GENERAL SCHEDULE FOR CIVIL WORKS PACKAGE

PLTU GORONTALO 2X25 MW


MAIN CONTRACTOR : PT. REKADAYA ELEKTRIKA
SUB CONTRACTOR : PT. WIKA REKAYASA KONSTRUKSI
2014
ID Task Name Feb '14 Mar '14 Apr '15 May '15 Jun '15 Jul '15 Aug '15 Sep '15 Oct '15 Nov '15 Dec '15 Jan '15 Feb '15 Mar '15 Apr '16 May '
1 PLTU
2 Contract Siged 3/28
3 Millestone
4 Effective Date 3/28
5 Steel Structure Erection 9/10
6 TOC 3/10
7 Civil Engineering Design
8 Earthworks
9 Turbin Foundation & Structure
10 Boiler & Auxiliary Foundation
11 Power Block Foundation & Structure
12 CW Intake & Discharge Structure
13 Chimney Foundation & Structure
14 BOP Foundation & Structure
15 Coal Storage & Facilities
16 Administration Building
17 Miscellienous Building
18 150 kV Switchyard Foundation & Structure
19 Substation Building
20 Site Finishing (Road, Drains, Fence, etc)
21 CONSTRUCTION
22 Preparation Works
23 Mobilitation
24 Survey & Setting Out
25 Site Facilities
26 Power Block Area

Task Inactive Milestone Finish-only


Split Inactive Summary External Tasks
Milestone Manual Task External Milestone
Project: schedule
Date: Sat 4/13/19 Summary Duration-only Progress
Project Summary Manual Summary Rollup Deadline
External Tasks Manual Summary
External Milestone Start-only

Page 1
GENERAL SCHEDULE FOR CIVIL WORKS PACKAGE
PLTU GORONTALO 2X25 MW
MAIN CONTRACTOR : PT. REKADAYA ELEKTRIKA
SUB CONTRACTOR : PT. WIKA REKAYASA KONSTRUKSI
2014
ID Task Name Feb '14 Mar '14 Apr '15 May '15 Jun '15 Jul '15 Aug '15 Sep '15 Oct '15 Nov '15 Dec '15 Jan '15 Feb '15 Mar '15 Apr '16 May '
27 Turbin Foundation and Structure
28 Unit 1
32 Unit 2
36 Boiler & Auxilary Foundation
37 Unit 1
40 Unit 2
43 ESP Control & Blower Room
44 ESP Foundation
45 ID Fan Foundation
46 Chimney Foundation
47 Architecture Turbine Generator House
48 CW Intake & Discharge Structure 3/28
49 Siphon Well 3/28
50 Sea Water Pump House 3/28
51 Discharge Channal 3/28
52 Ash Handling
53 Ash Clarifier
54 Ash Yard
55 Bottom Ash Silo Foundation
56 Fly Ash Silo Foundation
57 Settling Pond

Task Inactive Milestone Finish-only


Split Inactive Summary External Tasks
Milestone Manual Task External Milestone
Project: schedule
Date: Sat 4/13/19 Summary Duration-only Progress
Project Summary Manual Summary Rollup Deadline
External Tasks Manual Summary
External Milestone Start-only