Activity Description Immediate predecessor

A Calculate how many system needed none


B Evaluate how many stack and vessels needed A
C Pluck and place the system in container A
D Pluck and place the container in operation site C
E Install wiring and pipeline for a system A,B
F Install polution control system E
G Inspect and test E,F

A C F

E Finish
Start

B D G
Finish