1 TABLE OF CONTENTS
1 TABLE OF CONTENTS 2
2 TABLES 3
3 PLATE 3
4 ONE WASH PUS PROGRAM 3
3.1 General 3
3.2 Location and Access 4
3.3 Study Design and Construction 4
3.4 Contract Summary 5
3.5 Project Accomplishment drawbacks 5
5 MAJOR COMPONENTS OF THE PROJECT 9
6 THE PROJECT ACTIVITIES AND STATUS 12
3.6 General Item of Works 12
3.7 Drilling and Borehole Construction 12
3.8 Pipes and Fittings Works 12
3.9 Electro-Mechanical Work 15
3.10 Power Lines 15
No construction activity in this reporting month, however the cost estimate for the power lines,
transformers and associated works has been already given by EEPCO to the contractor. 15
3.11 Buildings and Operational Compounds 15
3.12 Reservoirs 18
7 SANITATION FACILITIES AND CONSTRUCTION 19
3.13 School Flush Toilets for Girls and boys 19
3.14 Septic tank and soak away for school toilets 20
3.15 Septic tank and soak away for public toilets 20
3.16 Sanitary Landfill and Sludge Drying Bed Site 20
8 MATERIAL, EQUIPMENT AND MAN-POWER STATUS 20
3.17 Contractor’s Material Supply Status 20
3.18 Machineries and Equipment Status 21
3.19 4.3 Manpower on Site 21
9 THE CONSULTANT SUPERVISION ON SITE 21
3.20 Consultant staff on site 21
3.21 Site Supervision Work in the reporting month 22
3.22 Quality Assurance 22
3.23 Conclusion 22
2 TABLES
3 PLATE
General
To accelerate progress in the water and sanitation sector, the Government of Ethiopia, in collaboration
with DFID and UNICEF have developed the ONEWASH PLUS program, which aims improvements
in water supply and sanitation in 8 Towns, introduce innovative approaches to address water supply
and sanitation projects and, further, advocate and formulate strategies to assist the Government of
Ethiopia accelerate sustainable sanitation and water provision in small towns.
The Town of Welenchiti and the satellite villages of Feto, DengaluWanga and DengoreTyio were
considered for intervention. Identification and selection of satellite villages was done in close
cooperation with Regional and Local authorities, based on a selection criteria developed by UNICEF
Contract Summary
Table 1: Contract Summary
As of our supervision staff close follow up the communication gap between the project office and the
coordinator/ purchasing staff at the head office contributes its share for delayed delivery of construction
materials.
1 Borehole drilling
Drilling (up to 280 mts) and construction of a positive borehole
with a reinforced PVC 215 mm (8”) OD casing and screen to
increase water production by at least 5 l/s. No 1
2 Transmission main
Construction of nearly 1000 m of a new transmission main
(HDPE, OD110 mm) to link the new borehole to a new service
reservoir constructed at the same location as the existing one
3 Reservoir construction
construction of one 150M3 elevated tank with 15 m high RC
support structure no 1
Supply of 2x25 m3 fiber glass tanks no 2
4 Distribution Pipe and Fittings
Supply and installation, new pipes and fittings of
primary/secondary mains consisting of HDPE, OD 50 to 110 mm
PN10 m 4930
Installation of up to 2 flushing (wash outs) devices, Installation
of up to 7 gate valves for installation in HDPE pipes, in the
distribution network no 9
5 Public water points
Construction of 11 public water points inclusive the connection to
secondary mains of the distribution network, fencing and gates no 11
6 Electromechanical
Supply and installation of 1 submersible pump with discharge
Q=5 l/sec, H=170 m, complete with electric motor three phase
squirrel cage, induction type, 380v, 50 HZ, 12.5 KW no 1
Supply and installation of one diesel powered generators, three
phase, 380v, 50 HZ, with a rated output of 33 KVA no 1
Supply and installation of chlorination equipment being 2x50 l
preparation tanks provided with two electrically driven mixers
of which one mounted on the top of the tank and two 15 l
metering tanks Ls 1
7 Buildings
1 Borehole drilling
Construction of one chlorination building within the existing
premises of the DengoreTyio distribution center, and one guard
house Ls 1
8 Miscellaneous work
As required specifically, construction of trust and anchor blocks
and valve chambers, site work (pavements, fencing, gates etc.) and
access roads to construction sites Ls 1
II. Demobilization
Surveying work
.setting out the fence limit of generator house.
NOTE:
The overall supply and installation planed in BOQ /Contract of HDPE pipeline is 35746m
The overall supply and installation requirement as of joint survey of HDPE pipeline is 30872m
The excess quantity of OD110 at Dengore Tiyo is due to shifted location of elevated reservoir location
Table 8: Table: The project plan for service connections, water kiosks and water points
Rehabilitation of 7 0 0
WPs
Water kiosks 5 0 0
a) Service Connections
No construction activity but the list of household identified by the towns Administration office in
collaboration with the utility office has been given to the contractor with formal letter.
To date,
All water points have been constructed for Welenchiti town but finishing and fittings are remained
1 out of 2 water points were constructed for Feto villages but finishing and fittings are remained
Twelve water points have been constructed for DengoreTiyo Town but finishing, Fencing and fittings
works remained.
d) Construction of Water Kiosks
- Rendering for one water kiosk at cattle market completed.
Power Lines
- No construction activity in this reporting month, however the cost estimate for the power lines,
transformers and associated works has been already given by EEPCO to the contractor.
Reservoirs
I. Two 500 Cubic meter Reservoir at main DC
No activity.
Manpower on Site
Table 10: Manpower status in the reporting month
GTB Engineering
Name of staff Position/Title
Tewodros koyu Project engineer
Abeba K/Michael Site Engineer
Tewodros Desta Senior Surveyor/
Tigist Cashier/
Mamush Chief Forman/
Sisay Pipe technician
Eshetu DCI plumber
Debele Calcisa Driver
Ermias Truck driver
Elias Hailu Truck driver
Total staff 10
Quality Assurance
Onsite Concrete slump tests and compressive strength test at recognized laboratory for different
batches from the construction concrete.
Conclusion
The construction progress continues to follow with a slow progress.
Delayed delivery of construction materials to the construction site and insufficient deployment of
semiskilled workers. Accordingly
The contractor has been already notified for slow progress of works with formal letter.
The contractor needs to accelerate the slippage as a result of the September and October delays
The contractor has indicated that his July 7, 2017 payment approved not effected until the end of the
reporting month.
Final addendum and interim payments are expected before Nov 31 2017 following UNICEF financial
closing date.
Nov Dec
Months/Cal.
September October emb emb
Days
er er
No Description Of Work Components Qty Details
45 60 7 9 1 1 1 1
Value in Birr 5 0 0 2 3 5
5 0 5 0
Portion Of
Octob Nove Dece
The September
er mber mber
Qt Amount
No Description Of The Works
y 1 3 4 6 7 9 1 1 1 1
Value in
5 0 5 0 5 0 0 2 3 5
Birr
5 0 5 0
Bill No
01: General Items Ls 672,000.00
Bill No 41
03 A4. Pipes and fittings-1 (Transmission Line) 00 480,800.00
Bill No 16
03 A4. Pipes and fittings-2 (Distribution Line) 00 507,691.34
Bill No
03 A4. Pipes and fittings-1 (Water Points) 12 526,980.00
Bill No
06: Buildings & Operational Compounds 165,572.40
Bill No
06: 2 Construction of one Chlorination buildings 1 221,288.00
Bill No
06: 3 Construction of guard house 1 75,306.44
Bill No
07: Construction of two 200 m3 RC ground reservoir 1 158,849.25
2,939,742.
Bill No .4 Electromechanical-1&2 Installation 58
Bill No 2,380,700.
5.A-8 Power Supply Lines 00
8,128,930.
01
Dengore
New/
Bill Misse Additi Omissio
Item No No Item Description Contract Revised d on n
Bill
No 2,048,00 2,048,000
A-1 .1 General items 0.00 .00 - - -
Bill
No Drilling & BH 2,490,62 2,490,622
A-2 .2 construct 2.50 .50
Bill
No Pipes & fittings - 331,800. 331,800.0
A-3 .3 1(lay out) 00 0 - - -
Bill
No Pipes & fittings -2 1,549,04 1,260,525 201,87 301,774.
A-4 .3 (lay out) 8.70 .54 - 1.00 16
Bill
No Pipes & fittings - 827,887. 738,359.2 35,023 174,59 339,386.
A-5 .3 3(Water point) 50 5 .80 5.65 40
Bill
No Electromechanical- 440,099. 440,099.8
A-6 .4 1 Installation 81 1
Bill
No Electromechanical-
A-7 .4 2 Installation -
Bill
No 553,700. 553,700.0
A-8 .5 Power supply lines 00 0
Bill
No Buildings 775,048. 911,418.4 1,056. 245,11 109,798.
A-9 .6 Construction 70 2 00 2.33 61
Bill
No 1,499,04 656,771.4 656,77 1,499,04
A-10 .7 Reservoirs 3.30 3 1.43 - 3.30
Bill
No
A-11 .8 Sanitation Facilities