Escolar Documentos
Profissional Documentos
Cultura Documentos
Improvement
Case study (Nazareth)
MICHAEL YIMER
ABSTRACT
The main purpose of this paper is to study the reliability due to the employment of distributed generations (DG) integrated to distribution
system. The system under this study is from NAZRETH substation Feeder-1 that is a part of EEP’s distribution system. The distance of
distribution line and location of load that are parameter of Feeder-1 is simulated using digital simulation and electrical network calculation
program (Dig SILENT) and ETAP.to analyze the impact of reliability with the installation of DG into the distribution system specifically
Feeder-1. SAIFI SAIDI CAIDI ASAI ASUI ENS(MWh) AENS and EIC are assessed as index of reliability by comparing them between the
base case (no DG) and the case that DG connected to the distribution system by assuming different scenarios. The results can be summarized
by focusing on location of DG, the capacity of DG and the distance of load which are factors able to impact the reliability of the system.
Keywords: Reliability; Distributed Generation; Interruption Cost; Distribution System; SAIFI; SAIDI; CAIDI; ASAI; ASUI; ENS(MWh);
AENS; EIC.
1
II. DISTRIBUTION RELIABILITY
INDICES CAIDI
UN i i i
N I i 0
N 8760
I i
1. System Average Interruption Frequency Index Where
(SAIFI): It is the average frequency of sustained λ is the failure rate at load point i,
interruptions per customer over a predefined area. It is Ni is the number of customers found at load point i
the total number of customers interruptions divided by No is total number of customer interruptions
the total number of customers served. Ui is the annual outage time at load point i
SAIFI
Ni i i
N I i
IV. LOAD OR ENERGY-ORIENTED
2. System Average Interruption Duration Index (SAIDI): INDICES
It is commonly referred to as customer minutes of
interruption or customer hours, and is designed to 1. Energy Not Supplied Index (ENS): This index represents
provide information as to the average time the the total energy not supplied by the system. And it is
customers are interrupted. It is the sum of the given by
restoration time for each interruption event times the
number of interrupted customers for each interruption
event divided by the total number of customers. ENS i La (i )U i
SAIDI
UN i i i
2. Average Energy Not Supplied Index (AENS): This index
represents the average energy not supplied by the system
N I i i
CAIFI
i
Ni In this thesis, all the reliability indices mentioned above were
taken for comparison of reliability indices after installation of
I
N0 DG.
4. Customer Average Interruption Duration Index
(CAIDI): It is the average time needed to restore
service to the average customer per sustained
interruption. It is the sum of customer interruption
durations divided by the total number of customer
interruptions.
V. METHODOLOGY
TABLE-1I DISTRIBUTION TRANSFORMER CHARACTERISTICS From Fig.1, it can be seen that there are a number of
distribution transformers and each transformer is give a
Transformer Capacity (KVA) Voltage rating Vector group general load to simulate customers connected to the feeder.
3-phase 315 15/0.4 KV Dyn5 Load flow has been done for the feeder under study and six
3-phase 200 15/0.4 KV Dyn5 branches are investigated for voltage violation and power loss
3-phase 100 15/0.4 KV Dyn5
3-phase 50 15/0.4 KV Dyn5
out of which 3 are find to be having a relatively higher values,
3-phase 25 15/0.4 KV Dyn5 the branches with the highest deviation are shown in fig.1&
2.the result of the load flow is summarized in the graph below
Besides this there is already a 0.6 Mvar capacitor and a for power loss and minimum voltage.
booster transformer with a capacity of 5000Kva with a As can be seen from the chart branches 4, 5 & 6 shows the
voltage rating of 12.5kv/15 kv installed in the distribution least amount of variation both for voltage and power loss
side of the feeder which implies that there is no need to consider these branches
for connection of DG.
Min Voltage(PU) To study the reliability, simulations were performed with
0.95 various changes as follows:
A number of DGs with different capacity are employed
0.9 depending on the load requirement of the specific branch
which is selected based on load flow analysis.
0.85 The location of distributed generators are designated on any
0.8
bus of distribution system and installed between buses of
distribution system.
0.75 The capacity of DG required for the braches of the feeder are
0.45 MVA, 0.4 MVA, and 0.35 MVA at branch 1, branch 2
0.7 and branch 3 respectively.
Fig.3 min voltage for various branches The main purpose of this section is to evaluate effects of DG.
To achieve this goal, three individual scenarios are presented
for which reliability indices are evaluated. These scenarios
are as follows;
Power Loss(MW)
SCENARIO 1: each individual DG is connected to the
0.0007 specific branch by itself
0.0006
0.0005 SCENARIO 2: combination of two DGs is consider by
0.0004 connecting them to their specific branch
0.0003
0.0002 SCENARIO 3: all the DGs are connected at the same time to
0.0001
their specific branch.
0
Connection of each DG is made through circuit breaker
which can be used to disconnect the feeder in case fault and
maintenance.
ASAI*100
CAIDI*100
SAIDI
SAIFI
DG base
DGB-1 DGB-2 DGB-3 DGB-1&2 DGB-1&3 DGB-2&3 DGB-123 case
AENS 11.7416
14.6667 14.3562 15.0048 12.8107 13.3727 13.2269 16.3808
(MW hr. / customer.yr)
ASAI(pu) 0.9708 0.9712 0.9711 0.9743 0.9742 0.9745 0.9773 0.9674
ASUI(pu) 0.0292 0.02878 0.02891 0.02571 0.02585 0.02555 0.02273 0.03262
CAIDI
(hr. / customer 2.202 2.236 2.266 2.452 2.491 2.510 2.856 2.048
interruption)
EENS 774.943
968.003. 947.509 990.317 845.504 882.600 872.976 1081.129
(MW hr. / yr.)
SAIDI
256.0412 252.0826 253.2540 225.2472 226.4187 223.7753 199.1339 285.7339
(hr. / customer.yr)
SAIFI
116.2611 112.7505 111.7499 91.8785 90.8779 89.1415 69.7349 139.4945
(f / customer.yr)
Result of ETAP
1200
1000
800
600
400
200
0
DGB-1 DGB-2 DGB-3 DGB-1&2 DGB-1&3 DGB-2&3 DGB-123 DG BASE CASE
AENS ASAI(pu)*100 ASUI(pu) CAIDI*100 ECOST($ / yr.)/1000 EENS(MW hr. / yr.) SAIDI SAIFI
Fig.8 (b) a single line diagram of Nazareth feeder 1after installation of DG using ETAP
IX. CONCLUSIONS X. REFERENCES