Você está na página 1de 10

BILL OF ENGINEERING MEASUREMENT AND EVALUATION (BEME) FOR ONE STOREY MINI-

SHOPPING COMPLEX

STRUCTURAL WORKS & FINISHES


S/N DESCRIPTION QTY UNIT RATE AMOUNT
A SUB-STRUCTURE
PLANT
1 Allow for bringing and removal from site
of all associated plants. lump sum 30,000.00
2 Allow for maitenance on site of all
associted plants for this work lump sum 30,000.00
EXCAVATION AND EARTHWORKS
1 Clear site of all shrubs,bushes, undergrowth,
small trees & remove all debris from site. 400.00 m2 50 20,000.00
2 Excavate oversite average 150mm deep to
remove vegetable topsoil 200.00 m2 25 5,000.00
3 Excavate foundation trench starting at
stripped level, max. depth not exceding 1.5m 91.35 m3 750 68,512.50
4 Ditto, for column bases 11.00 m3 750 8,250.00
5 Backfill & compact selected excavated
material around foundation 64.06 m3 500 32,030.00
6 Level and compact bottom of excavation to
receive concrete 169.11 m2 250 42,277.50
7 Laterite filling to make up level average
depth 750mm 126.83 m3 1500 190,245.00
8 Ditt0, 150mm consolidated bed of hardcore
filling spread and blinded with fine sand to
receive concrete nil m3 nil
CONCRETE WORK
Plain in-situ concrete (1:3:6-20mm aggregate)
1 Blinding bed in foundation trench and column
bases not exceeding 50mm thick 8.00 m3 28500 228,085.50
2 Foundation trenches 150-300mm thick poured
against surfaces of excavation 18.23 m3 28500 519,555.00
Reinforced in-situ concrete (vibrated & well
placed) (1:2:4-20mm aggregate)
3 Column bases (300mm thick) 3.04 m3 35000 106,400.00
4 Column starters 11.57 m3 35000 404,950.00
5 150mm thick mass floor slab (1:3:6) 25.37 m3 28500 723,045.00
REINFORCEMENT WORK
High tensile steel bars including bends, hooks,
tying wires, distance blocks & spacers
1 Column bases 0.52 tonnes 245000 127,400.00
2 Column starters 0.67 tonnes 245000 164,150.00
Carried forward 2,699,900.50

Brought forward 2,699,900.50


3 B.R.C Fabric square mesh reinforcement to BS:
4483 ref A143 single layer laid in bed
(measured net-allowance made for laps) 169.11 m2 1200 202,932.00
FORMWORK
Sawn hardwood formwork to
1 Vertical sides of column starters (section 225x 40.00 m2 1700 68,000.00
225mm)
2 Edges of floor bed not exceeding 300mm 65.00 m 750 48,750.00
BLOCKWORK
Sandcrete hollow blockwork bedded and
jointed in cement and sand mortar (1:6)
1 225mm wall 150.00 m2 2400 360,000.00

Sub-structure work Carried to summary 3,379,582.50

B SUPER STRUCTURE (Ground Floor)


CONCRETE WORK
Reinforced in-situ concrete (vibrated & well
placed) (1:2:4-20mm aggregate)
1 Square columns (0.03 - 0.20m2 sectional area) 6.68 m3 35000 233,800.00
2 Lintel 5.40 m3 35000 189,000.00
3 Floor beams 8.08 m3 35000 282,800.00
4 Suspended floor slab(s) not exceeding 175mm
thick 26.24 m3 35000 918,400.00
5 Staircase 1.79 m3 35000 62,650.00
REINFORCEMENT WORK
High tensile steel bars including bends, hooks,
tying wires, distance blocks & spacers
1 Columns 0.87 tonnes 245000 213,150.00
2 Beams and lintel 1.65 tonnes 245000 404,250.00
3 Slab 2.17 tonnes 245000 531,650.00
4 Staircase 0.19 tonnes 245000 46,550.00
FORMWORK
Sawn hardwood formwork to
1 Vertical sides of columns (section 225x225mm) 85.00 m2 1700 144,500.00
2 Sides and soffits of beams and lintel 225.13 m2 1800 405,234.00
3 Horizontal soffit of Slab 146.00 m2 2100 306,600.00
4 Sloping soffit of staircase 7.50 m2 2100 15,750.00
BLOCKWORK
Sandcrete hollow blockwork bedded and
jointed in cement and sand mortar (1:6)
1 225mm wall 288.00 m2 2400 691,200.00
Super structure(G-Floor) Carried to summary 4,445,534.00

C SUPER STRUCTURE (First Floor)


CONCRETE WORK
Reinforced in-situ concrete (vibrated & well
placed) (1:2:4-20mm aggregate)
1 Square columns (0.03 - 0.20m2 sectional area) 6.68 m3 36000 240,480.00
2 Lintel 5.40 m3 36000 194,400.00
3 Floor beams 7.29 m3 36000 262,440.00
4 Concrete Fascia (parapet) 4.49 m3 36000 161,640.00
REINFORCEMENT WORK
High tensile steel bars including bends, hooks,
tying wires, distance blocks & spacers
1 Columns 0.55 tonnes 245000 134,750.00
2 Beams and lintel 1.14 tonnes 245000 279,300.00
3 Concrete Fascia (parapet) 0.20 tonnes 245000 49,000.00
FORMWORK
Sawn hardwood formwork to
1 Vertical sides of columns (section 225x225mm) 85.00 m2 1700 144,500.00
2 Sides and soffits of beams and lintel 202.00 m2 1800 363,600.00
3 Concrete Fascia (parapet) 33.72 m2 3100 104,532.00
BLOCKWORK
Sandcrete hollow blockwork bedded and
jointed in cement and sand mortar (1:6)
1 225mm wall 338.00 m2 2400 811,200.00

Super structure(First Floor) Carried to summary 2,745,842.00

D ROOF & INSTALLATIONS


ROOFING WOOD
Sawn hardwood polished with solignum wood
preservative
1 50 x 100mm hardwood (rafters) 1085.20 m 325 352,690.00
2 50 x 150mm hardwood (tie beam/wall plate) 195.00 m 500 97,500.00
3 50 x 50mm hardwood (noggins& purlins) 1935.70 m 250 483,925.00
ROOFING SHEETS
1 Stone coated roofing sheets (melano black 0.45) 392.00 m2 3000 1,176,000.00
2 Roofing accessories & installation 78.40 m2 2700 211,680.00

E PLUMBING & MECHANICAL INSTALLATION


1 Allow a provisional sum of 300,000 for all piping lump sum 300,000.00
work associated with plumbing installation.
2 Allow a provisional sum of 400000 for the
construction of soak-away pit, septic tank and
associated chambers. lump sum 400,000.00

Roof and Installations carried forward 3,021,795.00

Roof and Installations brought forward 3,021,795.00

ELECTRICAL INSTALLATION
Allow a provisional sum of 400000 for all
electrical installation (piping work) lump sum 300,000.00

Roof and Installations carried to summary 3,321,795.00

F FINISHES
PLASTERING/SCREEDING
Insitu wall finishes, cement and sand (1:6)
rendered and trowolled smooth
1 15mm thick on blockwall 1012.50 m2 700 708,750.00
2 Ditto but for slab soffit (1:4) 146.00 m2 800 116,800.00
Floor screed, cement and sand (1:8)
1 40mm thick floor screed 316.00 m2 700 221,200.00
TILING
1 High quality vitrified floor tiles(400x400mm) in
cement and sand (1:3) screeded bed 316.00 m2 2100 663,600.00
2 High quality wall tiles(200x400mm) 227.50 m2 2100 477,750.00
POP
1 Pop ceiling finishing of approved design/
cornices. 292.00 m2 2700 788,400.00
WINDOWS
Tower Casement windows with aluminium pipe
buglary proofing & mosquito net
1 size 600x750mm 8.00 no 12000 96,000.00
2 size 750x1500mm 31.00 no 31000 961,000.00
3 size 900x4500mm (curtain wall) 4.00 no 100000 400,000.00
4 Window dressing (internal & external) 410.2 m 200 82,040.00

Roof and Installations carried to summary 4,515,540.00

SUMMARY
SUB-STRUCTURE WORK 3,379,582.50

SUPER STRUCTURE (GROUND FLOOR) 4,445,534.00

SUPER STRUCTURE (FIRST FLOOR) 2,745,842.00


ROOF AND INSTALLATIONS 3,321,795.00

FINISHES 4,515,540.00

SUMMARY 18,408,293.50
BILL OF ENGINEERING MEASUREMENT AND EVALUATION (BEME) FOR ONE STOREY
MINI-SHOPPING COMPLEX

STRUCTURAL WORKS & FINISHES


S/N DESCRIPTION QTY UNIT RATE AMOUNT
A SUB-STRUCTURE
PLANT
1 Allow for bringing and removal from site
of all associated plants. 100,000.00
2 Allow for maitenance on site of all 80,000.00
associted plants for this work 30,000.00
3 Allow for monitoring by Development Control Provisional sum 150,000.00
Dvision.
4 Allow for geophysical investigation and sinking of
borehole. Lump Sum 1,000,000.00
5 Allow for soil test. Lump Sum 150,000.00
6 Allow for anti-termite treatment Lump sum 30,000.00
7 Allow for provision and erection of project signboard Lump Sum 100,000.00
8 Allow for material testing (Concrete and reinforcement) Lump Sum 80,000.00
9 Allow for demolition and removal of debris of existing Lump Sum 180,000.00
building
EXCAVATION AND EARTHWORKS
1 Clear site of all shrubs,bushes, undergrowth,
small trees & remove all debris from site. 354.00 m2 80 28,320.00
2 Excavate oversite average 150mm deep to
remove vegetable topsoil 200.00 m2 25 5,000.00
3 Excavate foundation trenches except rock to a
maximum depth not exceeding 1.5m, haul exc 80.88 m3 1500 121,320.00
material to any distance.
4 Ditto, for column bases 9.00 m3 1500 13,500.00
5 Backfill & compact selected excavated
material around foundation 116.00 m3 1500 174,000.00
6 Level and compact bottom of excavation to
receive concrete 77.00 m2 500 38,500.00
7 Laterite filling to make up level average
depth 750mm 80.00 m3 1000 80,000.00
8 Provide and place 300mm consolidated bed 40.0 m3 2700 108,000.00
of hardcore.
CONCRETE WORK
Plain in-situ concrete (1:3:6-20mm aggregate)
1 Provide, mix and place blinding concrete C15 (50mm
thickness) for foundation trenches and column 77.00 m2 900 69,300.00
2 Prrovide, mix and place mass floor concrete. 18.00 m3 38000 684,000.00
Reinforced in-situ concrete (vibrated & well
placed) (1:2:4-20mm aggregate)
3 Ditto (2) for column bases (350mm thick) 9.00 m3 38000 342,000.00
4 Ditto (2) for column starter (225mmx225mm) 2.00 m3 38000 76,000.00
REINFORCEMENT WORK
High tensile steel bars including bends, hooks,
tying wires, distance blocks & spacers
1 Column bases 0.52 tonnes 245000 127,400.00
2 Column starters 0.67 tonnes 245000 164,150.00

Carried forward 3,931,490.00

Brought forward 3,931,490.00


3 B.R.C Fabric square mesh reinforcement to BS:
4483 ref A143 single layer laid in bed
(measured net-allowance made for laps) 169.11 m2 2000 338,220.00
FORMWORK
Sawn hardwood formwork to
1 Vertical sides of column starters (section 225x 36.00 m2 2000 72,000.00
225mm)
BLOCKWORK
Sandcrete hollow blockwork bedded and
jointed in cement and sand mortar (1:6)
1 225mm wall 160.00 m2 2800 448,000.00

Sub-structure work Carried to summary 4,789,710.00

B SUPER STRUCTURE (Ground Floor)


CONCRETE WORK
Reinforced in-situ concrete (Well placed & properly
vibrated ) (1:2:4-20mm aggregate)
1 Square columns 225mm x 225mm 5.00 m3 38000 190,000.00
2 Lintel 10.00 m3 38000 380,000.00
3 Floor beams 6.00 m3 38000 228,000.00
4 Suspended floor slab(s) not exceeding 175mm
thick 20.00 m3 38000 760,000.00
5 Staircase 2.00 m3 38000 76,000.00
REINFORCEMENT WORK
High tensile steel bars including bends, hooks,
tying wires, distance blocks & spacers
1 Columns 0.87 tonnes 245000 213,150.00
2 Beams and lintel 1.65 tonnes 245000 404,250.00
3 Slab 2.17 tonnes 245000 531,650.00
4 Staircase 0.19 tonnes 245000 46,550.00
FORMWORK
1 Marine Plywood
Vertical formwork
sides of columns (section 225x225mm) 85.00 m2 1700 144,500.00
1 Sides and soffits of beams and lintel 180.00 m2 3800 684,000.00
2 Horizontal soffit of Slab 110.00 m2 3800 418,000.00
3 Sloping soffit of staircase 8.64 m2 3800 32,832.00
4 Vertical sides of columns (section 225x225mm) 62.00 m2 3800 235,600.00
BLOCKWORK
Sandcrete hollow blockwork bedded and
jointed in cement and sand mortar (1:6)
1 225mm wall 320.00 m2 2800 896,000.00

Super structure(G-Floor) Carried to summary 5,240,532.00

C SUPER STRUCTURE (First Floor)


CONCRETE WORK
Reinforced in-situ concrete (vibrated & well
placed) (1:2:4-20mm aggregate)
1 Square columns 225mmx225mm 5.00 m3 38000 190,000.00
2 Lintel 10.00 m3 38000 380,000.00
3 Roof beams 6.00 m3 38000 228,000.00
4 Concrete Fascia 2.50 m3 38000 95,000.00
REINFORCEMENT WORK
High tensile steel bars including bends, hooks,
tying wires, distance blocks & spacers
1 Columns 0.55 tonnes 245000 134,750.00
2 Beams and lintel 1.14 tonnes 245000 279,300.00
3 Concrete Fascia 0.20 tonnes 245000 49,000.00
FORMWORK
Marine plywood formwork
1 Vertical sides of columns (section 225x225mm) 62.00 m2 3800 235,600.00
2 Sides and soffits of beams and lintel 180.00 m2 3800 684,000.00
3 Concrete Fascia (parapet) 18.00 m2 3800 68,400.00
BLOCKWORK
Sandcrete hollow blockwork bedded and
jointed in cement and sand mortar (1:6)
1 225mm wall 280.00 m2 2800 784,000.00

Super structure(First Floor) Carried to summary 3,128,050.00


D ROOF & INSTALLATIONS
ROOFING WOOD
Sawn hardwood polished with solignum wood
preservative
1 50 x 100mm hardwood (rafters) 1100.00 m 400 440,000.00
2 50 x 150mm hardwood (tie beam/wall plate) 240.00 m 500 120,000.00
3 50 x 75mm hardwood (noggins& purlins) 1800.00 m 300 540,000.00
ROOFING SHEETS
1 Stone coated roofing sheets 372.00 m2 5200 1,934,400.00
2 Roofing accessories & installation 78.40 m2 2700 211,680.00

E PLUMBING & MECHANICAL INSTALLATION


1 Provide and Install all plumbing works Lump sum 600,000.00
associated with plumbing installations.
2 Allow for the construction of soak-away,
septic tank and all associated chambers. Lump sum 500,000.00

Roof and Installations carried forward 4,346,080.00

Roof and Installations brought forward 4,346,080.00

ELECTRICAL INSTALLATION
1 Provide and Install all electrical works
associated with electrical installations. Lump sum 700,000.00

Roof and Installations carried to summary 5,046,080.00

F FINISHES
PLASTERING/SCREEDING
Insitu wall finishes, cement and sand (1:6)
rendered and trowolled smooth
1 25mm thick on blockwall 1050.00 m2 1400 1,470,000.00
2 Ditto but for slab soffit 250.00 m2 1600 400,000.00
Floor screed, cement and sand (1:8)
1 50mm thick floor screed 180.00 m2 1800 324,000.00
TILING (Marbles)
1 High quality Marbles (600x300mm) in
cement and sand (1:3) screeded bed 130.00 m2 15000 1,950,000.00
2 High quality wall tiles(200x400mm) 340.00 m2 2400 816,000.00
POP
1 Pop ceiling finishing of approved design/
cornices. 292.00 m2 2700 788,400.00
WINDOWS
Tower Casement windows with aluminium pipe
buglary proofing & mosquito net
1 size 600x750mm 8.00 no 12000 96,000.00
2 size 750x1500mm 31.00 no 31000 961,000.00
3 Window dressing (internal & external) 410.2 m 200 82,040.00

Roof and Installations carried to summary 6,887,440.00

SUMMARY
SUB-STRUCTURE WORK 4,789,710.00

SUPER STRUCTURE (GROUND FLOOR) 5,240,532.00

SUPER STRUCTURE (FIRST FLOOR) 3,128,050.00

ROOF AND INSTALLATIONS 5,046,080.00

FINISHES 6,887,440.00

SUMMARY 25,091,812.00

Você também pode gostar