BETON ET MORTIER A PIED D'ŒUVRE

www.mmlweb.e-monsite,com
Fait Par MML ‫ﻻ ﺗﻧﺳوﻧﻲ و واﻟدي ﺑﺎﻟدﻋﺎء‬

FABRICATION DES BETONS ET MORTIERS


A/- Fabrication de béton:
1/- Central à béton 30 m3 / h:
4 mn 1 m3
480 mn/J Q/J
3
480 mn/j x 1 m
Q/J = = 120 m 3 / J
4 mn

Cu / J 27 500.00 DA / J
I1 = = = 229.16 DA / m3
Q/J 120 m3 / J

2/- Transport Camion malaxeur:


4 mn 1 m3
480 mn/J Q/J
480 mn/j x 1 m3
Q/J = = 120 m 3 / J
4 mn

Cu / J 13 283.49 DA / J
I2 = = 3 = 110.69 DA / m 3
Q/J 120 m / J

B/- Fabrication de mortier:


1/- Bétonnière 400 L / h:
17 mn 1 m3
480 mn/J Q/J
480 mn/j x 1 m3
Q/J = = 28.23 m3 / J
17 mn

Cu / J 1 819.48 DA / J
I1 = = = 64.45 DA / m3
Q/J 28.23 m3 / J

2/- Dumper 2m3 :


7 mn 1 m3
480 mn/J Q/J
3
480 mn/j x 1 m
Q/J = = 68.57 m3 / J
7 mn

Cu / J 2 017.40 DA / J
I2 = = = 29.42 DA / m3
Q/J 68.57 m3 / J
BETON ET MORTIER A PIED D'ŒUVRE
www.mmlweb.e-monsite,com
Fait Par MML ‫ﻻ ﺗﻧﺳوﻧﻲ و واﻟدي ﺑﺎﻟدﻋﺎء‬

COMPOSITION DES BETONS ET MORTIERS


1/- Béton de propreté dosé a 150 kg de CPJ 325:
 Ciment CPJ 325 0.150 T / m 3
 Gravier 7/15 0.900 m 3 / m3
 Sable 0.450 m 3 / m3
 Eau 0.160 m 3 /m3

2/- Béton de remplissage dosé a 250 kg de CPJ 325:


 Ciment CPJ 325 0.250 T / m3
 Gravier 7/15 0.900 m 3 / m3
 Sable 0.450 m 3 / m3
 Eau 0.160 m 3 /m3

3/- Béton armé dosé a 350 kg de CPJ 325:


 Ciment CPJ 325 0.350 T / m3
 Gravier 7/15 0.900 m 3 / m3
 Sable 0.450 m 3 / m3
 Eau 0.160 m 3 /m3

4/- Béton armé dosé a 400 kg de CPJ 325:


 Ciment CPJ 325 0.400 T / m 3
 Gravier 7/15 0.900 m3 / m3
 Sable 0.450 m 3 / m3
 Eau 0.160 m 3 /m3

5/- Chape en gravillons lavés et poncer en ciment blanc


épaisseur 0.04 m "Unité en M²"
 Ciment blanc 215/325 sac 0.050 T / m²
 Gravier 3/8 0.032 m3 / m²
 Sable 03. 0.016 m3 / m²
 Eau 0.060 m3 /m²
BETON ET MORTIER A PIED D'ŒUVRE
www.mmlweb.e-monsite,com
Fait Par MML ‫ﻻ ﺗﻧﺳوﻧﻲ و واﻟدي ﺑﺎﻟدﻋﺎء‬

COMPOSITION DES MORTIERS


1/- Mortier (350 kg)
 Ciment CPJ 325 0.350 T / m3
 Sable 1.100 m3 / m3
 Eau 0.160 m 3 /m3

2/- Mortier (300 kg)


 Ciment CPJ 325 0.300 T / m 3
 Sable 1.100 m3 / m3
 Eau 0.160 m 3 /m3

3/- Mortier bâtard (150 kg)


 Ciment CPJ 325 0.350 T / m 3
 Chaux hydraulique 0.150 T / m 3
 Sable 1.100 m 3 / m3
 Eau 0.160 m3 /m3
BETON ET MORTIER A PIED D'ŒUVRE
www.mmlweb.e-monsite,com
Fait Par MML ‫ﻻ ﺗﻧﺳوﻧﻲ و واﻟدي ﺑﺎﻟدﻋﺎء‬

LES CALCULE:
A/- les bétons:
1/- Béton de propreté dosé a 150 kg de CPJ 325:
 Ciment CPJ 325 0.150 T / m3 x 4 566.42 DA/T = 684.96 DA / m3
 Gravier 8/15 0.900 m3 / m3 x 966.67 DA /m3 = 870.00 DA /m3
 Sable 0.450 m 3 / m3 x 989.48 DA /m3 = 445.27 DA /m3
 Eau 0.160 m 3 /m3 x 121.89 DA / m3 = 19.50 DA / m3
 ST = 2 019.73 DA / m3
 Perte 1% x ST = 20.19 DA / m 3
 Fab + Transp = 339.85 DA / m 3
 TOTAL = 2 379.77 DA / m3

2/- Béton de remplissage dosé a 250 kg de CPJ 325:


 Ciment CPJ 325 0.250 T / m3 x 4 566.42 DA/T = 1 141.60 DA / m3
 Gravier 8/15 0.900 m3 / m3 x 966.67 DA /m3 = 870.00 DA /m3
 Sable 0.450 m3 / m3 x 989.48 DA /m3 = 445.27 DA /m3
 Eau 0.160 m 3 /m3 x 121.89 DA / m3 = 19.50 DA / m3
 ST = 2 476.37 DA / m3
 Perte 1% x ST = 24.76 DA / m 3
 Fab + Transp = 339.85 DA / m 3
 TOTAL = 2 840.98 DA / m3

3/- Béton armé dosé a 350 kg de CPJ 325:


 Ciment CPJ 325 0.350 T / m3 x 4 566.42 DA/T = 1 598.25 DA/m3
 Gravier 8/15 0.900 m3 / m3 x 966.67 DA /m3 = 870.00 DA /m3
 Sable 0.450 m 3 / m3 x 989.48 DA /m3 = 445.27 DA /m3
 Eau 0.160 m 3 /m3 x 121.89 DA / m3 = 19.50 DA / m3
 ST = 2 933.02 DA / m3
 Perte 1% x ST = 29.33 DA/m3
 Fab + Transp = 339.85 DA / m 3
 TOTAL = 3 302.20 DA / m3
BETON ET MORTIER A PIED D'ŒUVRE
www.mmlweb.e-monsite,com
Fait Par MML ‫ﻻ ﺗﻧﺳوﻧﻲ و واﻟدي ﺑﺎﻟدﻋﺎء‬

4/- Béton armé dosé a 400 kg de CPJ 325:


 Ciment CPJ 325 0.400 T / m3 x 4 566.42 DA/T = 1 826.57 DA /m3
 Gravier 8/15 0.900 m3 / m3 x 966.67 DA /m3 = 870.00 DA /m3
 Sable 0.450 m 3 / m3 x 989.48 DA /m3 = 445.27 DA /m3
 Eau 0.160 m3 /m3 x 121.89 DA / m3 = 19.50 DA / m3
 ST = 3 161.34 DA / m3
 Perte 1% x ST = 31.61 DA / m3
 Fab + Transp = 339.85 DA / m 3
 TOTAL = 3 532.80 DA / m3

5/- Chape en gravillons lavés et poncer en ciment blanc


épaisseur 0.04 m "Unité au M²"
 Ciment blanc sac 0.050 T / m² x 11 894.16 DA / T = 599.21 DA /m²
 Gravier 3/8 0.032 m3 / m² x 966.67 DA /m3 = 30.93 DA / m²
 Sable 03. 0.016 m3 / m² x 989.48 DA /m3 = 31.66 DA /m²
 Eau 0.060 m3 /m² x 121.89 DA / m3 = 7.31 DA / m²
 ST = 669.11 DA / m²
 Perte 5% x ST = 33.45 DA /m²
 Fab + Transp = 13.59 DA / m²
 TOTAL = 716.15 DA / m²
BETON ET MORTIER A PIED D'ŒUVRE
www.mmlweb.e-monsite,com
Fait Par MML ‫ﻻ ﺗﻧﺳوﻧﻲ و واﻟدي ﺑﺎﻟدﻋﺎء‬

B/- LES MORTIERS


1/- Mortier (350 kg)
 Ciment CPJ 325 0.350 T / m3 x 4 566.42 DA/T = 1 598.25 DA / m3
 Sable 1.100 m3 / m3 x 989.48 DA /m3 = 1 088.42 DA / m3
 Eau 0.160 m3 /m3 x 121.89 DA / m3 = 19.50 DA / m3
 ST = 2 706.17 DA / m3
 Perte 1% x ST = 27.06 DA / m3
 Fab + Transp = 93.87 DA / m3
 TOTAL = 2 827.10 DA / m3

2/- Mortier (300 kg)


 Ciment CPJ 325 0.300 T / m3 x 4 566.42 DA/T = 1 369.92 DA / m3
 Sable 1.100 m3 / m3 x 989.48 DA /m3 = 1 088.42 DA / m3
 Eau 0.160 m3 /m3 x 121.89 DA / m3 = 19.50 DA / m3
 ST = 2 477.84 DA / m3
 Perte 1% x ST = 24.78 DA / m3
 Fab + Transp = 93.87 DA / m3
 TOTAL = 2 596.49 DA / m3

3/- Mortier bâtard (150 kg)


 Ciment CPJ 325 0.350 T / m3 x4 566.42 DA/T = 1 598.25 DA / m3
 Chaux hydraulique 0.150 T / m3 x 16 331.03 DA/T= 2 449.65 DA / m3
 Sable 1.100 m3 / m3 x 989.48 DA /m3 = 1 088.42 DA / m3
 Eau 0.160 m3 /m3 x 121.89 DA / m3 = 19.50 DA / m3
 ST = 5 155.85 DA / m3
 Perte 1% x ST = 51.55 DA / m3
 Fab + Transp = 93.87 DA / m3
 TOTAL = 5 301.27 DA / m3