Você está na página 1de 15

PROJECT : PROPOSED TWO APARTMENT WITH ROOFDECK

SUBJECT : BILL OF MATERIALS


OWNER

SCOPE OF WORKS
ITEM PARTICULARS QTY UNIT TOTAL AMOUNT

GENERAL CONSTRUCTION WORKS

A EARTHWORKS 13,100.00
Site clearing and Excavations 1 lot 11,100.00
Layout and Batten board Staking 2,000.00

B STEEL AND REINFORCEMENTS WORKS 92,144.00


Footings & Columns
16 mm. dia. 12 pcs. 314.00 3,768.00
16 mm. dia. 64 pcs. 314.00 20,096.00
Beams
12 mm. dia 48 pcs. 175.00 8,400.00
16 mm. dia. 70 pcs. 314.00 21,980.00
Slabs and Dowels
12 mm. dia 120 pcs. 175.00 21,000.00
10 mm. dia. 120 pcs. 130.00 15,600.00
Tie Wires #16 10 kg. 130.00 1,300.00

C CONCRETE AND MASONRY WORKS 229,695.00


Cement 701 bags 175.00 122,675.00
Sand 51 m³ 500.00 25,500.00
3/4 Crushed Gravel 54 m³ 750.00 40,500.00
4" CHB 1300 pcs. 9.00 11,700.00
5" CHB 2932 pcs. 10.00 29,320.00

D FORMS AND FORMWORKS 48,450.00


2"x3" Coco Lumbers 150 pcs. 125 18,750.00
2"x2" Coco Lumbers 120 pcs. 150 18,000.00
Plywood Forms Panelling 15 780 11,700.00

G PLUMBING FIXTURES & INSTALLATION 72,810.00


Faucet 13 pcs. 150.00 1,950.00
Shower Valve 4 pc. 150.00 600.00
Floor Drain 12 pcs. 75.00 900.00
Shower Drain 8 pc. 75.00 600.00
Kitchen Sink 4 pcs. 1,500.00 6,000.00
Water Line (Complete System) 2.4 Is. 8,500.00 20,400.00
Sewerage System 2.4 Is. 900.00 2,160.00
Storm Drainage System 2.4 Is. 9,000.00 21,600.00
Water Closet 4 pcs. 1,800.00 7,200.00
Lavatory 4 pcs. 1,500.00 6,000.00

PROJECT : PROPOSED TWO STOREY APARTMENT WITH ROOFDECK


SUBJECT : BILL OF MATERIALS
OWNER

SCOPE OF WORKS
ITEM PARTICULARS QTY UNIT TOTAL AMOUNT

H. ELECTRICAL WORKS 20,000.00


Outlet Complete 13 Set s 200.00 2,600.00
Lighting Outlet 14 Sets 200.00 2,800.00
Wires and Cables
#12 mm THWN 2 box 3,200.00 6,400.00
Switch 11 200.00 2,200.00
Circuit Breakers/Panel Board 4 1,500.00 6,000.00

I. DOORS AND WINDOWS 65,400.00


Main Door - Panel Type Door 4 sets 2000 8,000.00
Bedroom Doors - Flush Type Door 3 sets 4100 12,300.00
Toilet Door - PVC Door QDE Paint Finish 4 sets 2100 8,400.00
Locksets/Doorknob 10 pcs. 150 1,500.00
All Windows - Steel Casement with Clear Glass Panels 11 sets 3200 35,200.00

J. PAINTING WORKS 21,750.00


Exterior and Interior Walls (semi-gloss paint finish) 10 gal 900.00 9,000.00
Exterior and Interior Ceilings (flat paint finish) 10 gal 1,100.00 9,900.00
Doors Paint finish (QDE paint finish) 2 galons 525.00 1,050.00
Steel Casement Windows (QDE paint finish) 2 galons 900.00 1,800.00

K. TILE WORKS 62,155.00


Toilet Wall and Floors (Ceramic Tile Finish)
30 x 60 cm. Glazed Wall Tiles 435 pcs 35 15,225.00
30 x 30cm. Unglazed Floor Tiles 91 pcs. 30 2,730.00
Living, Dining, Bedroom (Vinyl Tile Finish) 300 pcs 130 39,000.00
Kitchen Counters (Mosaic Tile Finish) 40 pcs. 130 5,200.00

TOTAL AMOUNT 625504


OTAL AMOUNT

OTAL AMOUNT
: PROPOS PROJECT : PROPOS PROJECT
: BILL OF SUBJECT : BILL OF SUBJECT
: MR. & M OWNER : MR. & M OWNER
: PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS
: BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF
: MR. & M OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M
PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT
SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT
OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M OWNER
: PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS
: BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF
: MR. & M OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M
PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT
SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT
OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M OWNER
: PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS
: BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF
: MR. & M OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M
PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT
SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT
OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M OWNER
: PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS
: BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF
: MR. & M OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M
PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT
SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT
OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M OWNER
: PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS
: BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF
: MR. & M OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M
PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOS PROJECT : PROPOSED TWO STOREY HOUSE
SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF SUBJECT : BILL OF MATERIALS
OWNER : MR. & M OWNER : MR. & M OWNER : MR. & M OWNER : MR. & MRS. ARNOLD SANGUIR
POSED TWO STOREY HOUSE
L OF MATERIALS
& MRS. ARNOLD SANGUIR

Você também pode gostar