Escolar Documentos
Profissional Documentos
Cultura Documentos
C a p a c it y fo r a ll 2 50 0
g e n e ra to rs in th e 2 00 0
G r id S ys te m
1 50 0
fo r F Y0 5 0 6
MW
1 00 0
50 0
TJPS
TNB Prai
TTPC
PDP
PGPS
TNBJ
G SP
CBPS
Panglima
Paka
GB3
Serdang
Hydro
SEV
KEV
Gelugor
Teluk Ewa
Prai Power
Powertek
Pahlawan
YTL
P la n t
M arke t Sh a r e - Ca p a city
M a rk e t S h a re o f
TNB
C a p a c it y b e t we e n 48%
T NB P la n ts & IP P
IPP
P la n ts 52 %
THE 3 GENERATIONS OF PPAs/IPPs
Shareholders
Agreement
Concession
Agreement Other
Agreements
POWER PURCHASE
AGREEMENT
TYPICAL PPA TERMS
• Definitions and Interpretation
• Term
• Conditions Precedent
2 Conditions Precedent to Effectiveness of PPA
2 Conditions Precedent to Commencement of Generation
(IOD)
2 Conditions Precedent to Commercial Operations (COD)
2 Critical Milestones
• Pre Operations
2 Design & Construction, Initial Operations, Interconnection
Facility, Insurance, Maintenance Reserve
• Sale & Purchase
2 Test Energy, Availability and Capacity, Energy
TYPICAL PPA TERMS (cont.)
• Dispatch
2 Annual Schedule Available Capacity, Scheduling, Dispatch
and Tests,
2 Billing & Payment
2 Fuel, Start-up, CRF, FOR, VOR
• Additional Legal Elements
2 Force Majuere, Change-in-Law, Default and Termination,
Step-in Rights, Liquidated Damages
HOW IPP PROPOSALS ARE ANALYSED
External Process
• IPP submits unsolicited proposals
• Deliberation by Privatisation Committee of EPU
2 Discussion on technical commercial matters with MOF,
MEWC, EC, TNB
• Offer made to IPP
• Cabinet Approval obtained
• Finalisation of the PPA
HOW IPP PROPOSALS ARE ANALYSED
(cont.)
Internal Process
• Specialized sub-groups
• Technical (Power Plants, Heat Rate & Start-ups, System
Technical Requirements, Interconnection Facilities
(Transmission Equipment))
2 Fuel
• Financial and Commercial
• Legal
• Appoint a Technical Officer
• Technical Proposal
2 Check against standard practice
2 Accepted benchmarks
2 Sources - Internal (TNBE, TNB Fuel, TNBT, System
Planning (SPD & OPP)), External (SKM, PowerGen, etc.)
HOW IPP PROPOSALS ARE ANALYSED
(cont.)
Internal Process
• Financial and Commercial
2 Project Cost Breakdown
2 Verification of operational assumptions - availability, heat
rate, fuel consumption
2 Accepted benchmarks
2 Current practises
2 Sources - Other financial proposals, Financing Parties
(Bank America, Citibank, MacQuarie, ANZ Bank)
PPA PROCESS
IPP submit project
proposal to GOM
TNB management
GOM to inform
issues directive to
GOM approve IPP TNB to commence
EPU to commence
proposal discussion &
discussion /
negotiation
negotiation
Supply/ Demand
input by TNB
Operationalization
of Agreement
Settlement of
Invoices
End
PPA PROCESS (cont.)
Government - EPU, MOEWC, EC, Privatization Committee
Advisors - (Legal, Technical, Financial)
IPPs
Power Purchase
Agreement
OFFTAKER
PRODUCT
PAYMENT
SCHEDULING & DESPATCH
CHANGE IN LAW
FORCE MAJEURE EVENTS
DEFAULT AND TERMINATION
INDUSTRY RESTRUCTURING
PRODUCT
- Unsanctioned rescheduling of
- This results in GSO having to Outages by the IPP has dire
despatch other units in the commercial consequences on
System which costs are the IPPs (Forced Outage)
borne by TNB
- Failure to comply with a
- No immediate consequence Despatch Instruction will result in
if IPPs fails to make a penalty be imposed on the
available the capacity as IPPs
declared
CHANGE IN LAW