Escolar Documentos
Profissional Documentos
Cultura Documentos
0 TECHNICAL DESCRIPTION
The additional compressor unit to be located within the existing BS-3 site will include the
following:
a) Caterpillar G3608TALE natural gas reciprocating engine with a site rating of 1823
kW (2445 BHP)
(a) Approximately 70 metres of new 323.9 mm (12.75 inches) main gas inlet and outlet
piping to connect the new unit to the existing BS-3 piping.
(c) Cooler and associated equipment, unit isolation valves, unit blowdown valves, unit
purge valves and associated piping and fittings, instrumentation, and electrical and
control equipment.
(d) A new compressor unit control panel (“UCP”) to monitor and control the new
compressor unit. The UCP will interface to an existing control panel and will house
a local human machine interface. The unit will be controlled and operated from the
existing control room.
(e) A lube oil system to provide lube oil to the new compressor unit. This system will
consist of an oil storage vessel (contained within the compressor skid), oil transfer
pump, oil cooler, oil vent demister system, isolator valves, and associated piping
and fittings, instrumentation, and electrical and control equipment.
-1-
2.2 Specifications, Codes and Standards
The Project will be designed, constructed and tested in accordance with the provisions of the
National Energy Board Act (the “NEB Act”), the Onshore Pipeline Regulations, 1999 (“OPR-
99”), Westcoast’s specifications and the following codes and standards:
-2-
2.2.1 Station Main Gas Mechanical Design Parameters
The main gas piping will be designed, constructed and tested in accordance with CSA Z662-11
including Clause 16 for Sour Service requirements and OPR-99. The maximum design stress
levels to be used are those permitted by the applicable codes, standards and regulations. The
mechanical design parameters, including maximum operating pressure (“MOP”) for the new
facilities, are shown in Table 2-1 below.
Description Value
MOP – Station Piping for New Unit 6895 kPag (1000 psig)
The auxiliary and utility piping within the new facilities will be designed, constructed and tested
in accordance with the requirements of ASME B31.3-2010 subject to receiving approval of the
requested exemption in Section 2.4.2, Non-destructive Examination. The maximum design
stress levels to be used are those permitted by the codes and standards.
-3-
Based on the anticipated loads, the auxiliary and utility system for the new facilities will be
designed to the operating parameters defined in Table 2-2 below.
General
The Project will be designed to have minimal underground piping. All buried piping will be
protected from external corrosion by using an external coating system supplemented with
impressed current cathodic protection. The existing cathodic protection system will be
augmented, if required, once the new facilities are installed and the necessary testing
completed. Above-ground steel materials will be protected from external corrosion by applying
a coating system.
Coating
External coating for buried service will be in accordance with Westcoast Specification
ACL-GB.5, Approved Coating List – Below Ground, August 6, 2012. It will be applied in
accordance with Westcoast Specification CS-PC1.5, Field Application of Liquid Epoxy Coating,
November 24, 2011.
-4-
Painting
Above-ground piping will be prepared, primed and painted in accordance with Westcoast
Specification ACL-AG, June 21, 2012, Approved Coating List – Above Ground.
Currently raw gas is delivered to the inlet of BS-3. The gas is routed through a gas-to-gas
exchanger where the inlet gas cools gas discharging from the booster compressors. The inlet
gas from the exchanger is then routed to a slug-catcher where liquids are removed and then to
booster compression which consists of three gas driven reciprocating compressors. The
existing reciprocating compressor units require frequent regular maintenance and are routinely
taken out of service. The addition of a fourth gas driven reciprocating compressor will not
change the booster station process, but will ensure that three compressor units are operating at
all times. Preliminary Piping and Instrumentation Diagrams (“P&IDs”) for the Project are
presented in Appendix 4 of the application.
The control system for the Project will be a Programmable Logic Controller-based system with
input/output modules. Monitoring and control inputs will be from the Unit and Station Control
system and a personal computer based operator console in the BS-3 control room. The control
system will perform both facility control and safety shutdowns. The facility control will include
controls for unit speed, discharge pressure and temperature. The pressure controller will
control unit speed to bring the measured pressure to control set points and also to prevent
overpressure. The discharge temperature control will effect action on the aerial cooler fans and
gas/gas exchanger bypass valves to achieve the operating set point. Emergency shutdown
pushbuttons will permit a total facility shutdown regardless of the state of the control system.
There will be an auto unit shutdown on high temperature, high pressure or high vibration.
Fire detectors, combustible gas detectors and H2S detectors in the compressor building will be
continuously monitored by the control system. The activation of any one of these detectors will
trigger system alarms, which will activate horns and area beacon lights to alert personnel of
potential danger. The control system will activate appropriate block and blow-down functions
based on the level of alarm. Ventilation equipment will be activated for gas and H2S detection,
but will shut down for fire.
-5-
Fire detection at the new compressor building will include flame detection via UV-IR detection.
Combustible gas detection will be by means of electro-catalytic detection. These devices will be
connected to the main station control system, which will indicate the appropriate alarms and
shutdowns according to the Compressor Station Shutdown Key drawings.
A hazard and operability study (“HAZOP”) will be conducted during the detailed design phase
of the Project. A site safety assessment will be performed prior to commencement of
construction.
2.3 Materials
All valves, fittings and flanges will comply with the requirements of CSA-Z245.15-09, CSA
Z245.11-09 and CSA Z245.12-09, respectively, for Sour Service.
All auxiliary and utility piping will be ASTM A333 Grade 6 or ASTM A106 Grade B seamless
material having a minimum yield of 241 MPa. The main gas pipe to be used on this Project will
conform to Westcoast Specification SP-51-33, Rev. 5, November 29, 2006, Piping Materials for
CSA Z662-11 Compressor Stations and Meter Stations Sour Natural Gas Service, and CSA
Z245.1-12 or ASTM Specifications.
2.4 Joining
All joining for the Project will be conducted in accordance with the requirements of CSA Z662-
11, ASME B31.3-2010, and 2011 ASME VIII Division 1.
The main gas piping within the compressor facilities will be designed, constructed and tested in
accordance with the requirements of CSA Z662-11. The maximum design stress levels and the
types and minimum extent of non-destructive examination (“NDE”) to be used are those
permitted by the codes and standards.
-6-
Auxiliary and utility piping will be designed and constructed in accordance with the requirements
of ASME B31.3-2010. Westcoast will test to the maximum design stress levels and the types
and minimum extent of NDE as permitted by the codes and standards, subject to receiving
approval of the requested exemption set out in the Exemptions/Relief Requested section of the
Online Application System form, summarized below:
Section 344 of ASME B31.3-2010 allows the following as acceptable NDE methodologies:
• visual examination
• magnetic particle examination (MP)
• liquid penetrant examination (LP)
• radiographic examination (R)
• ultrasonic examination (U)
The general requirements for the piping to be designed to ASME B31.3-2010 requirements are
summarized in Table 2-3 below. The Project piping specifications allow the use of either ASTM
A106 Gr. B or A333 Gr. 6 material for all of the above service classes. The maximum allowable
stress level for these materials for normal operating temperatures is 138 MPa. Code allowed
maximum stress levels would not be exceeded for any operating conditions.
-7-
Table 2-3 Auxiliary and Utility Piping Requested Non-destructive Examination Testing
Requirements
Design Design
Service Pressures Temperatures Joint Type Minimum NDE
(kPag/psi) (°C)
Fuel Gas 1 034/150 -40/65 Butt weld 10% R
Socket weld 10% MP
Visual Inspection
Instrument/Utility 1 034/150 -20/65 Butt weld 10% R
Air Socket weld 10% MP
Visual Inspection
Lube Oil Piping 206/30 -29/120 Butt weld 10% R
Socket weld 10% MP
Visual Inspection
Low/High Pressure 1 965/285 -40/65 Butt weld 10% R
Flare Piping Socket weld 10% MP
Visual Inspection
2.5 Construction
The successful contractor will be responsible for the health and safety of all personnel employed
by it or its subcontractors, as well as any other personnel at the Project site who are connected
with the contractor’s construction activities.
Westcoast will develop and submit a Project-specific Construction Safety Manual to the NEB in
accordance with section 20 of the OPR-99.
The successful contractor will supply Westcoast with a site specific construction security plan for
approval prior to the commencement of any site work. The site specific security plan will be
-8-
reviewed to ensure it meets or exceeds the requirements of the Westcoast Operations Security
Plan and the requirements of the NEB Proposed Regulatory Change 2010-01.
All piping will be tested in accordance with OPR-99 and all other applicable codes and
standards. A detailed Pressure Testing Plan will be developed during the detailed engineering
phase of the Project.
Westcoast will obtain the necessary permits required in respect of the use and disposal of water
for test purposes.
Auxiliary and utility piping will be pressure tested in accordance with Westcoast Specification
SP-50-09, Rev. 2, October 26, 2011, Field Pressure Testing. Main gas piping will be pressure
tested in accordance with Westcoast’s Specification CS-TST.1, Rev. 1, September 18, 2012,
Pipeline Construction – Pressure Testing.
Westcoast is requesting an exemption from the provisions of subsection 47(1) of the NEB Act
exempting the auxiliary and utility systems set out in Table 2-4 below from submission to the
Board as part of the leave to open application required for the Project. The exemption of these
auxiliary and utility systems from the leave to open requirement will not compromise the
environment or the safety of Westcoast employees and the public as the systems are low
pressure, low volume auxiliary and utility systems designed and tested in accordance with the
applicable codes and standards. This exemption will allow Westcoast to commission the
auxiliary and utility systems and to perform preliminary tests on the compressor unit in a timely
manner prior to the in-service date of the main facilities.
-9-
Table 2-4 – Leave to Open Exemption Table
Design Pressure Design Temperature
Service
(kPag/psig) (°C)
Instrument/Utility Air 1 034/150 -20/150
Fuel Gas Auxiliary 1 034/150 -40/65
Lube Oil 206/30 120
Atmospheric vents 1965/285 -40/65
A quality assurance program will be used for the engineering, procurement and construction of
the Project. The quality assurance program will ensure that the supplied products and services
conform to the specified requirements during design/development, production and installation.
Detailed design completed to date follows the program for the Project. Completion of the
engineering will follow the quality assurance program used by the engineering consulting
firm. Supplied products will follow the manufacturer’s quality program. Construction will follow
the quality assurance program used by the construction contractors. Westcoast
representatives will periodically audit the programs of the engineering consulting firm and the
construction contractors.
The Project’s major milestones are set out in Table 2-5 below.
- 10 -