated, traditional land use control MS4
(provided the regulated, traditional land use control MS4 is not the owner
or operator of the construction activity) in writing prior to the shutdown. If
soil disturbance activities are not resumed within 2 years from the date of
shutdown, the owner or operator shall have the qualified inspector perform
a final inspection and certify that all disturbed areas have achieved final
stabilization, and all temporary, structural erosion and sediment control
measures have been removed; and that all post-construction stormwater
management practices have been constructed in conformance with the
SWPPP by signing the “Final Stabilization” and “Post-Construction
Stormwater Management Practice” certification statements on the NOT.
The owner or operator shall then submit the completed NOT form to the
address in Part II.A.1 of this permit.
At a minimum, the qualified inspector shall inspect all erosion and sediment
control practices and pollution prevention measures to ensure integrity and
effectiveness, all post-construction stormwater management practices
under construction to ensure that they are constructed in conformance with
the SWPPP, all areas of disturbance that have not achieved final
stabilization, all points of discharge to natural surface waterbodies located
within, or immediately adjacent to, the property boundaries of the
construction site, and all points of discharge from the construction site.
c. A description of the weather and soil conditions (e.g. dry, wet, saturated)
at the time of the inspection;
h. Description and sketch of areas with active soil disturbance activity, areas
that have been disturbed but are inactive at the time of the inspection, and
areas that have been stabilized (temporary and/or final) since the last
inspection;
27
(Part IV.C.4.i)
i. Current phase of construction of all post-construction stormwater
management practices and identification of all construction that is not in
conformance with the SWPPP and technical standards;
l. Digital photographs, with date stamp, that clearly show the condition of all
practices that have been identified as needing corrective actions. The
qualified inspector shall attach paper color copies of the digital
photographs to the inspection report being maintained onsite within seven
(7) calendar days of the date of the inspection. The qualified inspector
shall also take digital photographs, with date stamp, that clearly show the
condition of the practice(s) after the corrective action has been completed.
The qualified inspector shall attach paper color copies of the digital
photographs to the inspection report that documents the completion of the
corrective action work within seven (7) calendar days of that inspection.
28
(Part V.A.2)
An owner or operator may terminate coverage when one or more the
following conditions have been met:
For construction activities meeting subdivision 2a. or 2b. of this Part, the
owner or operator shall have the qualified inspector perform a final site
inspection prior to submitting the NOT. The qualified inspector shall, by
signing the “Final Stabilization” and “Post-Construction Stormwater
Management Practice certification statements on the NOT, certify that all
the requirements in Part V.A.2.a. or b. of this permit have been achieved.
29
(Part V.A.5)
For construction activities that require post-construction stormwater
management practices and meet subdivision 2a. of this Part, the owner or
operator must, prior to submitting the NOT, ensure one of the following:
A. Record Retention
B. Addresses
With the exception of the NOI, NOT, and MS4 SWPPP Acceptance form (which
must be submitted to the address referenced in Part II.A.1 of this permit), all written
correspondence requested by the Department, including individual permit
applications, shall be sent to the address of the appropriate DOW Water (SPDES)
Program contact at the Regional Office listed in Appendix F.
30
(Part VII)
Part VII. STANDARD PERMIT CONDITIONS
A. Duty to Comply
The owner or operator must comply with all conditions of this permit. All contractors
and subcontractors associated with the project must comply with the terms of the
SWPPP. Any non-compliance with this permit constitutes a violation of the Clean
Water Act (CWA) and the ECL and is grounds for an enforcement action against the
owner or operator and/or the contractor/subcontractor; permit revocation,
suspension or modification; or denial of a permit renewal application. Upon a finding
of significant non-compliance with this permit or the applicable SWPPP, the
Department may order an immediate stop to all construction activity at the site until
the non-compliance is remedied. The stop work order shall be in writing, shall
describe the non-compliance in detail, and shall be sent to the owner or operator.
This permit expires five (5) years from the effective date. If a new general permit is
not issued prior to the expiration of this general permit, an owner or operator with
coverage under this permit may continue to operate and discharge in accordance
with the terms and conditions of this general permit, if it is extended pursuant to the
State Administrative Procedure Act and 6 NYCRR Part 621, until a new general
permit is issued.
C. Enforcement
31
(Part VII.E)
E. Duty to Mitigate
The owner or operator and its contractors and subcontractors shall take all
reasonable steps to minimize or prevent any discharge in violation of this permit
which has a reasonable likelihood of adversely affecting human health or the
environment.
The owner or operator shall furnish to the Department, within a reasonable specified
time period of a written request, all documentation necessary to demonstrate
eligibility and any information to determine compliance with this permit or to
determine whether cause exists for modifying or revoking this permit, or suspending
or denying coverage under this permit, in accordance with the terms and conditions
of this permit. The NOI, SWPPP and inspection reports required by this permit are
public documents that the owner or operator must make available for review and
copying by any person within five (5) business days of the owner or operator
receiving a written request by any such person to review these documents. Copying
of documents will be done at the requester’s expense.
G. Other Information
When the owner or operator becomes aware that they failed to submit any relevant
facts, or submitted incorrect information in the NOI or in any of the documents
required by this permit , or have made substantive revisions to the SWPPP (e.g. the
scope of the project changes significantly, the type of post-construction stormwater
management practice(s) changes, there is a reduction in the sizing of the post-
construction stormwater management practice, or there is an increase in the
disturbance area or impervious area), which were not reflected in the original NOI
submitted to the Department, they shall promptly submit such facts or information to
the Department using the contact information in Part II.A. of this permit. Failure of
the owner or operator to correct or supplement any relevant facts within five (5)
business days of becoming aware of the deficiency shall constitute a violation of this
permit.
H. Signatory Requirements
32
(Part VII.H.1.a.i)
corporation in charge of a principal business function, or any other
person who performs similar policy or decision-making functions
for the corporation; or
c. For a municipality, State, Federal, or other public agency these forms shall
be signed by either a principal executive officer or ranking elected official.
For purposes of this section, a principal executive officer of a Federal
agency includes:
c. The written authorization shall include the name, title and signature of the
authorized representative and be attached to the SWPPP.
I. Property Rights
The issuance of this permit does not convey any property rights of any sort, nor
any exclusive privileges, nor does it authorize any injury to private property nor
any invasion of personal rights, nor any infringement of Federal, State or local
laws or regulations. Owners or operators must obtain any applicable
conveyances, easements, licenses and/or access to real property prior to
commencing construction activity.
J. Severability
The provisions of this permit are severable, and if any provision of this permit, or
the application of any provision of this permit to any circumstance, is held invalid,
the application of such provision to other circumstances, and the remainder of
this permit shall not be affected thereby.
34
(Part VII.K.1)
discharge under this general permit shall be terminated. Applications must
be submitted to the appropriate Permit Administrator at the Regional Office.
The Department may grant additional time upon demonstration, to the
satisfaction of the Department, that additional time to apply for an
alternative authorization is necessary or where the Department has not
provided a permit determination in accordance with Part 621 of this Title.
The owner or operator shall at all times properly operate and maintain all facilities
and systems of treatment and control (and related appurtenances) which are
installed or used by the owner or operator to achieve compliance with the conditions
of this permit and with the requirements of the SWPPP.
Have access to and copy at reasonable times, any records that must be
kept under the conditions of this permit; and
35
(Part VII.N)
N. Permit Actions
This permit may, at any time, be modified, suspended, revoked, or renewed by the
Department in accordance with 6 NYCRR Part 621. The filing of a request by the
owner or operator for a permit modification, revocation and reissuance, termination,
a notification of planned changes or anticipated noncompliance does not limit,
diminish and/or stay compliance with any terms of this permit.
O. Definitions
P. Re-Opener Clause
In accordance with 6NYCRR Part 750-2.4 and 750-2.5, any person who knowingly
makes any false material statement, representation, or certification in any
application, record, report or other document filed or required to be maintained under
this permit, including reports of compliance or noncompliance shall, upon conviction,
be punished in accordance with ECL §71-1933 and or Articles 175 and 210 of the
New York State Penal Law.
R. Other Permits
Nothing in this permit relieves the owner or operator from a requirement to obtain
any other permits required by law.
36
APPENDIX A
Definitions
Alter Hydrology from Pre to Post-Development Conditions - means the post-
development peak flow rate(s) has increased by more than 5% of the pre-developed
condition for the design storm of interest (e.g. 10 yr and 100 yr).
Combined Sewer - means a sewer that is designed to collect and convey both “sewage”
and “stormwater”.
Direct Discharge (to a specific surface waterbody) - means that runoff flows from a
construction site by overland flow and the first point of discharge is the specific surface
waterbody, or runoff flows from a construction site to a separate storm sewer system and
the first point of discharge from the separate storm sewer system is the specific surface
waterbody.
Discharge(s) - means any addition of any pollutant to waters of the State through an
outlet or point source.
Equivalent (Equivalence) – means that the practice or measure meets all the
performance, longevity, maintenance, and safety objectives of the technical standard and
will provide an equal or greater degree of water quality protection.
Final Stabilization - means that all soil disturbance activities have ceased and a uniform,
perennial vegetative cover with a density of eighty (80) percent over the entire pervious
surface has been established; or other equivalent stabilization measures, such as
permanent landscape mulches, rock rip-rap or washed/crushed stone have been applied
37
on all disturbed areas that are not covered by permanent structures, concrete or
pavement.
General SPDES permit - means a SPDES permit issued pursuant to 6 NYCRR Part 750-
1.21 and Section 70-0117 of the ECL authorizing a category of discharges.
Historic Property – means any building, structure, site, object or district that is listed on
the State or National Registers of Historic Places or is determined to be eligible for listing
on the State
or National Registers of Historic Places.
Impervious Area (Cover) - means all impermeable surfaces that cannot effectively
infiltrate rainfall. This includes paved, concrete and gravel surfaces (i.e. parking lots,
driveways, roads, runways and sidewalks); building rooftops and miscellaneous
impermeable structures such as patios, pools, and sheds.
For discrete construction projects that are located within a larger common plan of
development or sale that are at least 1/4 mile apart, each project can be treated as a
separate plan of development or sale provided any interconnecting road, pipeline or utility
project that is part of the same “common plan” is not concurrently being disturbed.
Minimize – means reduce and/or eliminate to the extent achievable using control
measures (including best management practices) that are technologically available and
economically practicable and achievable in light of best industry practices.
38
ditches, man-made
channels, or storm drains):
(i) Owned or operated by a State, city, town, borough, county, parish, district,
association, or other public body (created by or pursuant to State law) having
jurisdiction over disposal of sewage, industrial wastes, stormwater, or other
wastes, including special districts under State law such as a sewer district, flood
control district or drainage district, or similar entity, or an Indian tribe or an
authorized Indian tribal organization, or a designated and approved management
agency under section 208 of the CWA that discharges to surface waters of the
State;
(ii) Designed or used for collecting or conveying stormwater;
(iii) Which is not a combined sewer; and
(iv) Which is not part of a Publicly Owned Treatment Works (POTW) as defined at 40
CFR 122.2.
New Development – means any land disturbance that does not meet the definition of
Redevelopment Activity included in this appendix.
NOI Acknowledgment Letter - means the letter that the Department sends to an owner
or operator to acknowledge the Department’s receipt and acceptance of a complete
Notice of Intent. This letter documents the owner’s or operator’s authorization to
discharge in accordance with the general permit for stormwater discharges from
construction activity.
Owner or Operator - means the person, persons or legal entity which owns or leases the
property on which the construction activity is occurring; and/or an entity that has
operational control over the construction plans and specifications, including the ability to
make modifications to the plans and specifications.
Performance Criteria – means the design criteria listed under the “Required Elements”
sections in Chapters 5, 6 and 10 of the technical standard, New York State Stormwater
Management Design Manual, dated January 2015. It does not include the Sizing Criteria
(i.e. WQv, RRv, Cpv, Qp and Qf ) in Part I.C.2. of the permit.
Pollutant - means dredged spoil, filter backwash, solid waste, incinerator residue,
sewage, garbage, sewage sludge, munitions, chemical wastes, biological materials,
radioactive materials, heat, wrecked or discarded equipment, rock, sand and industrial,
municipal, agricultural waste and ballast discharged into water; which may cause or might
reasonably be expected to cause pollution of the waters of the state in contravention of
the standards or guidance values adopted as provided in 6 NYCRR Parts 700 et seq .
39
Qualified Inspector - means a person that is knowledgeable in the principles and
practices of erosion and sediment control, such as a licensed Professional Engineer,
Certified Professional in Erosion and Sediment Control (CPESC), Registered Landscape
Architect, or other Department endorsed individual(s).
It can also mean someone working under the direct supervision of, and at the same
company as, the licensed Professional Engineer or Registered Landscape Architect,
provided that person has training in the principles and practices of erosion and sediment
control. Training in the principles and practices of erosion and sediment control means
that the individual working under the direct supervision of the licensed Professional
Engineer or Registered Landscape Architect has received four (4) hours of Department
endorsed training in proper erosion and sediment control principles from a Soil and Water
Conservation District, or other Department endorsed entity. After receiving the initial
training, the individual working under the direct supervision of the licensed Professional
Engineer or Registered Landscape Architect shall receive four (4) hours of training every
three (3) years.
It can also mean a person that meets the Qualified Professional qualifications in addition
to the Qualified Inspector qualifications.
Regulated, Traditional Land Use Control MS4 - means a city, town or village with land
use control authority that is required to gain coverage under New York State DEC’s
SPDES General Permit For Stormwater Discharges from Municipal Separate Stormwater
Sewer Systems (MS4s).
40
Routine Maintenance Activity - means construction activity that is performed to
maintain the original line and grade, hydraulic capacity, or original purpose of a facility,
including, but not limited to:
- Re-grading of gravel roads or parking lots,
- Stream bank restoration projects (does not include the placement of spoil
material),
- Cleaning and shaping of existing roadside ditches and culverts that maintains the
approximate original line and grade, and hydraulic capacity of the ditch,
- Cleaning and shaping of existing roadside ditches that does not maintain the
approximate original grade, hydraulic capacity and purpose of the ditch if the
changes to the line and grade, hydraulic capacity or purpose of the ditch are
installed to improve water quality and quantity controls (e.g. installing grass lined
ditch),
- Placement of aggregate shoulder backing that makes the transition between the
road shoulder and the ditch or embankment,
- Full depth milling and filling of existing asphalt pavements, replacement of
concrete pavement slabs, and similar work that does not expose soil or disturb the
bottom six (6) inches of subbase material,
- Long-term use of equipment storage areas at or near highway maintenance
facilities,
- Removal of sediment from the edge of the highway to restore a previously
existing sheet-flow drainage connection from the highway surface to the highway
ditch or embankment,
- Existing use of Canal Corp owned upland disposal sites for the canal, and
- Replacement of curbs, gutters, sidewalks and guide rail posts.
Site limitations – means site conditions that prevent the use of an infiltration technique
and or infiltration of the total WQv. Typical site limitations include: seasonal high
groundwater, shallow depth to bedrock, and soils with an infiltration rate less than 0.5
inches/hour. The existence of site limitations shall be confirmed and documented using
actual field testing (i.e. test pits, soil borings, and infiltration test) or using information from
the most current United States Department of Agriculture (USDA) Soil Survey for the
County where the project is located.
Sizing Criteria – means the criteria included in Part I.C.2 of the permit that are used to
size post-construction stormwater management control practices. The criteria include;
Water Quality Volume (WQv), Runoff Reduction Volume (RRv), Channel Protection
Volume (Cpv), Overbank Flood (Qp), and Extreme Flood (Qf).
Steep Slope – means land area with a Soil Slope Phase that is identified as an E or F, or
41
the map unit name is inclusive of 25% or greater slope, on the United States Department
of Agriculture (“USDA”) Soil Survey for the County where the disturbance will occur.
Surface Waters of the State - shall be construed to include lakes, bays, sounds, ponds,
impounding reservoirs, springs, rivers, streams, creeks, estuaries, marshes, inlets,
canals, the Atlantic ocean within the territorial seas of the state of New York and all other
bodies of surface water, natural or artificial, inland or coastal, fresh or salt, public or
private (except those private waters that do not combine or effect a junction with natural
surface waters), which are wholly or partially within or bordering the state or within its
jurisdiction. Waters of the state are further defined in 6 NYCRR Parts 800 to 941.
Temporarily Ceased – means that an existing disturbed area will not be disturbed again
within 14 calendar days of the previous soil disturbance.
Temporary Stabilization - means that exposed soil has been covered with material(s) as
set forth in the technical standard, New York Standards and Specifications for Erosion
and Sediment Control, to prevent the exposed soil from eroding. The materials can
include, but are not limited to, mulch, seed and mulch, and erosion control mats (e.g. jute
twisted yarn, excelsior wood fiber mats).
Total Maximum Daily Loads (TMDLs) - A TMDL is the sum of the allowable loads of a
single pollutant from all contributing point and nonpoint sources. It is a calculation of the
maximum amount of a pollutant that a waterbody can receive on a daily basis and still
meet water quality standards, and an allocation of that amount to the pollutant's sources.
A TMDL stipulates wasteload allocations (WLAs) for point source discharges, load
allocations (LAs) for nonpoint sources, and a margin of safety (MOS).
It can also mean an employee from the contracting (construction) company, identified in
Part III.A.6., that meets the qualified inspector qualifications (e.g. licensed Professional
Engineer, Certified Professional in Erosion and Sediment Control (CPESC), Registered
Landscape Architect, or someone working under the direct supervision of, and at the
same company as, the licensed Professional Engineer or Registered Landscape
Architect, provided they have received four (4) hours of Department endorsed training in
proper erosion and sediment control principles from a Soil and Water Conservation
District, or other Department endorsed entity).
The trained contractor is responsible for the day to day implementation of the SWPPP.
Uniform Procedures Act (UPA) Permit - means a permit required under 6 NYCRR Part
42
621 of the Environmental Conservation Law (ECL), Article 70.
Water Quality Standard - means such measures of purity or quality for any waters in
relation to their reasonable and necessary use as promulgated in 6 NYCRR Part 700 et
seq.
43
APPENDIX B
Table 1
CONSTRUCTION ACTIVITIES THAT REQUIRE THE PREPARATION OF A SWPPP
THAT ONLY INCLUDES EROSION AND SEDIMENT CONTROLS
The following construction activities that involve soil disturbances of one (1) or more acres of
land, but less than five (5) acres:
• Single family home not located in one of the watersheds listed in Appendix C or not directly
discharging to one of the 303(d) segments listed in Appendix E
• Single family residential subdivisions with 25% or less impervious cover at total site build-out
and not located in one of the watersheds listed in Appendix C and not directly discharging to
one of the 303(d) segments listed in Appendix E
• Construction of a barn or other agricultural building, silo, stock yard or pen.
The following construction activities that involve soil disturbances of one (1) or more acres of
land:
• Installation of underground, linear utilities; such as gas lines, fiber-optic cable, cable TV,
electric, telephone, sewer mains, and water mains
• Environmental enhancement projects, such as wetland mitigation projects, stormwater
retrofits and stream restoration projects
• Bike paths and trails
• Sidewalk construction projects that are not part of a road/ highway construction or
reconstruction project
• Slope stabilization projects
• Slope flattening that changes the grade of the site, but does not significantly change the
runoff characteristics
• Spoil areas that will be covered with vegetation
• Land clearing and grading for the purposes of creating vegetated open space (i.e.
recreational parks, lawns, meadows, fields), excluding projects that alter hydrology from pre
to post development conditions
• Athletic fields (natural grass) that do not include the construction or reconstruction of
impervious area and do not alter hydrology from pre to post development conditions
• Demolition project where vegetation will be established and no redevelopment is planned
• Overhead electric transmission line project that does not include the construction of
permanent access roads or parking areas surfaced with impervious cover
• Structural practices as identified in Table II in the “Agricultural Management Practices
Catalog for Nonpoint Source Pollution in New York State”, excluding projects that involve soil
disturbances of less than five acres and construction activities that include the construction
or reconstruction of impervious area
The following construction activities that involve soil disturbances between five thousand (5000)
square feet and one (1) acre of land:
44
Table 2
CONSTRUCTION ACTIVITIES THAT REQUIRE THE PREPARATION OF A SWPPP THAT INCLUDES
POST-CONSTRUCTION STORMWATER MANAGEMENT PRACTICES
The following construction activities that involve soil disturbances of one (1) or more acres of
land:
• Single family home located in one of the watersheds listed in Appendix C or directly
discharging to one of the 303(d) segments listed in Appendix E
• Single family residential subdivisions located in one of the watersheds listed in Appendix C
or directly discharging to one of the 303(d) segments listed in Appendix E
• Single family residential subdivisions that involve soil disturbances of between one (1) and
five (5) acres of land with greater than 25% impervious cover at total site build-out
• Single family residential subdivisions that involve soil disturbances of five (5) or more acres
of land, and single family residential subdivisions that involve soil disturbances of less than
five (5) acres that are part of a larger common plan of development or sale that will ultimately
disturb five or more acres of land
• Multi-family residential developments; includes townhomes, condominiums, senior housing
complexes, apartment complexes, and mobile home parks
• Airports
• Amusement parks
• Campgrounds
• Cemeteries that include the construction or reconstruction of impervious area (>5% of
disturbed area) or alter the hydrology from pre to post development conditions
• Commercial developments
• Churches and other places of worship
• Construction of a barn or other agricultural building(e.g. silo) and structural practices as
identified in Table II in the “Agricultural Management Practices Catalog for Nonpoint Source
Pollution in New York State” that include the construction or reconstruction of impervious
area, excluding projects that involve soil disturbances of less than five acres.
• Golf courses
• Institutional, includes hospitals, prisons, schools and colleges
• Industrial facilities, includes industrial parks
• Landfills
• Municipal facilities; includes highway garages, transfer stations, office buildings, POTW’s
and water treatment plants
• Office complexes
• Sports complexes
• Racetracks, includes racetracks with earthen (dirt) surface
• Road construction or reconstruction
• Parking lot construction or reconstruction
• Athletic fields (natural grass) that include the construction or reconstruction of impervious
area (>5% of disturbed area) or alter the hydrology from pre to post development conditions
• Athletic fields with artificial turf
• Permanent access roads, parking areas, substations, compressor stations and well drilling
pads, surfaced with impervious cover, and constructed as part of an over-head electric
transmission line project , wind-power project, cell tower project, oil or gas well drilling
project, sewer or water main project or other linear utility project
• All other construction activities that include the construction or reconstruction of impervious
area or alter the hydrology from pre to post development conditions, and are not listed in
Table 1
45
APPENDIX C
• Entire New York City Watershed located east of the Hudson River - Figure 1
• Onondaga Lake Watershed - Figure 2
• Greenwood Lake Watershed -Figure 3
• Oscawana Lake Watershed – Figure 4
• Kinderhook Lake Watershed – Figure 5
46
Figure 1 - New York City Watershed East of the Hudson
47
Figure 2 - Onondaga Lake Watershed
48
Figure 3 - Greenwood Lake Watershed
49
Figure 4 - Oscawana Lake Watershed
50
51
APPENDIX D
Entire New York City Watershed that is located east of the Hudson River - See Figure
1 in Appendix C
52
APPENDIX E
List of 303(d) segments impaired by pollutants related to construction activity (e.g. silt, sediment
or nutrients). Owners or operators of single family home and single family residential subdivisions
with 25% or less total impervious cover at total site build-out that involve soil disturbances of one
or more acres of land, but less than 5 acres, and directly discharge to one of the listed segments
below shall prepare a SWPPP that includes post-construction stormwater management practices
designed in conformance with the New York State Stormwater Management Design Manual
(“Design Manual”), dated January 2015.
53
APPENDIX E
List of 303(d) segments impaired by pollutants related to construction activity, cont’d.
54
APPENDIX F
2 BRONX, KINGS, NEW YORK, 1 HUNTERS POINT PLAZA, 1 HUNTERS POINT PLAZA,
QUEENS AND RICHMOND 47-40 21ST ST. 47-40 21ST ST.
LONG ISLAND CITY, NY 11101-5407 LONG ISLAND CITY, NY 11101-5407
TEL. (718) 482-4997 TEL. (718) 482-4933
3 DUTCHESS, ORANGE, PUTNAM, 21 SOUTH PUTT CORNERS ROAD 100 HILLSIDE AVENUE, SUITE 1W
ROCKLAND, SULLIVAN, ULSTER NEW PALTZ, NY 12561-1696 WHITE PLAINS, NY 10603
AND W ESTCHESTER TEL. (845) 256-3059 TEL. (914) 428 - 2505
4 ALBANY, COLUMBIA, 1150 NORTH WESTCOTT ROAD 1130 NORTH WESTCOTT ROAD
DELAWARE, GREENE, SCHENECTADY, NY 12306-2014 SCHENECTADY, NY 12306-2014
MONTGOMERY, OTSEGO, TEL. (518) 357-2069 TEL. (518) 357-2045
RENSSELAER, SCHENECTADY
AND SCHOHARIE
5 CLINTON, ESSEX, FRANKLIN, 1115 STATE ROUTE 86, PO BOX 296 232 GOLF COURSE ROAD
FULTON, HAMILTON, RAY BROOK, NY 12977-0296 WARRENSBURG, NY 12885-1172
SARATOGA, WARREN AND TEL. (518) 897-1234 TEL. (518) 623-1200
WASHINGTON
7 BROOME, CAYUGA, 615 ERIE BLVD. WEST 615 ERIE BLVD. WEST
CHENANGO, CORTLAND, SYRACUSE, NY 13204-2400 SYRACUSE, NY 13204-2400
MADISON, ONONDAGA, TEL. (315) 426-7438 TEL. (315) 426-7500
OSWEGO, TIOGA AND
TOMPKINS
8 CHEMUNG, GENESEE, 6274 EAST AVON-LIMA ROAD 6274 EAST AVON-LIMA RD.
LIVINGSTON, MONROE, AVON, NY 14414-9519 AVON, NY 14414-9519
ONTARIO, ORLEANS, TEL. (585) 226-2466 TEL. (585) 226-2466
SCHUYLER, SENECA,
STEUBEN, WAYNE AND
YATES
55
APPENDIX D
________________________________________________________________________________
NYS Department of Environmental Conservation
Division of Water
625 Broadway, 4th Floor
Albany, New York 12233-3505
Page 1 of 2
MS4 SWPPP Acceptance Form - continued
V. Certification Statement - MS4 Official (principal executive officer or ranking elected official) or
Duly Authorized Representative
I hereby certify that the final Stormwater Pollution Prevention Plan (SWPPP) for the construction project
identified in question 5 has been reviewed and meets the substantive requirements in the SPDES
General Permit For Stormwater Discharges from Municipal Separate Storm Sewer Systems (MS4s).
Note: The MS4, through the acceptance of the SWPPP, assumes no responsibility for the accuracy and
adequacy of the design included in the SWPPP. In addition, review and acceptance of the SWPPP by
the MS4 does not relieve the owner/operator or their SWPPP preparer of responsibility or liability for
errors or omissions in the plan.
Printed Name:
Title/Position:
Signature:
Date:
VI. Additional Information
Page 2 of 2
APPENDIX E
________________________________________________________________________________
TOWN OF BETHLEHEM
SWPPP APPLICATION REVIEW CHECKLIST
Instructions: This form must be included with an initial submittal of a Site Plan or Subdivision Application.
Use the ‘Applicant’ column to indicate if the SWPPP contains each of the minimum components. Leave the
check box blank if the item is not included in the SWPPP and provide an explanation in the available space.
Project Name: Selkirk Solar Farm Site Address: 93 Bridge Street, Bethlehem, NY 12158
Project Applicant: NextEra Energy Resources Contact Person: Tony Yonnone
Mailing Address: 700 Universe Boulevard Phone Number: (561)619-2160
City, State, Zip: Juno Beach, FL 33408 Email: anthony.yonnone@nee.com
SWPPP Preparer: Kleinfelder, Inc. Contact Person: John Wendelburg
Mailing Address: 300 Westage Business Center Drive, Suite 407 Phone Number: (845)231-2500
City, State, Zip: Fishkill, NY 12524 Email: JWendelburg@Kleinfelder.com
Do not use the gray ‘MS4’ column; this is used by the MS4 Reviewer to verify checked items in the SWPPP.
MS4 SWPPP Reviewer: SWPPP DATE:
Submittal Date: Review Date: Approval Date:
GENERAL REQUIREMENTS:
Applicant MS4
1. X Project street address, tax parcel ID(s), and legal descriptions and boundary line surveys
2. X Vicinity Map - showing project boundary, adjacent parcels, streets, and receiving water(s)
3. X Construction drawings and SWPPP with the signature and seal of a ‘qualified professional’
4. X Copies of other approvals, agreements, or permits required for construction of the project
X
Documentation of consultation with NYSHPO about potential impacts to Historic Places,
5.
include a printout from the NYSOPRHP website at: www.oprhp.state.ny.us/nr/main.asp
6. X A description of any measures necessary to avoid or minimize said adverse impacts
7. Completed copy of a NYSDEC and US ACOE Joint Application for Permit, if applicable
8. X Completed and signed copy of DEC Notice of Intent (NOI) for general permit coverage
9. X Completed MS4 SWPPP Acceptance Form, available online: www.townofbethlehem.org
10. X Signed SWM Certification Form: Part A Developer/Applicant & Qualified Professional
Last Revised: February 2009 page 1 of 5
Project Name: SWPPP Date:
BASIC SWPPP:
A) Existing and Proposed Mapping and Site Plans:
(Minimum scale of 1” = 50’, or as requested by the MS4, with clear and legible detail)
Applicant MS4
11. X Existing and proposed topography a minimum of 50’ beyond the property (min. 2’contours)
12. X Location of adjacent perennial and intermittent streams ( NYSDEC classification/naming)
13. X Mapping and description of all soils on the site, including the Hydrologic Soil Group (HSG)
14. X Description and boundaries of the existing predominant vegetative cover on the project site
15. X Boundary of the proposed limits of clearing and, if different, limits of grading on the site
16. X Delineated boundary and acreage of any upstream watersheds draining onto the project site
X
Location and boundaries of resource protection areas such as wetlands, lakes, ponds and
17.
other setbacks (e.g. stream buffers, water supply well setbacks, septic system setbacks, etc.)
Logs and mapping of borehole or test pit investigations performed on the site to determine
18.
soil properties and groundwater elevations (include the geotechnical report, if generated)
19. X Seasonal high groundwater elevation at the locations of sediment and/or detention basins
20. X NYSDEC freshwater wetland and adjacent area boundaries or certification of no wetlands
21. X Boundary of US ACOE wetlands under federal jurisdiction or certification of no wetlands
22. X Location of existing and proposed roadways, lot boundaries, buildings, and other structures
23. X Location of existing and proposed utilities (e.g. water, sewer, gas, electric) and easements
24. X Location of existing and proposed conveyance systems (i.e. swales, MHs, CBs, pipes, etc.)
25. X Flow paths of surface and subsurface stormwater management structures (use flow arrows)
26. X Location of 100-yr floodplain and floodway limits if disturbance proposed in the floodplain
27. X Locations and dimensions of all proposed channel modifications (i.e. bridges & culverts)
X
Use of TR-20 or TR-55 methodology to compute pre and post-construction peak discharge
28.
rates from the site or if soil disturbance is under 1 acre, the Rationale Method is acceptable
29. X Calculations for the acreage of impervious cover created within the proposed disturbances
30. X Time of Concentration (Tc) travel time flow path for subcatchments within project limits
31. X Curve Number (CN) values and square footage or acreage of evaluated subcatchment areas
32. X Location of Design Points (DPs) for the pre- and post-development hydrological analysis
X
Use of Town Standard Specifications for design of the storm drain system (i.e. catch basins,
33.
manholes, piping, etc.) – copies are available from the Engineering Division at 439-4955
X
Use of Town standard rainfall amounts for the 1, 2, 10, 100-year 24-hour and 90% rainfall
34.
events: 1-yr = 2.5”, 2-yr = 2.8”:, 10-yr = 4.5”, 100-yr = 6.5”, and 90% rainfall (P) = 1.0”
35. X Existing and proposed elevations for storm drain structures (i.e. pipes, CBs, manholes, etc.)
X
Summary table on sizing of stormwater collection and conveyance structures: must include
36.
runoff coefficient, storm intensity, manning’s n-value, and peak discharge rate and velocity
X
Map of contributing drainage areas for all stormwater collection and conveyance structures:
37.
illustrating the watershed, land cover, and square footage or acreage of each drainage area
X
Illustration of the design water surface elevations (WSE) for all applicable rainfall events
38.
within any proposed storage or diversion structure (excluding all piping, CBs, and MHs)
Page 2 of 5
Project Name: SWPPP Date:
BASIC SWPPP:
C) Erosion and Sediment Control (E&SC) Plan:
(Minimum scale of 1” = 50’, must include all areas of disturbance within the project)
Applicant MS4
39. X Erosion and sediment control plan satisfying requirements as outlined in the Blue Book
X
Site map/construction drawing(s) showing the specific location(s), size(s), and length(s) of
40.
each E&SC practice for all anticipated soil disturbance activities for the entire project
X
Material specifications, dimensions, and installation details for proposed E&SC practices,
41.
including calculations for siting and sizing of any temporary sediment basins and/or traps
X
If construction activity is utility installation or single family home, use the Town Standard
42.
Detail Sheets for Typical E&SC Measures or provide equivalent details and specifications
X
Typical E&SC measures and specific details for material stockpiling, equipment staging,
43.
material storage, borrow/spoil areas, dewatering operations, and spill/waste containment
X
Description of temporary and permanent structural and vegetative measures for erosion
44.
control, runoff control, and sediment control for each stage and/or phase of the project
45. X Specifications for temporary and permanent seeding – note seed types and application rates
46. X Statement requiring soil stabilization on inactive portions of the site in maximum 14 days
47. X Construction phasing plan describing all the major construction activities for the project
48. X Anticipated start and end dates for each phase of the project and the total duration of work
X
Sequencing schedule for all known soil disturbance activities at the site, including clearing,
49.
grubbing, grading, stockpiling, excavation, infrastructure installation, and final stabilization
X
Include a schedule identifying the timing of initial placement or implementation of each
50.
E&SC practice and minimum time frames each practice remains in place or implemented
X
Maintenance schedule for the continuous and effective operation of all temporary E&SC
51.
practices - indicate all expected daily, weekly, pre and post-rainfall, and seasonal activities
X
Identification of temporary practices to be converted to permanent control measures and
52.
any maintenance or inspection actions that are required prior to converting these practices
X
Descriptions of structural practices used to divert flows from exposed soils, store flows, or
53.
otherwise limit runoff and the discharge of pollutants from the exposed areas of the site
Description of construction and waste materials expected to be utilized on-site, controls to
54. X reduce pollutants from these materials, storage practices to minimize exposure of materials
to stormwater, cleanup procedures, and spill prevention and notification for each material
55. Final landscaping plans - include buffer zones, reforestation, or wetland mitigation areas
X
Winter month, October 15 to April 15, requirements related to E&SC (i.e. anchoring mulch
56.
material, sediment removal from basins/traps, use of winter rye seed, offset silt fence, etc.)
57. X Copy of Contractor Certification Form with a statement equivalent to DEC general permit
58. X Copy of the Owner or Operator Inspection Form satisfying requirements in the Blue Book
59. X Engineer’s estimate for the cost of implementing identified components of the E&SC Plan
SWPPP Preparer Comments - explanation for any required items not being provided in the SWPPP
# NYSDEC Green Infrastructure Design Worksheets - Please see SWPPP Part D.1 for WQV / RRV / CPv / Qp / Qf Calculations
#7 NYSDEC and US ACOE Joint Application is not necessary as no wetland impacts are being proposed.
# 18 Soil properties will be verified onsite.
# 55 No Landscaping is proposed onsite
#
**STOP HERE if the project does not require installation of a post-construction SMP**
Page 3 of 5
Project Name: SWPPP Date:
FULL SWPPP:
D) Hydrologic and Hydraulic Analysis:
(For all structural components of the stormwater system – i.e. channels, swales, SMPs, etc.)
Applicant MS4
Existing condition analysis for time of concentration, runoff rates, volumes, and velocities,
60. X and water surface elevations showing methodologies used and supporting calculations,
including existing watershed map with design points, catchment IDs, and Tc flow paths
Proposed condition analysis for time of concentration, runoff rates, volumes, and velocities,
61. X and water surface elevations showing methodologies used and supporting calculations,
including proposed watershed map with design points, catchment IDs, and Tc flow paths
X
Sizing calculations for all the post-construction stormwater management practices (SMPs)
62.
including: contributing drainage area, land use cover, storage volumes, and outlet structures
X
Stage-discharge table or outlet rating curves and inflow/outflow hydrographs for all SMPs –
63.
information must be generated from TR-20 based hydrologic/hydraulic modeling software
64. Dam Hazard Class determined in conformance with DEC Guidelines for Design of Dams
Detailed comparison and summary of post-development stormwater runoff conditions with
65. X pre-development conditions for 1-year, 2-year, 10-year, 100-year 24-hour design storms in
accordance with the Unified Sizing Criteria identified in Chapter 4 of the Design Manual
66. X Water Quality volume (WQv) calculations based on the Town 90% rainfall event, P=1.0”
67. X Calculations for WQv and CPv (use Chapter 4, 8, and Appendix B of the Design Manual)
X
Representative cross sections and plans with dimensions, material specifications, and
68.
installation details for each SMP (comparable in detail to Chapter 6 of the Design Manual)
Infiltration and percolation test pit report (performed in accordance with Appendix D of the
69.
Design Manual at the required frequency) where required by the SMP Group or the Town
70. Copy of Geotechnical Evaluation Report conducted for the project, if required by the Town
71. X Copy of Site Inspection Form that satisfies the requirements in GP-0-10-001, or as updated
72. X Statement for inspections to be conducted by the qualified inspector every 7 calendar days
73. X Identification of the expected discharge points to be evaluated during these site inspections
Page 4 of 5
Project Name: SWPPP Date:
G) Downstream Analysis:
(Requirements for waiving quantity control of Qp (10-yr), and/or Qf (100-yr) storm events)
Applicant MS4
87. Preparation of downstream analysis report based upon current NYSDEC or MS4 guidelines
88. Map illustrating the points of analysis or outfalls with direct discharge to a 4th order stream
89. Verification of correspondence with downstream municipalities until the 4th order stream
J) Performance Guarantee:
(Requirement for all land development activities)
Applicant MS4
97. X Engineer’s estimate for the cost of implementing all the components of the approved plans
X
Irrevocable letter of credit or surety bond to ensure completion and O&M of all identified
98.
components of the approved plans for one full year after the final acceptance by the Town
99. X Final version(s) of signed O&M Agreement (s) with the Town for all the constructed SMPs
SWPPP Preparer Comments - explanation for any required items not being provided in the SWPPP
# 64 Dam hazards classes not applicable
# 69 Infiltration and percolation report is not anticipated to be required
# 70 No geotechnical report is anticipated to be required.
# 75 Easement illustrations are not shown as SMPs (Dry Swales) will be located well within the property boundary, thus not affecting other properties.
Page 5 of 5
APPENDIX F
________________________________________________________________________________
SWPPP Preparer Certification Form
SPDES General Permit for Stormwater Discharges
From Construction Activity (GP-0-15-002)
Owner/Operator Information
Owner/Operator (Company Name/Private Owner/Municipality Name)
DG Suny Solar 1, LLC
I hereby certify that the Stormwater Pollution Prevention Plan (SWPPP) for this
project has been prepared in accordance with the terms and conditions of the
GP-0-1-00. Furthermore, I understand that certifying false, incorrect or inaccurate
information is a violation of this permit and the laws of the State of New York and
could subject me to criminal, civil and/or administrative proceedings.
John Wendelburg
3/17/2017
Signature Date
________________________________________________________________________________
CONTRACTOR and SUBCONTRACTOR CERTIFICATION STATEMENT
for the New York State Department of Environmental Conservation (DEC) State Pollutant Discharge
Elimination System Permit for Stormwater Discharges from Construction Activity (GP-0-10-001)
As per Part III.A.6 on page 13 of GP-0-10-001 (effective January 29, 2010):
‘Prior to the commencement of construction activity, the owner or operator must identify the
contractor(s) and subcontractor(s) that will be responsible for installing, constructing, repairing,
replacing, inspecting and maintaining the erosion and sediment control practices included in the
SWPPP; and the contractor(s) and subcontractor(s) that will be responsible for constructing the post-
construction stormwater management practices included in the SWPPP. The owner or operator shall
have each of the contractors and sub-contractors identify at least one person from their company that
will be responsible for implementation of the SWPPP. This person shall be known as the trained
contractor. The owner or operator shall ensure that at least one trained contractor is on site on a daily
basis when soil disturbance activities are being performed.’
The owner or operator shall have each contractor and subcontractor involved in soil disturbance
sign a copy of the following certification statement before they commence any construction activity:
A copy of this signed contractor certification statement must be maintained at the SWPPP on site
APPENDIX H
________________________________________________________________________________
APPENDIX I
________________________________________________________________________________
EROSION & SEDIMENT CONTROL COST ESTIMATE
SELKIRK SOLAR FARM
CLEARING & GRUBBING; EROSION & SEDIMENT CONTROLS
QUANTITY UNIT UNIT PRICE FINAL PRICE
CONSTRUCTION ENTRANCE 1 EA $3,200.00 $3,200.00
COMPOST FILTER SOCK 13356 LF $5.00 $66,780.00
SITE SEEDING 42 AC $1,500.00 $63,000.00
TOTAL $132,980.00
4/10/2017 11:48 AM
Erosion Control Cost Estimate.xlsx
M.ASH
APPENDIX J
________________________________________________________________________________
ATTACHMENT 1
Construction Stormwater Compliance Inspection Report
Project Name and Location: Selkirk Solar Farm Date: Page 1 of 2
INSPECTION CHECKLIST
SPDES Authority
SWPPP Content
Recordkeeping
Visual Observations
Names/Agencies of
Other Inspectors:
12
Rev. 10-16-06
Page 2 of 2
Water Quality Observations
_____________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________
Describe the quality of the receiving water(s) both upstream and downstream of the discharge_________________________________________________
___________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_________________________________________________________________________________________________________________________
Additional Comments:_________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________________
_______________________________________________________________________________________________
Photographs attached
13
APPENDIX K
________________________________________________________________________________
United States
Department of
A product of the National
Cooperative Soil Survey,
Custom Soil Resource
Agriculture a joint effort of the United Report for
States Department of
Natural
Agriculture and other
Federal agencies, State
agencies including the
Albany County,
Resources
Conservation
Service
Agricultural Experiment
Stations, and local
participants
New York
April 7, 2017
Preface
Soil surveys contain information that affects land use planning in survey areas.
They highlight soil limitations that affect various land uses and provide information
about the properties of the soils in the survey areas. Soil surveys are designed for
many different users, including farmers, ranchers, foresters, agronomists, urban
planners, community officials, engineers, developers, builders, and home buyers.
Also, conservationists, teachers, students, and specialists in recreation, waste
disposal, and pollution control can use the surveys to help them understand,
protect, or enhance the environment.
Various land use regulations of Federal, State, and local governments may impose
special restrictions on land use or land treatment. Soil surveys identify soil
properties that are used in making various land use or land treatment decisions.
The information is intended to help the land users identify and reduce the effects of
soil limitations on various land uses. The landowner or user is responsible for
identifying and complying with existing laws and regulations.
Although soil survey information can be used for general farm, local, and wider area
planning, onsite investigation is needed to supplement this information in some
cases. Examples include soil quality assessments (http://www.nrcs.usda.gov/wps/
portal/nrcs/main/soils/health/) and certain conservation and engineering
applications. For more detailed information, contact your local USDA Service Center
(https://offices.sc.egov.usda.gov/locator/app?agency=nrcs) or your NRCS State Soil
Scientist (http://www.nrcs.usda.gov/wps/portal/nrcs/detail/soils/contactus/?
cid=nrcs142p2_053951).
Great differences in soil properties can occur within short distances. Some soils are
seasonally wet or subject to flooding. Some are too unstable to be used as a
foundation for buildings or roads. Clayey or wet soils are poorly suited to use as
septic tank absorption fields. A high water table makes a soil poorly suited to
basements or underground installations.
The National Cooperative Soil Survey is a joint effort of the United States
Department of Agriculture and other Federal agencies, State agencies including the
Agricultural Experiment Stations, and local agencies. The Natural Resources
Conservation Service (NRCS) has leadership for the Federal part of the National
Cooperative Soil Survey.
Information about soils is updated periodically. Updated information is available
through the NRCS Web Soil Survey, the site for official soil survey information.
The U.S. Department of Agriculture (USDA) prohibits discrimination in all its
programs and activities on the basis of race, color, national origin, age, disability,
and where applicable, sex, marital status, familial status, parental status, religion,
sexual orientation, genetic information, political beliefs, reprisal, or because all or a
part of an individual's income is derived from any public assistance program. (Not
all prohibited bases apply to all programs.) Persons with disabilities who require
2
alternative means for communication of program information (Braille, large print,
audiotape, etc.) should contact USDA's TARGET Center at (202) 720-2600 (voice
and TDD). To file a complaint of discrimination, write to USDA, Director, Office of
Civil Rights, 1400 Independence Avenue, S.W., Washington, D.C. 20250-9410 or
call (800) 795-3272 (voice) or (202) 720-6382 (TDD). USDA is an equal opportunity
provider and employer.
3
Contents
Preface.................................................................................................................... 2
How Soil Surveys Are Made..................................................................................5
Soil Map.................................................................................................................. 8
Soil Map................................................................................................................9
Legend................................................................................................................10
Map Unit Legend................................................................................................ 11
Map Unit Descriptions.........................................................................................11
Albany County, New York................................................................................13
HuB—Hudson silt loam, 3 to 8 percent slopes............................................13
HuE—Hudson silt loam, 25 to 45 percent slopes........................................14
RhA—Rhinebeck silty clay loam, 0 to 3 percent slopes.............................. 15
RhB—Rhinebeck silty clay loam, 3 to 8 percent slopes.............................. 16
Uh—Udorthents, clayey-Urban land complex............................................. 18
UnB—Unadilla silt loam, 3 to 8 percent slopes........................................... 19
Soil Information for All Uses...............................................................................21
Soil Properties and Qualities.............................................................................. 21
Soil Erosion Factors........................................................................................21
K Factor, Whole Soil....................................................................................21
Soil Qualities and Features.............................................................................24
Hydrologic Soil Group................................................................................. 24
References............................................................................................................29
4
How Soil Surveys Are Made
Soil surveys are made to provide information about the soils and miscellaneous
areas in a specific area. They include a description of the soils and miscellaneous
areas and their location on the landscape and tables that show soil properties and
limitations affecting various uses. Soil scientists observed the steepness, length,
and shape of the slopes; the general pattern of drainage; the kinds of crops and
native plants; and the kinds of bedrock. They observed and described many soil
profiles. A soil profile is the sequence of natural layers, or horizons, in a soil. The
profile extends from the surface down into the unconsolidated material in which the
soil formed or from the surface down to bedrock. The unconsolidated material is
devoid of roots and other living organisms and has not been changed by other
biological activity.
Currently, soils are mapped according to the boundaries of major land resource
areas (MLRAs). MLRAs are geographically associated land resource units that
share common characteristics related to physiography, geology, climate, water
resources, soils, biological resources, and land uses (USDA, 2006). Soil survey
areas typically consist of parts of one or more MLRA.
The soils and miscellaneous areas in a survey area occur in an orderly pattern that
is related to the geology, landforms, relief, climate, and natural vegetation of the
area. Each kind of soil and miscellaneous area is associated with a particular kind
of landform or with a segment of the landform. By observing the soils and
miscellaneous areas in the survey area and relating their position to specific
segments of the landform, a soil scientist develops a concept, or model, of how they
were formed. Thus, during mapping, this model enables the soil scientist to predict
with a considerable degree of accuracy the kind of soil or miscellaneous area at a
specific location on the landscape.
Commonly, individual soils on the landscape merge into one another as their
characteristics gradually change. To construct an accurate soil map, however, soil
scientists must determine the boundaries between the soils. They can observe only
a limited number of soil profiles. Nevertheless, these observations, supplemented
by an understanding of the soil-vegetation-landscape relationship, are sufficient to
verify predictions of the kinds of soil in an area and to determine the boundaries.
Soil scientists recorded the characteristics of the soil profiles that they studied. They
noted soil color, texture, size and shape of soil aggregates, kind and amount of rock
fragments, distribution of plant roots, reaction, and other features that enable them
to identify soils. After describing the soils in the survey area and determining their
properties, the soil scientists assigned the soils to taxonomic classes (units).
Taxonomic classes are concepts. Each taxonomic class has a set of soil
characteristics with precisely defined limits. The classes are used as a basis for
comparison to classify soils systematically. Soil taxonomy, the system of taxonomic
classification used in the United States, is based mainly on the kind and character
of soil properties and the arrangement of horizons within the profile. After the soil
5
Custom Soil Resource Report
scientists classified and named the soils in the survey area, they compared the
individual soils with similar soils in the same taxonomic class in other areas so that
they could confirm data and assemble additional data based on experience and
research.
The objective of soil mapping is not to delineate pure map unit components; the
objective is to separate the landscape into landforms or landform segments that
have similar use and management requirements. Each map unit is defined by a
unique combination of soil components and/or miscellaneous areas in predictable
proportions. Some components may be highly contrasting to the other components
of the map unit. The presence of minor components in a map unit in no way
diminishes the usefulness or accuracy of the data. The delineation of such
landforms and landform segments on the map provides sufficient information for the
development of resource plans. If intensive use of small areas is planned, onsite
investigation is needed to define and locate the soils and miscellaneous areas.
Soil scientists make many field observations in the process of producing a soil map.
The frequency of observation is dependent upon several factors, including scale of
mapping, intensity of mapping, design of map units, complexity of the landscape,
and experience of the soil scientist. Observations are made to test and refine the
soil-landscape model and predictions and to verify the classification of the soils at
specific locations. Once the soil-landscape model is refined, a significantly smaller
number of measurements of individual soil properties are made and recorded.
These measurements may include field measurements, such as those for color,
depth to bedrock, and texture, and laboratory measurements, such as those for
content of sand, silt, clay, salt, and other components. Properties of each soil
typically vary from one point to another across the landscape.
Observations for map unit components are aggregated to develop ranges of
characteristics for the components. The aggregated values are presented. Direct
measurements do not exist for every property presented for every map unit
component. Values for some properties are estimated from combinations of other
properties.
While a soil survey is in progress, samples of some of the soils in the area generally
are collected for laboratory analyses and for engineering tests. Soil scientists
interpret the data from these analyses and tests as well as the field-observed
characteristics and the soil properties to determine the expected behavior of the
soils under different uses. Interpretations for all of the soils are field tested through
observation of the soils in different uses and under different levels of management.
Some interpretations are modified to fit local conditions, and some new
interpretations are developed to meet local needs. Data are assembled from other
sources, such as research information, production records, and field experience of
specialists. For example, data on crop yields under defined levels of management
are assembled from farm records and from field or plot experiments on the same
kinds of soil.
Predictions about soil behavior are based not only on soil properties but also on
such variables as climate and biological activity. Soil conditions are predictable over
long periods of time, but they are not predictable from year to year. For example,
soil scientists can predict with a fairly high degree of accuracy that a given soil will
have a high water table within certain depths in most years, but they cannot predict
that a high water table will always be at a specific level in the soil on a specific date.
After soil scientists located and identified the significant natural bodies of soil in the
survey area, they drew the boundaries of these bodies on aerial photographs and
6
Custom Soil Resource Report
identified each as a specific map unit. Aerial photographs show trees, buildings,
fields, roads, and rivers, all of which help in locating boundaries accurately.
7
Soil Map
The soil map section includes the soil map for the defined area of interest, a list of
soil map units on the map and extent of each map unit, and cartographic symbols
displayed on the map. Also presented are various metadata about data used to
produce the map, and a description of each soil map unit.
8
Custom Soil Resource Report
4711800
4711700
4711700
4711600
4711600
4711500
4711500
4711400
4711400
4711300
4711300
4711200
4711200
4711100
4711100
4711000
4711000
Miscellaneous Water This product is generated from the USDA-NRCS certified data as
Perennial Water of the version date(s) listed below.
Rock Outcrop
Soil Survey Area: Albany County, New York
Saline Spot Survey Area Data: Version 14, Sep 23, 2016
Sandy Spot
Soil map units are labeled (as space allows) for map scales
Severely Eroded Spot 1:50,000 or larger.
Sinkhole
Date(s) aerial images were photographed: Data not available.
Slide or Slip
The orthophoto or other base map on which the soil lines were
Sodic Spot
compiled and digitized probably differs from the background
imagery displayed on these maps. As a result, some minor
shifting of map unit boundaries may be evident.
10
Custom Soil Resource Report
Map Unit Symbol Map Unit Name Acres in AOI Percent of AOI
HuB Hudson silt loam, 3 to 8 percent 14.8 35.6%
slopes
HuE Hudson silt loam, 25 to 45 0.8 1.8%
percent slopes
RhA Rhinebeck silty clay loam, 0 to 19.2 46.4%
3 percent slopes
RhB Rhinebeck silty clay loam, 3 to 3.5 8.5%
8 percent slopes
Uh Udorthents, clayey-Urban land 0.1 0.1%
complex
UnB Unadilla silt loam, 3 to 8 percent 3.1 7.6%
slopes
Totals for Area of Interest 41.4 100.0%
11
Custom Soil Resource Report
mentioned in the descriptions, especially where the pattern was so complex that it
was impractical to make enough observations to identify all the soils and
miscellaneous areas on the landscape.
The presence of minor components in a map unit in no way diminishes the
usefulness or accuracy of the data. The objective of mapping is not to delineate
pure taxonomic classes but rather to separate the landscape into landforms or
landform segments that have similar use and management requirements. The
delineation of such segments on the map provides sufficient information for the
development of resource plans. If intensive use of small areas is planned, however,
onsite investigation is needed to define and locate the soils and miscellaneous
areas.
An identifying symbol precedes the map unit name in the map unit descriptions.
Each description includes general facts about the unit and gives important soil
properties and qualities.
Soils that have profiles that are almost alike make up a soil series. Except for
differences in texture of the surface layer, all the soils of a series have major
horizons that are similar in composition, thickness, and arrangement.
Soils of one series can differ in texture of the surface layer, slope, stoniness,
salinity, degree of erosion, and other characteristics that affect their use. On the
basis of such differences, a soil series is divided into soil phases. Most of the areas
shown on the detailed soil maps are phases of soil series. The name of a soil phase
commonly indicates a feature that affects use or management. For example, Alpha
silt loam, 0 to 2 percent slopes, is a phase of the Alpha series.
Some map units are made up of two or more major soils or miscellaneous areas.
These map units are complexes, associations, or undifferentiated groups.
A complex consists of two or more soils or miscellaneous areas in such an intricate
pattern or in such small areas that they cannot be shown separately on the maps.
The pattern and proportion of the soils or miscellaneous areas are somewhat similar
in all areas. Alpha-Beta complex, 0 to 6 percent slopes, is an example.
An association is made up of two or more geographically associated soils or
miscellaneous areas that are shown as one unit on the maps. Because of present
or anticipated uses of the map units in the survey area, it was not considered
practical or necessary to map the soils or miscellaneous areas separately. The
pattern and relative proportion of the soils or miscellaneous areas are somewhat
similar. Alpha-Beta association, 0 to 2 percent slopes, is an example.
An undifferentiated group is made up of two or more soils or miscellaneous areas
that could be mapped individually but are mapped as one unit because similar
interpretations can be made for use and management. The pattern and proportion
of the soils or miscellaneous areas in a mapped area are not uniform. An area can
be made up of only one of the major soils or miscellaneous areas, or it can be made
up of all of them. Alpha and Beta soils, 0 to 2 percent slopes, is an example.
Some surveys include miscellaneous areas. Such areas have little or no soil
material and support little or no vegetation. Rock outcrop is an example.
12
Custom Soil Resource Report
Description of Hudson
Setting
Landform: Lake plains
Landform position (two-dimensional): Summit
Landform position (three-dimensional): Tread
Down-slope shape: Concave
Across-slope shape: Convex
Parent material: Clayey and silty glaciolacustrine deposits
Typical profile
H1 - 0 to 11 inches: silt loam
H2 - 11 to 16 inches: silty clay loam
H3 - 16 to 31 inches: silty clay
H4 - 31 to 60 inches: clay
Properties and qualities
Slope: 3 to 8 percent
Depth to restrictive feature: More than 80 inches
Natural drainage class: Moderately well drained
Capacity of the most limiting layer to transmit water (Ksat): Moderately low to
moderately high (0.06 to 0.20 in/hr)
Depth to water table: About 18 to 24 inches
Frequency of flooding: None
Frequency of ponding: None
Calcium carbonate, maximum in profile: 15 percent
Available water storage in profile: High (about 9.7 inches)
Interpretive groups
Land capability classification (irrigated): None specified
Land capability classification (nonirrigated): 2e
Hydrologic Soil Group: C/D
Hydric soil rating: No
Minor Components
Rhinebeck
Percent of map unit: 5 percent
Hydric soil rating: No
13
Custom Soil Resource Report
Madalin
Percent of map unit: 2 percent
Landform: Depressions
Hydric soil rating: Yes
Unnamed soils
Percent of map unit: 2 percent
Claverack
Percent of map unit: 1 percent
Hydric soil rating: No
Description of Hudson
Setting
Landform: Lake plains
Landform position (two-dimensional): Summit
Landform position (three-dimensional): Riser
Down-slope shape: Concave
Across-slope shape: Convex
Parent material: Clayey and silty glaciolacustrine deposits
Typical profile
H1 - 0 to 11 inches: silt loam
H2 - 11 to 16 inches: silty clay loam
H3 - 16 to 31 inches: silty clay
H4 - 31 to 60 inches: clay
Properties and qualities
Slope: 25 to 45 percent
Depth to restrictive feature: More than 80 inches
Natural drainage class: Moderately well drained
Capacity of the most limiting layer to transmit water (Ksat): Moderately low to
moderately high (0.06 to 0.20 in/hr)
Depth to water table: About 18 to 24 inches
Frequency of flooding: None
14
Custom Soil Resource Report
Minor Components
Unadilla
Percent of map unit: 5 percent
Hydric soil rating: No
Unnamed soils
Percent of map unit: 5 percent
Colonie
Percent of map unit: 3 percent
Hydric soil rating: No
Udifluvents
Percent of map unit: 1 percent
Hydric soil rating: No
Fluvaquents
Percent of map unit: 1 percent
Landform: Flood plains
Hydric soil rating: Yes
Description of Rhinebeck
Setting
Landform: Lake plains
Landform position (two-dimensional): Footslope
15
Custom Soil Resource Report
Minor Components
Madalin
Percent of map unit: 5 percent
Landform: Depressions
Hydric soil rating: Yes
Raynham
Percent of map unit: 5 percent
Landform: Depressions
Hydric soil rating: Yes
16
Custom Soil Resource Report
Description of Rhinebeck
Setting
Landform: Lake plains
Landform position (two-dimensional): Footslope
Landform position (three-dimensional): Tread
Down-slope shape: Concave
Across-slope shape: Linear
Parent material: Clayey and silty glaciolacustrine deposits
Typical profile
H1 - 0 to 7 inches: silty clay loam
H2 - 7 to 34 inches: silty clay
H3 - 34 to 64 inches: silty clay
Properties and qualities
Slope: 3 to 8 percent
Depth to restrictive feature: More than 80 inches
Natural drainage class: Somewhat poorly drained
Capacity of the most limiting layer to transmit water (Ksat): Moderately low to
moderately high (0.06 to 0.20 in/hr)
Depth to water table: About 6 to 18 inches
Frequency of flooding: None
Frequency of ponding: None
Calcium carbonate, maximum in profile: 15 percent
Available water storage in profile: Moderate (about 8.5 inches)
Interpretive groups
Land capability classification (irrigated): None specified
Land capability classification (nonirrigated): 3w
Hydrologic Soil Group: C/D
Hydric soil rating: No
Minor Components
Claverack
Percent of map unit: 5 percent
Hydric soil rating: No
Madalin
Percent of map unit: 5 percent
Landform: Depressions
Hydric soil rating: Yes
Raynham
Percent of map unit: 5 percent
Landform: Depressions
Hydric soil rating: Yes
17
Custom Soil Resource Report
Minor Components
Scio
Percent of map unit: 10 percent
Hydric soil rating: No
Hudson
Percent of map unit: 10 percent
Hydric soil rating: No
Rhinebeck
Percent of map unit: 7 percent
Hydric soil rating: No
18
Custom Soil Resource Report
Madalin
Percent of map unit: 3 percent
Landform: Depressions
Hydric soil rating: Yes
Description of Unadilla
Setting
Landform: Lake plains
Landform position (two-dimensional): Summit
Landform position (three-dimensional): Tread
Down-slope shape: Convex
Across-slope shape: Convex
Parent material: Glaciolacustrine deposits, eolian deposits, or old alluvium,
comprised mainly of silt and very fine sand
Typical profile
H1 - 0 to 9 inches: silt loam
H2 - 9 to 64 inches: silt loam
Properties and qualities
Slope: 3 to 8 percent
Depth to restrictive feature: More than 80 inches
Natural drainage class: Well drained
Capacity of the most limiting layer to transmit water (Ksat): Moderately high to
high (0.57 to 1.98 in/hr)
Depth to water table: More than 80 inches
Frequency of flooding: None
Frequency of ponding: None
Available water storage in profile: High (about 11.5 inches)
Interpretive groups
Land capability classification (irrigated): None specified
Land capability classification (nonirrigated): 2e
19
Custom Soil Resource Report
Minor Components
Scio
Percent of map unit: 7 percent
Hydric soil rating: No
Unnamed soils
Percent of map unit: 5 percent
Raynham
Percent of map unit: 3 percent
Hydric soil rating: Yes
20
Soil Information for All Uses
"Erosion factor Kw (whole soil)" indicates the erodibility of the whole soil. The
estimates are modified by the presence of rock fragments.
21
Custom Soil Resource Report
4711800
4711700
4711700
4711600
4711600
4711500
4711500
4711400
4711400
4711300
4711300
4711200
4711200
4711100
4711100
4711000
4711000
.20 Not rated or not available The orthophoto or other base map on which the soil lines were
Water Features
compiled and digitized probably differs from the background
imagery displayed on these maps. As a result, some minor
shifting of map unit boundaries may be evident.
23
Custom Soil Resource Report
K Factor, Whole Soil— Summary by Map Unit — Albany County, New York (NY001)
Map unit symbol Map unit name Rating Acres in AOI Percent of AOI
HuB Hudson silt loam, 3 to 8 .49 14.8 35.6%
percent slopes
HuE Hudson silt loam, 25 to .49 0.8 1.8%
45 percent slopes
RhA Rhinebeck silty clay .49 19.2 46.4%
loam, 0 to 3 percent
slopes
RhB Rhinebeck silty clay .49 3.5 8.5%
loam, 3 to 8 percent
slopes
Uh Udorthents, clayey- 0.1 0.1%
Urban land complex
UnB Unadilla silt loam, 3 to 8 .37 3.1 7.6%
percent slopes
Totals for Area of Interest 41.4 100.0%
24
Custom Soil Resource Report
The soils in the United States are assigned to four groups (A, B, C, and D) and
three dual classes (A/D, B/D, and C/D). The groups are defined as follows:
Group A. Soils having a high infiltration rate (low runoff potential) when thoroughly
wet. These consist mainly of deep, well drained to excessively drained sands or
gravelly sands. These soils have a high rate of water transmission.
Group B. Soils having a moderate infiltration rate when thoroughly wet. These
consist chiefly of moderately deep or deep, moderately well drained or well drained
soils that have moderately fine texture to moderately coarse texture. These soils
have a moderate rate of water transmission.
Group C. Soils having a slow infiltration rate when thoroughly wet. These consist
chiefly of soils having a layer that impedes the downward movement of water or
soils of moderately fine texture or fine texture. These soils have a slow rate of water
transmission.
Group D. Soils having a very slow infiltration rate (high runoff potential) when
thoroughly wet. These consist chiefly of clays that have a high shrink-swell
potential, soils that have a high water table, soils that have a claypan or clay layer at
or near the surface, and soils that are shallow over nearly impervious material.
These soils have a very slow rate of water transmission.
If a soil is assigned to a dual hydrologic group (A/D, B/D, or C/D), the first letter is
for drained areas and the second is for undrained areas. Only the soils that in their
natural condition are in group D are assigned to dual classes.
25
Custom Soil Resource Report
4711800
4711700
4711700
4711600
4711600
4711500
4711500
4711400
4711400
4711300
4711300
4711200
4711200
4711100
4711100
4711000
4711000
B/D The orthophoto or other base map on which the soil lines were
compiled and digitized probably differs from the background
imagery displayed on these maps. As a result, some minor
shifting of map unit boundaries may be evident.
27
Custom Soil Resource Report
Hydrologic Soil Group— Summary by Map Unit — Albany County, New York (NY001)
Map unit symbol Map unit name Rating Acres in AOI Percent of AOI
HuB Hudson silt loam, 3 to 8 C/D 14.8 35.6%
percent slopes
HuE Hudson silt loam, 25 to C/D 0.8 1.8%
45 percent slopes
RhA Rhinebeck silty clay C/D 19.2 46.4%
loam, 0 to 3 percent
slopes
RhB Rhinebeck silty clay C/D 3.5 8.5%
loam, 3 to 8 percent
slopes
Uh Udorthents, clayey- 0.1 0.1%
Urban land complex
UnB Unadilla silt loam, 3 to 8 B 3.1 7.6%
percent slopes
Totals for Area of Interest 41.4 100.0%
28
References
American Association of State Highway and Transportation Officials (AASHTO).
2004. Standard specifications for transportation materials and methods of sampling
and testing. 24th edition.
American Society for Testing and Materials (ASTM). 2005. Standard classification of
soils for engineering purposes. ASTM Standard D2487-00.
Cowardin, L.M., V. Carter, F.C. Golet, and E.T. LaRoe. 1979. Classification of
wetlands and deep-water habitats of the United States. U.S. Fish and Wildlife
Service FWS/OBS-79/31.
Federal Register. July 13, 1994. Changes in hydric soils of the United States.
Federal Register. September 18, 2002. Hydric soils of the United States.
Hurt, G.W., and L.M. Vasilas, editors. Version 6.0, 2006. Field indicators of hydric
soils in the United States.
National Research Council. 1995. Wetlands: Characteristics and boundaries.
Soil Survey Division Staff. 1993. Soil survey manual. Soil Conservation Service.
U.S. Department of Agriculture Handbook 18. http://www.nrcs.usda.gov/wps/portal/
nrcs/detail/national/soils/?cid=nrcs142p2_054262
Soil Survey Staff. 1999. Soil taxonomy: A basic system of soil classification for
making and interpreting soil surveys. 2nd edition. Natural Resources Conservation
Service, U.S. Department of Agriculture Handbook 436. http://
www.nrcs.usda.gov/wps/portal/nrcs/detail/national/soils/?cid=nrcs142p2_053577
Soil Survey Staff. 2010. Keys to soil taxonomy. 11th edition. U.S. Department of
Agriculture, Natural Resources Conservation Service. http://
www.nrcs.usda.gov/wps/portal/nrcs/detail/national/soils/?cid=nrcs142p2_053580
Tiner, R.W., Jr. 1985. Wetlands of Delaware. U.S. Fish and Wildlife Service and
Delaware Department of Natural Resources and Environmental Control, Wetlands
Section.
United States Army Corps of Engineers, Environmental Laboratory. 1987. Corps of
Engineers wetlands delineation manual. Waterways Experiment Station Technical
Report Y-87-1.
United States Department of Agriculture, Natural Resources Conservation Service.
National forestry manual. http://www.nrcs.usda.gov/wps/portal/nrcs/detail/soils/
home/?cid=nrcs142p2_053374
United States Department of Agriculture, Natural Resources Conservation Service.
National range and pasture handbook. http://www.nrcs.usda.gov/wps/portal/nrcs/
detail/national/landuse/rangepasture/?cid=stelprdb1043084
29
Custom Soil Resource Report
30
Geotechnical Engineering Report
Propose Solar Power Facility
Selkirk, New York
November 13, 2015
Terracon Project No. J5155144
Prepared for:
Nextera Energy Resources
Portland, Oregon
Prepared by:
Terracon Consultants – NY, Inc.
Rochester, New York
TABLE OF CONTENTS
Page
EXECUTIVE SUMMARY ............................................................................................................ i
1.0 INTRODUCTION .............................................................................................................1
2.0 PROJECT INFORMATION .............................................................................................1
2.1 Project Description..................................................................................... 1
2.2 Site Location and Description .................................................................... 2
3.0 SUBSURFACE EXPLORATIONS AND CONDITIONS ...................................................2
3.1 Typical Profile ............................................................................................ 2
3.2 Groundwater .............................................................................................. 3
3.3 Laboratory Testing ..................................................................................... 4
4.0 RECOMMENDATIONS FOR DESIGN AND CONSTRUCTION ......................................5
4.1 Geotechnical Considerations ..................................................................... 5
4.2 Earthwork................................................................................................... 5
4.2.1 Site Preparation ....................................................................................... 5
4.2.2 Material Types.......................................................................................... 6
4.2.3 Compaction Requirements ....................................................................... 7
4.2.4 Trench Backfill.......................................................................................... 7
4.2.5 Grading and Drainage .............................................................................. 7
4.2.6 Earthwork Construction Considerations.................................................... 7
4.3 Foundation Recommendations .................................................................. 8
4.3.1 Foundations ............................................................................................. 8
4.3.1.1 Driven Post Design Recommendations ......................................8
4.3.1.2 Driven Post Construction Considerations ...................................8
4.3.1.3 Drilled Shaft Foundation Design Recommendations ..................9
4.3.1.4 Drilled Shaft Foundation Construction Considerations .............10
4.3.1.5 Ballasted Foundation Design Recommendations .....................10
4.3.1.6 Ballasted Foundation Construction Considerations ..................10
4.3.2 Ancillary Equipment Foundations ........................................................... 10
4.3.2.1 Slab Design Recommendations ...............................................11
4.3.2.2 Slab Construction Considerations ............................................11
4.4 Seismic Considerations ........................................................................... 12
4.5 Gravel Roadway ...................................................................................... 12
4.5.1 Gravel Roadway Design Recommendations .......................................... 12
4.5.2 Gravel Roadway Construction Considerations ....................................... 12
5.0 GENERAL COMMENTS ...............................................................................................13
EXECUTIVE SUMMARY
A geotechnical engineering report has been completed for the proposed solar power facility
consisting of ground-mounted fixed tilt photovoltaic panel arrays in Selkirk, New York. Twelve
test borings and four test pits were advanced to depths ranging from about 8 to 17 feet below
the existing ground surface to provide geotechnical information.
Site is underlain by a glaciolacustrine deposit with an upper stratum of medium stiff to very stiff
lean clay over a stratum of soft to medium stiff fat clay. The following geotechnical
considerations for project design and construction were identified and are discussed in the
report:
n The proposed solar arrays may be supported on driven steel posts or drilled
shafts embedded in the upper native glaciolacustrine clay. As an alternative, the
photovoltaic panels may be founded on ballasted foundations at the ground
surface.
n The drilled shafts and driven steel posts should not extend more than about 10
feet below existing grades because of the presence of underlying softer clay.
n The site is judged to be International Building Code (IBC) seismic Site Class “E”.
This summary should be used in conjunction with the entire report for design purposes. Details
are not included or fully developed in this summary; the report must be read in its entirety for a
comprehensive understanding of the information contained herein. The section titled
GENERAL COMMENTS should be read for an understanding of the report limitations.
1.0 INTRODUCTION
The geotechnical engineering evaluation for the proposed photovoltaic (PV) panel installations
in Selkirk, New York, as shown on the Site Location Map (Exhibit A-1) in Appendix A, has been
completed. Twelve test borings (B-1 through B-12) and four test pits (TP-1 through TP-4) were
advanced throughout the site to depths ranging from 8 to 17 feet below existing ground surface
to provide geotechnical information. An Exploration Location Diagram (Exhibit A-2) and
individual exploration logs are included in Appendix A.
The project site, which is agricultural land, is located on the northwest side of Bridge Street (Rte.
396), approximately ¼ mile west of its intersection with Lasher Road in Selkirk, a hamlet in the
town of Bethlehem, Albany County, New York. A National Grid substation borders the site to
the south. The site is undulating, sloping down to the northwest towards the Vloman Kill.
Our knowledge of the project is based on our recent discussions and review of your “Preliminary
Site Plan”, Drawing No. E-1, dated February 4, 2015. The overall project will consist of the
construction of a 10.4-Megawatt (MW) DC solar array field with the installation of ground-
mounted photovoltaic arrays. Access to the site will be provided from both Bridge Street and
the substation. A summary description of the project is presented below:
Geotechnical Engineering Report
Proposed Solar Power Facility ■ Selkirk, New York
November 13, 2015 ■ Terracon Project No. J5155144
Item Description
Site layout Appendix A, Exhibit A-2, Exploration Location Diagram.
Ground-mounted photovoltaic panel arrays with various electrical
Structures
appurtenances, including transformers and inverters.
Assumed array construction Steel-framed
2 to 3 kips (axial)
Estimated maximum loads
1 to 2 kips (lateral)
Minor cuts and fill, up to about 2 feet or so, anticipated to develop
Grading
the site.
Item Description
Approximately 72-acre field, northwest of Bridge Street,
Location approximately ¼ mile west of its intersection with Lasher Road, in
hamlet of Selkirk, town of Bethlehem, New York.
Existing improvements Agricultural field
Current ground cover Grass
Existing topography Undulating, sloping down to the northwest towards the Vloman Kill
Based on the results of the explorations and observations at the time of fieldwork, subsurface
conditions on the project site can be generalized as follows:
Approximate Depth
1 Consistency / Relative
Description to Bottom of Stratum Material Encountered
Density
(feet)
Upper
Lean clay (CL), trace to little
Glaciolacustrine 9 to 15 Medium stiff to very stiff
fine sand, brown
Deposit
Lower
Soft (occasionally
Glaciolacustrine >17 Fat clay (CH), gray
medium stiff)
Deposit
1. Topsoil (about 3 to 12 inches in thickness) was encountered at the ground surface in the
explorations.
The Surficial Geologic Map of New York – Hudson-Mohawk Sheet (1987) identifies the soil
underlying the site as a glaciolacustrine deposit. The Geologic Map of New York – Hudson-
Mohawk Sheet (1970) identifies the bedrock, at depth, in the vicinity of the site as shale.
However, bedrock was not encountered.
B-1 through B-12 terminated without refusal in the lower glaciolacustrine deposit at a depth of
approximately 17 feet below the existing ground surface. TP-1 through TP-4 terminated without
refusal in the upper glaciolacustrine deposit at a depth of about 8 feet.
Conditions encountered at each exploration location are indicated on the individual exploration
logs in Appendix A of this report. Stratification boundaries on the exploration logs represent the
approximate location of changes in soil types; in situ, the transition between materials may be
gradual. Further details of the explorations can be found on the exploration logs.
3.2 Groundwater
Groundwater was encountered in the test borings at a depth of approximately 15 feet below
existing ground surface prior to casing removal. However, upon removal of the casing, the
borings caved at depths ranging from approximately 5 to 13 feet, possibly indicating layers of
more permeable, water-bearing material. Groundwater was encountered in the test pits at
depths ranging from approximately 7 to 8 feet.
Fluctuations in groundwater level may occur because of seasonal variations in the amount of
rainfall, runoff, and other factors. Additionally, grade adjustments on and around the site, as
well as surrounding drainage improvements, may affect the water table. The possibility of
groundwater level fluctuations should be considered when developing the design and
construction plans for the project. Groundwater levels are tabulated below:
The following laboratory testing was performed on representative soil samples from the borings
taken at the site:
The results of the moisture contents and estimates of unconfined compressive strength are
presented on the boring logs in Appendix A. The results of the grain size distributions and
Atterberg limits are presented in Appendix B. The results of the corrosivity testing are tabulated
below:
The results of the laboratory soil resistivity results indicate that the site soils are highly corrosive.
The pH of the soils was measured at 8.4 and 8.6, i.e., moderately to strongly alkaline. These
test results are provided to assist in determining the type and degree of corrosion protection that
may be required. We recommend that a certified corrosion engineer be employed to determine
the need for corrosion protection and to design appropriate protective measures, if required.
Subsurface conditions throughout the site consist of an approximately 9- to 15-foot thick layer of
medium stiff to very stiff lean clay over soft to medium stiff fat clay. Based on these
encountered subsurface conditions, we recommend that the proposed photovoltaic panels be
supported on either drilled shafts or driven steel posts, which should not extend more than
about 10 feet below existing grade because of the presence of the underlying softer clay. As an
alternative, the photovoltaic panels may be founded on ballasted foundations at the ground
surface. We recommend that lightly-loaded equipment cabinets and other ancillary structures
be founded on slabs deriving support from the native clay. Our recommendations are based on
significant areas of fill not exceeding a thickness of about 2 feet. The clay is easily disturbed by
construction activity, exacerbated by excess moisture; care should be exercised during
construction. Design recommendations are presented below.
4.2 Earthwork
Construction traffic over the completed subgrade should be avoided to the extent practical. The
site should also be graded to prevent ponding of surface water on the prepared subgrades or in
any excavations. If the subgrade should become frozen, wet, or disturbed, the affected material
should be removed, or should be scarified, moisture conditioned, and recompacted or replaced
with structural fill.
conditions. The contractor, by his contract, is usually responsible for designing and constructing
stable, temporary excavations and should shore, slope or bench the sides of the excavations,
as required, to maintain stability of both the excavation sides and bottom. All excavations
should comply with applicable local, State, and federal safety regulations, including the current
OSHA Excavation and Trench Safety Standards.
The geotechnical engineer should be retained during the construction phase of the project to
observe earthwork and to perform necessary tests and observations during subgrade
preparation; proofrolling; placement and compaction of controlled compacted fills; and
construction of foundations.
4.3.1 Foundations
We recommend the photovoltaic panels be supported on either driven steel posts or drilled
shafts. The depth of the posts and shafts will be limited by the presence of soft clay below
about 10 feet from existing grade. Alternatively, the photovoltaic panels may be founded on
ballasted foundations at the ground surface. Design recommendations and construction
considerations for the recommended foundation systems are presented in the following
paragraphs and tables.
Driving resistance should be correlated to vertical load capacity, based on the equipment used
to install the posts. A minimum factor of safety of 2 should be applied to the vertical load
capacity. Full-scale pull-out testing should be performed on selected posts to determine uplift
capacity. A minimum factor of safety of 1.5 should be applied to the uplift capacity. Full-scale
lateral load testing should also be performed. The required lateral capacity should be mobilized
with less than ½ inch of movement at ground level. Corrosion protection should be applied to
the steel posts, if warranted by the results of the testing presented in this report.
should be replaced. The explorations did not encounter material that would present a significant
obstruction to driving the steel posts; however, should obstructions be encountered, pre-
augering the post holes may be required to facilitate driving.
The base of the drilled shaft should be in the clay, at least 4 feet below ground surface;
however, we do not recommend that the drilled shafts extend deeper than 10 feet (based on
existing grades), because of the underlying soft clay. The drilled shafts will be designed to
resist tension loads and therefore should have reinforcing steel installed throughout the entire
length of the shaft. Technical specifications should be prepared that require material and
installation detail submittals, proof of experience in drilled shaft installation, concrete placement
methods, and the use and removal of temporary steel casing.
We recommend the 12-inch thick granular support layer beneath the slabs in order to provide
both a uniform bearing surface and a capillary break between the underlying clay and the
concrete and to allow the slab to adjust to any variation in the support characteristics of the
native soils. Should this layer be omitted, there is the possibility of distress in the slab due to
differential movement and of moisture in the concrete of the slab. However, provided the soil
support characteristics are uniform over the area of the slab and the capillary break is not
required, the slab could be placed directly on the underlying clay. In this case, the modulus of
subgrade reaction should be reduced to 100 psi/in and the net allowable bearing pressure
reduced to 1,000 psf.
We recommend the area underlying the slabs be rough graded and then thoroughly proofrolled
with a heavy roller compactor without vibration prior to final grading and placement of the
granular support layer. Particular attention should be paid to high traffic areas that were rutted
and disturbed earlier and to areas previously filled or backfilled. Areas where unsuitable or
unstable conditions are located should be repaired by removing and replacing the affected
material with properly compacted the granular support layer material, as necessary.
Description Value
Code Used 1 2010 Building Code of New York State (NYS Code)
Site Class 2 E
Maximum considered earthquake 0.068g (S1 – 1.0 second spectral response acceleration)
ground motions (5 percent damping)
0.226g (Ss – 0.2 second spectral response acceleration)
heavy roller compactor without vibration, before being proofrolled with a loaded tandem-axle
dump truck. Particular attention should be paid to high traffic areas that were rutted and
disturbed, and areas where backfilled trenches are located. Areas where unsuitable conditions
are located should be repaired by replacing the materials with properly compacted fill. When
proofrolling/subgrade stabilization has been completed to the satisfaction of the geotechnical
engineer, the geotextile may be placed followed by the crushed stone.
Future performance of the gravel roadway constructed on the site will be partially dependent
upon maintaining stable moisture content of the subgrade soil. The performance may be
enhanced by reducing excess moisture that can reach the subgrade soils, for example, by
grading to a minimum 2 percent slope away from the roadway.
Terracon should be retained to review the final design plans and specifications, so comments
can be made regarding interpretation and implementation of our geotechnical recommendations
in the design and specifications. Terracon also should be retained to provide observation and
testing services during grading, excavation, foundation construction, and other earth-related
construction phases of the project.
The analysis and recommendations presented in this report are based upon the data obtained
from the explorations performed at the indicated locations and from other information discussed
in this report. This report does not reflect variations that may occur between explorations,
across the site, or due to the modifying effects of weather. The nature and extent of such
variations may not become evident until during or after construction. If variations appear, we
should be immediately notified so that further evaluation and supplemental recommendations
can be provided.
The scope of services for this project does not include either specifically or by implication any
environmental or biological (e.g., mold, fungi, bacteria) assessment of the site or identification or
prevention of pollutants, hazardous materials, or conditions. If the owner is concerned about the
potential for such contamination or pollution, other studies should be undertaken.
This report has been prepared for the exclusive use of our client for specific application to the
project discussed and prepared in accordance with generally accepted geotechnical engineering
practices. No warranties, either express or implied, are intended or made. Site safety,
excavation support, and dewatering requirements are the responsibility of others. In the event
that changes in the nature, design, or location of the project as outlined in this report are
planned, the conclusions and recommendations contained in this report shall not be considered
valid unless Terracon reviews the changes and either verifies or modifies the conclusions of this
report in writing.
1 .5 0 1 KILOMETER
The approximate exploration locations, which are shown Exhibit A-2, were measured by taping
from existing features in the field and by estimating right angles. The locations of the
explorations should be considered accurate only to the degree implied by the method used to
define them. The ground elevations were not provided at the time of this report.
Terracon monitored the advancement of 12 test borings (B-1 through B-12) on September 24
and 25, 2015. The borings were advanced using 2¼-inch inside diameter continuous flight
hollow-stem augers (HSA) with a truck-mounted CME-55 rotary drill rig, owned and operated by
Northeast Specialized Drilling, Inc. of Liverpool, New York. The borings terminated without
refusal in the lower glaciolacustrine deposit at a depth of about 17 feet below the existing
ground surface.
In the split-barrel sampling procedure, which was used to take soil samples in the test borings,
the number of blows required to advance a standard 2-inch O.D. split-barrel sampler typically
the middle 12 inches of the total 24-inch penetration by means of a 140-pound autohammer with
a free fall of 30 inches is the Standard Penetration Test (SPT) resistance value “N”. This “N”
value is used to estimate the in-situ relative density of cohesionless soils and consistency of
cohesive soils.
Terracon monitored four test pits on September 24, 2015. The test pits were excavated using a
Kubota KX1213 track-mounted mini-excavator owned and operated by JKS Contracting LLC of
Averill Park, New York. The test pits were terminated in the upper glaciolacustrine deposit at
approximately 8 feet below existing ground surface.
The samples were placed in labeled glass jars and transported to our Rocky Hill (Hartford)
laboratory for further review by a Terracon geotechnical engineer, laboratory testing, and
classification. Information provided on the exploration logs attached to this report includes soil
descriptions, relative density and/or consistency evaluations, exploration depths, sampling
intervals, and groundwater conditions. The borings were backfilled with auger cuttings prior to
the drill crew leaving the site. The excavator backfilled the test pits after our observations.
Field logs of the explorations were prepared by a Terracon field engineer. These logs included
visual classifications of the materials encountered during explorations as well as interpretation
by our field engineer of the subsurface conditions between samples. Final exploration logs
included with this report represent further interpretation by the geotechnical engineer of the field
logs and incorporate, where appropriate, modifications based on laboratory classification of the
samples.
Exhibit A-3
BORING LOG NO. B-1 Page 1 of 1
PROJECT: Proposed Solar Power Facility CLIENT: Nextera Energy Resources
Portland, Oregon
SITE: 93 Bridge Street
Selkirk, New York
TORVANE/HP (tsf)
LOCATION See Exhibit A-2
OBSERVATIONS
RECOVERY (In.)
GRAPHIC LOG
SAMPLE TYPE
WATER LEVEL
LABORATORY
CONTENT (%)
FIELD TEST
DEPTH (Ft.)
RESULTS
WATER
DEPTH
0.7 TOPSOIL
3-4-5-7 4
LEAN CLAY (CL), trace to little fine sand, brown, medium stiff to very stiff, 15
N=9 (HP)
(UPPER GLACIOLACUSTRINE DEPOSIT)
7-9-13-12 3.5
20
N=22 (HP)
5
5-4-4-6 4.5
24
N=8 (HP)
6-8-7-8 3
24
N=15 (HP)
10.0
FAT CLAY (CH), gray, soft,
10
(LOWER GLACIOLACUSTRINE DEPOSIT) 3-2-1-2 0.25
24
N=3 (HP)
GEO SMART LOG-NO WELL J5155144 LOGS.GPJ
15
WOH-1-1-1 0.25
24
N=2 (HP)
17.0
Boring Terminated at 17 Feet
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT.
TORVANE/HP (tsf)
LOCATION See Exhibit A-2
OBSERVATIONS
RECOVERY (In.)
GRAPHIC LOG
SAMPLE TYPE
WATER LEVEL
LABORATORY
CONTENT (%)
FIELD TEST
DEPTH (Ft.)
RESULTS
WATER
DEPTH
TOPSOIL
0.8
3-3-3-4
LEAN CLAY (CL), trace to little fine sand, brown, medium stiff to very stiff, 15
N=6
(UPPER GLACIOLACUSTRINE DEPOSIT)
3-4-4-7
20
N=8
5
4-4-7-8
20
N=11
8-8-8-8
20 22
N=16
10
2-2-2-2
24
N=4
GEO SMART LOG-NO WELL J5155144 LOGS.GPJ
15.0
FAT CLAY (CH), gray, soft,
15
(LOWER GLACIOLACUSTRINE DEPOSIT) WOH-1-1-1
24
N=2
17.0
Boring Terminated at 17 Feet
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT.
TORVANE/HP (tsf)
LOCATION See Exhibit A-2
OBSERVATIONS
RECOVERY (In.)
GRAPHIC LOG
SAMPLE TYPE
WATER LEVEL
LABORATORY
CONTENT (%)
FIELD TEST
DEPTH (Ft.)
RESULTS
WATER
DEPTH
TOPSOIL
1.0 2-3-3-4
20
LEAN CLAY (CL), trace to little fine sand, brown, medium stiff to very stiff, N=6
(UPPER GLACIOLACUSTRINE DEPOSIT)
6-6-8-10
15
N=14
5
8-7-8-9
20
N=15
6-7-5-5
14 30
N=12
10
3-6-16-15
16
N=22
GEO SMART LOG-NO WELL J5155144 LOGS.GPJ
15.0
FAT CLAY (CH), gray, soft,
15
(LOWER GLACIOLACUSTRINE DEPOSIT) 1-1-1-1
15
N=2
17.0
Boring Terminated at 17 Feet
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT.
TORVANE/HP (tsf)
LOCATION See Exhibit A-2
OBSERVATIONS
RECOVERY (In.)
GRAPHIC LOG
SAMPLE TYPE
WATER LEVEL
LABORATORY
CONTENT (%)
FIELD TEST
DEPTH (Ft.)
RESULTS
WATER
DEPTH
0.5 TOPSOIL
LEAN CLAY (CL), trace to little fine sand, brown, medium stiff to very stiff, 3-4-4-5
14
(UPPER GLACIOLACUSTRINE DEPOSIT) N=8
6-8-7-8
18
N=15
5
4-5-5-4
16
N=10
5-5-5-5
14
N=10
10
3-6-7-14
20
N=13
GEO SMART LOG-NO WELL J5155144 LOGS.GPJ
15.0
FAT CLAY (CH), gray, soft,
15
(LOWER GLACIOLACUSTRINE DEPOSIT) 1-2-1-1
22
N=3
17.0
Boring Terminated at 17 Feet
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT.
TORVANE/HP (tsf)
LOCATION See Exhibit A-2
OBSERVATIONS
RECOVERY (In.)
GRAPHIC LOG
SAMPLE TYPE
WATER LEVEL
LABORATORY
CONTENT (%)
FIELD TEST
DEPTH (Ft.)
RESULTS
WATER
DEPTH
TOPSOIL
0.8
3-3-4-4
LEAN CLAY (CL), trace to little fine sand, brown, medium stiff to stiff, 18
N=7
(UPPER GLACIOLACUSTRINE DEPOSIT)
5-6-8-9
16
N=14
5
4-5-6-8
14
N=11
6-7-6-6
15
N=13
10.0
FAT CLAY (CH), gray, soft,
10
(LOWER GLACIOLACUSTRINE DEPOSIT) 1-1-1-3
13
N=2
GEO SMART LOG-NO WELL J5155144 LOGS.GPJ
15
2-1-1-1
20
N=2
17.0
Boring Terminated at 17 Feet
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT.
TORVANE/HP (tsf)
LOCATION See Exhibit A-2
OBSERVATIONS
RECOVERY (In.)
GRAPHIC LOG
SAMPLE TYPE
WATER LEVEL
LABORATORY
CONTENT (%)
FIELD TEST
DEPTH (Ft.)
RESULTS
WATER
DEPTH
0.4 TOPSOIL
LEAN CLAY (CL), trace to little fine sand, brown, medium stiff to very stiff, 2-2-3-3
11
(UPPER GLACIOLACUSTRINE DEPOSIT) N=5
6-10-8-7
14
N=18
5
8-8-8-9
20
N=16
7-7-6-7
16
N=13
10.0
FAT CLAY (CH), gray, soft to medium stiff,
10
(LOWER GLACIOLACUSTRINE DEPOSIT) 2-2-3-3
18
N=5
GEO SMART LOG-NO WELL J5155144 LOGS.GPJ
15
1-1-1-2
14
N=2
17.0
Boring Terminated at 17 Feet
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT.
TORVANE/HP (tsf)
LOCATION See Exhibit A-2
OBSERVATIONS
RECOVERY (In.)
GRAPHIC LOG
SAMPLE TYPE
WATER LEVEL
LABORATORY
CONTENT (%)
FIELD TEST
DEPTH (Ft.)
RESULTS
WATER
DEPTH
0.6 TOPSOIL
LEAN CLAY (CL), trace to little fine sand, brown, medium stiff to stiff, 3-3-3-4
16
(UPPER GLACIOLACUSTRINE DEPOSIT) N=6
4-6-5-5
18
N=11
5
4-4-6-6
14
N=10
5-5-4-5
10
N=9
10.0
FAT CLAY (CH), gray, soft to medium stiff,
10
(LOWER GLACIOLACUSTRINE DEPOSIT) 3-3-2-3
17
N=5
GEO SMART LOG-NO WELL J5155144 LOGS.GPJ
15
1-1-2-1
24
N=3
17.0
Boring Terminated at 17 Feet
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT.
TORVANE/HP (tsf)
LOCATION See Exhibit A-2
OBSERVATIONS
RECOVERY (In.)
GRAPHIC LOG
SAMPLE TYPE
WATER LEVEL
LABORATORY
CONTENT (%)
FIELD TEST
DEPTH (Ft.)
RESULTS
WATER
DEPTH
0.2 TOPSOIL
LEAN CLAY (CL), trace to little fine sand, brown, medium stiff to very stiff, 3-4-4-5
12
(UPPER GLACIOLACUSTRINE DEPOSIT) N=8
6-10-10-6
20
N=20
5
4-4-4-5
15
N=8
7-6-7-7
10
N=13
10.0
FAT CLAY (CH), gray, soft to medium stiff,
10
(LOWER GLACIOLACUSTRINE DEPOSIT) 1-2-2-2
20
N=4
GEO SMART LOG-NO WELL J5155144 LOGS.GPJ
15
WOH-1-1-1
4
N=2
17.0
Boring Terminated at 17 Feet
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT.
TORVANE/HP (tsf)
LOCATION See Exhibit A-2
OBSERVATIONS
RECOVERY (In.)
GRAPHIC LOG
SAMPLE TYPE
WATER LEVEL
LABORATORY
CONTENT (%)
FIELD TEST
DEPTH (Ft.)
RESULTS
WATER
DEPTH
0.7 TOPSOIL
2-4-4-5
LEAN CLAY (CL), trace to little fine sand, brown, medium stiff to very stiff, 14
N=8
(UPPER GLACIOLACUSTRINE DEPOSIT)
8-11-11-13
20
N=22
5
4-4-3-3
15
N=7
3-4-4-6
20
N=8
10.0
FAT CLAY (CH), gray, soft to medium stiff,
10
(LOWER GLACIOLACUSTRINE DEPOSIT) 3-3-2-3
18
N=5
GEO SMART LOG-NO WELL J5155144 LOGS.GPJ
15
2-1-1-2
15
N=2
17.0
Boring Terminated at 17 Feet
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT.
TORVANE/HP (tsf)
LOCATION See Exhibit A-2
OBSERVATIONS
RECOVERY (In.)
GRAPHIC LOG
SAMPLE TYPE
WATER LEVEL
LABORATORY
CONTENT (%)
FIELD TEST
DEPTH (Ft.)
RESULTS
WATER
DEPTH
0.4 TOPSOIL
LEAN CLAY (CL), trace to little fine sand, brown, medium stiff to very stiff, 2-3-4-4
12
(UPPER GLACIOLACUSTRINE DEPOSIT) N=7
5-9-11-12
16
N=20
5
6-9-11-14
14
N=20
10-12-17-12
14
N=29
10.0
FAT CLAY (CH), gray, soft,
10
(LOWER GLACIOLACUSTRINE DEPOSIT) 1-2-1-1
20
N=3
GEO SMART LOG-NO WELL J5155144 LOGS.GPJ
15
2-1-2-1
18
N=3
17.0
Boring Terminated at 17 Feet
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT.
TORVANE/HP (tsf)
LOCATION See Exhibit A-2
OBSERVATIONS
RECOVERY (In.)
GRAPHIC LOG
SAMPLE TYPE
WATER LEVEL
LABORATORY
CONTENT (%)
FIELD TEST
DEPTH (Ft.)
RESULTS
WATER
DEPTH
0.5 TOPSOIL
LEAN CLAY (CL), trace to little fine sand, brown, medium stiff to very stiff, 3-4-5-6
13
(UPPER GLACIOLACUSTRINE DEPOSIT) N=9
8-9-9-10 4.5
20
N=18 (HP)
5
8-7-10-10
20
N=17
8-10-13-15 2.5
12
N=23 (HP)
10.0
FAT CLAY (CH), gray, soft to medium stiff,
10
(LOWER GLACIOLACUSTRINE DEPOSIT) 2-2-2-2 1.5
19 53
N=4 (HP)
GEO SMART LOG-NO WELL J5155144 LOGS.GPJ
15
2-2-2-1 0.25
18
N=4 (HP)
17.0
Boring Terminated at 17 Feet
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT.
TORVANE/HP (tsf)
LOCATION See Exhibit A-2
OBSERVATIONS
RECOVERY (In.)
GRAPHIC LOG
SAMPLE TYPE
WATER LEVEL
LABORATORY
CONTENT (%)
FIELD TEST
DEPTH (Ft.)
RESULTS
WATER
DEPTH
0.7 TOPSOIL
2-2-2-4
LEAN CLAY (CL), trace to little fine sand, brown, medium stiff to very stiff, 17
N=4
(UPPER GLACIOLACUSTRINE DEPOSIT)
6-7-9-8
14
N=16
5
5-6-16-6
10
N=22
3-2-2-3
15
N=4
9.0
FAT CLAY (CH), gray, soft,
(LOWER GLACIOLACUSTRINE DEPOSIT)
10
1-2-1-2
17
N=3
GEO SMART LOG-NO WELL J5155144 LOGS.GPJ
15
1-1-1-1
12
N=2
17.0
Boring Terminated at 17 Feet
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT.
OBSERVATIONS
RECOVERY (In.)
GRAPHIC LOG
SAMPLE TYPE
WATER LEVEL
LABORATORY
CONTENT (%)
FIELD TEST
DEPTH (Ft.)
RESULTS
WATER
HP (tsf)
DEPTH
0.7 TOPSOIL
LEAN CLAY (CL), trace to little fine sand, brown,
(UPPER GLACIOLACUSTRINE DEPOSIT)
8.0
Test Pit Terminated at 8 Feet
GEO SMART LOG-NO WELL J5155144 LOGS.GPJ
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT.
WATER LEVEL OBSERVATIONS Test Pit Started: 9/24/2015 Test Pit Completed: 9/24/2015
7' While Excavating
Excavator: Kubota KX1213 Operator: J. Svennson
15 Marway Circle, Suite 2B
Rochester, New York Project No.: J5155144 Exhibit: A-16
TEST PIT LOG NO. TP-2 Page 1 of 1
PROJECT: Proposed Solar Power Facility CLIENT: Nextera Energy Resources
Portland, Oregon
SITE: 93 Bridge Street
Selkirk, New York
LOCATION See Exhibit A-2
OBSERVATIONS
RECOVERY (In.)
GRAPHIC LOG
SAMPLE TYPE
WATER LEVEL
LABORATORY
CONTENT (%)
FIELD TEST
DEPTH (Ft.)
RESULTS
WATER
HP (tsf)
DEPTH
0.7 TOPSOIL
LEAN CLAY (CL), trace to little fine sand, brown,
(UPPER GLACIOLACUSTRINE DEPOSIT)
8.0
Test Pit Terminated at 8 Feet
GEO SMART LOG-NO WELL J5155144 LOGS.GPJ
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT.
WATER LEVEL OBSERVATIONS Test Pit Started: 9/24/2015 Test Pit Completed: 9/24/2015
8' While Excavating
Excavator: Kubota KX1213 Operator: J. Svennson
15 Marway Circle, Suite 2B
Rochester, New York Project No.: J5155144 Exhibit: A-17
TEST PIT LOG NO. TP-3 Page 1 of 1
PROJECT: Proposed Solar Power Facility CLIENT: Nextera Energy Resources
Portland, Oregon
SITE: 93 Bridge Street
Selkirk, New York
LOCATION See Exhibit A-2
OBSERVATIONS
RECOVERY (In.)
GRAPHIC LOG
SAMPLE TYPE
WATER LEVEL
LABORATORY
CONTENT (%)
FIELD TEST
DEPTH (Ft.)
RESULTS
WATER
HP (tsf)
DEPTH
0.7 TOPSOIL
LEAN CLAY (CL), trace to little fine sand, brown,
(UPPER GLACIOLACUSTRINE DEPOSIT)
8.0
Test Pit Terminated at 8 Feet
GEO SMART LOG-NO WELL J5155144 LOGS.GPJ
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT.
WATER LEVEL OBSERVATIONS Test Pit Started: 9/24/2015 Test Pit Completed: 9/24/2015
9' While Excavating
Excavator: Kubota KX1213 Operator: J. Svennson
15 Marway Circle, Suite 2B
Rochester, New York Project No.: J5155144 Exhibit: A-18
TEST PIT LOG NO. TP-4 Page 1 of 1
PROJECT: Proposed Solar Power Facility CLIENT: Nextera Energy Resources
Portland, Oregon
SITE: 93 Bridge Street
Selkirk, New York
LOCATION See Exhibit A-2
OBSERVATIONS
RECOVERY (In.)
GRAPHIC LOG
SAMPLE TYPE
WATER LEVEL
LABORATORY
CONTENT (%)
FIELD TEST
DEPTH (Ft.)
RESULTS
WATER
HP (tsf)
DEPTH
0.7 TOPSOIL
LEAN CLAY (CL), trace to little fine sand, brown,
(UPPER GLACIOLACUSTRINE DEPOSIT)
8.0
Test Pit Terminated at 8 Feet
GEO SMART LOG-NO WELL J5155144 LOGS.GPJ
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT.
WATER LEVEL OBSERVATIONS Test Pit Started: 9/24/2015 Test Pit Completed: 9/24/2015
8' While Excavating
Excavator: Kubota KX1213 Operator: J. Svennson
15 Marway Circle, Suite 2B
Rochester, New York Project No.: J5155144 Exhibit: A-19
APPENDIX B
LABORATORY TESTING
Geotechnical Engineering Report
Proposed Solar Power Facility ■ Selkirk, New York
November 13, 2015 ■ Terracon Project No. J5155144
Descriptive classifications of the soils indicated on the exploration logs are in accordance with
the enclosed General Notes and the Unified Soil Classification System (USCS). USCS symbols
are also shown. A brief description of the USCS is attached to this report. Classification was
generally by visual/manual procedures aided by the results of the laboratory testing.
The following laboratory testing was performed on representative soil samples from the borings
taken at the site:
The results of the corrosivity testing are tabulated in Section 3.3 of this report. The results of
the moisture contents and estimates of unconfined compressive strength are presented on the
boring logs in Appendix A. The results of the grain size distributions and Atterberg limits are
presented in Appendix B.
Exhibit B-1
GRAIN SIZE DISTRIBUTION TEST REPORT
ASTM TEST METHOD: D422
#100
#200
2.50
#10
#18
#20
#40
#60
3.5
1.5
3/4
1/2
3/8
1/4
#4
8
1
100
90
Specification Maximum
70
PERCENT FINER
60
50
40
30
20
10
0
100.0
10.0
1.00
0.100
0.01
0.001
GRAIN SIZE -- mm
% Cobbles % Gravel Coarse Medium Fine % Fines
0 12 88 Silt (>0.002mm) Clay (<0.002mm)
0 0 % Sand 1.4 59.2 39.4
Classification: Lean clay (CL), brown
Project: Proposed Solar Power Facility Project No.: J5155144 Date: 11/12/2015
City: Selkirk, New York Specification: Terracon Structural Fill Report No: J5155144.0001
Source: B-3 Sampled from: 7 to 9 feet (Upper Glaciolacustrine Deposit)
15 Marway Circle, Suite 2B Remarks:
Rochester, New York D10 (mm)=0.00
585-247-3471 (p) Tested By: C. Klopfer Date: 10/14/2015
http://www.terracon.com/ Reviewed By: B.D.O Date: 11/12/2015
ASTM C136GSP1, Rev. 6
Exhibit B-2
GRAIN SIZE DISTRIBUTION TEST REPORT
ASTM TEST METHOD: D422
#100
#200
2.50
#10
#18
#20
#40
#60
3.5
1.5
3/4
1/2
3/8
1/4
#4
8
1
100
90
% Passing (Total Sample)
80 Specification Minimum
Specification Maximum
70
PERCENT FINER
60
50
40
30
20
10
0
10.000
1.000
0.100
0.010
0.001
100.000
GRAIN SIZE -- mm
% Cobbles % Gravel Coarse Medium Fine % Fines
0 61 39 Silt (>0.002mm) Clay (<0.002mm)
0 0 % Sand 0.3 31.7 68.0
Classification: Lean clay (CL), brown
Project: Proposed Solar Power Facility Project No.: J5155144 Date: 11/12/2015
City: Selkirk, New York Specification: Terracon Structural Fill Report No: J5155144.0002
Source: B-11 Sampled from: 10 to 12 feet (Upper Glaciolacustrine Deposit)
15 Marway Circle, Suite 2B Remarks:
Rochester, New York D10 (mm)=0.00
585-247-3471 (p) Tested By: C. Klopfer Date: 10/14/2015
http://www.terracon.com/ Reviewed By: B.D.O Date: 11/12/2015
ASTM C136GSP1, Rev. 6
Exhibit B-3
APPENDIX C
SUPPORTING DOCUMENTS
GENERAL NOTES
DESCRIPTION OF SYMBOLS AND ABBREVIATIONS
FIELD TESTS
WATER LEVEL
a Specified Period of Time (b/f) Standard Penetration
SAMPLING
Descriptive Term Standard Penetration or Ring Sampler Descriptive Term Unconfined Compressive Standard Penetration or Ring Sampler
STRENGTH TERMS
Exhibit C-1
UNIFIED SOIL CLASSIFICATION SYSTEM
Soil Classification
Criteria for Assigning Group Symbols and Group Names Using Laboratory Tests A Group B
Group Name
Symbol
Cu 4 and 1 Cc 3
E F
Gravels: Clean Gravels: GW Well-graded gravel
C
Cu 4 and/or 1 Cc 3
E F
More than 50% of Less than 5% fines GP Poorly graded gravel
F,G,H
coarse fraction retained Gravels with Fines: Fines classify as ML or MH GM Silty gravel
Coarse Grained Soils: on No. 4 sieve More than 12% fines
C F,G,H
Fines classify as CL or CH GC Clayey gravel
More than 50% retained
Cu 6 and 1 Cc 3
E I
Sands: Clean Sands: SW Well-graded sand
on No. 200 sieve D
Cu 6 and/or 1 Cc 3
E I
50% or more of coarse Less than 5% fines SP Poorly graded sand
G,H,I
fraction passes No. 4 Sands with Fines: Fines classify as ML or MH SM Silty sand
sieve More than 12% fines
D
Fines classify as CL or CH SC Clayey sand
G,H,I
A H
Based on the material passing the 3-inch (75-mm) sieve If fines are organic, add “with organic fines” to group name.
B
If soil contains 15% gravel, add “with gravel” to group name.
I
If field sample contained cobbles or boulders, or both, add “with cobbles
J
or boulders, or both” to group name. If Atterberg limits plot in shaded area, soil is a CL-ML, silty clay.
C K
Gravels with 5 to 12% fines require dual symbols: GW-GM well-graded If soil contains 15 to 29% plus No. 200, add “with sand” or “with gravel,”
gravel with silt, GW-GC well-graded gravel with clay, GP-GM poorly whichever is predominant.
If soil contains 30% plus No. 200 predominantly sand, add “sandy” to
L
graded gravel with silt, GP-GC poorly graded gravel with clay.
D
Sands with 5 to 12% fines require dual symbols: SW-SM well-graded group name.
sand with silt, SW-SC well-graded sand with clay, SP-SM poorly graded If soil contains 30% plus No. 200, predominantly gravel, add
M
sand with silt, SP-SC poorly graded sand with clay “gravelly” to group name.
PI 4 and plots on or above “A” line.
2 N
(D 30 )
PI 4 or plots below “A” line.
E O
Cu = D60/D10 Cc =
P
D 10 x D 60 PI plots on or above “A” line.
Q
PI plots below “A” line.
If soil contains 15% sand, add “with sand” to group name.
F
G
If fines classify as CL-ML, use dual symbol GC-GM, or SC-SM.
Exhibit C-2
APPENDIX L
________________________________________________________________________________
APPENDIX M
________________________________________________________________________________
ANDREW M. CUOMO ROSE HARVEY
Governor Commissioner
Re: SEQRA
Selkirk Solar Project
Bridge St at Speeder Rd, Bethlehem, NY
17PR00093
Thank you for requesting the comments of the Office of Parks, Recreation and Historic
Preservation (OPRHP). We have reviewed the project in accordance with the New
York State Historic Preservation Act of 1980 (Section 14.09 of the New York Parks,
Recreation and Historic Preservation Law). These comments are those of the Division
for Historic Preservation and relate only to Historic/Cultural resources. They do not
include potential environmental impacts to New York State Parkland that may be
involved in or near your project. Such impacts must be considered as part of the
environmental review of the project pursuant to the State Environmental Quality
Review Act (New York Environmental Conservation Law Article 8) and its implementing
regulations (6 NYCRR Part 617).
Daniel A. Bagrow
Scientist (Archaeology)
Enclosure
Kleinfelder, Inc. (Kleinfelder), on behalf of our client DG SUNY Solar 1, LLC. (Client), is requesting
a regulatory review from the New York State Office of Parks, Recreation & Historic Preservation
(OPRHP) in the form of a Short-term and Long-term Avoidance Plan (Avoidance Plan). The
project area is located on a 46-acre parcel located on the northwest side of Bridge Street (Rte.
396), approximately 1/4 mile west of its intersection with Lasher Road in Selkirk, a hamlet in the
Town of Bethlehem, Albany County, New York (Site). Our request for consultation emanates from
the Town of Bethlehem Planning Board who has specifically requested documentation of the
OPRHP review prior to completing the site plan approval process for a solar farm located on the
Site. A Site location map has been provided as Figure 1.
Property Owner:
Mr. David Frick
93 Bridge Street
Selkirk, NY 12010
Contact:
Dr. Richard Estabrook, Archaeologist
DG SUNY Solar 1, LLC.
700 Universe Blvd.
Juno Beach, FL 33408
Office: 561-691-3054
Richard.Estabrook@nexteraenergy.com
Applicant:
DG SUNY Solar 1, LLC.
700 Universe Blvd.
Juno Beach, FL 33408
300 Westage Business Center, Suite 407, Fishkill, NY 12524 p | 845.231.2500 f | 845.897.2636
Environmental Consultant:
Michael Newhouse
Environmental Scientist
Kleinfelder, Inc.
300 Westage Business Center Drive, Suite 407
Fishkill, New York, 12524
Office: 845-231-2534
Cell: 410-829-5942
The Phase IB archeological field reconnaissance was conducted January 22nd to the 30th, 2017.
Three (3) precontact sites were discovered; named Areas of Concern (AOC) 1, 2, and 3. All AOC’s
occurred near topographic features in the landscape, with AOC’s 1 and 3 on small rises and AOC
2 at the edge of a terrace overlooking a section of the Vloman Kill (Figure 2). A Phase I
Archeological Survey report was submitted to the OPRHP, via CRIS, and subsequently reviewed
by your office. During your review, OPRHP has requested that a Phase II survey be conducted
or an Avoidance Plan be prepared documenting how the project will not impact the AOC’s
discovered during the Phase I survey. During a conversation with you on March 1, 2017, it was
decided that an Avoidance Plan outlining our activities will satisfy the requirements for this review.
To outline our procedures for avoidance and describing the efforts that will be undertaken during
construction, see below for the short-term and long-term avoidance methods that will be followed
throughout this project.
Short-term avoidance is the protection/preservation of the Site during construction. NextEra will
ensure that the following measures are implemented for AOC’S 1-3:
AOC 2 (see Figure 2), will be avoided during all construction activities and throughout
the duration of the project.
For AOC’s 1 and 3, steps will be taken during the design to minimize ground disturbance
within Site boundaries. Design modifications may include re-routing electrical collector
lines, placement of the access road, and placement of the security fence.
Only three to six piles will be driven within AOC’s 1 and 3. Piles will be driven using a
small rubber track mounted pile driver to reduce ground disturbance. The size of the
piles will be 6” x 6”.
No trenching for placement of the collector lines will occur in the AOC’s.
The AOC areas will be clearly indicated in the construction plan set and obviously
marked with flagging prior to construction activities.
At the preconstruction meeting, the Engineer in Charge (EIC) shall be notified regarding
the need to protect/avoid the AOC’s. A professional archaeologist will be present at the
preconstruction meeting to facilitate these discussions.
Inadvertent construction impacts are to be reported to the Avoidance Plan Coordinator
(Richard Estabrook, NextEra Energy) and the OPRHP immediately. Activity shall cease in
KLEINFELDER 300 Westage Business Center, Suite 407, Fishkill, NY 12524 p | 845.231.2500 f | 845.897.2636
the vicinity of the AOC so the damage can be assessed and a recommendation provided
to remediate the situation.
In the event that human remains are encountered during construction, all work must stop
in the vicinity of the find and be reported to the Avoidance Plan Coordinator and the
OPRHP immediately. The Coordinator will notify the appropriate parties.
Long-term avoidance measures are intended to protect the site from adverse impacts after
construction is complete. NextEra will ensure that the following measures are implemented for
AOC’s 1-3:
AOC 2 will be avoided during all construction activities and throughout the duration of
the project.
During decommissioning, all piles located within AOC 1 and 3 will be cut below the
ground surface instead of removing the piles to minimize ground disturbance.
Once construction is complete, there will be no further ground disturbing activities in
AOC’s 1 and 3.
A restrictive covenant identifying the site locations and requiring consultation with OPRHP
regarding future development of the Site will be filed with the Town of Bethlehem.
A copy of the restrictive covenant will be provided to OPRHP after it is filed with the
Town of Bethlehem.
If you have any questions, please contact David Tompkins at 845.231.2547 or via email at
dtompkins@kleinfelder.com or Michael Newhouse at 845.231.2534 or via email at
mnewhouse@kleinfelder.com.
Sincerely,
KLEINFELDER
_________________________ __________________________
Michael Newhouse David B. Tompkins CWB, PWS
Environmental Scientist Vice President
Senior Principal Professional
cc:
Mithun Vyas, NextEra Energy Resources, LLC
Susie Marsh, NextEra Energy Resources, LLC
Richard Estabrook, NextEra Energy Resources, LLC
Enclosures:
Figure 1: Site Location Map
Figure 2: AOC location map
Attachment A: 30% Construction and Erosion and Sediment Control Drawing
KLEINFELDER 300 Westage Business Center, Suite 407, Fishkill, NY 12524 p | 845.231.2500 f | 845.897.2636
FIGURES
Project Area
The information included on this graphic representation has been compiled from a variety of
sources and is subject to change without notice. Kleinfelder makes no representations or
DS, USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, swisstopo, and
intended as a construction design document. The use or misuse of the information contained on this
graphic representation is at the sole risk of the party using or misusing the information.
1
DRAWN BY: SMW
Selkirk
CHECKED BY: JC
NextEra Energy
FILE NAME:
www.kleinfelder.com
Fig1_Selkirk_Location_v1
Selkirk Solar Project, 93 Bridge Street, Town of Bethlehem, Albany County, New York
Phase I Archeological Survey
233 265
ST 234 Inset 583 Overview Map
4 3 2
582
6 5 1
6 84
8
7
55
85 Current View
11 56
9
10 12
13 83
86
119
120
155 Site 2 584
156
54 57
16 118
17 15
14 82
87
121
154 234 270
53
157 185 216 217 249
266
58 117 250
18 19 20 21 3 122
153 285
52 187 215 218 248
286
585
59 116
123 251
24 81 152 284 287
23 22
88 214
115
124
186 219
247
252
586
151 158 283 288
25 26 7 80 89 184
114 213 220
125 188
51
60 90
150 159
246 253 282
25 587
28 27 79 113 183
126 212 221
149
189
281 Feet
50
61
78
91
112
160
182
254
267 269
127 211
190 222
148
62 1 92
111
161 481 462
77 181
29 128
147
162
191 210 223 245
STs 452 and 463 Inset 453
434
93 255
63 110
76 129 180
31
30 146 192 209 224 280 393
94 163 244 359 375
256 340 339 344 358 394 408 409
64 109
179
32
49 75 130
145 193 8 279 376 392 425 581 580 579 578
33 95 164 208 225 289 357 360 410
108 341 338 345 395 407
65 243
74 131 178 257
35 48 391
96 144 194 278 377 424
34 165 207 242 290 342 346 361 411
107 226 258 313 337 396 406
66
39 38 73 132 177
37 47 195 378 390
36
67
97
106
143
166 206 227
241
259
277 291
312
343
336 347 397 405 412 423
480 572 452 577
133
40
41 13
72
98 142
176 314 463 435
46 196 240 276 292 422
42 167 260 398
68 105 205 228 311
175 356 362 374 379
44 71 134 315
43 197 275
45 99 104 141 239 293
261 348
69
70
135
168 204 229 310 335 10 380 Site 3
100 140 174
198
316 355 363 373
421 573 574 575
103
136 169 230
238
262
274 294
349
413
576
173 203 309 334 354 372 381 389 399 426
101 139 364
102 317 420
199 237 273 295
137 170 231 263
202 333 350 353 414
172
138
308
365 371 382 388 400
419
427
25
171
200 236 272 296
318
479
e
232 264
351 352
Feet 464
Slop
201 307 332
366 370 383 387 404 428
14 319
401 415 418 436
See ST 98 Inset 233
235 265 271 297 331
367 369 384 386 429
234 298
306
320 9 402 403 416
417 North 5m
266 270
305
329 330
368 385 ST 98 Inset
267 269 299 321
328
304
268 300 322
327
West 5m North 1m
303
532 516 496 West 1m
301
323
533 517
485 457
98
458 430
302 326 East 1m East 5m
See ST 234 Inset 324 545 544 534 531 518 515 497 South 1m
557 556 484 459 456 431
325
535 498
558
555
546 543 530 519 514
483
460 455 432 See
567 536 499
482 461 STs 452 and 463 South 5m
Legend 566 559 547 542 529 520 513 454 433
Inset
554 481 15
500 462 453 434
Photo Angles Slope 568
565 560 548 541
537 528
521 512
480
Right-of-Way
553 452
Powerline
463 435
Shovel Tests (STs) Existing Pond 569 564 561 549
538 527
522
501
479 5
511
R:\Active Projects\5111 Selkirk Solar\5111-31\Maps\GIS\IBMap2.mxd, 2/10/2017 12:54:50 PM
2
552 464
STs containing cultural material Proposed Arrays 562 502
451 436
Meters Site 1
570 563
510 478 465
551 450 437
550
Archeological Sites Project Parcel 477 466 492 493 494 495
509 449 438 486 487 489 490 491
488
Wet Areas Area of Potential Effects 540 539 523 476
467
526 503 5 4
448 439
508
Proposed Tree Removal, Stumps Left in Place 12
524 475
468
525 504
447 440
507 474
469
505 446 441
473
100 0 100 200 470
445 442
506
Feet 472
471
Re: DEC
Selkirk Solar Project
Bridge St at Speeder Rd, Bethlehem, NY
17PR00093
Thank you for requesting the comments of the Office of Parks, Recreation and Historic
Preservation (OPRHP). We have reviewed the project in accordance with the New
York State Historic Preservation Act of 1980 (Section 14.09 of the New York Parks,
Recreation and Historic Preservation Law). These comments are those of the Division
for Historic Preservation and relate only to Historic/Cultural resources. They do not
include potential environmental impacts to New York State Parkland that may be
involved in or near your project. Such impacts must be considered as part of the
environmental review of the project pursuant to the State Environmental Quality
Review Act (New York Environmental Conservation Law Article 8) and its implementing
regulations (6 NYCRR Part 617).
On March 8, 2017 OPRHP received a Short-Term and Long-Term Avoidance Plan for
Selkirk Solar Site 1 (00102.0009550, Selkirk Solar Site 2 (00102.000956), and Selkirk
Solar site 3 (00102.000957). The details of the Avoidance Plan were further clarified
via email on March 15, 2017. The Plan provides an outline of measures that will be
taken while the proposed solar project is under construction to avoid or significantly
minimize impacts to identified archaeological resources. Sites 1 and 3 will have
minimal construction impacts while Site 2 will be fully avoided under this Plan. It also
includes an agreement to submit a signed and filed copy of a restrictive deed covenant
to ensure that OPRHP has an opportunity to comment on any ground disturbing
activities in the future.
Based upon this review, it is the OPRHP’s opinion that the project will have No Adverse
Sincerely,
Daniel A. Bagrow
Scientist (Archaeology)
CC via CRIS:
________________________________________________________________________________
WWW.KLEINFELDER.COM
16
4
163
16
6
2
16
165
REVISIONS
165 DSN CHK
REV DESCRIPTION DATE
164
5
MDD DLH
16
16
DRAINAGE 16
3
3
JAT JTS
PRE-1 162
16
JAT DLH
7
DRAINAGE 16
16 JTS JTS
16
PRE-4 TOWN OF BETHLEHEM
11 0 C 4/11/17
111415151515151535455565789
5
161 7 COMMENTS
164
16.22 ac. JTS JW
9012 16
169
168
170
171
6
60
167
POINT OF
16
1
INTEREST 1 164 172
165 DRAINAGE 173
PRE-5 & POST-5
16
DRAINAGE 166
6
16
PRE-2 3.94 ac.
161
4
17
2.72 ac.
165
160
159
4
16
159 166
158
163
155
164
150 165
157
162
145 164
163
140
163 161
16
15 160
16
POINT OF 2
2
158 9
16
INTEREST 2
1
1556
POINT OF
1
16
7
16 INTEREST 3
1
4 164
159
DRAINAGE POINT OF
160
163 INTEREST 4
155678 5
PRE-3 161
5
158
163
1325145
POINT OF
15 58876
158
16
6.43 ac.
153
154 111555
11554
9
INTEREST 5
16 0
5
155
162
1
2
1
161 11661
1
161
16
160
161
159
158
DRAINAGE
0
16
0
151 1 160160 160 PRE-6
959 60
15 0
9.48 ac.
15 45
5
160
1 409
113
167
15
8
166
11557 PERMITTING
165
7
164
EXISTING
157
15
WETLAND 16
158
3
159
POINT OF EXISTING
162
161
INTEREST 6 WETLAND
160
SCALE VERIFICATION
SPEEDER ROAD
0 100 200 300
EXISTING WETLAND
1
5. WETLAND DELINEATION WAS COMPLETED BY KLEINFELDER, CURRENT REVISION H
DATED 06/06/2016.
DESIGNED BY MDD
DRAWN BY JAT
CHECKED BY JTS
APPROVED BY JW SHEET 1 of 25
2
WWW.KLEINFELDER.COM
16
4
163
16
6
2
16
165
REVISIONS
165 DSN CHK
REV DESCRIPTION DATE
164
5
MDD DLH
16
16
DRAINAGE 16
3
3
JAT JTS
POST-1 162
16
JAT DLH
7
DRAINAGE 16
16 JTS JTS
16
POST-4 TOWN OF BETHLEHEM
11 0 C 4/11/17
111415151515151535455565789
5
161 7 COMMENTS
164
16.22 ac. JTS JW
9012 16
169
168
170
171
6
60
167
POINT OF
16
1
INTEREST 1 164 172
DRAINAGE
165 173
POST-5 &
16
DRAINAGE 166 POST-5
6
16
POST-2 3.94 ac.
161
4
17
2.72 ac.
165
160
159
4
16
159 166
158
163
155
164
150 165
157
162
145 164
163
140
163 161
16
15 160
16
POINT OF 2
2
158 9
16
INTEREST 2
1
1556
POINT OF
1
16
PROPOSED 20'-WIDE
7
16 INTEREST 3
1
4 164 GRAVEL ACCESS ROAD
159
DRAINAGE POINT OF
160
163 INTEREST 4
155678 5
POST-3 161
5
158
163
1325145
POINT OF
15 58876
158
16
6.43 ac.
153
154 111555
11554
9
INTEREST 5
16 0
5
155
162
1
2
1
161 11661
1
161
16
160
161
159
158
DRAINAGE
0
16
0
151 1 160160 160 POST-6
959 60
15 0
9.48 ac.
15 45
5
160
1 409
113
167
15
8
166
11557 PERMITTING
165
7
164
EXISTING
157
15
WETLAND 16 EXISTING
158
3 WETLAND
159
POINT OF
162
161
INTEREST 6
160
SCALE VERIFICATION
SPEEDER ROAD
0 100 200 300
EXISTING WETLAND
2
3. PARENT PARCEL INFORMATION: CURRENT REVISION H
PROPERTY OWNER: DAVID E. FRICK
DESIGNED BY MDD
PIN: 121.00-2-20
DRAWN BY JAT
5. WETLAND DELINEATION WAS COMPLETED BY KLEINFELDER,
CHECKED BY JTS
DATED 06/06/2016.
APPROVED BY JW SHEET 2 of 25
2
APPENDIX O
________________________________________________________________________________
PRE-3 PRE-4
PRE-2
Pre-Dev Pre-Dev PRE-5
Pre-Dev
Pre-Dev
PRE-1 PRE-6
1L
Pre-Dev Pre-Dev
Pre-Dev
Area CN Description
(acres) (subcatchment-numbers)
0.910 73 Woods, Fair, HSG C (PRE-1,PRE-2,PRE-3)
0.390 82 Dirt roads, HSG B (PRE-6)
3.130 83 Fallow, crop residue, Good, HSG B (PRE-4,PRE-5,PRE-6)
0.020 87 Dirt roads, HSG C (PRE-6)
36.620 88 Fallow, crop residue, Good, HSG C (PRE-1,PRE-2,PRE-3,PRE-4,PRE-5,PRE-6)
41.070 TOTAL AREA
Selkirk SW Model Type II 24-hr 1-Yr Rainfall=2.25"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 3
Runoff = 1.75 cfs @ 12.33 hrs, Volume= 0.177 af, Depth> 0.83"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 1-Yr Rainfall=2.25"
Runoff
1.75 cfs
Type II 24-hr 1-Yr
Rainfall=2.25"
Runoff Area=2.540 ac
Runoff Volume=0.177 af
Flow (cfs)
1 Runoff Depth>0.83"
Flow Length=100'
Tc=36.0 min
CN=84
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 1-Yr Rainfall=2.25"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 4
Runoff = 2.22 cfs @ 12.32 hrs, Volume= 0.221 af, Depth> 1.00"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 1-Yr Rainfall=2.25"
Runoff
2.22 cfs
Type II 24-hr 1-Yr
2
Rainfall=2.25"
Runoff Area=2.640 ac
Runoff Volume=0.221 af
Flow (cfs)
Runoff Depth>1.00"
Flow Length=100'
1
Tc=36.0 min
CN=87
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 1-Yr Rainfall=2.25"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 5
Runoff = 5.78 cfs @ 12.30 hrs, Volume= 0.556 af, Depth> 1.07"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 1-Yr Rainfall=2.25"
Runoff
6 5.78 cfs
Type II 24-hr 1-Yr
5 Rainfall=2.25"
Runoff Area=6.250 ac
4 Runoff Volume=0.556 af
Flow (cfs)
Runoff Depth>1.07"
3
Flow Length=100'
Tc=34.2 min
2
CN=88
1
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 1-Yr Rainfall=2.25"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 6
Runoff = 6.64 cfs @ 13.11 hrs, Volume= 1.322 af, Depth> 0.98"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 1-Yr Rainfall=2.25"
Runoff
7 6.64 cfs
Type II 24-hr 1-Yr
6
Rainfall=2.25"
5
Runoff Area=16.220 ac
Runoff Volume=1.322 af
Flow (cfs)
4 Runoff Depth>0.98"
Flow Length=100'
3
Tc=96.0 min
2 CN=87
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 1-Yr Rainfall=2.25"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 7
Runoff = 3.56 cfs @ 12.31 hrs, Volume= 0.350 af, Depth> 1.07"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 1-Yr Rainfall=2.25"
Runoff
3.56 cfs
Type II 24-hr 1-Yr
3
Rainfall=2.25"
Runoff Area=3.940 ac
Runoff Volume=0.350 af
Flow (cfs)
2
Runoff Depth>1.07"
Flow Length=20,276'
Tc=35.4 min
1
CN=88
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 1-Yr Rainfall=2.25"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 8
Runoff = 11.24 cfs @ 12.14 hrs, Volume= 0.798 af, Depth> 1.01"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 1-Yr Rainfall=2.25"
Runoff
12 11.24 cfs
11 Type II 24-hr 1-Yr
10 Rainfall=2.25"
9
Runoff Area=9.480 ac
8
Runoff Volume=0.798 af
Flow (cfs)
7
Runoff Depth>1.01"
6
Flow Length=100'
5
Tc=21.0 min
4
3
CN=87
2
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 1-Yr Rainfall=2.25"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 9
Inflow Area = 41.070 ac, 0.00% Impervious, Inflow Depth > 1.00" for 1-Yr event
Inflow = 23.77 cfs @ 12.22 hrs, Volume= 3.425 af
Primary = 23.77 cfs @ 12.22 hrs, Volume= 3.425 af, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Inflow
26 23.77 cfs Primary
23.77 cfs
24 Inflow Area=41.070 ac
22
20
18
16
Flow (cfs)
14
12
10
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 2-Yr Rainfall=2.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 10
Runoff = 2.53 cfs @ 12.32 hrs, Volume= 0.252 af, Depth> 1.19"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 2-Yr Rainfall=2.75"
Runoff
2.53 cfs
Type II 24-hr 2-Yr
Rainfall=2.75"
2 Runoff Area=2.540 ac
Runoff Volume=0.252 af
Flow (cfs)
Runoff Depth>1.19"
Flow Length=100'
1 Tc=36.0 min
CN=84
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 2-Yr Rainfall=2.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 11
Runoff = 3.08 cfs @ 12.32 hrs, Volume= 0.307 af, Depth> 1.39"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 2-Yr Rainfall=2.75"
Runoff
3.08 cfs
3 Type II 24-hr 2-Yr
Rainfall=2.75"
Runoff Area=2.640 ac
2
Runoff Volume=0.307 af
Flow (cfs)
Runoff Depth>1.39"
Flow Length=100'
Tc=36.0 min
1
CN=87
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 2-Yr Rainfall=2.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 12
Runoff = 7.92 cfs @ 12.29 hrs, Volume= 0.764 af, Depth> 1.47"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 2-Yr Rainfall=2.75"
Runoff
7.92 cfs
8
Type II 24-hr 2-Yr
7 Rainfall=2.75"
6
Runoff Area=6.250 ac
Runoff Volume=0.764 af
Flow (cfs)
5
Runoff Depth>1.47"
4 Flow Length=100'
3
Tc=34.2 min
CN=88
2
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 2-Yr Rainfall=2.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 13
Runoff = 9.26 cfs @ 13.10 hrs, Volume= 1.837 af, Depth> 1.36"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 2-Yr Rainfall=2.75"
10 Runoff
9.26 cfs
9 Type II 24-hr 2-Yr
8 Rainfall=2.75"
7
Runoff Area=16.220 ac
6
Runoff Volume=1.837 af
Flow (cfs)
Runoff Depth>1.36"
5
Flow Length=100'
4
Tc=96.0 min
3
CN=87
2
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 2-Yr Rainfall=2.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 14
Runoff = 4.89 cfs @ 12.31 hrs, Volume= 0.481 af, Depth> 1.47"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 2-Yr Rainfall=2.75"
Runoff
5
4.89 cfs
Type II 24-hr 2-Yr
Rainfall=2.75"
4
Runoff Area=3.940 ac
Runoff Volume=0.481 af
Flow (cfs)
3
Runoff Depth>1.47"
Flow Length=20,276'
2 Tc=35.4 min
CN=88
1
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 2-Yr Rainfall=2.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 15
Runoff = 15.55 cfs @ 12.14 hrs, Volume= 1.107 af, Depth> 1.40"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 2-Yr Rainfall=2.75"
17 Runoff
16
15.55 cfs
15 Type II 24-hr 2-Yr
14
13
Rainfall=2.75"
12 Runoff Area=9.480 ac
11
Runoff Volume=1.107 af
10
Flow (cfs)
9 Runoff Depth>1.40"
8
Flow Length=100'
7
6 Tc=21.0 min
5
CN=87
4
3
2
1
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 2-Yr Rainfall=2.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 16
Inflow Area = 41.070 ac, 0.00% Impervious, Inflow Depth > 1.39" for 2-Yr event
Inflow = 33.14 cfs @ 12.22 hrs, Volume= 4.747 af
Primary = 33.14 cfs @ 12.22 hrs, Volume= 4.747 af, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Inflow
36 33.14 cfs Primary
33.14 cfs
34 Inflow Area=41.070 ac
32
30
28
26
24
22
Flow (cfs)
20
18
16
14
12
10
8
6
4
2
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 10-Yr Rainfall=4.10"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 17
Runoff = 4.80 cfs @ 12.31 hrs, Volume= 0.478 af, Depth> 2.26"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 10-Yr Rainfall=4.10"
Runoff
5 4.80 cfs
Type II 24-hr 10-Yr
Rainfall=4.10"
4
Runoff Area=2.540 ac
Runoff Volume=0.478 af
Flow (cfs)
3
Runoff Depth>2.26"
Flow Length=100'
2
Tc=36.0 min
CN=84
1
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 10-Yr Rainfall=4.10"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 18
Runoff = 5.52 cfs @ 12.31 hrs, Volume= 0.555 af, Depth> 2.52"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 10-Yr Rainfall=4.10"
6 Runoff
5.52 cfs
Type II 24-hr 10-Yr
5
Rainfall=4.10"
Runoff Area=2.640 ac
4
Runoff Volume=0.555 af
Flow (cfs)
Runoff Depth>2.52"
3
Flow Length=100'
2
Tc=36.0 min
CN=87
1
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 10-Yr Rainfall=4.10"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 19
Runoff = 13.93 cfs @ 12.29 hrs, Volume= 1.361 af, Depth> 2.61"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 10-Yr Rainfall=4.10"
Runoff
15
13.93 cfs
14
13
Type II 24-hr 10-Yr
12 Rainfall=4.10"
11 Runoff Area=6.250 ac
10
9
Runoff Volume=1.361 af
Flow (cfs)
8 Runoff Depth>2.61"
7 Flow Length=100'
6
Tc=34.2 min
5
4 CN=88
3
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 10-Yr Rainfall=4.10"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 20
Runoff = 16.68 cfs @ 13.09 hrs, Volume= 3.332 af, Depth> 2.46"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 10-Yr Rainfall=4.10"
18 Runoff
16.68 cfs
17
16 Type II 24-hr 10-Yr
15
14
Rainfall=4.10"
13 Runoff Area=16.220 ac
12
11
Runoff Volume=3.332 af
Flow (cfs)
10 Runoff Depth>2.46"
9
8 Flow Length=100'
7
6
Tc=96.0 min
5 CN=87
4
3
2
1
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 10-Yr Rainfall=4.10"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 21
Runoff = 8.59 cfs @ 12.30 hrs, Volume= 0.858 af, Depth> 2.61"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 10-Yr Rainfall=4.10"
Runoff
9 8.59 cfs
Type II 24-hr 10-Yr
8
Rainfall=4.10"
7
Runoff Area=3.940 ac
6 Runoff Volume=0.858 af
Flow (cfs)
5 Runoff Depth>2.61"
4
Flow Length=20,276'
Tc=35.4 min
3
CN=88
2
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 10-Yr Rainfall=4.10"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 22
Runoff = 27.65 cfs @ 12.13 hrs, Volume= 2.001 af, Depth> 2.53"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 10-Yr Rainfall=4.10"
30 Runoff
27.65 cfs
28
26
Type II 24-hr 10-Yr
24 Rainfall=4.10"
22 Runoff Area=9.480 ac
20
18
Runoff Volume=2.001 af
Flow (cfs)
16 Runoff Depth>2.53"
14 Flow Length=100'
12
10
Tc=21.0 min
8 CN=87
6
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 10-Yr Rainfall=4.10"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 23
Inflow Area = 41.070 ac, 0.00% Impervious, Inflow Depth > 2.51" for 10-Yr event
Inflow = 59.71 cfs @ 12.21 hrs, Volume= 8.584 af
Primary = 59.71 cfs @ 12.21 hrs, Volume= 8.584 af, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Inflow
65 59.71 cfs Primary
59.71 cfs
60 Inflow Area=41.070 ac
55
50
45
40
Flow (cfs)
35
30
25
20
15
10
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 100-Yr Rainfall=6.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 24
Runoff = 9.47 cfs @ 12.31 hrs, Volume= 0.963 af, Depth> 4.55"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 100-Yr Rainfall=6.75"
Runoff
10 9.47 cfs
9
Type II 24-hr 100-Yr
8
Rainfall=6.75"
Runoff Area=2.540 ac
7
Runoff Volume=0.963 af
Flow (cfs)
6
Runoff Depth>4.55"
5
Flow Length=100'
4
Tc=36.0 min
3 CN=84
2
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 100-Yr Rainfall=6.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 25
Runoff = 10.41 cfs @ 12.30 hrs, Volume= 1.072 af, Depth> 4.87"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 100-Yr Rainfall=6.75"
Runoff
11 10.41 cfs
10 Type II 24-hr 100-Yr
9 Rainfall=6.75"
8 Runoff Area=2.640 ac
7 Runoff Volume=1.072 af
Flow (cfs)
6 Runoff Depth>4.87"
5 Flow Length=100'
4 Tc=36.0 min
3 CN=87
2
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 100-Yr Rainfall=6.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 26
Runoff = 25.87 cfs @ 12.28 hrs, Volume= 2.596 af, Depth> 4.99"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 100-Yr Rainfall=6.75"
28 Runoff
25.87 cfs
26
Type II 24-hr 100-Yr
24
22
Rainfall=6.75"
20 Runoff Area=6.250 ac
18 Runoff Volume=2.596 af
Flow (cfs)
16
Runoff Depth>4.99"
14
12
Flow Length=100'
10 Tc=34.2 min
8 CN=88
6
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 100-Yr Rainfall=6.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 27
Runoff = 31.64 cfs @ 13.08 hrs, Volume= 6.462 af, Depth> 4.78"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 100-Yr Rainfall=6.75"
Runoff
34
31.64 cfs
32
30
Type II 24-hr 100-Yr
28 Rainfall=6.75"
26
24
Runoff Area=16.220 ac
22 Runoff Volume=6.462 af
Flow (cfs)
20
18
Runoff Depth>4.78"
16 Flow Length=100'
14
12
Tc=96.0 min
10 CN=87
8
6
4
2
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 100-Yr Rainfall=6.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 28
Runoff = 15.96 cfs @ 12.30 hrs, Volume= 1.636 af, Depth> 4.98"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 100-Yr Rainfall=6.75"
Runoff
17 15.96 cfs
16
15
Type II 24-hr 100-Yr
14 Rainfall=6.75"
13
12
Runoff Area=3.940 ac
11 Runoff Volume=1.636 af
Flow (cfs)
10
9
Runoff Depth>4.98"
8 Flow Length=20,276'
7
6
Tc=35.4 min
5 CN=88
4
3
2
1
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 100-Yr Rainfall=6.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 29
Runoff = 51.80 cfs @ 12.13 hrs, Volume= 3.867 af, Depth> 4.89"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 100-Yr Rainfall=6.75"
Runoff
55 51.80 cfs
50 Type II 24-hr 100-Yr
45 Rainfall=6.75"
40 Runoff Area=9.480 ac
35 Runoff Volume=3.867 af
Flow (cfs)
30 Runoff Depth>4.89"
25 Flow Length=100'
20 Tc=21.0 min
15 CN=87
10
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 100-Yr Rainfall=6.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 30
Inflow Area = 41.070 ac, 0.00% Impervious, Inflow Depth > 4.85" for 100-Yr event
Inflow = 113.17 cfs @ 12.21 hrs, Volume= 16.597 af
Primary = 113.17 cfs @ 12.21 hrs, Volume= 16.597 af, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Inflow
125 113.17 cfs Primary
120 113.17 cfs
115 Inflow Area=41.070 ac
110
105
100
95
90
85
80
75
Flow (cfs)
70
65
60
55
50
45
40
35
30
25
20
15
10
5
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
APPENDIX P
________________________________________________________________________________
POST-3 POST-4
POST-2
Post-Dev Post-Dev POST-5
Post-Dev
Post-Dev
POST-1 POST-6
2L
Post-Dev Post-Dev
Post-Dev
Area CN Description
(acres) (subcatchment-numbers)
2.770 61 Pasture/grassland/range, Good, HSG B (POST-4,POST-5,POST-6)
36.500 74 Pasture/grassland/range, Good, HSG C (POST-1,POST-2,POST-3,POST-4,POST-5,POST-6)
0.190 82 Dirt roads, HSG B (POST-6)
0.360 85 Gravel roads, HSG B (POST-4,POST-5,POST-6)
1.100 89 Gravel roads, HSG C (POST-4,POST-5,POST-6)
40.920 TOTAL AREA
Selkirk SW Model Type II 24-hr 1-Yr Rainfall=2.25"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 3
Runoff = 0.73 cfs @ 12.37 hrs, Volume= 0.087 af, Depth> 0.41"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 1-Yr Rainfall=2.25"
0.8 Runoff
0.73 cfs
0.75
0.7 Type II 24-hr 1-Yr
0.65 Rainfall=2.25"
0.6
0.55
Runoff Area=2.540 ac
0.5 Runoff Volume=0.087 af
Flow (cfs)
0.45
Runoff Depth>0.41"
0.4
0.35 Flow Length=100'
0.3 Tc=36.0 min
0.25
0.2
CN=74
0.15
0.1
0.05
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 1-Yr Rainfall=2.25"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 4
Runoff = 0.76 cfs @ 12.37 hrs, Volume= 0.090 af, Depth> 0.41"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 1-Yr Rainfall=2.25"
0.85 Runoff
0.8 0.76 cfs
0.75 Type II 24-hr 1-Yr
0.7
0.65
Rainfall=2.25"
0.6 Runoff Area=2.640 ac
0.55
0.5
Runoff Volume=0.090 af
Flow (cfs)
Runoff = 1.83 cfs @ 12.35 hrs, Volume= 0.209 af, Depth> 0.41"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 1-Yr Rainfall=2.25"
2 Runoff
1.83 cfs
Type II 24-hr 1-Yr
Rainfall=2.25"
Runoff Area=6.100 ac
Runoff Volume=0.209 af
Flow (cfs)
Runoff Depth>0.41"
1
Flow Length=100'
Tc=34.2 min
CN=74
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 1-Yr Rainfall=2.25"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 6
Runoff = 1.71 cfs @ 13.62 hrs, Volume= 0.479 af, Depth> 0.35"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 1-Yr Rainfall=2.25"
Runoff
1.71 cfs
Type II 24-hr 1-Yr
Rainfall=2.25"
Runoff Area=16.220 ac
Runoff Volume=0.479 af
Flow (cfs)
1 Runoff Depth>0.35"
Flow Length=100'
Tc=122.4 min
CN=73
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 1-Yr Rainfall=2.25"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 7
Runoff = 0.69 cfs @ 13.05 hrs, Volume= 0.142 af, Depth> 0.43"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 1-Yr Rainfall=2.25"
0.75 Runoff
0.69 cfs
0.7
0.65
Type II 24-hr 1-Yr
0.6 Rainfall=2.25"
0.55 Runoff Area=3.940 ac
0.5
0.45
Runoff Volume=0.142 af
Flow (cfs)
0.25
Tc=82.2 min
0.2 CN=75
0.15
0.1
0.05
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 1-Yr Rainfall=2.25"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 8
Runoff = 4.01 cfs @ 12.17 hrs, Volume= 0.327 af, Depth> 0.41"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 1-Yr Rainfall=2.25"
Runoff
4.01 cfs
4
Type II 24-hr 1-Yr
Rainfall=2.25"
3
Runoff Area=9.480 ac
Runoff Volume=0.327 af
Flow (cfs)
Runoff Depth>0.41"
2 Flow Length=100'
Tc=21.0 min
CN=74
1
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 1-Yr Rainfall=2.25"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 9
Inflow Area = 40.920 ac, 0.00% Impervious, Inflow Depth > 0.39" for 1-Yr event
Inflow = 6.70 cfs @ 12.24 hrs, Volume= 1.333 af
Primary = 6.70 cfs @ 12.24 hrs, Volume= 1.333 af, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Inflow
6.70 cfs Primary
6.70 cfs
7
Inflow Area=40.920 ac
6
5
Flow (cfs)
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 2-Yr Rainfall=2.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 10
Runoff = 1.30 cfs @ 12.35 hrs, Volume= 0.141 af, Depth> 0.66"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 2-Yr Rainfall=2.75"
Runoff
1.30 cfs
Type II 24-hr 2-Yr
Rainfall=2.75"
1 Runoff Area=2.540 ac
Runoff Volume=0.141 af
Flow (cfs)
Runoff Depth>0.66"
Flow Length=100'
Tc=36.0 min
CN=74
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 2-Yr Rainfall=2.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 11
Runoff = 1.35 cfs @ 12.35 hrs, Volume= 0.146 af, Depth> 0.66"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 2-Yr Rainfall=2.75"
Runoff
1.35 cfs
Type II 24-hr 2-Yr
Rainfall=2.75"
1
Runoff Area=2.640 ac
Runoff Volume=0.146 af
Flow (cfs)
Runoff Depth>0.66"
Flow Length=100'
Tc=36.0 min
CN=74
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 2-Yr Rainfall=2.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 12
Runoff = 3.23 cfs @ 12.33 hrs, Volume= 0.338 af, Depth> 0.66"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 2-Yr Rainfall=2.75"
Runoff
3.23 cfs
Type II 24-hr 2-Yr
3
Rainfall=2.75"
Runoff Area=6.100 ac
Runoff Volume=0.338 af
Flow (cfs)
2
Runoff Depth>0.66"
Flow Length=100'
Tc=34.2 min
1 CN=74
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 2-Yr Rainfall=2.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 13
Runoff = 3.04 cfs @ 13.50 hrs, Volume= 0.794 af, Depth> 0.59"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 2-Yr Rainfall=2.75"
Runoff
3.04 cfs
3
Type II 24-hr 2-Yr
Rainfall=2.75"
Runoff Area=16.220 ac
2
Runoff Volume=0.794 af
Flow (cfs)
Runoff Depth>0.59"
Flow Length=100'
Tc=122.4 min
1
CN=73
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 2-Yr Rainfall=2.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 14
Runoff = 1.18 cfs @ 13.02 hrs, Volume= 0.227 af, Depth> 0.69"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 2-Yr Rainfall=2.75"
Runoff
1.18 cfs
Type II 24-hr 2-Yr
1
Rainfall=2.75"
Runoff Area=3.940 ac
Runoff Volume=0.227 af
Flow (cfs)
Runoff Depth>0.69"
Flow Length=100'
Tc=82.2 min
CN=75
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 2-Yr Rainfall=2.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 15
Runoff = 7.00 cfs @ 12.16 hrs, Volume= 0.529 af, Depth> 0.67"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 2-Yr Rainfall=2.75"
Runoff
7.00 cfs
7
Type II 24-hr 2-Yr
6 Rainfall=2.75"
Runoff Area=9.480 ac
5
Runoff Volume=0.529 af
Flow (cfs)
4 Runoff Depth>0.67"
Flow Length=100'
3
Tc=21.0 min
2 CN=74
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 2-Yr Rainfall=2.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 16
Inflow Area = 40.920 ac, 0.00% Impervious, Inflow Depth > 0.64" for 2-Yr event
Inflow = 11.97 cfs @ 12.22 hrs, Volume= 2.174 af
Primary = 11.97 cfs @ 12.22 hrs, Volume= 2.174 af, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Inflow
13 11.97 cfs Primary
11.97 cfs
12 Inflow Area=40.920 ac
11
10
8
Flow (cfs)
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 10-Yr Rainfall=4.10"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 17
Runoff = 3.15 cfs @ 12.33 hrs, Volume= 0.318 af, Depth> 1.50"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 10-Yr Rainfall=4.10"
Runoff
3.15 cfs
3 Type II 24-hr 10-Yr
Rainfall=4.10"
Runoff Area=2.540 ac
Runoff Volume=0.318 af
Flow (cfs)
2
Runoff Depth>1.50"
Flow Length=100'
Tc=36.0 min
1 CN=74
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 10-Yr Rainfall=4.10"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 18
Runoff = 3.28 cfs @ 12.33 hrs, Volume= 0.331 af, Depth> 1.50"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 10-Yr Rainfall=4.10"
Runoff
3.28 cfs
Type II 24-hr 10-Yr
3
Rainfall=4.10"
Runoff Area=2.640 ac
Runoff Volume=0.331 af
Flow (cfs)
2
Runoff Depth>1.50"
Flow Length=100'
Tc=36.0 min
1 CN=74
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 10-Yr Rainfall=4.10"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 19
Runoff = 7.84 cfs @ 12.31 hrs, Volume= 0.765 af, Depth> 1.51"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 10-Yr Rainfall=4.10"
Runoff
7.84 cfs
8
Type II 24-hr 10-Yr
7
Rainfall=4.10"
6 Runoff Area=6.100 ac
Runoff Volume=0.765 af
Flow (cfs)
5
Runoff Depth>1.51"
4 Flow Length=100'
3 Tc=34.2 min
CN=74
2
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 10-Yr Rainfall=4.10"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 20
Runoff = 7.69 cfs @ 13.47 hrs, Volume= 1.856 af, Depth> 1.37"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 10-Yr Rainfall=4.10"
Runoff
8 7.69 cfs
Type II 24-hr 10-Yr
7
Rainfall=4.10"
6 Runoff Area=16.220 ac
5
Runoff Volume=1.856 af
Flow (cfs)
Runoff Depth>1.37"
4
Flow Length=100'
3 Tc=122.4 min
CN=73
2
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 10-Yr Rainfall=4.10"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 21
Runoff = 2.80 cfs @ 12.94 hrs, Volume= 0.505 af, Depth> 1.54"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 10-Yr Rainfall=4.10"
Runoff
3
2.80 cfs
Type II 24-hr 10-Yr
Rainfall=4.10"
Runoff Area=3.940 ac
2
Runoff Volume=0.505 af
Flow (cfs)
Runoff Depth>1.54"
Flow Length=100'
Tc=82.2 min
1
CN=75
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 10-Yr Rainfall=4.10"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 22
Runoff = 16.73 cfs @ 12.15 hrs, Volume= 1.196 af, Depth> 1.51"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 10-Yr Rainfall=4.10"
Runoff
18
16.73 cfs
17
16 Type II 24-hr 10-Yr
15
14
Rainfall=4.10"
13 Runoff Area=9.480 ac
12
11
Runoff Volume=1.196 af
Flow (cfs)
10 Runoff Depth>1.51"
9
8 Flow Length=100'
7
Tc=21.0 min
6
5 CN=74
4
3
2
1
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 10-Yr Rainfall=4.10"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 23
Inflow Area = 40.920 ac, 0.00% Impervious, Inflow Depth > 1.46" for 10-Yr event
Inflow = 29.64 cfs @ 12.21 hrs, Volume= 4.971 af
Primary = 29.64 cfs @ 12.21 hrs, Volume= 4.971 af, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Inflow
32
29.64 cfs Primary
29.64 cfs
30 Inflow Area=40.920 ac
28
26
24
22
20
Flow (cfs)
18
16
14
12
10
8
6
4
2
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 100-Yr Rainfall=6.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 24
Runoff = 7.46 cfs @ 12.32 hrs, Volume= 0.742 af, Depth> 3.50"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 100-Yr Rainfall=6.75"
Runoff
8
7.46 cfs
7
Type II 24-hr 100-Yr
Rainfall=6.75"
6
Runoff Area=2.540 ac
5 Runoff Volume=0.742 af
Flow (cfs)
Runoff Depth>3.50"
4
Flow Length=100'
3 Tc=36.0 min
2
CN=74
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 100-Yr Rainfall=6.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 25
Runoff = 7.75 cfs @ 12.32 hrs, Volume= 0.771 af, Depth> 3.50"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 100-Yr Rainfall=6.75"
Runoff
8
7.75 cfs
Type II 24-hr 100-Yr
7
Rainfall=6.75"
6 Runoff Area=2.640 ac
Runoff Volume=0.771 af
5
Flow (cfs)
Runoff Depth>3.50"
4
Flow Length=100'
3 Tc=36.0 min
CN=74
2
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 100-Yr Rainfall=6.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 26
Runoff = 18.50 cfs @ 12.30 hrs, Volume= 1.782 af, Depth> 3.51"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 100-Yr Rainfall=6.75"
20 Runoff
19
18.50 cfs
18 Type II 24-hr 100-Yr
17
16 Rainfall=6.75"
15
14
Runoff Area=6.100 ac
13
12
Runoff Volume=1.782 af
Flow (cfs)
11 Runoff Depth>3.51"
10
9 Flow Length=100'
8
7
Tc=34.2 min
6
5
CN=74
4
3
2
1
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 100-Yr Rainfall=6.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 27
Runoff = 18.78 cfs @ 13.45 hrs, Volume= 4.429 af, Depth> 3.28"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 100-Yr Rainfall=6.75"
21
Runoff
20 18.78 cfs
19
18 Type II 24-hr 100-Yr
17
16
Rainfall=6.75"
15
14
Runoff Area=16.220 ac
13 Runoff Volume=4.429 af
12
Flow (cfs)
11 Runoff Depth>3.28"
10
9 Flow Length=100'
8
7
Tc=122.4 min
6
5
CN=73
4
3
2
1
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 100-Yr Rainfall=6.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 28
Runoff = 6.54 cfs @ 12.91 hrs, Volume= 1.162 af, Depth> 3.54"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 100-Yr Rainfall=6.75"
Runoff
7
6.54 cfs
Type II 24-hr 100-Yr
6
Rainfall=6.75"
5 Runoff Area=3.940 ac
Runoff Volume=1.162 af
Flow (cfs)
4
Runoff Depth>3.54"
3
Flow Length=100'
Tc=82.2 min
2 CN=75
1
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 100-Yr Rainfall=6.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 29
Runoff = 39.05 cfs @ 12.14 hrs, Volume= 2.783 af, Depth> 3.52"
Runoff by SCS TR-20 method, UH=SCS, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Type II 24-hr 100-Yr Rainfall=6.75"
Runoff
42
40
39.05 cfs
38 Type II 24-hr 100-Yr
36
34 Rainfall=6.75"
32
30 Runoff Area=9.480 ac
28
26 Runoff Volume=2.783 af
Flow (cfs)
24
22
Runoff Depth>3.52"
20
18
Flow Length=100'
16 Tc=21.0 min
14
12 CN=74
10
8
6
4
2
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
Selkirk SW Model Type II 24-hr 100-Yr Rainfall=6.75"
Prepared by Kleinfelder Printed 4/10/2017
HydroCAD® 8.50 s/n 002245 © 2007 HydroCAD Software Solutions LLC Page 30
Inflow Area = 40.920 ac, 0.00% Impervious, Inflow Depth > 3.42" for 100-Yr event
Inflow = 71.44 cfs @ 12.20 hrs, Volume= 11.669 af
Primary = 71.44 cfs @ 12.20 hrs, Volume= 11.669 af, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 5.00-20.00 hrs, dt= 0.05 hrs
Inflow
80 71.44 cfs Primary
71.44 cfs
75
70
Inflow Area=40.920 ac
65
60
55
50
Flow (cfs)
45
40
35
30
25
20
15
10
5
0
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (hours)
APPENDIX Q
________________________________________________________________________________
Selkirk Solar Farm Impervious Calculations
= 1.460 AC
4 pads on site
= 256 SF
= 0.006 AC
= 96 SF
= 0.002 AC
Total:
________________________________________________________________________________
U.S. Department of Agriculture FL-ENG-21B
Natural Resources Conservation Service 04/04
06/04
Project: Selkirk Solar Farm Designed By: Jake Stelten Date: 7/11/16
Circle one: ✔ Tc
Check Tt through subarea PRE-1
NOTES: Space for as many as two segments per flow type can be used for each worksheet. Include a map, schematic,
or description of flow segments.
Project: Selkirk Solar Farm Designed By: Jake Stelten Date: 7/11/16
Circle one: ✔ Tc
Check Tt through subarea PRE-2
NOTES: Space for as many as two segments per flow type can be used for each worksheet. Include a map, schematic,
or description of flow segments.
Project: Selkirk Solar Farm Designed By: Jake Stelten Date: 3/17/17
Circle one: ✔ Tc
Check Tt through subarea PRE-3
NOTES: Space for as many as two segments per flow type can be used for each worksheet. Include a map, schematic,
or description of flow segments.
Project: Selkirk Solar Farm Designed By: Jake Stelten Date: 7/11/16
Circle one: ✔ Tc
Check Tt through subarea PRE-4
NOTES: Space for as many as two segments per flow type can be used for each worksheet. Include a map, schematic,
or description of flow segments.
Project: Selkirk Solar Farm Designed By: Jake Stelten Date: 7/11/16
Circle one: ✔ Tc
Check Tt through subarea PRE-5
NOTES: Space for as many as two segments per flow type can be used for each worksheet. Include a map, schematic,
or description of flow segments.
Project: Selkirk Solar Farm Designed By: Jake Stelten Date: 7/11/16
Circle one: ✔ Tc
Check Tt through subarea PRE-6
NOTES: Space for as many as two segments per flow type can be used for each worksheet. Include a map, schematic,
or description of flow segments.
Project: Selkirk Solar Farm Designed By: Jake Stelten Date: 7/11/16
Circle one: ✔ Tc
Check Tt through subarea POST-1
NOTES: Space for as many as two segments per flow type can be used for each worksheet. Include a map, schematic,
or description of flow segments.
Project: Selkirk Solar Farm Designed By: Jake Stelten Date: 7/11/16
Circle one: ✔ Tc
Check Tt through subarea POST-2
NOTES: Space for as many as two segments per flow type can be used for each worksheet. Include a map, schematic,
or description of flow segments.
Project: Selkirk Solar Farm Designed By: Jake Stelten Date: 3/17/17
Circle one: ✔ Tc
Check Tt through subarea POST-3
NOTES: Space for as many as two segments per flow type can be used for each worksheet. Include a map, schematic,
or description of flow segments.
Project: Selkirk Solar Farm Designed By: Jake Stelten Date: 7/11/16
Circle one: ✔ Tc
Check Tt through subarea POST-4
NOTES: Space for as many as two segments per flow type can be used for each worksheet. Include a map, schematic,
or description of flow segments.
Project: Selkirk Solar Farm Designed By: Jake Stelten Date: 7/11/16
Circle one: ✔ Tc
Check Tt through subarea POST-5
NOTES: Space for as many as two segments per flow type can be used for each worksheet. Include a map, schematic,
or description of flow segments.
Project: Selkirk Solar Farm Designed By: Jake Stelten Date: 7/11/16
Circle one: ✔ Tc
Check Tt through subarea POST-6
NOTES: Space for as many as two segments per flow type can be used for each worksheet. Include a map, schematic,
or description of flow segments.
________________________________________________________________________________
Version 1.7 Total Water Quality Volume Calculation
Last Updated: 10/02/2015 WQv(acre‐feet) = [(P)(Rv)(A)] /12
Is this project subject to Chapter 10 of the NYS Design Manual (i.e. WQv is equal to post‐
development 1 year runoff volume)?...................................................................................... No
Design Point: SWPPP App N
Manually enter P, Total Area and Impervious Cover.
P= 1.20 inch
Breakdown of Subcatchments
Percent
Catchment Total Area Impervious Area WQv
Impervious Rv Description
Number (Acres) (Acres) (ft 3 )
%
1 39.90 0.37 1% 0.06 10,141 Filter Strips
2 0.50 0.50 100% 0.95 2,069 Dry Swale
3 0.10 0.10 100% 0.95 414 Dry Swale
4 0.32 0.32 100% 0.95 1,324 Dry Swale
5 0.18 0.18 100% 0.95 745 Dry Swale
6
7
8
9
10
Subtotal (1‐30) 41.00 1.47 4% 0.08 14,693 Subtotal 1
Total 41.00 1.47 4% 0.08 14,693 Initial WQv 0.34 af
Identify Runoff Reduction Techniques By Area
Total
Contributing
Contributing
Technique Impervious Area Notes
Area
(Acre) (Acre)
Conservation of Natural Areas 0.00 0.00 minimum 10,000 sf
maximum contributing length 75 feet to
Riparian Buffers 0.00 0.00
150 feet
Filter Strips 39.90 0.37
Up to 100 sf directly connected impervious
Tree Planting 0.00 0.00
area may be subtracted per tree
Total 39.90 0.37
Recalculate WQv after application of Area Reduction Techniques
Percent Runoff
Total Area Impervious Area WQv
Impervious Coefficient
(Acres) (Acres) (ft 3 )
% Rv
"<<Initial WQv" 41.00 1.47 4% 0.08 14,693
Subtract Area ‐39.90 ‐0.37
WQv adjusted after Area
1.10 1.10 100% 0.95 4,552
Reductions
Disconnection of Rooftops 0.00
Adjusted WQv after Area
Reduction and Rooftop 1.10 1.10 100% 0.95 4,552 0.10 af
Disconnect
WQv reduced by Area
10,141 0.23 af
Reduction techniques
Total Water Quality Volume Calculation
WQv(acre‐feet) = [(P)(Rv)(A)] /12
All Subcatchments
Impervious Percent Runoff
Catchment Total Area WQv Description
Cover Impervious Coefficient
3
(Acres) (Acres) % Rv (ft )
1 39.90 0.37 0.01 0.06 10140.77 Filter Strips
2 0.50 0.50 1.00 0.95 2,069 Dry Swale
3 0.10 0.10 1.00 0.95 413.82 Dry Swale
4 0.32 0.32 1.00 0.95 1324.22 Dry Swale
5 0.18 0.18 1.00 0.95 744.88 Dry Swale
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Runoff Reduction Volume and Treated volumes
Total
Total WQv
Runoff Reduction Techiques/Standard Contributing WQv
Contributing Reduced
SMPs Impervious Treated
Area (RRv)
Area
(acres) (acres) cf cf
Conservation of Natural Areas RR‐1 0.00 0.00
Sheetflow to Riparian Buffers/Filter
RR‐2 39.90 0.37
Area/Volume Reduction
Strips
Tree Planting/Tree Pit RR‐3 0.00 0.00
Disconnection of Rooftop Runoff RR‐4 0.00
Vegetated Swale RR‐5 0.00 0.00 0
Rain Garden RR‐6 0.00 0.00 0
Stormwater Planter RR‐7 0.00 0.00 0
Rain Barrel/Cistern RR‐8 0.00 0.00 0
Porous Pavement RR‐9 0.00 0.00 0
Green Roof (Intensive & Extensive) RR‐10 0.00 0.00 0
Infiltration Trench I‐1 0.00 0.00 0 0
Standard SMPs
w/RRv Capacity
Surface Sand filter (F‐1) F‐1
Underground Sand filter (F‐2) F‐2
Perimeter Sand Filter (F‐3) F‐3
Organic Filter (F‐4 F‐4
Shallow Wetland (W‐1) W‐1
Extended Detention Wetland (W‐2 W‐2
Pond/Wetland System (W‐3) W‐3
Pocket Wetland (W‐4) W‐4
Wet Swale (O‐2) O‐2
Totals by Area Reduction → 39.90 0.37 10141
Totals by Volume Reduction → 0.00 0.00 0
Totals by Standard SMP w/RRV → 1.10 1.10 2118 2434
Totals by Standard SMP → 0.00 0.00 0
Totals ( Area + Volume + all SMPs) → 41.00 1.47 12,259 2,434
Rain Garden RR‐6 0.00 0.00 0
Minimum RRv
Enter the Soils Data for the site
Soil Group Acres S
A 55%
B 9.03 40%
C 63.23 30%
D 20%
Total Area 72.26
Calculate the Minimum RRv
S = 0.31
Impervious = 1.47 acre
Precipitation 1.2 in
Rv 0.95
Minimum RRv 1,901 ft3
0.04 af
NOI QUESTIONS
# NOI Question Reported Value
cf af
28 Total Water Quality Volume (WQv) Required 14693 0.337
30 Total RRV Provided 12259 0.281
31 Is RRv Provided ≥WQv Required? No
32 Minimum RRv 1901 0.044
32a Is RRv Provided ≥ Minimum RRv Required? Yes
36 Channel Protection Cpv
37 Overbank Qp
37 Extreme Flood Control Qf
Are Quantity Control requirements met? Yes Plan Completed
Planning
Practice Description Application
Enter Impervious Area Reduced <<WQv after adjusting for
100% 0.95 2,069
by Disconnection of Rooftops Disconnected Rooftops
Pretreatment Provided Pretreatment Technique
3
Pretreatment (10% of WQv) 207 ft Grass Filter Strip
Calculate Available Storage Capacity
Design with a bottom width no greater than eight feet to avoid
Bottom Width 2 ft
potential gullying and channel braiding, but no less than two feet
Channels shall be designed with moderate side slopes (flatter
Side Slope
3 Okay than 3:1) for most conditions. 2:1 is the
(X:1)
absolute maximum side slope
Longitudinal
1% Okay Maximum longitudinal slope shall be 4%
Slope
Maximum ponding depth of one foot at the mid‐point of the
Flow Depth 1 ft channel, and a maximum depth of 18" at the end point of the
channel (for storage of the WQv)
Top Width 8 ft TW
Area 5.00 sf p
Minimum
372 ft
Length
Actual Length 1050 ft BW
End Point A maximum depth of 18" at the end point of the channel (for
1.00 Okay
Depth check storage of the WQv)
Storage
5,457 ft 3
Capacity
Soil Group (HSG) c
Runoff Reduction
Is the Dry Swale contributing flow to another
No Select Practice
practice?
3 Runnoff Reduction equals 40% in HSG A and B and 20% in HSG C
RRv 1,091 ft
and D up to the WQv
Volume 3 This is the difference between the WQv calculated and the runoff
978 ft
Treated reduction achieved in the swale
Volume
0 ft 3 This volume is directed another practice
Directed
Volume √ Okay Check to be sure that channel is long enough to store WQv
Dry Swale Worksheet
Design Point: SWPPP App N
Enter Site Data For Drainage Area to be Treated by Practice
Impervious Percent
Catchment Total Area WQv Precipitation
Area Impervious Rv 3 Description
Number (Acres) (ft ) (in)
(Acres) %
Enter Impervious Area Reduced <<WQv after adjusting for
100% 0.95 414
by Disconnection of Rooftops Disconnected Rooftops
Pretreatment Provided Pretreatment Technique
3
Pretreatment (10% of WQv) 41 ft Grass Filter Strip
Calculate Available Storage Capacity
Design with a bottom width no greater than eight feet to avoid
Bottom Width 2 ft
potential gullying and channel braiding, but no less than two feet
Channels shall be designed with moderate side slopes (flatter
Side Slope
3 Okay than 3:1) for most conditions. 2:1 is the
(X:1)
absolute maximum side slope
Longitudinal
1% Okay Maximum longitudinal slope shall be 4%
Slope
Maximum ponding depth of one foot at the mid‐point of the
Flow Depth 1 ft channel, and a maximum depth of 18" at the end point of the
channel (for storage of the WQv)
Top Width 8 ft TW
Area 5.00 sf p
Minimum
74 ft
Length
Actual Length 62 ft BW
End Point A maximum depth of 18" at the end point of the channel (for
1.00 Okay
Depth check storage of the WQv)
Storage
351 ft 3
Capacity
Soil Group (HSG) C
Runoff Reduction
Is the Dry Swale contributing flow to another
No Select Practice
practice?
3 Runnoff Reduction equals 40% in HSG A and B and 20% in HSG C
RRv 70 ft
and D up to the WQv
Volume 3 This is the difference between the WQv calculated and the runoff
344 ft
Treated reduction achieved in the swale
Volume
0 ft 3 This volume is directed another practice
Directed
Volume √ Error Check to be sure that channel is long enough to store WQv
Dry Swale Worksheet
Design Point: SWPPP App N
Enter Site Data For Drainage Area to be Treated by Practice
Impervious Percent
Catchment Total Area WQv Precipitation
Area Impervious Rv 3 Description
Number (Acres) (ft ) (in)
(Acres) %
Enter Impervious Area Reduced <<WQv after adjusting for
100% 0.95 1,324
by Disconnection of Rooftops Disconnected Rooftops
Pretreatment Provided Pretreatment Technique
3
Pretreatment (10% of WQv) 132 ft Grass Filter Strip
Calculate Available Storage Capacity
Design with a bottom width no greater than eight feet to avoid
Bottom Width 2 ft
potential gullying and channel braiding, but no less than two feet
Channels shall be designed with moderate side slopes (flatter
Side Slope
3 Okay than 3:1) for most conditions. 2:1 is the
(X:1)
absolute maximum side slope
Longitudinal
1% Okay Maximum longitudinal slope shall be 4%
Slope
Maximum ponding depth of one foot at the mid‐point of the
Flow Depth 1 ft channel, and a maximum depth of 18" at the end point of the
channel (for storage of the WQv)
Top Width 8 ft TW
Area 5.00 sf p
Minimum
238 ft
Length
Actual Length 574 ft BW
End Point A maximum depth of 18" at the end point of the channel (for
1.00 Okay
Depth check storage of the WQv)
Storage
3,002 ft 3
Capacity
Soil Group (HSG) C
Runoff Reduction
Is the Dry Swale contributing flow to another
No Select Practice
practice?
3 Runnoff Reduction equals 40% in HSG A and B and 20% in HSG C
RRv 600 ft
and D up to the WQv
Volume 3 This is the difference between the WQv calculated and the runoff
724 ft
Treated reduction achieved in the swale
Volume
0 ft 3 This volume is directed another practice
Directed
Volume √ Okay Check to be sure that channel is long enough to store WQv
Dry Swale Worksheet
Design Point: SWPPP App N
Enter Site Data For Drainage Area to be Treated by Practice
Impervious Percent
Catchment Total Area WQv Precipitation
Area Impervious Rv 3 Description
Number (Acres) (ft ) (in)
(Acres) %
Enter Impervious Area Reduced <<WQv after adjusting for
100% 0.95 745
by Disconnection of Rooftops Disconnected Rooftops
Pretreatment Provided Pretreatment Technique
3
Pretreatment (10% of WQv) 74 ft
Calculate Available Storage Capacity
Design with a bottom width no greater than eight feet to avoid
Bottom Width 2 ft
potential gullying and channel braiding, but no less than two feet
Channels shall be designed with moderate side slopes (flatter
Side Slope
3 Okay than 3:1) for most conditions. 2:1 is the
(X:1)
absolute maximum side slope
Longitudinal
1% Okay Maximum longitudinal slope shall be 4%
Slope
Maximum ponding depth of one foot at the mid‐point of the
Flow Depth 1 ft channel, and a maximum depth of 18" at the end point of the
channel (for storage of the WQv)
Top Width 8 ft TW
Area 5.00 sf p
Minimum
134 ft
Length
Actual Length 341 ft BW
End Point A maximum depth of 18" at the end point of the channel (for
1.00 Okay
Depth check storage of the WQv)
Storage
1,779 ft 3
Capacity
Soil Group (HSG) C
Runoff Reduction
Is the Dry Swale contributing flow to another
No Select Practice
practice?
3 Runnoff Reduction equals 40% in HSG A and B and 20% in HSG C
RRv 356 ft
and D up to the WQv
Volume 3 This is the difference between the WQv calculated and the runoff
389 ft
Treated reduction achieved in the swale
Volume
0 ft 3 This volume is directed another practice
Directed
Volume √ Okay Check to be sure that channel is long enough to store WQv
Dry Swale Worksheet
Total RRV 2,118.04
Total Area 1.10
Total Impervious Area 1.10
Total Volume Treated 2,433.98
Rooftop Disconnect Impervious Area Total 0.00
Filter Strip
Design Point: SWPPP App N
Enter Site Data For Drainage Area to be Treated by Practice
Impervious Percent
Catchment Total Area WQv Precipitation
Area Impervious Rv 3 Description
Number (Acres) (ft ) (in)
(Acres) %
TRUE
Filter Strip
Design Point: SWPPP App N
Enter Site Data For Drainage Area to be Treated by Practice
Impervious Percent
Catchment Total Area WQv Precipitation
Area Impervious Rv 3 Description
Number (Acres) (ft ) (in)
(Acres) %
Design Elements
Is another area based practice applied to
Y/N
this area?
Amended Soils & Dense Turf Cover? Y/N
Is area protected from compaction from
Y/N
heavy equipment during construction?
Small Area of Impervious Area & close to
Y/N
source?
Composte Amendments? Y/N
Boundary Spreader? Y/N Gravel Diaphram at top
Boundary Zone? Y/N 25 feet of level grass
level spreader shall be used for buffer
Specify how sheet flow will be ensured.
slopes ranging from 3‐15%
3% maximum unless a level spreader is
Average contributing slope %
used.
Slope of first 10 feet of Filter Strip % 2% maximum
Overall Slope % 8% maximum
Contributing Length of Pervious Areas (PC) ft 150 ft maximum
Contributing Length of Impervious areas ft 75 ft maximum
Maximum PC Contributing Length for
150 ft
combination of PC & IC
Soil Group (HSG)
50 ft minimum for slopes 0‐8%
75 ft minimum for slopes 8‐12%
Filter Strip Width ft
100 ft minimum for slopes 12‐15%
HSG C or D increase by 15‐20%
Are All Criteria for filter strips in Section
5.3.2 met?
Area Reduction Adjustments
Subtract 0.00 Acres from total Area
FALSE
Filter Strip
Design Point: SWPPP App N
Enter Site Data For Drainage Area to be Treated by Practice
Impervious Percent
Catchment Total Area WQv Precipitation
Area Impervious Rv 3 Description
Number (Acres) (ft ) (in)
(Acres) %
Design Elements
Is another area based practice applied to
Y/N
this area?
Amended Soils & Dense Turf Cover? Y/N
Is area protected from compaction from
Y/N
heavy equipment during construction?
Small Area of Impervious Area & close to
Y/N
source?
Composte Amendments? Y/N
Boundary Spreader? Y/N Gravel Diaphram at top
Boundary Zone? Y/N 25 feet of level grass
level spreader shall be used for buffer
Specify how sheet flow will be ensured.
slopes ranging from 3‐15%
Average contributing slope % 3% maximum unless a level spreader is
Slope of first 10 feet of Filter Strip % 2% maximum
Overall Slope % 8% maximum
Contributing Length of Pervious Areas (PC) ft 150 ft maximum
Contributing Length of Impervious areas ft 75 ft maximum
Maximum PC Contributing Length for
150 ft
combination of PC & IC
Soil Group (HSG)
50 ft minimum for slopes 0‐8%
75 ft minimum for slopes 8‐12%
Filter Strip Width ft
100 ft minimum for slopes 12‐15%
HSG C or D increase by 15‐20%
Are All Criteria in Section 5.3.2 (filter
strips) met?
Area Reduction Adjustments
FALSE
Filter Strip
Design Point: SWPPP App N
Enter Site Data For Drainage Area to be Treated by Practice
Impervious Percent
Catchment Total Area WQv Precipitation
Area Impervious Rv 3 Description
Number (Acres) (ft ) (in)
(Acres) %
Design Elements
Is another area based practice applied to
Y/N
this area?
Amended Soils & Dense Turf Cover? Y/N
Is area protected from compaction from
Y/N
heavy equipment during construction?
Small Area of Impervious Area & close to
Y/N
source?
Composte Amendments? Y/N
Boundary Spreader? Y/N Gravel Diaphram at top
Boundary Zone? Y/N 25 feet of level grass
level spreader shall be used for buffer
Specify how sheet flow will be ensured.
slopes ranging from 3‐15%
Average contributing slope % 3% maximum unless a level spreader is
Slope of first 10 feet of Filter Strip % 2% maximum
Overall Slope % 8% maximum
Contributing Length of Pervious Areas (PC) ft 150 ft maximum
Contributing Length of Impervious areas ft 75 ft maximum
Maximum PC Contributing Length for
150 ft
combination of PC & IC
Soil Group (HSG)
50 ft minimum for slopes 0‐8%
75 ft minimum for slopes 8‐12%
Filter Strip Width ft
100 ft minimum for slopes 12‐15%
HSG C or D increase by 15‐20%
Are All Criteria in Section 5.3.2 (fitler
strips) met?
Area Reduction Adjustments
Subtract 0.00 Acres from total Area
FALSE
Filter Strip
Total Subtracted from Total Area 39.90
Total Subtracted from Total Impervious
0.37
Area
APPENDIX T
________________________________________________________________________________
Precipitation Frequency Data Server Page 1 of 4
PF tabular
PDS-based point precipitation frequency estimates with 90% confidence intervals (in inches/hour)1
Average recurrence interval (years)
Duration
1 2 5 10 25 50 100 200 500 1000
3.54 4.32 5.58 6.64 8.08 9.19 10.3 11.7 13.6 15.0
5-min (2.82-4.40) (3.43-5.38) (4.43-6.97) (5.23-8.34) (6.14-10.6) (6.83-12.4) (7.42-14.4) (7.96-16.8) (8.84-20.1) (9.53-22.7)
2.51 3.05 3.95 4.70 5.72 6.51 7.30 8.31 9.65 10.7
10-min (2.00-3.12) (2.43-3.80) (3.14-4.94) (3.70-5.90) (4.35-7.53) (4.84-8.76) (5.26-10.2) (5.63-11.9) (6.27-14.3) (6.75-16.1)
1.97 2.40 3.10 3.68 4.49 5.11 5.73 6.52 7.57 8.36
15-min (1.57-2.45) (1.91-2.98) (2.46-3.88) (2.90-4.63) (3.41-5.91) (3.80-6.87) (4.12-8.01) (4.42-9.31) (4.92-11.2) (5.29-12.6)
1.35 1.64 2.13 2.53 3.08 3.51 3.93 4.48 5.20 5.74
30-min (1.08-1.68) (1.31-2.05) (1.69-2.66) (1.99-3.18) (2.34-4.05) (2.61-4.72) (2.83-5.50) (3.03-6.39) (3.37-7.69) (3.63-8.67)
0.857 1.05 1.35 1.61 1.96 2.23 2.50 2.85 3.30 3.65
60-min (0.683-1.07) (0.832-1.30) (1.07-1.69) (1.27-2.02) (1.49-2.58) (1.66-3.00) (1.80-3.50) (1.93-4.06) (2.15-4.89) (2.31-5.51)
0.536 0.648 0.833 0.986 1.20 1.36 1.52 1.76 2.06 2.30
2-hr (0.430-0.662) (0.520-0.802) (0.665-1.03) (0.782-1.23) (0.918-1.57) (1.02-1.83) (1.11-2.13) (1.19-2.49) (1.34-3.04) (1.46-3.45)
0.404 0.488 0.625 0.739 0.896 1.02 1.14 1.32 1.55 1.73
3-hr (0.325-0.498) (0.393-0.601) (0.501-0.774) (0.589-0.920) (0.690-1.17) (0.767-1.36) (0.833-1.59) (0.897-1.86) (1.01-2.28) (1.10-2.59)
0.250 0.302 0.386 0.457 0.553 0.628 0.702 0.808 0.948 1.05
6-hr (0.203-0.306) (0.244-0.370) (0.312-0.475) (0.366-0.564) (0.428-0.718) (0.475-0.834) (0.515-0.973) (0.553-1.14) (0.621-1.38) (0.673-1.57)
0.152 0.184 0.237 0.280 0.340 0.386 0.432 0.490 0.567 0.626
12-hr (0.124-0.185) (0.150-0.224) (0.192-0.289) (0.226-0.344) (0.264-0.437) (0.292-0.507) (0.316-0.590) (0.337-0.685) (0.374-0.821) (0.401-0.925)
0.091 0.110 0.142 0.168 0.204 0.232 0.260 0.293 0.337 0.371
24-hr (0.075-0.110) (0.091-0.133) (0.116-0.172) (0.137-0.205) (0.159-0.260) (0.176-0.302) (0.191-0.351) (0.203-0.406) (0.223-0.485) (0.238-0.544)
0.053 0.064 0.082 0.096 0.117 0.132 0.148 0.168 0.194 0.214
2-day (0.044-0.064) (0.053-0.077) (0.067-0.098) (0.079-0.117) (0.092-0.148) (0.101-0.172) (0.109-0.200) (0.117-0.231) (0.129-0.278) (0.138-0.313)
0.039 0.046 0.059 0.069 0.083 0.094 0.105 0.119 0.138 0.152
3-day (0.032-0.046) (0.039-0.056) (0.049-0.070) (0.057-0.083) (0.066-0.105) (0.072-0.121) (0.078-0.141) (0.083-0.164) (0.092-0.196) (0.098-0.221)
0.031 0.037 0.047 0.055 0.065 0.074 0.082 0.093 0.107 0.118
4-day (0.026-0.037) (0.031-0.044) (0.039-0.056) (0.045-0.066) (0.052-0.082) (0.057-0.095) (0.061-0.110) (0.065-0.127) (0.071-0.153) (0.077-0.172)
0.021 0.025 0.030 0.035 0.042 0.047 0.052 0.058 0.066 0.072
7-day (0.018-0.025) (0.021-0.029) (0.025-0.036) (0.029-0.042) (0.033-0.052) (0.036-0.060) (0.038-0.069) (0.041-0.079) (0.044-0.093) (0.047-0.104)
0.017 0.020 0.024 0.027 0.032 0.036 0.039 0.044 0.049 0.054
10-day (0.014-0.020) (0.017-0.023) (0.020-0.028) (0.023-0.033) (0.026-0.040) (0.028-0.045) (0.029-0.052) (0.031-0.059) (0.033-0.069) (0.035-0.077)
0.012 0.014 0.016 0.018 0.020 0.023 0.025 0.027 0.029 0.031
20-day (0.010-0.014) (0.012-0.016) (0.013-0.019) (0.015-0.021) (0.016-0.025) (0.018-0.028) (0.018-0.032) (0.019-0.036) (0.020-0.041) (0.020-0.045)
0.010 0.011 0.013 0.014 0.016 0.018 0.019 0.020 0.022 0.024
30-day (0.009-0.012) (0.009-0.013) (0.011-0.015) (0.012-0.017) (0.013-0.020) (0.014-0.022) (0.014-0.025) (0.015-0.027) (0.015-0.031) (0.015-0.034)
0.008 0.009 0.010 0.011 0.013 0.014 0.015 0.016 0.017 0.018
45-day (0.007-0.010) (0.008-0.011) (0.009-0.012) (0.010-0.014) (0.010-0.016) (0.011-0.017) (0.011-0.019) (0.011-0.021) (0.012-0.024) (0.012-0.026)
0.007 0.008 0.009 0.010 0.011 0.012 0.013 0.014 0.014 0.015
60-day (0.006-0.009) (0.007-0.009) (0.008-0.011) (0.008-0.012) (0.009-0.013) (0.009-0.015) (0.010-0.016) (0.010-0.018) (0.010-0.020) (0.010-0.021)
1
Precipitation frequency (PF) estimates in this table are based on frequency analysis of partial duration series (PDS).
Numbers in parenthesis are PF estimates at lower and upper bounds of the 90% confidence interval. The probability that precipitation frequency estimates (for a
given duration and average recurrence interval) will be greater than the upper bound (or less than the lower bound) is 5%. Estimates at upper bounds are not
checked against probable maximum precipitation (PMP) estimates and may be higher than currently valid PMP values.
Please refer to NOAA Atlas 14 document for more information.
Back to Top
PF graphical
http://hdsc.nws.noaa.gov/hdsc/pfds/pfds_printpage.html?lat=42.5486&lon=-73.8170&data=... 7/7/2016
APPENDIX U
________________________________________________________________________________
New York State Stormwater Management Design Manual Appendix G
Project:
Location:
Site Status:
Date:
Time:
Inspector:
SATISFACTORY/
MAINTENANCE ITEM COMMENTS
UNSATISFACTORY
1. Debris Cleanout (Monthly)
Contributing areas clean of debris
2. Check Dams or Energy Dissipators (Annual, After Major Storms)
No evidence of flow going around
structures
No evidence of erosion at downstream
toe
Soil permeability
Groundwater / bedrock
3. Vegetation (Monthly)
Mowing done when needed
Minimum mowing depth not exceeded
No evidence of erosion
Fertilized per specification
4. Dewatering (Monthly)
Dewaters between storms
G-13
New York State Stormwater Management Design Manual Appendix G
SATISFACTORY/
MAINTENANCE ITEM COMMENTS
UNSATISFACTORY
5. Sediment deposition (Annual)
Clean of sediment
6. Outlet/Overflow Spillway (Annual)
Good condition, no need for repairs
No evidence of erosion
Comments:
Actions to be Taken:
G-14
APPENDIX V
COMMERCIAL REQUIREMENTS
________________________________________________________________________________
OPERATION AND MAINTENANCE PLAN
Contact:
Mithun Vyas
Project Manager
Telephone: (561) 694-3842
Prepared For:
Prepared by:
Responsible Party
This Operation and Management (O&M) Plan provides guidance for the responsible
party on the long term maintenance of the stormwater facilities that have been
constructed. Long term maintenance is the critical component of a successful
stormwater management plan. Adherence to the O&M Plan ensures that the
permanent SMPs continue to function as designed and provide a level of performance
similar to that when they were initially constructed. In addition, regular maintenance
allows for potential problems to be identified and rectified before a component of the
system fails.
The stormwater drainage system for the Selkirk Solar Farm utilizes water quality dry
swales as a permanent SMPs. In order to achieve source treatment, the dry swales
will be located adjacent to proposed gravel access roads, which will be sloped to shed
runoff toward the swales.
Post-Construction Tasks
The Construction Documents will require that the Contractor remove all temporary
sediment and erosion control SMPs, as well as all accumulated sediments in the
temporary SMPs, when construction is complete and disturbed areas have vegetation
that is fully established. The Contractor shall also construct the permanent SMPs in
accordance with the Construction Plans and NYS DEC SMP standards.
1. A copy of the Operations and Maintenance Plan and the Construction Plans showing
the permanent stormwater facilities shall be kept on the project site.
2. Site access shall be maintained to a level acceptable to the local Fire Chief and
Emergency Medical Services.
a.
1
DG Solar Solar, 700 Universe Boulevard, Juno Beach, Florida
October, 2016 O&M PLAN
4. Regularly remove trash and natural debris from the site. Clean leaves or trash from
water quality swale when observed.
5. Mow site and water quality swales as needed to maintain a grass height of 4 to 6
inches.
6. The following should be done annually and within 48 hours of major storm events
(greater than one inch of rainfall depth):
7. Inspect pipe outlets monthly for erosion and accumulated sediments. Remove
sediments and repair any areas of erosion with new riprap.
8. Inspect sloped areas and other areas for any signs of erosion. Perform any necessary
soil stabilization, embankment replacement, earth repair, reseeding or mulching upon
identification.
9. On-site equipment should be inspected regularly for leaks and spills. Inspectors
should:
10. Snow should be stored on upland pervious areas and away from all water bodies
including wetlands. Avoid disposing of snow in water quality swales. Debris should
be cleared from the site prior to using the site for snow disposal. Debris should be
cleared from the site and properly disposed of at the end of the snow season and no
later than May 15.
2
DG Solar Solar, 700 Universe Boulevard, Juno Beach, Florida
October, 2016 O&M PLAN
1. Dry Swale
It is critical to provide access for maintenance, especially to the interior of the swale.
Inspect dry swales at least once per year to ensure that they are operating as intended.
Inspect the outlet structure for evidence of clogging or outflow release velocities that are
greater than design flow. Potential problems that should be checked include: subsidence,
erosion, cracking or tree growth on the embankment; sediment accumulation around the
outlet; inadequacy of the outlet channel erosion control measures; and erosion within the
swale banks. Make any necessary repairs immediately. During inspections, note changes
to the swales or the contributing watershed because these changes could affect future
performance. Mow the side slopes, embankment, and emergency spillway at least twice
per year or as needed to maintain a grass height of 4 to 6 inches. Remove trash and debris
at this time. Remove sediment from the basin when 25 percent of the original WQv
volume has been exceeded.
3
DG Solar Solar, 700 Universe Boulevard, Juno Beach, Florida
October, 2016 O&M PLAN
Annual Inspection:
Fences - Inspect fences, gates, security cameras for wear, corrosion and vandalism.
Signs - Verify all warning signs are visible and properly attached.
Weeds - Check fenced area for noxious plants. Note type and extent. Check for fire hazards.
Roads - Inspect roads for ruts, washouts and soft spots. Check culverts for blockage.
Stormwater - Check dry swales for sediment buildup and swale underdrains for clogging.
Shade - Inspect trees for shading issues.
Racking - Inspect piers, rails and H-frames for structural integrity, corrosion and safety hazards.
Electrical - Inspect modules, wire runs, combiners, inverters, AC panels, meters, disconnects and
transformers for visible damage.
Document with both visible light cameras and infrared thermal imagers. Test for ground faults.
Data - Inspect data acquisition systems, weather stations and energy meters.
Maintenance
Mowing - Mow site and 10’ around outside of perimeter fence as needed to maintain a grass
height of 4 to 6 inches to reduce the possibility of brush fire..
Repairs - Coordinate repair crews.
Calibration - Clean and calibrate weather station and tracking motor sensors.
Operations
Production - Compare actual power production against predicted, considering weather conditions.
Track times the PV array goes offline. Identify causes and effect solutions.
4
PERFORMANCE BOND SUMMARY
The Engineering Division has requested a Performance Bond which lists the Town of Bethlehem
as the Beneficiary:
Stated Amount: $
Check No.:
Project Information:
Project Name:
Section/Phase:
Location:
Work Covered/Purpose:
Street Name(s):
Location/Station(s):
Other:
Applicant/Account Party:
Name: Tony Yonnone
Page 1 of 3
PERFORMANCE BOND AGREEMENT
Project Name:
Work Covered/Purpose:
Street Name(s):
Location/Station(s):
Other:
Amount: Subject to the terms and conditions herein, this Performance Bond authorizes the Beneficiary
to draw an aggregate amount not to exceed $___________ US Dollars (the "Stated Amount").
Requests for Drawings: The Account Party hereby agrees that drawings under and in compliance with
the terms of this agreement shall be honored.
Requests for Drawings under this Agreement shall be documented by the Beneficiary in the form of
Annex A, executed by the Supervisor and attested by the Clerk of the Beneficiary. Each Drawing
honored shall reduce the Stated Amount, and drawings may not in the aggregate exceed the Stated
Amount.
The Beneficiary’s Bank shall have no duty to verify the correctness or completeness of any certificate or
instructions delivered to Bank by the Beneficiary, but rather, may rely without question on any
Beneficiary Certificate as to the amount for any Drawing, Reduction or Reinstatement.
Timing of Payments: Drawings, in the form of Annex A, may be presented by means of facsimile
transmission, with telephone confirmation and original documents to follow by United States mail, or by
courier to the Beneficiary’s Bank.
Payment Instructions: Drawings will be paid by means of Bank check or, at the request of the
Beneficiary, by electronic funds transfer, provided that the Beneficiary shall provide complete funds
transfer instructions at the time of the draw.
Expiration: This Agreement shall expire on the earliest of: (a) the close of business on the Stated
Expiration Date; (b) the date on which the aggregate amount of drawings have exhausted the Stated
Amount; or (c) the date on which Annex A is signed by the Supervisor and attested by the Clerk of the
Beneficiary certifying that all conditions have been met for the release of the Performance Bond or the
Beneficiary has accepted a substitute Performance Bond.
_____________________________________ ___________________________________
Name (please print) Name (please print)
_____________________________________ ___________________________________
Signature Signature
_____________________________________ ___________________________________
Page 2 of 3
Date Date
TOWN OF BETHLEHEM
Town Supervisor Albany County - New York
445 DELAWARE AVENUE
DELMAR, NEW YORK 12054
Town Clerk (518) 439-4955 x 1139
(518) 439-5808 Fax
ANNEX A
PERFORMANCE BOND
1. The Town is making a drawing under the Performance Bond as a result of either (a) failure of the
Account Party to honor their contractual agreement covering the remaining work within the
specified project on or before the required date therefore in accordance with applicable
requirements, or (b) failure of the Account Party to deliver an amended or substitute Performance
Bond or other acceptable security not less than thirty (30) days prior to the Stated Expiration
Date, in the amount of the Stated Amount or such lesser amount as shall be determined by the
Town, where such construction of project improvements has not been completed before the date
of this Drawing.
IN WITNESS WHEREOF, the undersigned has executed and delivered the Certificate as of the
_____ day of _________________, 20____.
TOWN OF BETHLEHEM
Page 3 of 3
APPENDIX W
________________________________________________________________________________
New York State Department of Environmental Conservation
Division of Water
625 Broadway, 4th Floor
Albany, New York 12233-3505
*(NOTE: Submit completed form to address above)*
Please indicate your permit identification number: NYR ___ ___ ___ ___ ___ ___
I. Owner or Operator Information
9a. Ƒ All disturbed areas have achieved final stabilization in accordance with the general permit and
SWPPP. *Date final stabilization completed (month/year):
9b. Ƒ Permit coverage has been transferred to new owner/operator. Indicate new owner/operator’s
permit identification number: NYR ___ ___ ___ ___ ___ ___
(Note: Permit coverage can not be terminated by owner identified in I.1. above until new
owner/operator obtains coverage under the general permit)
10a. Did this construction activity require the development of a SWPPP that includes post-construction
stormwater management practices? Ƒ yes Ƒ no ( If no, go to question 10f.)
10b. Have all post-construction stormwater management practices included in the final SWPPP been
constructed? Ƒ yes Ƒ no (If no, explain on Page 2)
10c. Identify the entity responsible for long-term operation and maintenance of practice(s)?
Page 1 of 3
NOTICE OF TERMINATION for Storm Water Discharges Authorized under the
SPDES General Permit for Construction Activity - continued
10d. Has the entity responsible for long-term operation and maintenance been given a copy of the
operation and maintenance plan required by the general permit? Ƒ yes Ƒ no
10e. Indicate the method used to ensure long-term operation and maintenance of the post-construction
stormwater management practice(s):
Ƒ Post-construction stormwater management practice(s) and any right-of-way(s) needed to
maintain practice(s) have been deeded to the municipality.
Ƒ Executed maintenance agreement is in place with the municipality that will maintain the
post-construction stormwater management practice(s).
Ƒ For post-construction stormwater management practices that are privately owned, a mechanism
is in place that requires operation and maintenance of the practice(s) in accordance with the operation
and maintenance plan, such as a deed covenant in the owner or operator’s deed of record.
Ƒ For post-construction stormwater management practices that are owned by a public or private
institution (e.g. school, university or hospital), government agency or authority, or public utility; policy and
procedures are in place that ensures operation and maintenance of the practice(s) in accordance with the
operation and maintenance plan.
10f. Provide the total area of impervious surface (i.e. roof, pavement, concrete, gravel, etc.) constructed
within the disturbance area?
(acres)
11. Is this project subject to the requirements of a regulated, traditional land use control MS4? Ƒ yes
Ƒ no
(If Yes, complete section VI - “MS4 Acceptance” statement
V. Additional Information/Explanation:
(Use this section to answer questions 9c. and 10b., if applicable)
VI. MS4 Acceptance - MS4 Official (principal executive officer or ranking elected official) or Duly
Authorized Representative (Note: Not required when 9b. is checked -transfer of coverage)
I have determined that it is acceptable for the owner or operator of the construction project identified in
question 5 to submit the Notice of Termination at this time.
Printed Name:
Title/Position:
Signature: Date:
Page 2 of 3
NOTICE OF TERMINATION for Storm Water Discharges Authorized under the
SPDES General Permit for Construction Activity - continued
I hereby certify that all disturbed areas have achieved final stabilization as defined in the current version
of the general permit, and that all temporary, structural erosion and sediment control measures have
been removed. Furthermore, I understand that certifying false, incorrect or inaccurate information is a
violation of the referenced permit and the laws of the State of New York and could subject me to
criminal, civil and/or administrative proceedings.
Printed Name:
Title/Position:
Signature: Date:
I hereby certify that all post-construction stormwater management practices have been constructed in
conformance with the SWPPP. Furthermore, I understand that certifying false, incorrect or inaccurate
information is a violation of the referenced permit and the laws of the State of New York and could
subject me to criminal, civil and/or administrative proceedings.
Printed Name:
Title/Position:
Signature: Date:
I hereby certify that this document was prepared by me or under my direction or supervision. My
determination, based upon my inquiry of the person(s) who managed the construction activity, or those
persons directly responsible for gathering the information, is that the information provided in this
document is true, accurate and complete. Furthermore, I understand that certifying false, incorrect or
inaccurate information is a violation of the referenced permit and the laws of the State of New York and
could subject me to criminal, civil and/or administrative proceedings.
Printed Name:
Title/Position:
Signature: Date:
Page 3 of 3