Escolar Documentos
Profissional Documentos
Cultura Documentos
Procurement Management
SC 3.7 (previously SC 3.5) [Agreement or Determination] has
been extended to include further matters for agreement /
determination.
The 1st Edition Clause 20 has been split into two clauses, i.e.
Clause 20 [Employer’s and Contractor’s Claims] for Claims, and
Clause 21 [Disputes and Arbitration] for Disputes, to recognise
the distinction and reflect the fact that claims only become
disputes if a Party gives a notice to that effect.
“Claims” and “Disputes” are defined and the meanings
of “Notice of Claim”, “contemporary records”, “fully detailed
Claim”, “Notice of the Engineer’s Determination” and “reference
of a Dispute to the DAAB”, among others, are described, thus
seeking to avoid past disputes regarding interpretation of these
or similar terms.
Contractor’s and Employer’s claims procedures are now
reciprocated, thus also seeking to avoid past disputes regarding
the 1st Edition SC 2.5 [Employer’s Claims] provisions and
remedies for non-compliance.
“Claims”, in addition to additional payment and EOT, also
include entitlement or relief “of any kind whatsoever (including
DISPUTE AVOIDANCE
Under the 2nd Edition the DAAB has an enhanced and focused
dispute avoidance role.
Under the GCs Clause 5 the DAB Member must be available to
give Informal Assistance when requested jointly by the Parties.
As noted above:
NN A new SC 21.3 [Avoidance of Disputes] includes express pro-
visions for the avoidance of disputes by the DAAB which go
well beyond the 1st Edition SC 20.2 provision for an opinion
by the DAB.
NN A new Procedural Rule (Rule 2.1) empowers the DAAB to
give Informal Assistance.
The 1st Edition reference to the DAB giving opinions (SC 20.2)
has been removed and replaced (Rule 2.1) with the DAAB
giving Informal Assistance during discussions at any meeting
with the Parties (whether face-to-face or by telephone or by
video conference) or at any Site visit or by an informal written
note to the Parties.
SC 21.3 provides that the Parties may jointly request, and
should the DAAB become aware of an issue or disagreement, Without change,
progress becomes
it may invite the Parties to make such a joint request, for the
DAAB to provide assistance and/or informally discuss and
attempt to resolve any issue or disagreement.
However, SC 21.3 contains a proviso that such joint
requests may not be made during the period that the Engineer
impossible
is carrying out his/her duties under SC 3.7 [Agreement or
Determination] on the matter in issue or in disagreement, un-
less the Parties agree otherwise. Our considered approach led us
As also noted above:
NN Rule 3 now extends the purpose of meetings with the
to a rebrand that will allow us to
Parties and Site visits by the DAAB to include the giving of grow and build a South Africa
Informal Assistance if and when jointly requested by the that is better for all.
Parties.
NN Should the DAAB become aware of an upcoming critical
construction event, it may also invite the Parties to make a www.hho.co.za
request for it to visit the Site.
NN Either Party may now additionally request an urgent
meeting or Site visit by the DAAB.
NN Furthermore, Rule 7 provides for a procedure in the event
the Parties request Informal Assistance during any hearing.
END NOTES
1 International Federation of Consulting Engineers.
2 FIDIC 2017. Conditions of Contract for Construction. Second Edition. Geneva:
FIDIC.
3 FIDIC 2017. Conditions of Contract for Plant and Design-Build. Second Edition.
Geneva: FIDIC.
4 FIDIC 2017. Conditions of Contracts for Engineering, Procurement &
Construction (EPC)/Turnkey. Second Edition. Geneva: FIDIC.
5 A generic term denoting various types of dispute boards.
6 Van Langelaar, A 2014. Dispute Boards – Operation, Part 1, Civil Engineering,
22(8): 60–64; Dispute Boards – Operation, Part 2, Civil Engineering, 22(9):
52–55; Dispute Boards – Operation, Part 3, Civil Engineering, 22(11): 62–66.
7 Van Langelaar, A 2015. Dispute Boards – Dispute Avoidance Role, Part 1, Civil
Engineering, 23(1): 69–74; Dispute Boards – Dispute Avoidance Role, Part 2.
Civil Engineering, 23(3): 72–77.
8 Approximate numbers.
9 Red, Yellow and Silver Books.