Date: 14/03/2019
West Central Railways- Kota Division
Comparison Report
Project Name MANDALGARH - TODARAISINGH NEW LINE
Project Description RECT Survey for new line from Mandalgarh to Todaraisingh
Alternative alignment 02 (Blue)
● 13 New Stations are proposed out of which one existing station at Todaraisingh has to be
relocated.
● Alignment has 21 curves having Maximum Degree Curve of 2 degree for Speed Potential of 130
KMPH, Out of which 18 curves are of 1 degree, 2 curves are of 1.5 degree and 1 curves is set at
2 degree.
● Approximate land to be acquired is 7.93 sq KM.
● There are 44 ROB/RUB proposed along the length of the alignment.
● There are 7 major bridges to be proposed on the alignment having a total length of around 1.24
KMs.
● Ruling gradient of 1 in 200 has been adopted and a gradient of 1 in 1200 is proposed at the
yards.
www.indshine.com 1
Alternative alignment 03 (Red)
● 11 New Stations are proposed out of which one existing station at Todaraisingh has to be
relocated.
● Alignment has 20 curves having Maximum Degree Curve of 2 degree for Speed Potential of
130 KMPH, Out of which 18 curves are of 1 degree and 2 curves are set at 2 degree.
● Approximate land to be acquired is 6.73 sq KM.
● There are 26 ROB/RUB proposed along the length of the alignment.
● There are 6 major bridges to be proposed on the alignment having a total length of around 1.16
KMs.
● Ruling gradient of 1 in 200 has been adopted and a gradient of 1 in 1200 is proposed at the
yards.
Comparative Analysis:
S. No. Description Route - I Route-II Route -III
1 Route length by Road (Km) 123.8 123.8 123.8
2 Route Length by Existing Railway Track No existing Track No existing Track No existing Track
3 Total Route Length (Km) 137.97 144.43 122.59
4 No of Proposed Stations 12 13 11
5 No. of Existing Stations 2 2 2
6 Existing Station to be relocated TodaRaiSingh TodaRaiSingh TodaRaiSingh
7 No. of Curves 20 21 20
8 Max. Degree of Curve 2 2 2
9 Ruling Gradient 1 in 200 1 in 200 1 in 200
10 Gradient at existing stations 1 in 400 1 in 400 1 in 400
11 Gradient at proposed stations 1 in 1200 1 in 1200 1 in 1200
12 No. of Tunnels 0 0 1
13 Total length of Tunnels (Meters) 0 0 1 KM
14 No. of Bridges (Major) 7 7 6
15 Total length of Bridges (Meters) 1130 1240 1160
16 No. of Highway crossings (RUB/ROB) 45 44 26
17 Land area to be acquired (Sq. KM) 7.5 7.93 6.73
18 Forest Area (Jungle and Open Babul) 3.98 KM 3.98 KM 3.13 KM