Escolar Documentos
Profissional Documentos
Cultura Documentos
1. Mutually Exclusive means that if one project is taken on, the other must also be
accepted. T/F
2. In case of discounted pay back period the expected cash flows are discounted by
the project’s cost of capital. T/F
3. If a project has a positive NPV, it means it would be generating more cash than is
needed to service the debt. T/F
4. Surplus that remains after paying for the capital accrues to the firm’s stockholders.
T/F
5. No cost is imposed on the current stockholders, if the IRR is less than the cost of
capital. T/F
6. In case of independent projects, NPV & IRR criteria leads to different accept /
reject decisions. T/F
7. MIRR assumes that cash flows from all projects are reinvested at project’s own
IRR
T/ F
10. Preemptive goal programming model deals with cases where there is a hierarchy
of priority levels. T/F
12. Fraction values of decision variables are not permitted in case of linear
programming model.
T/F
13. The value of the objective function at the succeeding vertex is less than at the
preceding vertex in case f simplex method. T/F
15. Optimization in case of goal programming means “as close as possible to the
indicated goal.” T/F
Section II: Multiple Choice Questions
2. For a project having cash outflow of $1000 and inflows of $500, $400, $300
and $ 100 respectively,what is the payback period?
a) 2 yrs b) 2.33 yrs c) 2.45 yrs d) 3 yrs
1. You are a financial analyst for the company. The director of capital budgeting
has asked you to analyze two proposed capital investments, project X & Y.
Each project has a cost of $ 10,000 and the cost of capital for each project is
12%.The projects’ expected cash flow are as follows:
Yr Project X Project Y
0 (10,000) (10,000)
1 6500 3500
2 3000 3500
3 3000 3500
4 1000 3500
a) Calculate each projects’ payback period, NPV, IRR, MIRR
b) Which project or projects should be accepted if they are independent
c) Which project should be accepted if they are mutually exclusive
d) How might a change in the cost of capital produce a conflict between the
NPV & IRR rankings of these two projects? Would this conflict exist if k were
5%
e) Why does the conflict exist?