PRICE EST NO:2018/110401

Data Analysis

data

1 Specification Code: 4.1.2

Providing and laying in position cement concrete of specified grade excluding the
4.1
cost of centering and shuttering - All work up to plinth level:

1:1/2:3 (cement : 11/2 coarse sand : 3 graded stone aggregate 20 mm nominal


4.1.2
size)

Code Description Unit Quantity Rate Amount

Details of cost for 1 cum


MATERIL:

Stone Aggregate(single size):20 mm


0295 nominal size cum 0.57 1300.00 741.00
nominal size

Stone Aggregate(single size): 10 mm


0297 nominal size cum 0.28 1300.00 364.00
nominal size

Carriage of Stone aggregate below 40 mm


2202 cum 0.85 103.77 88.20
nominal size

0982 Coarse sand (zone III) cum 0.425 1200.00 510.00

2203 Carriage of Coarse sand cum 0.425 103.77 44.10

0367 Portland Cement tonne 0.4 5700.00 2280.00

2209 Carriage of Cement tonne 0.4 92.24 36.90

0155 Mason (average) Day 0.1 467.00 46.70

0114 Beldar Day 1.63 368.00 599.84

0101 Bhisti Day 0.7 407.00 284.90

Hire charges of Concrete Mixer 0.25 to 0.40


0002 Day 0.07 800.00 56.00
cum with Hopper

0012 Vibrator (Needle type 40 mm) Day 0.07 350.00 24.50

9999 Sundries- L.S 14.3 1.73 24.74

TOTAL 5100.88

Add Water Charges @ 1% 51.01

printed on 27-03-2019 14:03:19 page 1


PRICE EST NO:2018/110401

TOTAL 5151.89

Add CPOH @ 15% 772.78

Cost of 1.0 cum 5924.67

Say 5924.65

Cost index 31.06 % 1840.20

Total with Cost index 7764.85

Say 7764.85

2 Specification Code: 4.1.3

Providing and laying in position cement concrete of specified grade excluding the
4.1
cost of centering and shuttering - All work up to plinth level:

4.1.3 1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)

Code Description Unit Quantity Rate Amount

Details of cost for 1 cum


MATERIAL:

Stone Aggregate(single size):20 mm


0295 nominal size cum 0.67 1300.00 871.00
nominal size

Stone Aggregate(single size): 10 mm


0297 nominal size cum 0.22 1300.00 286.00
nominal size

Carriage of Stone aggregate below 40 mm


2202 cum 0.89 103.77 92.36
nominal size

0982 Coarse sand (zone III) cum 0.445 1200.00 534.00

2203 Carriage of Coarse sand cum 0.445 103.77 46.18

Portland Cement
0367 tonne 0.32 5700.00 1824.00
(0.2225 cum)

2209 Carriage of Cement tonne 0.32 92.24 29.52

printed on 27-03-2019 14:03:19 page 2


PRICE EST NO:2018/110401

0155 Mason (average) Day 0.1 467.00 46.70

0114 Beldar Day 1.63 368.00 599.84

0101 Bhisti Day 0.7 407.00 284.90

Hire charges of Concrete Mixer 0.25 to 0.40


0002 Day 0.07 800.00 56.00
cum with Hopper

0012 Vibrator (Needle type 40 mm) Day 0.07 350.00 24.50

9999 Sundries- L.S 14.3 1.73 24.74

TOTAL 4719.74

Add Water Charges @ 1% 47.20

TOTAL 4766.94

Add CPOH @ 15% 715.04

Cost of 1.0 cum 5481.98

Say 5482.0

Cost index 31.06 % 1702.69

Total with Cost index 7184.64

Say 7184.64

3 Specification Code: 4.1.5

Providing and laying in position cement concrete of specified grade excluding the
4.1
cost of centering and shuttering - All work up to plinth level:

4.1.5 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)

Code Description Unit Quantity Rate Amount

Details of cost for 1 cum

Stone Aggregate(single size):20 mm


0295 nominal size cum 0.7 1300.00 910.00
nominal size

printed on 27-03-2019 14:03:19 page 3


PRICE EST NO:2018/110401

Stone Aggregate(single size): 10 mm


0297 nominal size cum 0.24 1300.00 312.00
nominal size

Carriage of Stone aggregate below 40 mm


2202 cum 0.94 103.77 97.54
nominal size

0982 Coarse sand (zone III) cum 0.47 1200.00 564.00

2203 Carriage of Coarse sand cum 0.47 103.77 48.77

Portland Cement
0367 tonne 0.22 5700.00 1254.00
(0.15674 cum)

Carriage of Cement
2209 tonne 0.22 92.24 20.29
LABOUR:

0155 Mason (average) Day 0.1 467.00 46.70

0114 Beldar Day 1.63 368.00 599.84

0101 Bhisti Day 0.7 407.00 284.90

Hire charges of Concrete Mixer 0.25 to 0.40


0002 Day 0.07 800.00 56.00
cum with Hopper

0012 Vibrator (Needle type 40 mm) Day 0.07 350.00 24.50

9999 Sundries- L.S 13.52 1.73 23.39

TOTAL 4241.93

Add Water Charges @ 1% 42.42

TOTAL 4284.35

Add CPOH @ 15% 642.65

Cost of 1.0 cum 4927.00

Say 4927.0

Cost index 31.06 % 1530.33

Total with Cost index 6457.33

Say 6457.33

printed on 27-03-2019 14:03:19 page 4


PRICE EST NO:2018/110401

4 Specification Code: 4.1.8

Providing and laying in position cement concrete of specified grade excluding the
4.1
cost of centering and shuttering - All work up to plinth level:

4.1.8 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)

Code Description Unit Quantity Rate Amount

Details of cost for 1 cum


MATERIAL:

Stone Aggregate(single size): 40 mm


nominal size
0293 nominal size cum 0.65 1250.00 812.50
(0.70 cum -7.5% for voids i.e. 0.05 =0.65
cum)

Stone Aggregate(single size):20 mm


0295 nominal size cum 0.24 1300.00 312.00
nominal size

Carriage of Stone aggregate 40 mm


2206 cum 0.65 112.79 73.31
nominal size and above

Carriage of Stone aggregate below 40 mm


2202 cum 0.24 103.77 24.90
nominal size

0982 Coarse sand (zone III) cum 0.47 1200.00 564.00

2203 Carriage of Coarse sand cum 0.47 103.77 48.77

0367 Portland Cement tonne 0.17 5700.00 969.00

Carriage of Cement
2209 tonne 0.17 92.24 15.68
LABOUR:

0155 Mason (average) Day 0.1 467.00 46.70

0114 Beldar Day 1.63 368.00 599.84

0101 Bhisti Day 0.7 407.00 284.90

Hire charges of Concrete Mixer 0.25 to 0.40


0002 Day 0.07 800.00 56.00
cum with Hopper

0012 Vibrator (Needle type 40 mm) Day 0.07 350.00 24.50

printed on 27-03-2019 14:03:19 page 5


PRICE EST NO:2018/110401

9999 Sundries- L.S 13.52 1.73 23.39

TOTAL 3855.49

Add Water Charges @ 1% 38.55

TOTAL 3894.04

Add CPOH @ 15% 584.11

Cost of 1.0 cum 4478.15

Say 4478.15

Cost index 31.06 % 1390.91

Total with Cost index 5869.06

Say 5869.06

5 Specification Code: 13.1.1

13.1 12 mm cement plaster of mix:

13.1.1 1:4 ( 1 cement : 4 fine sand)

Code Description Unit Quantity Rate Amount

Details of cost for 10 sqm


MATERIAL:
Cement mortar 1:4(1 cement: 4 fine sand)

Rate as per item Number3.4 of SH:


3.4 cum 0.144 3499.70 503.96
Mortars

0155 Mason (average) Day 0.67 467.00 312.89

0115 Coolie Day 0.75 368.00 276.00

0101 Bhisti Day 0.92 407.00 374.44

9999 Sundries- L.S 12.61 1.73 21.82

TOTAL 1489.11

Add Water Charges @ 1% 14.89

TOTAL 1504.00

printed on 27-03-2019 14:03:19 page 6


PRICE EST NO:2018/110401

Add CPOH @ 15% 225.60

Cost of 10.0 sqm 1729.60

Cost per sqm 172.96

Say 172.95

Cost index 31.06 % 53.72

Total with Cost index 226.67

Say 226.67

6 Specification Code: 13.1.2

13.1 12 mm cement plaster of mix:

13.1.2 1:6 (1 cement : 6 fine sand).

Code Description Unit Quantity Rate Amount

Details of cost for 10 sqm.


MATERIAL:
Cement mortar 1 : 6 (1 cement: 6 fine sand)

Rate as per item Number3.6 of SH:


3.6 Mortars cum 0.144 2746.75 395.53
LABOUR:

0155 Mason (average) Day 0.67 467.00 312.89

0115 Coolie Day 0.75 368.00 276.00

0101 Bhisti Day 0.92 407.00 374.44

9999 Sundries-Scaffolding and sundries L.S 12.61 1.73 21.82

TOTAL 1380.68

Add Water Charges @ 1% 13.81

TOTAL 1394.49

Add CPOH @ 15% 209.17

Cost of 10.0 sqm 1603.66

printed on 27-03-2019 14:03:19 page 7


PRICE EST NO:2018/110401

Cost per sqm 160.37

Say 160.35

Cost index 31.06 % 49.80

Total with Cost index 210.15

Say 210.15

7 Specification Code: 60.7.1

DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course


masonry with good quality blasted rubble including packing to compactness to
60.7.1
lines and levels cost and conveyance of all materials labour charges etc.
complete as per direction of Departmental officers at site

Code Description Unit Quantity Rate Amount

"Details of cost for 1 cum.


Material

Stone for masonry work


1157 cum 1.05 865.00 908.25
Carriage

Carriage of Soling stone & masonry stone


2215 cum 1.05 122.08 128.18
Labour

0125 Mason (for plain stone work) 2nd class Day 0.8 448.00 358.40

0114 Beldar Day 0.7 368.00 257.60

TOTAL 1652.43

Add Water Charges @ 1% 16.52

TOTAL 1668.95

Add CPOH @ 15% 250.34

Cost of 1.0 cum 1919.29

Cost per cum 1919.29

Say 1919.3

printed on 27-03-2019 14:03:19 page 8


PRICE EST NO:2018/110401

Cost index 31.06 % 596.13

Total with Cost index 2515.43

Say 2515.43

8 Specification Code: 7.1.1

Random rubble masonry with hard stone in foundation and plinth including
7.1 levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded
stone aggregate 20 mm nominal size) up to plinth level with:

7.1.1 Cement mortar 1:6 (1 cement : 6 coarse sand)

Code Description Unit Quantity Rate Amount

Details of cost for 1 cum


MATERIAL

1157 Stone for masonry work cum 1.0 865.00 865.00

Through and bond stone size 24 x 24 x


1154 39cm 100 nos 7.0 1260.00 88.2
CARRIAGE:

Carriage of Soling stone & masonry stone


7.00x24cmx39cm = 0.16 cum
2215 1.00 cum + 0.16 cum. = 1.16 cum cum 1.16 122.08 141.61
Cement mortar 1:6 (1 cement : 6 Coarse
sand)

Rate as per item Number3.11 of SH:


3.11 Mortars cum 0.33 3217.55 1061.79
LABOUR:

0125 Mason (for plain stone work) 2nd class Day 1.07 448.00 479.36

0114 Beldar Day 1.07 368.00 393.76

0115 Coolie Day 0.71 368.00 261.28

0101 Bhisti Day 0.09 407.00 36.63

9999 Sundries-Cement concrete 1:6:12 L.S 45.76 1.73 79.16

printed on 27-03-2019 14:03:19 page 9


PRICE EST NO:2018/110401

9999 Sundries- L.S 4.42 1.73 7.65

TOTAL 3414.44

Add Water Charges @ 1% 34.14

TOTAL 3448.58

Add CPOH @ 15% 517.29

Cost of 1.0 cum 3965.87

Cost of 1 cum 3965.87

Say 3965.85

Cost index 31.06 % 1231.79

Total with Cost index 5197.64

Say 5197.64

9 Specification Code: 50.6.7.1

Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or


50.6.7.1 nearest size in cement mortar 1:6 for foundation and basement including all cost
of materials, labour charges etc.

Code Description Unit Quantity Rate Amount

Details of cost for one cum.

MR9 laterate stone of size 40x20x15cm each 77.0 46.00 3542.00

Rate as per item Number3.11 of SH:


3.11 cum 0.0874 3217.55 281.21
Mortars

9999 Sundries- L.S 2.73 1.73 4.72

0123 Mason (brick layer) Ist class Day 0.4 487.00 194.80

0124 Mason (brick layer )2nd class Day 0.4 448.00 179.20

0115 Coolie Day 1.46 368.00 537.28

0101 Bhisti Day 0.45 407.00 183.15

TOTAL 4922.36

printed on 27-03-2019 14:03:19 page 10


PRICE EST NO:2018/110401

Add Water Charges @ 1% 49.22

TOTAL 4971.58

Add CPOH @ 15% 745.74

Cost of 1.0 cum 5717.32

Cost per cum 5717.32

Say 5717.3

Cost index 31.06 % 497.99

Total with Cost index 6215.34

Say 6215.34

printed on 27-03-2019 14:03:19 page 11