1 Data Profil
Area perhitungan Perencanaan Balok Perencanaan Kolom
2 Data Bahan
A Material :
Mutu beton K - 225 f'c : 18.74 Mpa =======> 187.4 Kg/cm2
Mutu baja Tulangan Utama U 40 : 400 Mpa =======> 4000 Kg/cm2
Mutu baja Tulangan Geser U 24 : 240 Mpa =======> 2400 Kg/cm2
Berat Jenis Baja : 7850 Kg/m3
Berat Jenis Beton : 2400 Kg/m3
Tebal Selimut Beton : 20 mm
Dimensi Balok : 140 x 300
Dimensi Kolom 1 : 130 x 300
Dimensi Kolom 2 : 130 x 300
L Balok : 4m
L Kolom : 3.5 m
B Pembebanan
Dead Load
Berat Sendiri Plat Lantai = 0.140x0.300x 2400 = 100.8 Kg/m2
Berat Sendiri Plat Lantai = 0.12 x 2400 = 288 Kg/m2
Berat Screed + Keramik = 90 Kg/m2
Dinding Setengah Bata = 250 Kg/m2
Plafon + Penggantung = 18 Kg/m2
Mechanical & Electrical = 40 Kg/m2
Total = 786.8 Kg/m2
Live Load
Beban Hidup Pada Lantai = 250 Kg/m2
4 Perhitungan Momen
Momen Maksimal Pada tumpuan dan tengah Bentang 4
A Tumpuan Dalam Intensitas Momen Negatif
Mu = 1/10 x Wu x Lu 2
= 2150.656 Kg.m
B Pada Tengah Bentang
Mu = 1/14 x Wu x Lu2 = 1536.1828571429 Kg.m
C Pada Tumpuan Luar
Mu = 1/24 x Wu x Lu2 = 896.1066666667 Kg.m
5 Tinjauan Penulangan
1 Perhitungan Penulangan Tumpuan Luar
Data Mu = 896.1066666667 Kg.m
f'c = 18.74 Mpa
fy = 400 Mpa
h = 120 mm
b = 1000 mm
ts = 20 mm
D = 8 mm =======> Diambil Tulangan D12
d = h - Ts - (0.5 . D)
94
Hitung :
A. Pmin = 1.4 = 0.0035
fy
B1 = 0.85 Untuk , f'c < 30Mpa
P Max = 75% . Pb
= 0.0152321063
B. ab = B1 x cb
= B1 x 600 xd
600+ fy
= 47.94 mm
a Max = 75% . Ab
= 0.75 . Ab
= 35.955 mm
C. Mn ada = Cc . (d - (a/2)
= 0.85 * f'c * b * a max *(d - a/2)
= 43540153.1818875 N.mm
Mn Perlu = Mu = 896106.666666667 = 1120133.333333 N.mm
D 0.8
Maka Mn ada > Mn Perlu =======> Pakai Tulangan Tunggal
D. Menghitung
m = fy = 25.1114319794
0.85 x f'c
Rn = Mu = 8961066.66666667 = 1.267692772 Mpa
D . B . d2 0.8 x 1000 x d2
P = 1/m(1-SQRT((1-(2*m*Rn)/fy)))
= 0.0033065031
Syarat
pmin < p < Pmax Karena Pmin > P Maka Menggunakan P min
Pmin = 0.0035
As = P min . B . D
329 mm2
dipakai Tulangan D8 - 150 = 351.68 mm2 > 329 mm2
2 Perhitungan Penulangan Tumpuan Dalam
Data Mu = 2150.656 mm2
f'c = 18.74 Mpa
fy = 400 Mpa
h = 120 mm
b = 1000 mm
ts = 20 mm
D = 12 mm =======> Diambil Tulangan D12
d = h - Ts - (0.5 . D)
94
Hitung :
A. Pmin = 1.4 = 0.0035
fy
B1 = 0.85 Untuk , f'c < 30Mpa
P Max = 75% . Pb
= 0.0152321063
B. ab = B1 x cb
= B1 x 600 xd
600+ fy
= 47.94 mm
a Max = 75% . Ab
= 0.75 . Ab
= 35.955 mm
C. Mn ada = Cc . (d - (a/2)
= 0.85 * f'c * b * a max *(d - a/2)
= 43540153.1818875 N.mm
Mn Perlu = Mu = 2150656 = 2688320 N.mm
D 0.8
Maka Mn ada > Mn Perlu =======> Pakai Tulangan Tunggal
D. Menghitung
m = fy = 25.1114319794
0.85 x f'c
Rn = Mu = 21506560 = 3.0424626528 Mpa
D . B . d2 0.8 x 1000 x d2
P = 1/m(1-SQRT((1-(2*m*Rn)/fy)))
= 0.0085169228
Syarat
pmin < p < Pmax Karena Pmin < P Maka Menggunakan P
P = 0.0085169228
As = P min . B . D
800.5907469948 mm2
dipakai Tulangan D12 - 125 = 904.32 mm2 > 800.5907 mm2
P Max = 75% . Pb
= 0.0152321063
B. ab = B1 x cb
= B1 x 600 xd
600+ fy
= 47.94 mm
a Max = 75% . Ab
= 0.75 . Ab
= 35.955 mm
C. Mn ada = Cc . (d - (a/2)
= 0.85 * f'c * b * a max *(d - a/2)
= 43540153.1818875 N.mm
Mn Perlu = Mu = 1536182.85714286 = 1920228.571429 N.mm
D 0.8
Maka Mn ada > Mn Perlu =======> Pakai Tulangan Tunggal
D. Menghitung
m = fy = 25.1114319794
0.85 x f'c
Rn = Mu = 15361828.5714286 = 2.1731876091 Mpa
D . B . d2 0.8 x 1000 x d2
P = 1/m(1-SQRT((1-(2*m*Rn)/fy)))
= 0.0058648398
Syarat
pmin < p < Pmax Karena Pmin < P Maka Menggunakan P
P = 0.0058648398
As = P min . B . D
551.2949381991 mm2
dipakai Tulangan D12 - 170 = 678.24 mm2 > 551.2949 mm2
3 Perhitungan Tulangan Susut
Data
Mutu Baja = 400 Mpa
Berarti Menggunakan P = 0.0035
As = P. B.D
329 mm2
dipakai Tulangan D12 - 250 = 452.16 mm2 > 329 mm2
Analisa Kolom dan Balok
Customer : Margorejo Indah Note:
Project Name : Analisa Kolom dan Balok
Project Location : Surabaya
Revision : ( 0 )
Date Revision : 17-03-2018
1 Data Profil
Area perhitungan As 7 - 8 Perencanaan Kolom
Perencanaan Balok
2 Data Bahan
A Material :
Mutu beton K - 225 f'c : 18.74 Mpa =======> 187.4 Kg/cm2
Mutu baja Tulangan Utama U 40 : 400 Mpa =======> 4000 Kg/cm2
Mutu baja Tulangan Geser U 24 : 240 Mpa =======> 2400 Kg/cm2
Berat Jenis Baja : 7850 Kg/m3
Berat Jenis Beton : 2400 Kg/m3
Tebal Selimut Beton : 20 mm
Dimensi Balok : 0.14 x 0.3
Dimensi Kolom 1 : 0.13 x 0.3
Dimensi Kolom 2 : 0.13 x 0.3
Lx : 3 m
Ly : 4 m
B Pembebanan
Dead Load
Berat Sendiri = 0.140x0.300x 2400 = 100.8 Kg/m2
Berat Sendiri Plat La = 0.12 x 2400 = 288 Kg/m2
Berat Screed + Keramik = 90 Kg/m2
Dinding Setengah Bata = 250 Kg/m2
Plafon + Penggantung = 18 Kg/m2
Mechanical & Electrical = 40 Kg/m2
Total = 786.8 Kg/m2
Live Load
Beban Hidup Pada Lantai = 250 Kg/m2
4 Perhitungan Momen
A Perataan beban trapesium
Wu = 1570.13 kg/m'
A 1126.70 kgm B
-2448.236 kgm
4 m
Σ MG = 0
RF . L - 1/2Wu.L2 - MFG + MGF = 0
RF 4 - ½ 1570.13 * 4 2 - 1126.70 + -2448.236 = 0
4 RF - 12561.06 + -3574.933 = 0
16135.993
RF =
4
= 4033.998 kg
Σ MF = 0
RG . L - 1/2Wu.L2 + MFG - MGF = 0
RG 4 - ½ 1570.13 * 4 2 + 1126.697 - -2448.236 = 0
4 RF - 12561.06 - -3574.933 = 0
8986.127
RG =
4
= 2246.532 kg
Momen maksimum Dx = 0
Maka, -1570.133 x = 4033.998
x = 2.569209 m
Be = 656.667 mm
L
1. Be = Bw +
h d 12
6200
= 140 +
12
= 656.7 mm
2. Be = Bw + 6,1 t
Bw= 140 mm = 140 + 6.1 * 120
= 872 mm
Hitung :
Mu 11266970
Mn perlu = = = 14083713 Nmm
Ø 0.8
2 Mu
a aktual = d- d2 -
0,85 * f'c * Ø * Be
2 * 11266970
= 474 - 474 2
-
= 474 - 474 2
-
0.85 * 19 * 0.8 * 656.7
= 474 - 471.1509
= 2.849132
Pakai ρmin
As = ρmin * Bw * d = 0.004667 * 140 * 474 = 309.7 mm2
Hitung :
Mu 24482370
Mn perlu = = = 30602963 Nmm
Ø 0.8
2 Mu
a aktual = d- d2 -
0,85 * f'c * Ø * Be
2 * 24482370
= 474 - 474 2
-
0.85 * 19 * 0.8 * 656.7
= 474 - 467.7869
= 6.213086
0,85 * f'c * Be * a aktual 0.85 * 19 * 656.7 * 6.213
ρ = =
Bw * d * fy 140 * 474 * 400
= 0.002448
Pakai ρmin
As = ρ * Bw * d = 0.002448 * 140 * 474 = 162.5 mm2
Hitung :
Mu 40553960
Mn perlu = = = 50692450 Nmm
Ø 0.8
2 Mu
a aktual = d- d2 -
0,85 * f'c * Ø * Be
2 * 40553960
= 474 - 474 2
-
0.85 * 19 * 0.8 * 656.7
= 474 - 463.663
= 10.33696
Pakai ρmin
As = ρ * Bw * d = 0.004073 * 140 * 474 = 270.3 mm2
Be = 656.667 mm
L
1. Be = Bw +
h d 12
6200
= 140 +
12
= 656.7 mm
2. Be = Bw + 6,1 t
Bw= 140 mm = 140 + 6.1 * 120
= 872 mm
Hitung :
Mu 11266970
Mn perlu = = = 14083713 Nmm
Ø 0.8
2 Mu
a aktual = d- d2 -
0,85 * f'c * Ø * Be
2 * 11266970
= 274 - 274 2
-
0.85 * 19 * 0.8 * 656.7
= 274 - 269.0412
= 4.958849
0,85 * f'c * Be * a aktual 0.85 * 19 * 656.7 * 4.959
ρ = =
Bw * d * fy 140 * 274 * 400
= 0.00338
Pakai ρmin
As = ρmin * Bw * d = 0.004667 * 140 * 274 = 179.0 mm2
Hitung :
Mu 24482370
Mn perlu = = = 30602963 Nmm
Ø 0.8
2 Mu
a aktual = d- d2 -
0,85 * f'c * Ø * Be
2 * 24482370
= 274 - 274 2
-
0.85 * 19 * 0.8 * 656.7
= 274 - 263.1057
= 10.89432
= 0.007427
Syarat ρmin < ρ < ρmax karena ρmin < ρ
ρmin = 0.007427
Pakai ρmin
As = ρ * Bw * d = 0.007427 * 140 * 274 = 284.9 mm2
Hitung :
Mu 40553960
Mn perlu = = = 50692450 Nmm
Ø 0.8
2 Mu
a aktual = d- d2 -
0,85 * f'c * Ø * Be
2 * 40553960
= 274 - 274 2
-
0.85 * 19 * 0.8 * 656.7
= 274 - 255.7018
= 18.2982
Pakai ρmin
As = ρ * Bw * d = 0.012474 * 140 * 274 = 478.5 mm2
k . Lu
< 22 SK. SNI T - 15 - 1991 - 03. 33 11 4)
r
dimana :
k = faktor tekuk = 1
lu = panjang kolom = 3.5
I 1 / 12 . 13 . 30 3
r = radius girasi = = = 8.660254
A 13 . 30
atau r = 0,3 . h. = 0.3 . 30 = 9
Jadi :
k . Lu 1 . 3.5
= = 38.88889 > 22
r 0.09
Cm
d = > 1
Pu
1 -
f . Pc
Dimana : Cm = 1 (konservatif)
M mn Re Balok Induk Tepi x 2 + M mn Rf Blk Anak Tepi
Pu =
1000
4055.39531 x 2 + 4055.3953098747
=
1000
= 12.1661859296 ton
p2 . EI
Pc =
(k . Lu)2
Ec . Ig
EI =
2,5 . (1 + bd)
Ec = 4700 . fc' = 4700 18.74 = 20346.169 Mpa = 2034616.9 t/m2
Ig = 1/12 . b. h = 3
1
Ig = . 0.1 . 0.3 3 = 0.0002925 m4
12
1,2 . qdl 1.2 . 786.8
Bd = = = 0.702416
1,2 . qdl + 1,6 . qll 1.2 . 786.8 + 1.6 . 250
diperoleh :
2034616.9 . 0.0002925
EI = = 139.8307618838
2.5 . ( 1 + 0.702416 )
p2 . 139.830762
Pc = = 112.5449
1 . 3.5 2
1
d = = 1.2 > 1 Ok !!!
12.1661859296
1 -
0.65 . 112.5449
Penulangan untuk kolom tepi
Mu = 1.12669652 tm
Mc = d . Mu
= 1.199485 . 1.12669652 = 1.351455 tm
Hitung :
Pu 12.1661859
Pn perlu = = = 18.71721 ton
f 0.65
Mc 1.3515
Mn perlu = = = 2.079162 tm
f 0.65
Eksentrisitas :
Mn perlu 2.0791621702
e = = = 0.111083 = 111.0829
Pn perlu 18.7172091225
Hitung nilai r
~ Sumbu vertikal
Pu 10000000
= = 57.14937
f . Ag . 0,85 . fc' 0.65 . 130 . 130 . 0.85 . 18.74
~ Sumbu horizontal
Pu e 111.0829
. = 57.14937 . = 48.83322
f . Ag . 0,85 . Fc' h 130
k . Lu
< 22 SK. SNI T - 15 - 1991 - 03. 33 11 4)
r
dimana :
k = faktor tekuk = 1
lu = panjang kolom = 3.5
I 1 / 12 . 13 . 30 3
r = radius girasi = = = 8.660254
A 13 . 30
atau r = 0,3 . h. = 0.3 . 30 = 9
Jadi :
k . Lu 1 . 3.5
= = 38.88889 > 22
r 0.09
Cm
d = > 1
Pu
1 -
f . Pc
Dimana : Cm = 1 (konservatif)
M mn Re Balok Induk tengah x 2 + ( Rg Balok FG + RG Balok GH Balok Anak Tengah )
Pu
1000
4055.3953098747 x 2 + ( 2246.53179 + 4033.99821463 )
=
1000
= 14.3913206
p2 . EI
Pc =
(k . Lu)2
Ec . Ig
EI =
2,5 . (1 + bd)
Ec = 4700 . fc' = 4700 18.74 = 20346.169 Mpa = 2034616.9 t/m2
Ig = 1/12 . b. h = 3
1
Ig = . 0.1 . 0.3 3 = 0.0002925 m4
12
1,2 . qdl 1.2 . 786.8
Bd = = = 0.702416
1,2 . qdl + 1,6 . qll 1.2 . 786.8 + 1.6 . 250
diperoleh :
2034616.9 . 0.0002925
EI = = 139.8307618838
2.5 . ( 1 + 0.702416 )
p2 . 139.830762
Pc = = 112.5449
1 . 3.5 2
1
d = = 1.244905 > 1 Ok !!!
14.3913206197
1 -
0.65 . 112.5449
Hitung :
Pu 14.3913206
Pn perlu = = = 22.14049 ton
f 0.65
Mc 2819.8141
Mn perlu = = = 4338.176 tm
f 0.65
Eksentrisitas :
Mn perlu 4338.17554674
e = = = 195.9385 = 195939
Pn perlu 22.1404932612
~ Sumbu horizontal
Pu e 195939
. = 0.822455 . = 1239.62
f . Ag . 0,85 . Fc' h 130
2, BALOK
Balok 140 x 300
- Tumpuan Luar - 1.13 3 f 12
- Tumpuan Dalam - 2.45 4 f 12
- Lapangan - 4.06 6 f 12
Balok 140 x 500
- Tumpuan Luar - 1.13 3 f 12
- Tumpuan Dalam - 2.45 4 f 12
- Lapangan - 4.06 3 f 12
3, Kolom
- Kolom 1 12.1661859 1.13 4 f 13