Phase 1 Project
Refinements
Executive Summary
Spring 2019
Contents
1 Background
2 Project history
8 Agency coordination
9 Stakeholder involvement
15 Next steps
Background
This Executive Summary (Summary) augments the full I-405 Bus Rapid Transit Phase 1 Report.
*Construction for most of the BRT projects is expected to begin by 2023 and be completed by 2024.
Construction of some elements may begin before 2023, and others may occur after service starts in 2024.
Downtown Everett
Everett
Link Light Rail Everett
2036
Future service:
SR 526/
Everett–Seattle–West Seattle 2024
Evergreen
Mukilteo SW Everett
Redmond–Seattle–Mariner
Industrial Center
Ballard–Seattle–Tacoma South Everett
SR 99/Airport Rd
Issaquah–Bellevue–South Kirkland
Mariner 2036
Tacoma Dome–Tacoma
Community College
In service: Ash Way
Univ. of Washington–Angle Lake
West Alderwood
Tacoma Dome –Theater District 2024
Lynnwood
Sounder Commuter Rail 2024
Edmonds
City Center
2024
Canyon Park
Future service:
Mountlake
DuPont–Lakewood Terrace Bothell
Lake Kenmore
In service: Shoreline North/185th Forest 2024 Woodinville
Park
North Line (Everett–Seattle)
South Line (Lakewood–Seattle) Shoreline South/145th
Brickyard
2031 NE 130th
Bus
2021 Northgate Kingsgate/Totem Lake
Future service:
Bus Rapid Transit (BRT) Kirkland NE 85th
Roosevelt 2024 Downtown Redmond
Ballard 2035
In service: SE Redmond
Interbay U District 2041
ST Express bus
Smith Cove South 2023 Redmond Technology
(service re-evaluated annually) University of Kirkland
Seattle Center Washington Overlake Village 2024
South Lake Union Evergreen Bel-Red/130th North
Denny Point Spring District/120th Sammamish
New station or bus facility Capitol Hill
Bellevue Wilburton
Added parking Seattle Westlake Downtown
Station improvements University Street Bellevue
Midtown East Main
Pioneer Square
Major transfer hub International District/Chinatown South South
& King Street Bellevue Richards Rd Sammamish
Existing station or bus facility Judkins Mercer
Stadium Park Island
Existing parking 2030 Eastgate
Alaska Mount
Provisional light rail station Junction Beacon Baker Lakemont Issaquah
De n
e
DO
dg
alo
Hill Highlands
SO
lri
Av
Angle Lake
S 272nd
2024
Federal Way
Tacoma 2023
Auburn
Stadium District S 4th South
Old City Hall Federal Way
Tacoma General Theater District
6th Ave Convention Center
Tacoma 2039 Hilltop District Union Station
Community S 25th
College 2022
St orth
Un s
Sp ion
ns e
ph
Ste arl
n
Ai ragu
ve
se
2030
Pe
East Fife
w
Jo
Tacoma Tacoma
Dome
South Tacoma 2022 2022 Sumner
Puyallup
Lakewood Bonney Lake
Towne Center
South Hill
Lakewood
Tillicum
Transit speed and Transit priority improvements, Entry and exit through
reliability including business access and multiple doors, level with
transit lanes, bus queue jumps, the station platform
and transit signal priority
Unique station design Unique brand identity for Dedicated fleet of BRT buses
buses and stations
These features will help riders avoid traffic congestion and enjoy more frequent and reliable service.
SR 522/NE 145th
BRT will connect
communities from Shoreline NE 44th
to Woodinville via NE 145th
Street, SR 522 and the transit
center at UW Bothell/Cascadia
College. The route has nine BRT Tukwila
Burien International South Renton
stations and an expanded transit Transit Blvd Transit Center
center at UW Bothell/Cascadia Center
518
College. It will connect to
2024 167
Link light rail at the Shoreline
South/145th Station and to
Map of the SR 522/ NE 145th and I-405 BRT representative projects.
I-405 BRT in Bothell.
Bellevue Bellevue
Downtown Transit Center
Seattle
NE 44th
Tukwila
Burien International South Renton
Transit Blvd Transit Center
Center
518
2024 167
BRT station
design
Sound Transit will continue to
develop the BRT station design
during the next few years. The
rendering, left, shows the general
station design concept. While
stations will have a consistent
look and feel throughout the
Sound Transit BRT system,
station design at each station
location will vary based on
ridership and site conditions.
4
WE ARE HERE!
Sound Transit also works closely with King County Metro, Community Transit and other local and regional
transportation agencies to determine routes, ensure fast and seamless transfers, and provide integrated transit
services that best serve the needs of the community.
Sound Transit will continue to coordinate with our transit partners to integrate I-405 BRT with local and regional
transit service.
2018 2019
MAR APR MAY JUN JUL AUG SEP OCT NOV DEC Q1
Project
Identify Range of Project Refinements Identify & Evaluate Range of Project Refinements Propose and Recommend Project
Milestones
Community
Updates &
Stakeholder Early Stakeholder Corridor-wide
Process Station Area
Interviews Event: Project Outreach
Launch
Ongoing
Outreach Briefings, fairs and festivals, social media updates, website updates, e-newsletters, community events
Activities
Interagency
Group
Elected
Leadership
Group
Kickoff Refined
Meeting Project
Corridor
Executive
Advisory Ongoing coordination with I-405/SR 167 Corridor Executive Advisory Group
Group
Sound Transit plans, builds, and operates regional transit systems and services to improve mobility for Central Puget Sound. 401 S. Jackson St. l Seattle, WA 98104-2826 l 1-800-201-4900 / TTY Relay: 711 l brt@soundtransit.org l soundtransit.org
Advisory Group
The I-405/SR 167 Corridor Executive Advisory Group The public
(EAG), made up of state and local elected officials,
Sound Transit engages the public to gather input on
and representatives from federal and regional transit
corridor-wide and local issues to ensure the priorities of
agencies, has been advising WSDOT on I-405 corridor
local communities are being heard and considered along
improvements since 1999. Sound Transit regularly
the corridor. During Phase 1, the project team conducted
updated the EAG about the I-405 BRT project in 2018.
the following outreach activities:
• 2 in-person open houses
• 2 online open houses
• 13 community briefings
• 6 fairs and festivals
• 2 project mailings
NB: Northbound
NB: Northbound SB: Southbound
SB: Southbound EB: Eastbound
EB: Eastbound WB: Westbound
WB: Westbound TSP: Transit
TSP: Transit Signal
Signal Priority
Priority BRT:
BRT: Bus
Bus Rapid
Rapid Transit
Transit ETL:
ETL: Express
Express Toll
Toll Lane
Lane
520
I-405 BRT
Puget
Project Elements BRT in Existing Express Toll Lanes
Bellevue
BRT in FutureTransit
Express Toll Lanes
Station Improvement
Sound Center
Proposed Refined ; BRT station at existing BRT in General Purpose Lanes Corridor Improvement
Bellevue Transit CenterExisting
with Bus On Shoulder
Project connections to light rail 0 1 2
Proposed Bus On Shoulder (Project Refinement) Miles
519
90
Lake
Washington
; WB lane reconfiguration
and approach widening to
extend merge area
509
; Revised in-line station and interchange by WSDOT with
local transit speed and reliability improvements NE 85th Street
; Spot transit speed and reliability improvements and
improved ped/bike connections along NE 85th Street
520
Bellevue
Puget Transit
Sound
; BRT station at existing Center
Bellevue Transit Center with
connections to light rail
519
90
Lake
Washington
; BRT station at existing Burien Transit Center ; BRT station on SR 518 with
; Transit-only WB entrance to Burien Transit Center pedestrian bridge to LRT station
NB: Northbound SB: Southbound EB: Eastbound WB: Westbound TSP: Transit Signal Priority BRT: Bus Rapid Transit ETL: Express Toll Lane
Next steps
Sound Transit will continue its work on all Proposed Refined Project elements with communities and stakeholders along
the corridor, transit partners, the IAG and the ELG in Phase 2 - Conceptual Engineering and Environmental Review during
2019 and into early 2020. The following next steps will also be part of the Phase 2 process: