1. Purpose
2. Reference
Items No.8, No.15, and checking points mentioned in No.11 from the Quality Control and
Management for Construction guidelines established by the Public Construction Commission
of the Republic of China (Taiwan).
3. Application
Applicable to all major construction, structural, and interior design projects carried out under
contract at all Center locations. Not applicable to small, simple repair jobs
4. Specification
5. Definition
5.1 Inspection
To ensure the items used during a construction project meet the specifications, and to
ensure a construction project has been completed properly and in accordance with
contractual requirements. Inspections are carried out by checking, measuring,
conducting a quantity survey, or visual inspection.
Points during a project when inspection is required and approval is necessary before
proceeding to the next construction stage. The checking points are set by the Architect,
and should include all common stages of a project, such as materials delivery, setting
layout, and installation.
1
6. Procedure and explanation
Upon the arrival of materials, the contractor is responsible for primary quality
control. A self-inspection should be carried out according to the quality control
plan based on the above-referenced quality control guidelines. After the
self-inspection is completed, the contractor must inform the Architect’s supervisor
and the Center’s technician, so that they may carry out a joint examination of the
materials. The inspection criteria must follow the contractual drawings, standard
specifications, and general guidelines for construction inspection. If the materials
do not meet specifications, the Center’s technician will work with the Architect’s
supervisor to immediately issue a Non-Conformity Report (NCR; Attachment 1)
to the contractor. The contractor must then change the materials immediately upon
receiving the NCR, and redo the primary self-inspection. After the self-inspection,
the contractor must contact the Architect’s supervisor and the Center’s technician
to request that the NCR be closed before the project moves to the next phase of
construction.
After the materials are confirmed and accepted, the contractor can proceed in
setting the layout. The contractor must perform a self-inspection of the layout, and
then inform the Architect’s supervisor and the Center’s technician to inspect the
layout work. If the layout work is unacceptable, the Center’s technician will work
with the Architect’s supervisor to immediately issue an NCR to the contractor.
Upon receiving the NCR, the contractor must immediately reset the layout and
redo the primary self-inspection. After the self-inspection, the contractor must
contact the Architect’s supervisor and the Center’s technician to request that the
NCR be closed before the project moves to the next phase of construction.
After the setting layout work is confirmed and accepted, the contractor can
proceed to the installation or assembly work. The contractor must perform a
self-inspection of this work, and then inform the Architect’s supervisor and the
Center’s technician to inspect the installation or assembly. If the installation or
assembly is unacceptable, the Center’s technician will work with the Architect’s
supervisor to immediately issue an NCR to the contractor. Upon receiving the
NCR, the contractor must immediately reinstall or reassemble the work, and redo
the primary self-inspection. After the self-inspection, the contractor must contact
the Architect’s supervisor and the Center’s technician to request that the NCR be
closed. At the completion of this phase, the Architect’s supervisor and the
Center’s technician must both sign the quality control card for the completion of a
specific working item. The contractor must attach the co-signed quality control
card with the payment request for the interim payment approval.
2
6.2.1.1 Materials inspection
a. Follow the survey plan in the method statement for detail inspection.
(Confirm the method statement has been approved by the Architect and
the Center.)
Please refer to the construction inspection flowchart (Figure 1) for the procedure.
7.2 Quality Control Card: Attachments 2-1 to 2-4 (Format developed by the contractor’s
quality control staff according to the various construction items in contract, and
approved by the Architect and the Center.)
3
Figure 1
Construction Inspection Flowchart
Arrival of Materials
Improvement
NCR Closeout after
Contractor’s primary self-inspection
NCR Notification
Fail Pass
★ Materials Setting Layout
Inspection
NCR Notification
Architect’s supervisor /
Center’s technician
Architect’s supervisor /
Center’s technician
“★” Center’s technicians should implement the inspection based on the checking points in the flowchart. All
NCRs should be issued by the Center and the Architect. TSO must record the NCR serial numbers and
file copies of the NCR when they are closed out.
4
Attachment 1
AVRDC – The World Vegetable Center
Confirmation of Improvement
Remarks:
5
Attachment 2-1
AVRDC – The World Vegetable Center
Under Vertical
Dimension, quantity, location and
Construction
overlap for the reserved rebar
Dimension, quantity, location and
overlap for the extra rebar
Embedded parts
Inspection results and comments: Rebar grade and quantity detail (Ton)
Remarks:
(1) Fill out the specification no. or reference resource according to the contractual requirement.
(2) Attach the contractor’s self-inspection report to this form.
(3) Write down the result with date and signature in sequence by Architect’s supervisor.
(4) Submit the Quality Control Card with 3 copies: one for the contractor’s file, one for the Architect, and one
for the payment request use.
6
Attachment 2-2
AVRDC – The World Vegetable Center
Panel grade
Working frame setup
Panel size
Support and accessories
Expansion and construction joints
Embedment
Pre-openings and reinforcing supports
Verticality and elevation control
Thickness of protection
Inspection results and comments:
Remarks:
(1) Fill out the specification no. or reference resource according to the contractual requirement.
(2) Attach the contractor’s self-inspection report to this form.
(3) Write down the result with date and signature in sequence by Architect’s supervisor.
(4) Submit the Quality Control Card with 3 copies: one for the contractor’s file, one for the Architect and
one for the payment request use.
7
Attachment 2-3
AVRDC – The World Vegetable Center
14 21 25 28 35
N/mm2 N/mm2 N/mm2 N/mm2 N/mm2
Remarks:
(1) Fill out the specification no. or reference resource according to the contractual requirement.
(2) Attach the contractor’s self-inspection report to this form.
(3) Write down the result with date and signature in sequence by Architect’s supervisor.
(4) Submit the Quality Control Card with 3 copies: one for the contractor’s file, one for the Architect and
one for the payment request use.
8
Attachment 2-4
AVRDC – The World Vegetable Center
Pre-assembly
Location and elevation layout
Support, joint, and connection
accessory
(2)
Finish surface
Construction Openings and embedment
Inspection Trim treatment
Verticality and horizontality
Cleaning and protection
Remarks:
(1) Fill out the specification no. or reference resource according to the contractual requirement.
(2) Attach the contractor’s self-inspection report to this form.
(3) Write down the result with date and signature in sequence by Architect’s supervisor.
(4) Submit the Quality Control Card with 3 copies: one for the contractor’s file, one for the Architect and
one for the payment request use.