CUMULATIVE PROGRESS
CUMMULATIVE
SCHEDULED ACCOMPLISHMENT TARGET
ITEM NO. ACTIVITY DESCRIPTION UNIT
QUANTITY NET WT. QUANTITY NET WT. QUANTITY NET WT.
(PERT-CPM) % % %
A.1.1(3) Construction of field office for the Engineer LS 1.00 0.195
A.1.1(6) Assistance to the Engineer mo. 9.00 0.132
B-5 Project Billboard each 2.00 0.010
B-7 Construction Safety And Health mo. 9.00 0.193
B-8 Traffic Management mo. 9.00 2.638
B-9 Mobilization & Demobilization LS 1.00 0.293
B.4(1) Construction Survey & Staking Km 1.92 0.024
100(1) Clearing & Grubbing ha 0.16 0.023
101(3)a2 Removal of Existing PCCP sq.m 13,870.40 3.389
102(2) Surplus Common Excavation cu.m 20,424.00 15.019
103(1)a Structure Excavation cu.m 1,201.88 0.824
103(3) Foundation Fill cu.m 22.11 0.015
103(6)a Pipe Culvert & Drain excavation cu.m 5,798.62 1.049
104(1)a1 Embankment from Roadway Excavation cu.m 2,748.00 0.687
105(1)a Subgrade Preparation sq.m 29,655.48 0.652
200(1) Aggregate Subbase Course cu.m 7,093.00 6.279
311(1)a PCCPavement (Unreinforced), 150mm thk. sq.m 2,925.00 2.509
311(1)e1 PCCPavement (Unreinforced), 280mm thk. sq.m 26,910.59 43.106
500(1)b3 PipeCulvert, 910mm dia. Class IV ln.m 1,057.00 5.174
502(1)c Manholes, 910mm dia. CHB each 43.00 1.251
504(3)c Cleaning of Pipe Culvert,910mm dia ln.m 60.00 0.023
TOTAL 83.485
Prepared by:
PROJECT COST:
Budget to Date :
Actual Budget :
ACCOMPLISHMENT
TO DATE
REMARKS
NET WT.
QUANTITY
%
1.00 0.195
9.00 0.132
2.00 0.01
9.00 0.193
9.00 2.638
0.50 0.1465
0.96 0.012
0.08 0.0115
7569.02 1.849363
6313.60 4.642771
103.90 0.071233
5.63 0.00382
959.83 0.173638
1639.00 0.40975
14937.96 0.328423
2280.65 2.01892
132.00 0.113227
11970.11 19.174
120.00 0.587398
10.00 0.29093
60.00 0.023
33.02447
Verified Correct by:
Project Inspector / Assistant Chief Engineer
Approved by:
Chief Engineer
PROJECT STATUS SUMMARY REPORT
SLIPPAGE %
SCHEDULE (PERT-CPM PROJECT IN-
PROJECT NAME PLANNED ACTUAL EXPIRY DATE STATUS
(PERT-CPM) SCHEDULE CHARGE
LESS ACTUAL)
Prepared By: Verified Correct By: Noted By:
CUMULATIVE PROGRESS
CUMMULATIVE
SCHEDULED ACCOMPLISHMENT
ITEM NO. ACTIVITY DESCRIPTION UNIT QUANTITY NET WT. NET WT.
QUANTITY
(PERT-CPM) % %
A.1.1(3) Construction of field office for the Engineer LS 1.00 0.195 0.00 0
A.1.1(6) Assistance to the Engineer mo. 9.00 0.132 0.00 0
B-5 Project Billboard each 2.00 0.010 0.00 0
B-7 Construction Safety And Health mo. 9.00 0.193 0.00 0
B-8 Traffic Management mo. 9.00 2.638 0.00 0
B-9 Mobilization & Demobilization LS 1.00 0.293 0.00 0
B.4(1) Construction Survey & Staking Km 1.92 0.024 0.00 0
100(1) Clearing & Grubbing ha 0.16 0.023 0.00 0
101(3)a2 Removal of Existing PCCP sq.m 13,870.40 3.389 0.00 0
102(2) Surplus Common Excavation cu.m 20,424.00 15.019 0.00 0
103(1)a Structure Excavation cu.m 1,201.88 0.824 0.00 0
103(3) Foundation Fill cu.m 22.11 0.015 0.00 0
103(6)a Pipe Culvert & Drain excavation cu.m 5,798.62 1.049 0.00 0
104(1)a1 Embankment from Roadway Excavation cu.m 2,748.00 0.687 0.00 0
105(1)a Subgrade Preparation sq.m 29,655.48 0.652 0.00 0
200(1) Aggregate Subbase Course cu.m 7,093.00 6.279 0.00 0
311(1)a PCCPavement (Unreinforced), 150mm thk. sq.m 2,925.00 2.509 0.00 0
311(1)e1 PCCPavement (Unreinforced), 280mm thk. sq.m 26,910.59 43.106 0.00 0
500(1)b3 PipeCulvert, 910mm dia. Class IV ln.m 1,057.00 5.174 0.00 0
502(1)c Manholes, 910mm dia. CHB each 43.00 1.251 0.00 0
PipeCulvert, 1220mm dia. Class IV ln.m 204.00 1.996 0.00 0
Manholes, 910mm dia. CONC each 16.00 1.094 0.00 0
Manholes, 1220mm dia. CONC each 11.00 0.86 0.00 0
Sidewalk sq.m 4,236.00 2.843 0.00 0
Curb and Gutter ln.m 3,530.00 3.476 0.00 0
504(3)c Cleaning of Pipe Culvert,910mm dia ln.m 60.00 0.023 0.00 0
TOTAL 0
Prepared b
Project / Resident Engineer
CUMULATIVE PROGRESS
CUMMULATIVE
SCHEDULED ACCOMPLISHMENT
ITEM NO. ACTIVITY DESCRIPTION UNIT QUANTITY NET WT. NET WT.
QUANTITY
(PERT-CPM) % %
A.1.1(3) Construction of field office for the Engineer LS 1.00 0.195 0.00 0
A.1.1(6) Assistance to the Engineer mo. 9.00 0.132 0.00 0
B-5 Project Billboard each 2.00 0.010 0.00 0
B-7 Construction Safety And Health mo. 9.00 0.193 0.00 0
B-8 Traffic Management mo. 9.00 2.638 0.00 0
B-9 Mobilization & Demobilization LS 1.00 0.293 0.00 0
B.4(1) Construction Survey & Staking Km 1.92 0.024 0.00 0
100(1) Clearing & Grubbing ha 0.16 0.023 0.00 0
101(3)a2 Removal of Existing PCCP sq.m 13,870.40 3.389 0.00 0
102(2) Surplus Common Excavation cu.m 20,424.00 15.019 0.00 0
103(1)a Structure Excavation cu.m 1,201.88 0.824 0.00 0
103(3) Foundation Fill cu.m 22.11 0.015 0.00 0
103(6)a Pipe Culvert & Drain excavation cu.m 5,798.62 1.049 0.00 0
104(1)a1 Embankment from Roadway Excavation cu.m 2,748.00 0.687 0.00 0
105(1)a Subgrade Preparation sq.m 29,655.48 0.652 0.00 0
200(1) Aggregate Subbase Course cu.m 7,093.00 6.279 0.00 0
311(1)a PCCPavement (Unreinforced), 150mm thk. sq.m 2,925.00 2.509 0.00 0
311(1)e1 PCCPavement (Unreinforced), 280mm thk. sq.m 26,910.59 43.106 0.00 0
500(1)b3 PipeCulvert, 910mm dia. Class IV ln.m 1,057.00 5.174 0.00 0
502(1)c Manholes, 910mm dia. CHB each 43.00 1.251 0.00 0
PipeCulvert, 1220mm dia. Class IV ln.m 204.00 1.996 0.00 0
Manholes, 910mm dia. CONC each 16.00 1.094 0.00 0
Manholes, 1220mm dia. CONC each 11.00 0.86 0.00 0
Sidewalk sq.m 4,236.00 2.843 0.00 0
Curb and Gutter ln.m 3,530.00 3.476 0.00 0
504(3)c Cleaning of Pipe Culvert,910mm dia ln.m 60.00 0.023 0.00 0
TOTAL 0
Prepared b
Project / Resident Engineer
HMENT REPORT
UMULATIVE PROGRESS
ACCOMPLISHMENT
TARGET TO DATE
NET WT. NET WT. REMARKS
QUANTITY QUANTITY
% %
0.01 0.00
3100.00 0.76 506.85 0.12
2176.00 1.60 500.49 0.37
370.44 0.25 174.47 0.12
13.00 0.01 2.30 0.00
2520.00 0.46 593.20 0.11
2000.00 0.50 0.00 0.00
6190.00 0.14 1251.23 0.03
1238.00 1.10 250.25 0.22
1500.00 1.29 0.00 0.00
4690.00 7.51 1251.23 2.00
580.00 2.84 170.00 0.83
19.00 0.55 9.00 0.26
220.00 2.15 80.00 0.78
10.00 0.68 0.00
11.00 0.86 0.00
750.00 0.50 0.00
500.00 0.49 0.00
21.691 4.850
Verified Correct by:
Project Inspector / Assistant Chief Engineer
Approved by:
Chief Engineer
HMENT REPORT
UMULATIVE PROGRESS
ACCOMPLISHMENT
TARGET TO DATE
NET WT. NET WT. REMARKS
QUANTITY QUANTITY
% %
0.01 0.00
3100.00 0.76 506.85 0.12
2176.00 1.60 500.49 0.37
370.44 0.25 174.47 0.12
13.00 0.01 2.30 0.00
2520.00 0.46 593.20 0.11
2000.00 0.50 0.00 0.00
6190.00 0.14 1251.23 0.03
1238.00 1.10 250.25 0.22
1500.00 1.29 0.00 0.00
4690.00 7.51 1251.23 2.00
580.00 2.84 170.00 0.83
19.00 0.55 9.00 0.26
220.00 2.15 80.00 0.78
10.00 0.68 0.00
11.00 0.86 0.00
750.00 0.50 0.00
500.00 0.49 0.00
21.691 4.850
Verified Correct by:
Project Inspector / Assistant Chief Engineer
Approved by:
Chief Engineer
PROJECT ACCOMPLISHMENT REPORT
PROJECT STATUS:
Accomplishment to Date 45.5131 Period : June 3 to July 3, 2018
Required as per PERT CPM 100.00 Project ID No. : 17LO-0063
Period Accomplishment Project Code Name : Tigatto Bypass Road
Project Ins
PROJECT COST:
Budget to Date
Actual Budget
TARGET ACCOMPLISHMENT
REL. WT. REMARKS
REL. WT. (%) QTY
(%)
- -
- -
- -
- -
- -
- -
- -
- -
- -
0.621 -
- -
0.020 -
4.523 -
0.246 -
0.006 -
0.285 -
0.277 -
0.147 -
2.259 -
1.595 -
11.826 -
- -
- -
- -
- -
- -
0.020 -
2.384 -
- -
- -
0.684 -
0.391 -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
25.286 -
Chief Engineer
PROJECT ACCOMPLISHMENT REPORT
PROJECT STATUS:
Accomplishment to D : 45.5131 Period : May 3 to June 3, 2018
Required as per PER : Project ID No. : 17LO-0063
Period Accomplishme : Project Code Name : Tigatto Bypass Road
PROJECT COST:
Budget to :
Actual Bud:
ACCOMPLISHMENT
REL. WT. REMARKS
QTY
(%)
-
-
-
-
-
-
-
-
-
1,302.00 0.318
-
-
600.23 0.441
100.80 0.078
0.29 0.000
237.25 0.050
-
1,567.40 0.034
310.12 0.275
-
1,125.60 1.803
-
-
-
-
-
-
-
73.00 0.714
4.00 0.156
-
0.50 0.039
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
3.909
Chief Engineer