Você está na página 1de 9

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/282504299

Cyclic Load Profiles for Offshore Wind Farm Cable Rating

Article  in  IEEE Transactions on Power Delivery · August 2015


DOI: 10.1109/TPWRD.2015.2469538

CITATIONS READS
7 346

5 authors, including:

Simon Catmull Richard D. Chippendale


RES Offshore University of Southampton
3 PUBLICATIONS   23 CITATIONS    24 PUBLICATIONS   67 CITATIONS   

SEE PROFILE SEE PROFILE

All content following this page was uploaded by Simon Catmull on 01 April 2016.

The user has requested enhancement of the downloaded file.


1

Cyclic Load Profiles for Offshore Wind Farm


Cable Rating
S. Catmull, R. D. Chippendale, J. A. Pilgrim, Member, IEEE, G. Hutton and P. Cangy

1
current rating. This is defined as the current which, if applied
Abstract— By its nature, the power generated by offshore wind on a continuous basis, would ensure that the conductor
farms varies substantially with time. Despite this fact, the cable temperature reaches but does not exceed its operational limit.
systems which connect such wind farms back to the onshore grid For the majority of cross-linked polyethylene (XLPE) cables
are typically sized based on a maximum, continuous current in use today, this will equate to 90°C, the maximum
rating. In order to develop techniques by which the sizing of
temperature at which such cables should be operated to give
such cable connections might be optimized, this paper presents a
method for deriving equivalent cyclic load curves from realistic, an acceptably low rate of thermal ageing of the insulation.
time variant generation data. These cyclic load profiles may be If the transient thermal behavior of common export cable
used with the conventional IEC 60853-2 cable rating calculation, systems is considered, the cable thermal response to a step
allowing the cable to be sized for a more realistic duty cycle. The change in load is relatively slow. This is particularly true for
example calculations presented show that this reduction in sections of the route which are the most thermally limiting,
conservatism permits the use of smaller cable sizes, helping to such as deeply buried cable sections at landfalls. The main sea
drive down project costs. The implications of using such methods section of the route is frequently not thermally limiting due to
are discussed, highlighting the tradeoff between cost and lower burial depths and better thermal resistivity compared to
conservatism.
soils at the landfall. In the case studied here, the rating of the
Index Terms-- Power cable insulation, Power transmission, Statistical
cable in the sea bed is 40% higher than at the deeply buried
analysis, Statistical distributions, Underwater cables, Wind energy, landfall section. It will be shown in Section V that achieving
Wind energy integration, Wind farms. the steady state maximum temperature can take 20 years.
Given the inherent intermittency of wind generation, such
I. INTRODUCTION steady state conditions will never in reality be attained. This
leads to the cable being sized for an overly worst case
H IGH voltage AC subsea cables represent a significant
proportion of the capital expenditure associated with
offshore wind farms. As wind farms go further offshore
scenario, which can result in larger conductor sizes than are
truly necessary.
One previous approach to reduce this conservatism is to
and the distance to the landfall of the export cable increases, dynamically predict the transient thermal rating based on the
the proportion of total capital expenditure becomes greater. local weather forecast [4, 5, 6]. This approach has been used
Raising the transmission voltage or moving to HVDC
for overhead lines [7, 8], where such approaches have
transmission both offer the possibility of reducing the number
obtained 120% increase in rating [7]. There is however an
of cables or, at the least, minimising the conductor size of the added complexity of applying these methods to buried cables,
cables needed to carry the rated output of a wind farm. An due to importance of accurately predicting the thermal
alternative approach, and one potentially requiring less of a properties of the burial environment [5]. Whilst these methods
technical advance, is to take advantage of the inherent could be used for wind farm export cables, they do not take
variability of the yield from a wind farm. Numerous published
into account the fluctuating generation of wind farm itself, and
studies have proposed different methods to predict short term
assume a maximum possible circuit load.
and long term wind farm yields from weather forecasts [1, 2,
3]. Whilst these studies have investigated the wind farm yield, B. Overview of Proposed Methodology
they have not considered how the fluctuating yield impacts the This paper begins by defining an example wind farm,
thermal rating of the export circuit. Therefore another followed by a method for the statistical analysis of a wind
approach is to find the appropriate cable size according to the speed time series to obtain an equivalent cyclic load profile for
load that they are likely to experience. use in IEC60853-2 calculations [9]. Although it is a
A. Conventional Cable Sizing Approach generalization to approximate wind farm output by a
cyclically varying load, it is a closer reflection of reality than
The conventional approach to sizing cable systems for assuming a constant output. This equivalent load cycle may
offshore wind farms has been to use a steady state, continuous
then be used to size the export cable, with due consideration
for the thermal behavior of the cable system itself. Such wind
1
R. D. Chippendale, J. A. Pilgrim and P. Cagny are with the Tony Davies speed time series are now commonly used in the evaluation of
High Voltage Laboratory, University of Southampton, SO17 1BJ, UK (e-mail: potential wind farm sites, hence the data is readily available at
jp2@ecs.soton.ac.uk). the design stage of the project. The final part of the paper
S. Catmull and G. Hutton are with RES Offshore, Kings Langley,
Hertfordshire, WD4 8LH, UK (email: simon.catmull@res-offshore.com). compares the predicted cyclic load against traditional ratings,
2
Insulation screen
analyzing the importance of the wind speed assumptions. Insulation Water Tape
Conductor screen Sheath
Conductor Inner Sheath
II. EXAMPLE EXPORT CIRCUIT
The method will be demonstrated by carrying out the initial
sizing of the export system for a hypothetical 300MW
offshore wind farm. Long term historical wind speed data will
be obtained from a meso-scale wind model of the UK and its
surrounding waters [10]. The wind speed data shall be
converted into a time series of wind farm power output using a
generic wind turbine power curve with an appropriate number
of turbines assumed. Account shall be taken of the wake losses
associated with the turbine array, but for the sake of simplicity
it will be assumed that there will be no losses associated with Filler
Armour
the reliability of the turbines or the balance of plant. Serving
A. System Architecture
The transmission architecture will be assumed to be Fig. 2. Simplified cross section of 3 phase export cable
composed of two offshore transformers to step up the array TABLE I
voltage of 33kV to a transmission voltage of 132kV and that Cable dimensions and material properties
an export cable per transformer would be required. The time Volumetric
Thermal
Heat Radius
series of the wind farm power output at 132kV will be Geometry Material Conductivity
Capacity (mm)
converted to a current on the basis that the landfall is the (Wm-1K-1)
(MJm-3K-1)
thermally limiting location and that the reactive power Conductor Copper 320 3.45 20
compensation has been designed so that the power factor at Conductor Semicon
0.5 2.4 21.5
the landfall minimises the power loss. A sketch of the wind Screen XLPE
farm transmission system is shown in Fig. 1. Insulation XLPE 0.286 2.4 38.5
Inulation Semicon
0.5 2.4 40
Screen XLPE
Unknown
Water Tape 0.286 2.4 41.5
Polymer
Sheath Lead 35.3 1.45 43.8
Inner
Semicon PE 0.5 2.4 46
Sheath
Bedding Polypropylene
0.123 1.9 101
and filler yarn
Armour Steel 18 3.8 106.5
Serving PE 0.2 1.7 111

TABLE II
Cable System Properties
Fig. 1. Export system sketch. Parameter Value
Conductor Strand Fill Factor 0.8
B. Cable Systems Conductor Resistivity 1.72 x 10-8 Ωm
Conductor kp 0.8
This study considers a wind farm export system with two Conductor ks 1
export cables which consist of 132kV 3 phase XLPE insulated Conductor Coefficient Of Resistance 3.93 x10-3 K-1
SL-type (each phase in separate lead sheath) cable with Sheath Resistivity 2.14 x 10-7 Ωm
1000mm2 conductors. The three phases are protected and held Sheath Temp Coefficient Of Resistance 4x10-3 K-1
Armour Resistivity 1.38 x 10-7 Ωm
together by layers of PE and steel armour wires. A cross Armour Temp Coeff Of Resistance 4.5 x 10-3 K-1
sectional illustration of the cable layout is presented in Fig. 2. Armour kp 1
The cable dimensions and thermal material properties are Armour ks 1
presented in Table I. The materials properties are considered Relative Permittivity Of Insulation 2.5
as per relevant IEC values, summarized in Table I and II [9]. Insulation Tan Delta 0.001
Voltage of cable 132kV
The filler region is typically comprised of a mixture of plastic Frequency 50Hz
ropes with air voids between the strands. Therefore the
material properties for the filler region are given by a TABLE III
summation of individual material properties weighted by their Seasonal soil and ambient conditions
volume fraction. The burial depth at the landfall is 4m with a Soil
Ambient Air
circuit spacing of 20m. The seasonal soil and ambient Thermal Volumetric
Season Temperature
Conductivity Heat Capacity
conditions are presented in Table III. (Wm-1K-1) (MJm-3K-1)
[ºC]
Summer 0.83 2 15
Winter 0.95 2 10
Dry (above 50ºC) 0.4 1 -
3

C. Power Generation Time Series


A time series of the current at the landfall was obtained by
modeling the power output from a large array of wind turbines
with respect to an 11year wind speed and direction time series.
Estimates of wind speed variation across an offshore wind
farm site on an hourly time resolution were obtained through
the use of the WRF Mesoscale Model [10]. This industry-
standard model uses a combination of measured data and
meteorological theory to estimate long-term mean wind speeds
in each direction sector for points on a grid of 2km resolution.
By interpolating between these grid points the wind speed at
each turbine location can be estimated. The mechanical power,
Pturbine(t), captured by a turbine is a function of the wind speed
at hub height, given by
1
𝑃𝑃𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡 (𝑡𝑡) = 𝐶𝐶𝑝𝑝 𝜌𝜌𝜌𝜌𝑣𝑣 3 (𝑡𝑡) (1) Fig. 3. Single cable output load as function of wind speed for a dual export
2 cable system
Where Cp is the turbine performance coefficient, ρ is the air
density, A is rotor area and 𝑣𝑣(t) is the wind speed. The B. IEC 60853-2 Cyclic Ratings
velocity deficit in wind speed downstream of a turbine, also The IEC standard 60853-2 presents an analytical method to
known as its wake, is accounted for by the Ainslie eddy model calculate the cyclic rating for a buried cable. The method
[11] with overlapping wakes from multiple turbines calculated requires a continuous rating to be calculated using IEC 60287,
using the maximum wake deficit and Root-Sum-Square which is then multiplied by a cyclic rating factor M, defined as
methods in combination, as outlined in [12]. The wind speed 𝑡𝑡𝑚𝑚𝑚𝑚𝑚𝑚 −1 −1�2
𝜃𝜃𝑅𝑅 (𝑖𝑖 + 1) 𝜃𝜃𝑅𝑅 (𝑖𝑖) 𝜃𝜃𝑅𝑅 (𝑡𝑡𝑚𝑚𝑚𝑚𝑚𝑚 )
time series was entered into the wind farm model to obtain the 𝑀𝑀 = � � �𝑌𝑌𝑖𝑖 � − �� + 𝜇𝜇 �1 − �� (3)
𝜃𝜃𝑅𝑅 (∞) 𝜃𝜃𝑅𝑅 (∞) 𝜃𝜃𝑅𝑅 (∞)
real power, P(t), as a function of time (t). The power was 𝑡𝑡=0
converted to a current time series, I(t), using Where 𝜃𝜃𝑅𝑅 (𝑡𝑡) is the conductor temperature rise above
𝑃𝑃(𝑡𝑡) ambient in ºC at the next time step (𝑖𝑖 + 1) or at the end of the
𝐼𝐼(𝑡𝑡) = (1 + ℎ𝑓𝑓 ) (2)
√3𝑉𝑉𝑟𝑟𝑟𝑟𝑟𝑟 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 cyclic profile. The given standard equation only takes into
Where Vref is 132kV, cos𝜙𝜙 is the power factor and hf is the account the 6 hours before the peak value of the cyclic curve,
harmonic current allowance. The typical assumed values for thus the equation shown in equation (3) is modified to take
these parameters are stated in Table IV. into account ‘i’ hours for the full length of the load cycle for
the time considered. The final terms which need to be defined
TABLE IV are the loss-load factor (μ), which is expressed as the average
Assumptions used in derivation of current time series
of all the ordinates of the loss factor load cycle (Yi), by
Parameter Value 𝑡𝑡𝑚𝑚𝑚𝑚𝑚𝑚−1
Power Factor at Landfall (cos φ ) 0.98 1
𝜇𝜇 = � 𝑌𝑌𝑖𝑖 (4)
Harmonic Current Allowance (ℎ𝑓𝑓 ) 2.5% 𝑡𝑡𝑚𝑚𝑚𝑚𝑚𝑚
𝑡𝑡=0
Transformer losses 0% The value of Y is calculated by taking each element in the
Wind farm reliability 100%
cyclic load and dividing it by the maximum of the cyclic load
Wind farm rating (P(t)) 310 MW
Load division between cables 50% and squaring the value. The method proposed in (3) and (4)
are for a non-drying out case, and [9] proposes an equivalent
The variation of current with respect to the wind speed for the equation to include the effect of soil dry out.
duration of the time series is shown in Fig. 3. The maximum C. Finite Element Analysis
output from the wind farm sets a target rating for the export
system of 710A. This would be the typical value of current Finite Element Analysis (FEA) has previously been shown
used to size the cable system under the conventional steady to be a useful tool for the rating of cables, allowing for better
state assumptions. representation of physical processes than the analytical IEC
standards [15, 16]. This paper considers a de-coupled
transient thermal response of the cable due to the thermal
III. CURRENT RATING CALCULATIONS
losses from the applied load. Heat sources within the cable are
This section presents a summary of the thermal current defined using conventional IEC equations following the
rating methods used for the analysis of Section VI. principles outlined in [13]. Fig. 4 shows an illustration of the
A. IEC 60287 two dimensional (2D) landfall geometry implemented, along
with the external boundary conditions. Due to the symmetry
The international standard method for calculating the
plane between the two export cables, the FEA model only
continuous seasonal ratings for cables installed in a variety of
needs to consider one half of the circuit i.e. only one cable.
installations is IEC 60287-1 [13]. This method has proven to
The right hand boundary is set as thermal insulation, as this
be suitable for predicting the continuous seasonal rating of
boundary is far enough away from the cable that there is no
buried cables, however its analytical nature does force some
heat flux passing through the boundary.
assumptions [14].
4

lower current level fixed, the high load current (Irate) is then
varied to find the thermal rating of the cable due to the
application of the cyclic load.
Load (A)
Δtrate
Irate

Ilow
Δtlow

Time
Fig. 4. Numerical geometry with boundary conditions Fig. 5. Generic cyclic load profile

Both the top and bottom boundary are held at a constant


temperature, with the bottom boundary being 10°C and the top
boundary temperature is defined by the ambient seasonal
temperature [14].
IV. CYCLIC LOAD DERIVATION
This section presents the method by which cyclic load
profiles are derived for subsequent use in rating calculations.
A. Load Profile Shape
A cyclic load is characterised by the ratio of time spent at
high power to low power and the magnitude of high and low
loads as is illustrated in Fig. 5. There are two main steps for
Fig. 6. Circuit load for various Conductor temperatures
deriving an equivalent cyclic load for a wind farm. The first is
to determine a threshold by which a time series can be B. Determining Durations of Spells
separated into periods of high and low load, this is based on The duration for which the high (Irate) and low (Ilow) loads
the assumption that the cable temperature will rise more are likely to persist was determined through a simple analysis
rapidly than the burial environment when the cable is subject of the long term wind time series and the amount of time spent
to load. The second is to determine the duration of periods of within and without a 9 to 25ms-1 range. In addition to basing
high load relative to low, based on the ratio of the average this analysis on the hourly wind speed data from the WRF
period of high to low load for a long term load time series. model, the use of a rolling average filter to smooth the wind
A. Calculating Current Thresholds speeds by removing short term fluctuations before assessing
persistence was investigated. The length of the filter affects
A threshold for separating the high loads (Irate) and low load the persistence of the series; the longer the averaging period,
(Ilow) was determined through calculation of the steady state the smoother the series and so the longer the load cycle. An
temperature rise in a cable over a range of currents. The low appropriate filter length for smoothing was determined
current level (Ilow) was initially determined by calculating the through an assessment of the underlying structure of the wind
load on the 1000mm2 cable which produces a steady state of data in terms of its serial correlation. Fig. 7 shows the
30ºC, which corresponds to a current which is mainly heating autocorrelation function of the wind speed data and the clear,
the cable and not having a significant impact on the cyclic, pattern which corresponds to seasonal variations of
temperature of the burial environment, which is demonstrated wind speed.
in Fig. 6. The impact of assuming this 30ºC threshold is This seasonality was removed to expose the underlying
investigated in detail in Section V part C. The steady state structure via a multiplicative decomposition by moving
conductor temperature due to a range of wind speed and averages which takes the form of
current load are presented in Fig. 6. This figure shows a
30 °C conductor temperature is obtained from a load of 302 A, 𝑣𝑣(𝑡𝑡) = 𝑆𝑆(𝑡𝑡) 𝑇𝑇(𝑡𝑡) 𝑅𝑅(𝑡𝑡) (5)
which from Fig. 3 equates to an approximate wind speed of Where, v is the wind speed and S, T and R respectively
9 ms-1. This sets the wind speed bounds for a high load denote the seasonality, trend and irregular components of the
between 9 ms-1 and 25 ms-1, the wind speed at which the time series. Removing the seasonality also gets to a structure
turbine cuts out as a form of mechanical protection. Wind that remains constant throughout the year. Further details of
speeds in this range are assumed to generate an output load of the method can be found in [17].
Irate. Any wind speed below this bound is considered to result The effect on the autocorrelation function of removing
in a low load (Ilow) of 302 A, which is equivalent to a steady seasonality in the time series is shown in Fig. 8. The short-
state current that would cause a 30 °C temperature. With the term persistence of the deseasonalised wind data is then
5

assessed via the order of a simple autoregressive time series by considering the probability density function of the wind
model, taking the form speed durations, which is shown in Fig. 10.
𝑣𝑣(𝑡𝑡) = 𝛼𝛼1 𝑣𝑣(𝑡𝑡1 ) + 𝛼𝛼2 𝑣𝑣(𝑡𝑡2 ) + … 𝛼𝛼𝑛𝑛 𝑣𝑣(𝑡𝑡𝑛𝑛 ) + 𝜖𝜖𝑡𝑡 (6)

Fig. 9. Partial autocorrelation of deseasonalised wind speed data.

TABLE V
Fig. 7. Autocorrelation of wind speed data. Distribution of wind speed with different filter lengths
Persistence of periods Persistence of periods
Filter
Length
inside 9-25 m/s range below 9 m/s
(hrs) Mean Max Mean Max
length (hr) length (hr) length (hr) length (hr)
1 13.62 191.00 13.58 293.00
3 21.44 259.00 21.49 387.00
6 28.83 333.00 29.03 448.00

From Fig. 10, it is clear that the wind speed threshold of


9ms-1 is approximately the peak of the wind speed distribution
with occurrence of wind speeds both above and below this
threshold approximately equal. That means durations are also
approximately equal, which indicates that the persistence is
stable across the range of observed wind speeds

Fig. 8. Decomposition of wind speed data

The order of the autocorrelation, n in (6), was identified


through visual inspection of the partial autocorrelation
function of the deseasonalised time series, as shown in Fig.9.
Fig. 10. Probability density of wind speed
This suggests that the data are at least an autoregressive
process of order 1, with potentially significant lags at orders 2, Finally it is important to consider the frequency of
3 and 4, but no clear structure beyond lag 1. On this basis occurrence of periods above the 9ms-1 threshold, as shown in
filter lengths, of 1hr (corresponding to no smoothing or Fig.11. From this figure, it is apparent that the majority of
persistence) and 3hr (corresponding to persistence over 3 occurrences when the wind speed is above the 9ms-1 threshold
hours) have been chosen. An additional filter of 6hr was used are for durations less than, or equal to the mean (Table V), i.e.
to further demonstrate the effect of an increased filter length as a measure of the persistence in time of high load periods the
and to capture the maximum persistence in the time series that mean gives a conservative estimate. This is important since
could be interpreted from the data. Carrying out a persistence the frequency of occurrences where the mean duration is
analysis on each of the filtered time series returned high and exceeded and therefore the likelihood of a steady state thermal
low load durations with the characteristics detailed in Table V. rating of the cable being exceeded is small but probable over
As the moving average filter length increases the persistence the operational lifetime of the modeled offshore wind farm.
of the series also increases, as expected. The ratio of mean V. CALCULATION OF CYCLIC RATINGS
periods inside the wind speed limits to those outside them is
In the previous section three cyclic load profiles were
consistently 1:1 for each of the filter lengths. This is an artifact
derived on the basis of the following:
of the chosen wind speed threshold which is ultimately a result
1. Steady state load that caused a 30°C temperature rise.
of the steady state current that would cause a 30°C
temperature rise in the conductor. This can be demonstrated 2. The ratio of the mean length of periods where the wind
speed would cause a greater than 30°C temperature rise to
6

those that caused less. of 6 hrs is presented in Fig.13, which shows that there is a
3. Calculate the rated current (Irate) on the basis of Ilow and continual temperature oscillation due to the cyclic load. The
cycle duration. model is assumed to be in a quasi-steady state when the peak
conductor temperature for each oscillation is approximately
A. Steady State Ratings to IEC60287 constant with neighbouring peaks. The quasi-steady state
The continuous seasonal ratings at the landfall, calculated solution occurs after approximately 15 to 20 years, with the
using IEC 60287, are 604 A in summer and 660 A in winter. oscillation height being approximately 26ºC.
Using (2), it is possible to calculate that the total output load
from the considered wind farm is 1420 A. Assuming this load
is equally divided between the two export cables, each cable
needs to carry 710 A. Based on IEC 60287 continuous ratings
above, it is evident that under this conservative scenario, three
rather than two export cables at 1000mm2 would be required
to avoid exceeding the thermal limit. The incremental cost is
of the order of £1 million per route mile.

Fig. 13. Conductor temperature response due to a cyclic profile with a 6hour
filter length.

C. Comparison of cyclic rating methods


Table VI compares cyclic ratings obtained from both the FE
model, which provides a full transient temperature
distribution, and the simpler IEC method which uses (3) to
obtain a multiplier of the continuous rating. It is also possible
to calculate a full time domain solution using IEC 60853-2 to
Fig. 11. Probability density of wind speed durations above the 9ms-1
wind speed threshold when the filter length is 1hr avoid the simplifications inherent in the use of (3).
TABLE VI
B. Finite Element Results Comparison of seasonal cyclic rating for various filter lengths predicted by
Using the 2D FEA model the transient response of the FEA and IEC 60583
conductor temperature due to a single step load can be Filter Summer Rating, Irate (A) Winter Rating, Irate (A)
investigated. Using the summer continuous rating from IEC length
FEA IEC 60853 FEA IEC 60853
60287 as the step load, the conductor temperature response is (hr)
presented in Fig.12. From Fig.12 it is evident that there is an 1 762 738 828 815
initial rapid increase in temperature, up to approximately 89% 3 745 728 819 805
of the thermal limit after 1.75 years. After this, there is a much 6 735 725 814 801
slower increase in temperature as the soil heat capacity begins
to dominate. It is therefore evident that with a step load at the Table VI shows that as the filter length increases there is a
continuous rating, it would take the circuit approximately 20 decrease in cyclic rating from both IEC and FEA. This is a
years to reach a steady state temperature. caused by the increased high and low levels as the filter length
is increased. The result indicates that as the duration of the
high (Irate) and low (Ilow) load level decreases, the current
rating will increase. Further it is apparent that the ratings
obtained from FEA are 1% to 3% greater than by IEC60853,
primarily due to the more detailed model of the temperature
distribution within the soil. Such differences are within the
bounds of uncertainties associated with measuring the soil
thermal properties. By comparing the cyclic ratings in Table
VI with the continuous ratings in Section V A, it is apparent
that by using a cyclic rating there is a 22% increase in
maximum rating. Whilst the cyclic ratings predict an
Fig. 12. Conductor temperature response due to step load of 604A
increased peak rating it is important to ascertain if the
With the application of a cyclic load, the same global temperature from the representative wind farm load exceeds
conductor temperature trend as presented in Fig.12 is visible. the conductor temperature from the cyclic rated profile. The
However due to the comparably high frequency cyclic load temperature exceedance is investigated through the difference
profile, there is also a short duration temperature oscillation in conductor temperature caused by the realistic wind farm
within the cable. The quasi-steady state conductor profile due load minus the temperature caused by the rated cyclic load.
to the application of the cyclic load profile with a filter length For this comparison a five year period is chosen and the
conductor temperature difference is presented in Fig.14.
7

threshold reaches 10 ms-1 there is a decrease in cyclic rating,


which is caused by the increase in low level load, which as the
low duration exceeds the high duration, begins to dominate.

VI. IMPLICATIONS FOR WIND FARM DESIGN


The method that has been outlined in this paper is intended for
use during the Front End Engineering and Design (FEED) of
an offshore wind farm. It is dependent upon a limited amount
of data about the burial conditions of the cable and wind speed
time series data for the potential wind farm. Data that it is
anticipated would be available at the FEED stage of most
Fig. 14. Conductor temperature difference between rate cyclic load profile and
the wind farm results (6hr filter length, summer season)
wind farms.
TABLE VII
The temperature difference in Fig. 14 demonstrates that the Cyclic load profile duty durations for various wind speed thresholds (filter
conductor temperature predicted by the rated cyclic load is length is 3hrs)
generally greater than that from the real wind farm load Lower Wind Low
Mean duration Mean duration
(negative values). Despite this there are instances where the Speed Threshold current
Above (days) Below (days)
temperature from the wind farm load is greater. Fig. 15 plots (ms-1) level
an extract of the thermal time series from two FEA models. 7 1.27 0.60 120
7.5 1.15 0.66 150
The red curve shows the thermal response to the simplified 8 1.04 0.72 182
load cycle, while the blue curve shows the thermal response to 8.5 0.95 0.80 221
the full time series data from Section II C. The periods where 9 0.89 0.90 262
the blue curve shows a higher temperature than the red occur 9.5 0.84 1.01 311
during the low load levels within the cycle and hence the 10 0.79 1.13 322
10.5 0.71 1.22 360
conductor temperature remains at least 9 ºC below the thermal
11 0.67 1.39 477
limit. Although this demonstrates that the equivalent load
This method would also be dependent upon a commitment to
cycles method is still conservative, the rating calculations may
using an alternative rating methodology during the operational
be performed much more quickly, without the need to rely on
stage of the wind farm. This could take the form of short-term
FEA tools.
transient ratings, dynamic ratings or dynamic curtailment of
the wind farm output. At some point there would be periods
of high wind speed in excess of the high load duration used in
the cyclic load, potentially causing the temperature threshold
of the cable insulation to be exceeded. For a reduced cable
size and dynamic operation to be a viable choice the likely
loss of production would need to be weighed up against the
reduction in capital expenditure. This could be done on the
basis of probability of exceedance, as is commonly done for
elements of the structural design of an offshore wind farm that
are driven by wind and wave loading. Return periods for wind
Fig. 15. Conductor temperature comparison for a cyclic and a realistic load.
speed durations longer than the high load (Irate) duration can be
D. Impact of wind speed threshold on Cyclic Ratings obtained through statistical analysis of long term time series in
In previous studies the wind speed threshold has been set as the same way that the persistence analysis was done to obtain
9ms-1. The impact on the cyclic rating due to variations of the cycle durations.
wind speed threshold has been investigated. Since the wind
speed threshold is changed, the cyclic profiles need to be re-
calculated based on the method proposed in Section IV. The
variation of cyclic profile with respect to wind speed threshold
is presented in Table VII. As the wind speed threshold
increases, the ratio of mean duration above to mean duration
below decreases i.e. duration above decreases whilst the mean
duration below increases. Such a variation in the balance of
the load profile will cause a variation in cyclic rating, which is
presented in Fig.16. This shows that as the wind speed
threshold increases up to 9 ms-1 there is an increase in
continuous rating. This is explained by the mean duration of
the high load decreasing, which results in shorter high load
applications and so less time for the temperature of the Fig. 16. Cyclic rating from IEC 60853-2 as the wind speed threshold is varied
conductor to increase due to the high load. However as the
Controlling the output of an offshore wind farm on the
8

basis of the cable temperature is within the reach of present ratings for cables of all voltages, IEC60853-2, 1989
[10] Weather Research and forecasting (WRF): ARW User Guide V3,
technology. It is widely understood within the offshore wind September 2014.
industry that the cost of generation needs to reduce for it to [11] J.F. Ainslie, “Calculating the flowfield in the wake of wind turbines”,
continue to be a viable part of the generation mix. This paper Journal of Wind Engineering and Industrial Aerodynamics, vol 27,
Issues 1–3, pp 213-224 Jan 1988.
has outlined a method by which the cost of a significant
[12] G. Habenicht, “Offshore Wake Modelling” presented at the 10th annual
contributor, the export cables, to the total capital expenditure Renewable UK Offshore Wind conference, Liverpool, England, Jun.
of an offshore wind farm may be reduced. 29-30, 2011.
[13] Electric cables - Calculation of the current rating - Part 1-1: Current
rating equations (100 % load factor) and calculation of losses -
VII. CONCLUSIONS General, IEC60287-1-1, 2006.
A method has been presented for the sizing of a wind farm [14] Current Ratings for Cables, TGN(T)67, 1996.
[15] D. Swaffield, P. L, Lewin, S. Sutton, "Methods for rating directly buried
export cable based on likely generation profiles. This is high voltage cable circuits", IET Generation, Transmission &
achieved through the use of cyclic ratings, where the cyclic Distribution, 2008, page 393-401
load profile is derived through the statistical analysis of long [16] Electric cables - Calculation of the current rating - Part 2: Thermal
resistance, Section 2.1 Calculation of thermal resistance, IEC 60287-2-
term wind time series data. Comparisons between the steady 1, 2006
state and cyclic rating were shown for a thermally challenging [17] E. D. Meyer. (2014, Nov 08). R-Manual. (3.2.0) [Online]. Available:
location section of the subsea cable route for an offshore wind https://stat.ethz.ch/R-manual/R-devel/library/stats/html/decompose.html
farm. The cyclic rating calculated using IEC60853 was shown IX. BIOGRAPHIES
to be in good agreement with results obtained through 2D
FEA. The ampacity increase of 22% as a result of considering Simon Catmull received the Bachelor’s degree in
cyclic ratings over the traditional continuous rating method is Mechatronics from the University of Sussex in 2003 and
then went on to obtain a Master’s degree in Renewable
sufficiently great that the target rating could be met with two Energy Systems and Technologies from Loughborough
export cables of conductor cross-sectional area of 1000mm2. University in 2010. He has been employed by RES
This would remove the need to add an extra cable, or change Offshore since 2010 and currently works as a Project
Engineer supporting the development, construction and
the conductor size for all, or part, of the cable. Although the operation of wind farms on- and offshore.
use of such methods have a clear benefit in terms of reduced
costs, it must be noted that a suitable curtailment strategy must Richard D Chippendale received the Master’s degree in
be in place to mitigate the risk that a period of high power Physics from University of Southampton in 2009. He
generation could be longer than predicted. To fully assess the pursued his doctoral degree at the same university,
investigating the thermal chemical degradation to
cost reduction achieved, it would be necessary to compare the composite materials due to a lightning strike, for which
capital saving with lost production due to output curtailment, he was awarded a PhD in 2013. He is currently employed
for which further development is presently underway. as a Research Fellow, working on a variety of projects
related to high voltage cable systems. He is a member of
IEEE DEIS and an associate member of the IOP.
VIII. REFERENCES
[1] J.W. Taylor, P.E. McSharry, R. Buizza, "Wind Power Density James A. Pilgrim (M’09) received the Bachelor’s degree
Forecasting Using Ensemble Predictions and Time Series Models," in electrical engineering from the University of
Energy Conversion, IEEE Transactions on , vol.24, no.3, pp.775,782, Southampton in 2007, subsequently gaining his PhD in
Sept. 2009 2011 from the same institution. He joined the academic
[2] M.C. Mabel, E. Fernandez, "Estimation of Energy Yield From Wind staff of the University in 2012. His research interests
Farms Using Artificial Neural Networks," Energy Conversion, IEEE include all aspects of high voltage cables and associated
Transactions on , vol.24, no.2, pp.459,464, June 2009 insulation systems. He is actively involved in the
[3] R. Amiri, Wang, Bingsen "A generic framework for wind power development of current rating methodologies, acting as
forecasting", IECON 2011 - 37th Annual Conf on IEEE Industrial the UK member of IEC TC 20 WG19 and Cigre Working
Electronics Society, pg 796 - 801 Group B1.35 “Guide to rating calculations”.
[4] J. Heckenbergerova, J. Hosek, "Dynamic thermal rating of power
transmission lines related to wind energy integration," Environment and Gail Hutton received the Bachelor of Science degree
Electrical Engineering (EEEIC), 2012 11th International Conference from Strathclyde University in 2003, and gained a PhD
on, pp.798,801, May 2012 from the same University in 2008 for research into
[5] R. Olsen, G.J. Anders, J. Holboell, U.S Gudmundsdottir, "Modelling of stochastic models of share prices. She worked for
Dynamic Transmission Cable Temperature Considering Soil-Specific National Air Traffic Services from 2007 to 2010 as a
Heat, Thermal Resistivity, and Precipitation," Power Delivery, IEEE statistician, focusing on the measurement and modelling
Transactions on , vol.28, no.3, pp.1909,1917, July 2013 of aviation risk. She joined RES in 2010, providing
[6] G.J. Anders, A. Napieralski, M. Zubert, M. Orlikowski, "Advanced analysis of technical aspects of wind farm development
modeling techniques for dynamic feeder rating systems," 37th Industry both onshore and offshore and with a particular interest
Applications Conference, vol.2, pp.1012-1019 Oct. 2002 in characterizing uncertainty. She is a member of the Royal Statistical Society
[7] Huu-Minh Nguyen; Lilien, J.-L.; Schell, P., "Dynamic line rating and and has attained both Chartered Statistician and Chartered Scientist status.
ampacity forecasting as the keys to optimise power line assets with the
integration of res. The European project Twenties Demonstration inside Priank Cangy was born in Maputo, Mozambique on
Central Western Europe," Electricity Distribution (CIRED 2013), 22nd the 5th of April, 1993. He is currently studying at the
International Conference and Exhibition on, pp.1- 4, June 213 University of Southampton for an MEng in Electrical
[8] J.K Raniga, R.K. Rayudu, "Dynamic rating of transmission lines-a New Engineering, having recently completed an internship
Zealand experience," Power Engineering Society Winter Meeting, 2000. at the Tony Davies High Voltage Laboratory.
IEEE , vol.4, pp.2403,2409
[9] Calculation of the cyclic and emergency current rating of cables. Part 2:
Cyclic rating of cables greater than 18/30 (36) kV and emergency

View publication stats

Você também pode gostar