Title of Project: Computer Controlled Surface Grinding Machine

Manufacturing Assembly
Design Finance Logistics &
Research and Department Department
&Planning Purchasing
Development Department
Muhammad Ali Asfand ZainMajid Saad Ibrahim Taimoor Abid Hussain Saadiq
Amna (15-ME-34) (15-ME-07) (15-ME-4) (15-ME-05) (15-ME-06)
(15-ME-178) Muhammad Maarij Areeb Iftikhar Muhammad Farhan Noman Azhar Maqbool
Zartasha (15-ME-09) (15-ME-124) (15-ME-158) (15-ME-40) (15-ME-15)
(15-ME-180) Shaharyaar Ahmed Muhammad Umair Ammar Shoaib Umer Usman Touqir
(15-ME-50) (15-ME-36) (15-ME- 14) (15-ME-31) (15-ME-19)
Javeria
Noman
(15-ME-181) (15-ME-42)
Activities Predecessor Duration (Days)
Research and Development ___ 10
(R&D)
Design Department (DD) Research and Development 15
Finance and Planning (F&P) Research and Development 6
Logistics and purchasing (L&P) Design Department 10
Manufacturing Department Finance and Planning (F&P) 30
(MD)
Assembly Department (AD) Manufacturing Department and 10
Logistics and purchasing

DD L&P

R&D AD

F&P MD
KEY For Network Diagram:

Early Start Activity Early finish


Late Start Duration Late Finish

10 DD 25 25 L&P 35

21 15 36 36 10 46
0 R&D 10 46 AD 56

0 10 10 46 10 56
10 F&P 16 16 MD 46

10 06 16 16 30 46