Escolar Documentos
Profissional Documentos
Cultura Documentos
January
Prepared by:-
2014
3.4.1. Temperature................................................................................................................................. 42
The proposed project involves the following construction works: ....................................... 116
7.2. SERVICES OF ABC TECHNO LABS INDIA PRIVATE LIMITED ................................. 170
7.3. Sectors Accredited by National Accreditation Board for Education and Training
(NABET) ................................................................................................................................................... 172
Table 3-1 Baseline Environmental Components & their Attributes, Frequency &
Monitoring Methodology .......................................................................................................................... 38
Table 4-1 Activity-Impact Identification Matrix for Construction Phase of the Proposed
Project ........................................................................................................................................................... 109
Table 4-2 Activity – Impact Identification Matrix for Operation Phase of the Proposed
Project ........................................................................................................................................................... 111
Table 5-1 Potential Impacts on Noise Environment due to the Proposed Facility ......... 135
Table 5-2 Impact and Mitigation Measures for Noise Emissions ........................................... 137
Table 5-3 Odour Generation Sources and its Design Measures:............................................. 139
Table 5-4 Environmental Management Plan for Pre-Construction Phase .......................... 153
Table 5-5 Environmental Management Plan for Construction Phase - Sewage Treatment
Plant ............................................................................................................................................................... 155
Table 5-10 Cost Estimate for Environmental Management Plan ........................................... 168
LIST OF FIGURES
Figure 2-9 Demarcation Map of the Project Site (CRZ MAP) ...................................................... 23
Urban development schemes in the notified areas are governed by the Master plan of
Chennai Metropolitan CMDA. The respective Local Bodies are responsible for the
infrastructural facilities. Chennai Metropolitan Water supply and Sewerage Board
(CMWSSB) is the authorized agency to provide water supply and sewerage -facilities to
some of the Local Bodies around Chennai in the CMA and, also in areas of CMWSSBs
jurisdiction. Chennai city sewerage system comprises of 10 Sewage Treatment Plants
(STPs) which are located at Kodungaiyur (3 Nos-270 MLD), Koyambedu (2 Nos- 94
MLD), Nesapakkam (3 Nos-117 MLD) and Perungudi (2 Nos- 114 MLD).
Detailed Project Reports were prepared for some of the AUAs like Madhavaram, Porur
and Maduravoyal for treatment and disposal of sewage into the existing STPs in CMA
due to non-availability of lands for locating STPs 'in these areas. Consequently, the
available capacities in the existing STPs need to be assessed in detail for accommodating
additional sewage flows from the AUAs.
Rapid urbanization has resulted in a significant impact on the environment. All the
concerned authorities have realized that development cannot be sustained unless the
environment is protected. Therefore, most of the governments in the world have made
it mandatory for project developers to carryout Environmental Assessment (EA) of their
1
development project(s) and prepare Environmental Management Plans (EMPs) so that
the environmental quality is protected.
The Government in its G.O.No.48 M.A & W.S Department dated 06.02.04 have accorded
administrative sanction for Rs.28S5.46 Lakh towards providing underground sewerage
facilities to Thiruvottiyur Municipality. The scheme sanction is for providing collection
system, construction of pumping stations, pumping mains and improvements to the
existing STP (WSP) at Thiruvottiyur Municipality. The project is funded by TNUDF. The
sewerage scheme is divided into five packages. Packages I to IV contemplate laying of
sewers for a length of 82 km and 6 No of pumping stations. Package -V is for laying 10
km length of pumping main. Tenders were settled for all the five packages and the work
commenced on 08.05.2007. At present, work is in progress in Package I to VI.
Regarding Package V, it is to be stated that the pumping main work was partly
completed and the balance work could not be taken up within the contract period due to
non-accordance of permission by Railways and NHAI. Hence, the . Board decided to re-
tender the balance work with the revision of estimate. Subsequently, tenders were
called for and the work orders issued on 20.05.10 for laying pumping main in
SH/NH/Municipal road. The World Bank Mission during the meeting held in July 2010
suggested providing external coating for PSC pipes to prevent corrosion.
The pumping main is to be laid across four railway crossings at three locations. Further,
as per the proposal the final reach of the pumping main from the Terminal pumping
station at Subramanya Pond to the existing STP at Sathankadu could not be laid as there
was no feasibility. Alternate alignment has been identified for laying the pumping main
and the work is under progress. An alternate site for the construction of new STP was
identified by the Municipality to an extent of about 5 acres of land (Meykal Poramboke)
near the existing Municipality compost yard at Sathankadu, Thiruvottiyur for this
purpose.
2
the STP was decided considering the sewage from Thiruvottiyur as well as
Kathiwakkam Municipalities. The estimated flow from Thiruvottiyur is 36.24 mld and
8.47 mld from Kathiwakkam for the ultimate stage i.e year 2040. For the proposed STP,
the project initialization year was assumed as 2010 and the perspective design year as
2025 i.e., 15 years after implementation. Though, the Technical Standing Committee
decided that 40 mld plant can be constructed, the anticipated sewage generation from
Thiruvottiyur and Kathiwakkam Municipalities for the year 2025 is 30.43 mld and 6.30
mld respectively totaling to 36.73 mld oniy. Hence, the capacity of the proposed STP
was considered as 37 mld.
Based on the comments of TNUDF/ World Bank, the capacity of the proposed STP was
restricted to the sewage generated in Thiruvottiyur Municipality only. For the proposed
STP, the estimated flow for the perspective design year as 2025 (i.e., 15 years after
implementation) was arrived at 30.43 mid. Hence, the capacity of the STP was adopted
as 31 mld. Accordingly, the draft bid document was revised and concurrence was
accorded by TNUDF for the same.
If the sewerage scheme is implemented for these local bodies, there: will be an
enhancement in environmental quality and improvement in health status of the
community.
3
1.3 SCOPE OF THE STUDY
To assess the effect on Land, Air, Water and Noise environment and measures
proposed and to take mitigation measure for any adverse effects.
To assess impact on wildlife (including birds) habitat in project area, if any;
Assessment of impact on flora and fauna which would possibly be affected by the
project and to suggest plans for their conservation.
To collect available water quality data; observe and analyze water quality at the
project area and to collect information on known pollution sources in the area
To evaluate the impact of the project on public health, quality of life etc. during
construction and after commissioning of the project.
To assess impact on human settlements in project area, if any. To assess impact
of project on existing and proposed infrastructure including roads and to identify
measures for overcoming the same.
Analysis of Census data for demographic profile.
Preparation of environmental monitoring plan for construction and operational
phases.
Identifying mitigatory measures.
Preparation of sound Environment Management plan (EMP) outlining additional
control technologies to be adopted for mitigation of adverse impacts, if any.
This section reviews the policies, regulations and administrative framework within
which the project is to be implemented. The review includes the Environmental and
Social framework of TNUIFSL, operational policies / directions of the World Bank and
sector-specific environmental policies and regulations of the Govt. of India and Govt. of
Tamilnadu.
4
1.4.2 Water Act, 1974
These laws seek to control pollution of water and enhance the quality of water. Under
this law, it is mandatory to obtain Consent to Establishment of STP and the effluent to
be treated to meet the discharge standards of inland surface water and discharged as
per the standards stipulated by TNPCB before discharge into the river or on land for
irrigation and pay consent fees as stipulated for local bodies viz., Town Panchayat,
Municipality, Corporation which are causing water pollution.
This Act provides prevention, control and abatement of air pollution. With a framework
similar to the Water Act, the Air Act gave the central and State Board’s authority to issue
consents to industries operating within the designated air pollution control areas. The
State also prescribes emission standards for stationary and mobile sources.
1.4.4 The Water (Prevention and Control of Pollution) Act, 1974 amended
in 1988
Its objective was to ensure that the domestic and industrial pollutants are not
discharged into rivers, and lakes without adequate treatment. The reason is that such a
discharge renders the water unsuitable as a source of drinking water, for the purposes
of irrigation and to support marine life. In order to achieve its objective Pollution
Control Boards at Central and State levels were created to establish and enforce
standards for factories discharging pollutants into bodies of water. The State Boards are
empowered to issue Consent for Establishment (CFE) whenever a firm wanted to
establish a new factory and also issue Consent for Operation (CFO) for existing factories.
They were also given the authority to close factories or, in the case of disconnecting
power and water supply, issue directions to the concerned Departments for
enforcement of Boards standards
5
1.4.5 Environment Protection Act 1986, & Notifications
In order to create national environmental legislation, the EPA articulates a policy for
environmental protection covering air, water and land and provide a framework for
Central Government to coordinate between Central and State Authorities established
under various laws, including the Water Act and Air Act. Under this umbrella Act, the
Central Government must set National Ambient and Emissions Standards, establish
procedures for managing hazardous substances, regulate industrial sites, investigate
and research pollution issues and establish laboratories and collect and disseminate
information.
Among other relevant legislation, the Public Liability Insurance Act (PLIA) of 1991
mandates that business owners operating with hazardous substances take out
insurance policies covering potential liability from an accident and establish
Environmental Relief Funds to deal with accidents involving hazardous substances. The
National Environmental Appellate Authority Act of 1997 requires the Central
Government to establish an authority to hear appeals on area restrictions where
operations will not be carried out or will be carried out with certain safeguard
measures.
Operational Policy 4.01 (OP 4.01) is one of the ten safeguard policies of the World Bank,
which provides the Environmental Impact Assessment (EIA) guidance for the lending
operations. The OP 4.01 requires the borrower to screen projects upstream in the
project cycle for potential impacts. Thereafter, an appropriate Environmental
Assessment (EA) approach to assess, minimize/ enhance and mitigate potentially
adverse impacts is selected depending on nature and scale of project. The EA needs to
be integrated in the project development process such that timely measures can be
applied to address the identified impacts. The policy requires consultation with affected
6
groups and NGOs to recognize community concerns and the need to address the same as
part of EA.
The TNPCB has the mandate for environmental management at the state level, with
emphasis on air and water quality. The board is responsible for:
Planning and executing state-level air and water initiatives,
Advising state government on air, water and industry issues,
Establishing standards based on National Minimum Standards,
Enforcing and monitoring of all activities within the State under the Air Act, the
Water act and the Cess Act, etc.
Conducting and organizing public hearings for projects as defined by the various
Acts and as stipulated by the Amendment (April 1997) to the EIA Act; and,
Issuing No-objection
1.4.6.3 Noise Pollution Rules 2000
In order to curb the growing problems of noise pollution, the government of India has
enacted the noise pollution rules 2000 that includes the following main provisions:
The state government may categorize the areas as industrial or commercial or
residential.
The Ambient air quality Standards in respect of Noise for different areas has
been specified.
The State government shall take measures for abatement of noise including
noise emanating from vehicular movement and ensure that the existing noise
levels do not exceed the ambient air quality standards specified under these
rules.
Areas not less than 100 m around Hospitals, Educational institutions and Court
is declared as silence area under these rules.
A loud speaker or a public address system shall not be used except after
obtaining written permission from the authority and the same shall not be used
at night, between 10 pm to 6 am.
7
A person found violating the provisions as to the maximum noise permissible
in any particular area shall be liable to be punished for it, under the provision
of these rules and any other law in force.
1.4.6.4 Coastal Regulation Zone (CRZ) Notification, 2011.
The NOC from the Tamil Nadu Pollution Control Board TNPCB in pursuant to the
Water
(Prevention and Control of Pollution) Act of 1974, the Cess Act of 1977 and the
Air (Prevention and Control of Pollution) Act of 1981.
The State Pollution Control Board issues a No-objection Certificate (NOC) after
accepting the application for the project.
8
1.5 METHODOLOGY
The EA study encompasses the area within 10 km radius of the proposed Sewage
Treatment Plant project. For the preparation of EA report for the STP, the baseline data
was collected during the period of March to May 2013. The micro climatic parameters
were recorded using automatic weather monitoring station for the study period. Wind
9
speed, wind direction and relative humidity were recorded on hourly basis. Minimum &
Maximum temperatures were also recorded during the study period.
The description of the existing air environment in and around the proposed project site
is based on actual monitoring during the month of March to May 2013. The
concentrations of important air pollutants like PM10, PM2.5, SO2 and NO2 at the study
area are well within the permissible limits prescribed by Central Pollution Control
Board (CPCB).
The baseline noise levels in and around 10 km radius of the proposed Project Site were
established as per the Noise Pollution Level (Regulation and Control) Rules, 2000 in line
with the Ambient Air Quality monitoring stations.
The baseline water environment in and around 10 km radius of the proposed Project
Site were established in line with the ISO 19001 Standards. There is no major river
system in the 10 Km radius of the STP Site. Buckingham Canal is 150 mts away from the
project site boundary. Discharge of treated water into B’ canal requires CRZ clearance
Soil samples were collected from the project site, not only at its immediate vicinity but
also in the surrounding villages in the study area. Physico-chemical properties of the
soils were determined; information on land use pattern in the study area was also
collected. The proposed STP site is located in the commercial area as per CMDA land use
plan.
10
1.5.2.6. Ecosystem
Information on eco-system within the study area was collected from the State
Agricultural and Forest departments. The important floral species native to the project
area is enumerated and discussed in the Chapter 3. A physical survey was also
undertaken to validate the correctness of the data collected.
A field survey was conducted within study area of the site and the surrounding impact
zone. The parameters selected under socio-economic component were demographic
structure of the study area, provision of basic amenities, industries likely to come up in
the study area, welfare facilities by the project proponent, safety training and
management, community and occupational health hazards. Relevant information was
collected from selected villages and analyzed.
11
2. PROJECT DESCRIPTION
The Government in its G.O.No.48 M.A & W.S Department dated 06.02.04 have accorded
administrative sanction for Rs.28S5.46 Lakh towards providing underground sewerage
facilities to Thiruvottiyur Municipality. The scheme sanction is for providing collection
system, construction of pumping stations, pumping mains and improvements to the
existing STP (WSP) at Thiruvottiyur Municipality. The project is funded by TNUDF. The
sewerage scheme is divided into five packages. Packages I to IV contemplate laying of
sewers for a length of 82 km and 6 No of pumping stations. Package -V is for laying
10.06.9 km length of pumping main. Tenders were settled for all the five packages and
the work commenced on 08.05.07. At present, work is in progress in Package I to IV.
12
tenders for this work by CMWSSB pending. Administrative Sanction by the government.
However, tender could not be floated immediately, as funds for the work was allotted by
the Municipality.
Based on the comments of TNUDF/ World Bank, the capacity of the proposed STP was
restricted to the sewage generated in Thiruvottiyur Municipality only. For the proposed
STP, the estimated flow for the perspective design year as 2025 (i.e.,15 years after
implementation) was arrived at 30.43 mid. Hence, the capacity of the STP was adopted
as 31 MLD. Accordingly, the draft bid document was revised and concurrence was
accorded by TNUDF for the same.
If the sewerage scheme is implemented for these local bodies, there will be an
enhancement in environmental quality and improvement in health status of the
community.
13
2.3. PROJECT LOCATION
Proposed construction of 31 MLD Sewage Treatment Plant (STP) based on ASP
Technology at T.S.No:3/2 at Santhankadu village, Thiruvottiyur, Block no: 14, Chennai
by Chennai Metropolitan Water Supply and Sewerage Board (CMWSSB), Chennai
14
Figure 2-2 Topo map of the Project Site
16
Figure 2-3 Drainage Pattern of the Project Site
17
Figure 2-4 Road Network map of the Project Site
18
Figure 2-5 land use of the Project Site
19
Figure 2-6 CMDA land use of the Project Site
20
Figure 2-7 Contour Plan of the Project Site
21
Figure 2-8 Layout of the Project Site
22
Figure 2-9 Demarcation Map of the Project Site (CRZ MAP)
23
Figure 2-10 Demarcation Map of the Project Site (CRZ MAP)
24
2.4. PROJECT COST
An estimate has been prepared based on the settled cost towards the Construction, trail
run for six months & O&M charges for five years for the work of " construction of 31 mid
capacity STP with ASP & Filtration) at Thiruvottiyur" . The estimate works out to Rs
2633.00 Lakhs (Construction cost-Civil, Mechanical, and Electrical & Instrumentation
works-Rs '1777.23 Lakhs, Tail run for six months Rs -2.821 Lakhs, 0& M Cost for five
years-Rs 519.66 Lakhs). The break up details is enclosed herewith. !t may be also seen
that the estimate includes overheads such as contingencies @2.5 %, Price escalation
@10 % centage charges @ 5% on the settled construction cost. Necessary provision has
been made towards third party inspection.charges & EB charges.
With regard to O&M cost, it is to be stated that settled cost for five years O&M is Rs
169.26 Lakhs which includes fixed cost (Man power, Maintenance of civil structures &
plant housekeeping, repairs including spares& replacement, oil & Grease etc). Variable
cost (covering consumables, chemicals and disposal of grit & sludge) but excludes TNEB
power charges, Diesel cost for DG set & Chlorine Dosage costs as per the tender. The
costs for these items have been worked out· separately. An amount of Rs 350.40 Lakhs
has been estimated towards these items and has been included in the estimate. Hence
the total estimated cost for the O&M works for 5 years works out to Rs 519.66 Lakhs (Rs
1.69.26 Lakhs+ Rs 350.40 Lakhs)
25
2.6. MANPOWER
During Construction phase, 100 persons will be employed in peak period and an
average of 50 persons in normal period.
The STP will have skilled and unskilled employees for its three shift operation. Table 2.4
shows the total manpower requirement for the STP.
26
2.7. TECHNICAL DESCRIPTION OF THE PROJECT
This is a Socio Environmental Project. This STP will be treating 31 MLD of raw sewage
received from Thiruvottiyur Area as per standards prescribed by the TNPCB and
treated effluent will be let out into nearby water course Buckingham Canal maintained
by PWD for which separate action initiated to get the concurrence of PWD for letting out
the effluent into B’ Canal. Part of treated sewage will be utilised for development of
Green Belt Area around STP campus part of effluent for development of parks and Road
side Lawn maintained by Corporation of Chennai and Highways Department.
The Screenings will be disposed off in the Dumping Yard of Corporation of Chennai
where there is no residence available.
The Grit from the Detritor tank will be utilised as manure on drying in the Kodungaiyur
Farm land. Similarly the sludge cake (dried) will be utilised as manure for Kodungaiyur
Farm land and for filling low level pockets. 3.0 m wide strip of land within the STP area
boundary will be utilised for development of Greeneries such as Teak, Casurina,
Eucalyptus, sibabul, etc. for maintaining good environment and to avoid odour nuisance.
The lowest evaluated bidder M/s Sekhar Deepak Construction Company Ltd, Chennai
has satisfied all the required qualifications as per the bid document. The Director,
Centre for Environmental Studies, Anna University vide letter dated 14.09.10 has also
offered opinion that the process design proposed by the M/s Sekhar Deepak
Construction Company Ltd, Chennai may be accepted. With the approval of Board and
concurrence from the TNUDF World Bank, the work order to the lowest bidder M/s
Sekhar Deepak Construction Company Ltd, Chennai at was issued on 22.10.10.
27
Since, the contractor M/s Sekhar Deepak Construction Company Ltd, Chennai had
adopted ASP with filtration, the amendment for establishment of STP (due to change of
technology) is obtained from the TNPCB.
As per the requirement of tender conditions, the contractor is to provide a layout for
constructing a 14 MLD capacity STP in the future, in addition to the 31 MLD capacities
within the total available area of 5.0 acre (2 .02 Ha). Accordingly, the land requirement
by the contractor is as follows
Proposed 31 MLD STP Capacity - 7468 sq.m
Proposed 14 MLD STP capacity in the future - 4106 Sq.m
Total area of STP proposed - 15,000 Sq.m (1.50 ha)
Raw Sewage will be made available to the STP contractor at Stilling Chamber through
600/800 mm dia PSC pipelines to be laid under the scope of the contract package-V. As
per the proposal, the treated effluent is to be discharged into the nearby B’ Canal.
28
2.7.1.3.2. CIVIL UNIT DETAILS
29
2.7.1.4. Raw Sewage Quality:
Sewage is treated to conform to standards such that the treated sewage may be
disposed off into surface water course. It is desired to treat the sewage to a level
whereby the treated sewage can be utilized. Quality characteristics of treated sewage
will be as given the below table.
1. Receiving Chamber:
Raw Sewage will be delivered through 600 mm / 800 mm dia PSC pipe into the
Receiving Chamber (Size of 1.94 m x 5.0 m x 5 m LD) and from where it will be taken to
30
down stream screens. The function of the receiving chamber is to reduce the incoming
velocity.
2. Screen Chamber:
Manual coarse screen and mechanical coarse screen chamber of size 5.6 m x 0.9 m x 1.0
m LD each and manual fine screen and mechanical fine screen chamber of size 5.15 m x
0.86 m x 1.0 m LD each are provided.
After the Receiving chamber minimum 2 nos. of coarse screen and two no. of fine
screens are to be provided for removal of floating and oversized materials and fine
floating materials coming with sewage. The coarse screen should be capable of
screening materials such as plastic rags, debris, weeds, paper, cloth, rags etc. which
could clog the waste water pump impeller. Similarly the fine screen should be capable
of screening materials such as hair, debris, weeds, paper, rags etc. The bar screen shall
be of stainless steel flats. A conveyor system of suitable width shall be provided which
shall be adjacent to screens. The screening material as collected will drop automatically
into a wheel barrows for disposal. It is disposed in the near by dumping yard of
Corporation of Chennai.
3. Detritor Tank:
Screened sewage will be gravitable to minimum two nos. of Grit Separator Tank
(Detritor Tank) for removal of grit and small inorganic particles of specific gravity
above 2.65 and particle size above 150 microns. The Grit Separator tank of size 8.6 m x
8.6 m x 0.7 m LD each shall be have RCC construction complete with mechanical
intervals and square in size will be constructed. The grit separated shall be properly
collected through scrapping mechanism and screw mechanism and disposed. As this is
a good manure, it can be used in Kodungaiyur Farm Land. The detrited sewage shall
flow through open channels from the grit separators and confluence into a single
channel of suitable width. The sewage is collected in the syphon well and reaches
Equalization Tank.
31
4. Equalization Tank (or) Balancing Tank:
An equalization tank of size 40.90 m O.D, 31.0 MLD with 5 MLD. will be constructed.
The purpose of this tank is to collect the excess water during the peak flow time and to
supply the uniform flow of 31/24 M.L. for each hour so as to maintain the flow
uniformly to achieve the standards of treated effluent as per requirement.
5. Primary Clarifier:
Primary clarifier tank of size 30.48 m I.D. with 3.5 m liquid depth will be constructed in
RCC construction complete with mechanical internals and circular in shape. During the
time of detention the sludge portion of sewage will settle down at the bottom and the
primary effluent will be reaching Aeration Tank. Due to settlement of sludge, about
60% of suspended solids and 30 to 40% of BOD impurity will be removed from the
sewage. The settled sludge which is called Raw Sludge is sent to Digester through
sludge sump, thickener and thickener overflow sump for getting digested for disposal.
6. Aeration Tank:
An Aeration Tank of 58.69 m O.D. 45.04 m I.D. with 5.50 m L.D. will be constructed in
RCC construction complete.
The effluent from Primary clarifier will enter into the aeration tank. Here Air is
introduced in the system to create an aerobic environment that meets the needs of the
biological community and the aeration source ensures that adequate oxygen is fed into
the tank and appropriate mixing takes place. This reduces the BOD. By aerating the
mixed liquor the aerobic process will be stimulated, the growth rate of bacteria will be
much faster. The Aerated effluent reaches Secondary Clarifier for further treatment.
About 90% of the impurities such as BOD and suspended solids are removed in Aeration
Tank.
32
7. Secondary Clarifier:
A Secondary Clarifier of size 44.40 m I.D. with 2.5 m SWD will be constructed in RCC
Construction complete with mechanical internals and circular shape. During the time of
detention period the solids separate from the water by the process of gravity
sedimentation in which the sludge settles towards the bottom of the clarifier. As this
sludge portion contains good quantity of micro organism this is collected in a separate
sump and sent to Aeration Tank for activation purpose. The effluent from the
Secondary clarifier is collected in chlorination contact Tank for further disinfection
treatment.
A chlorine contact tank of size 69.30 m dia 4.20 m wide 2.3 m LD will be constructed.
The treated sewage from the Secondary Clarifier is sent to the chlorination Tank for
disinfection using sufficient quantities of chlorine by which potential disease causing
organisms are eliminated.
A sludge sump of size 1.77 m x 4.20 m wide will be constructed to receive raw sludge
from Primary clarifier for pumping to thickener.
10. Thickener:
11. Digestor:
A digestor of size 86.90 m x 4.20 m wide in RCC construction will be constructed with
necessary mechanical internals and circular in shape. The Digestor receives the sludge
from the thickener which digest the sludge within the digestion period produces biogas
and digested sludge. The digested sludge is sent to centrifuge for further treatment and
disposal.
33
12. Centrifuge:
A centrifuge room of size 7 m x 4 m will be constructed. The centrifuge unit with other
auxiliary units such as dosing tank are erected in the centrifuge room. The digested
sludge from the digestor mixes with poly electrolyte in the centrifuge and sludge in the
form of cakes will be collected and disposed. As this contains good manure value the
cakes can be utilised in Kodungaiyur Farm Land.
Treated Sewage from Activated Sludge Process units will be collected in a chlorination
tank where disinfectant will be added for disinfection at suitable dosing rate. Baffle
walls shall be provided in the tank to facilitate hydraulic mixing of treated sewage.
Adequate reaction time shall be considered for while selecting the chlorination tank
volume to ensure proper disinfection of treated sewage.
Chlorination system covering chlorine tonners chlorinator, water feed pumps, piping,
booster pumps, ejector, trunnions, lifting device with weighing scale, leak detection and
leak absorption system, safety equipments like canisters, gasmasks etc. and other
ancillary shall be provided in the chlorine house. Chlorine house of adequate plinth area
shall be provided. It shall have sufficient ventilation as per the latest norms for safety
purpose with necessary lifting arrangement and EOT of minimum 2 T capacity etc.
complete.
The treated sewage is to be disposed into Buckingham Canal through PSC pipe by
gravity flow.
Treated sewage after chlorine contact tank will be conveyed through PSC pipe to
Buckingham Canal running at a distance of about 181 m.
34
2.7.1.9. AUXILIARY POWER SOURCE
In order to ensure uninterrupted working of the plant when the TNEB grid power fails,
a Diesel Generator set is proposed in the plant. The capacity of the DG set proposed is
380 KVA. DG set is acoustically enclosed. Stack rising 5m above the building top is
considered for exhausting the gaseous emissions.
An estimate has been prepared based on the settled cost towards the Construction, trial
run for six months & O&M charges for five years for the work of " construction of 31 mid
capacity STP with ASP & Filtration) at Thiruvottiyur" . The estimate works out to
Rs.2633.00 Lakhs (Construction cost-Civil, Mechanical, and Electrical & Instrumentation
works-Rs '1777.23 Lakhs, Tail run for six months Rs -2.821 Lakhs, 0& M Cost for five
years-Rs 519.66 Lakhs). The break up details is enclosed herewith. !t may be also seen
that the estimate includes overheads such as contingencies @2.5 %, Price escalation
@10 % centage charges @ 5% on the settled construction cost. Necessary provision has
been made towards third party inspection.charges & EB charges.
With regard to O&M cost, it is to be stated that settled cost for five years O&M is Rs
169.26 Lakhs which includes fixed cost (Man power, Maintenance of civil structures &
plant housekeeping, repairs including spares& replacement, oil & Grease etc) , Variable
cost (covering consumables, chemicals and disposal of grit & sludge) but excludes TNEB
power charges, Diesel cost for DG set & Chlorine Dosage costs as per the tender. The
costs for these items have been worked out· separately. An amount of Rs 350.40 Lakhs
has been estimated towards these items and has been included in the estimate. Hence
the total estimated cost for the O&M works for 5 years works out to Rs 519.66 Lakhs (Rs
1.69.26 Lakhs+ Rs 350.40 Lakhs)
35
3. DESCRIPTION OF THE ENVIRONMENT
3.1. INTRODUCTION
Baseline Environmental Studies have been conducted to determine the existing status of
various Environmental attributes viz., Climatic and Atmospheric conditions, Air, Water,
Noise, Soil, Hydro geological, Land use pattern, Ecological and Socio-Economical
environment, prior to setting up of the proposed project. This study would help to
undertake corrective mitigation measures for protection of the environment on account
of any change deviation of attributes due to activities of the proposed project.
36
Table 3-1 Baseline Environmental Components & their Attributes, Frequency & Monitoring Methodology
Attributes Sampling Measurement Method Remarks
Network Frequency
1. Air Environment
Meteorological Data
• Wind speed At project site (Site Weather Monitoring Station IS 5182 Part 1-20
• Wind direction specific) Sit-specific
• Dry bulb temperature primary data is
• Wet bulb temperature essential Secondary
• Relative humidity data from IMD-
• Rainfall Regional
Meteorological
Centre, Chennai
Ambient Air Quality
• Suspended Particulate Matter Requisite locations 24 hourly twice • Gravimetric (High – As per CPCB
(SPM) in the project a week Volume) Standards under
• Particulate Matter (PM 10) influence area • Gravimetric (High – November 18th 2009
• Particulate Matter (PM 2.5) Volume with Cyclone) Notification for
• Sulphur Di-oxide (SO2) • EPA Modified West & NAAQS
• Oxides of Nitrogen (NOX) Gaeke method
8 Hourly twice a • Arsenite Modified Jacob &
week Hochheiser
2. Noise Environment
Hourly equivalent noise levels Requisite locations One day Sound level meter IS: 4954-1968
in the project continuous on a
38
influence area working and
non-working
day
3. Water environment
Parameters for water quality: pH, Set of grab samples Once Samples for water quality
temp, turbidity, Total hardness, total At requisite collected and analyzed as per
alkalinity, chloride, sulphate, nitrate, locations for ground IS : 2488 (Part 1-5) methods
fluoride, sodium, potassium, and surface water for sampling and testing of
Electrical Conductivity, Ammonical Industrial effluents Standard
nitrogen, Nitrate-Nitrogen total methods for examination of
phosphorus, , BOD, COD, Calcium, water and wastewater
Magnesium, Total Dissolved Solids, analysis published by
Total Suspended Solids American Public Health
Association.
4. Land Environment
• Soil quality Requisite soil Once Collected and analyzed as per
• Particle size distribution samples be collected soil analysis reference book,
• Texture as per BIS M.L.Jackson
• pH specification within
• Electrical conductivity project influence
• Caution exchange capacity area
• Alkali metals
• Sodium Absorption Ratio
(SAR)
• Permeability
• Porosity
39
5. Land Use
• Location code - - • Global positioning system Drainage within the
• Total project area • Topo-sheets plant area and
• Topography • Satellite Imageries surrounding is very
• Drainage (natural) important for storm
• Cultivated, forest plantations, water impacts.
water bodies, roads and From land use maps
settlements sensitive receptors
(forests, parks,
mangroves etc.) can
be identified
6. Biological Environment
Terrestrial
Vegetation – species, list, economic One season for • Point quarter plot-less
importance, forest produce, terrestrial biota, method (random
medicinal value, Importance value in addition to sampling) for Terrestrial
index (IVI) of trees, Wild animals Vegetation vegetation survey.
Avifauna studies during • Secondary data to collect
Rare and endangered species monsoon season from Government offices,
Sanctuaries/National NGOs, published literature
park/Biosphere reserve
Socio-Economic
• Demographic structure Socio-economic • Survey is based on
• Infrastructure resource base survey is based personal interviews and
• Economic resource base on proportionate, questionnaire.
• Health status: Morbidity pattern stratified and • Secondary data from
40
• Cultural and aesthetic attributes random sampling census records, statistical
method hard books, toposheets,
health records and
relevant official records
available with Govt.
agencies
41
3.3. SAMPLING LOCATIONS
Six sampling locations are selected for Air, Water, Noise and Soil. All the samples are
analyzed and results are shown in below chapter.
The Air, Noise, Water and Soil Sampling locations were selected based on the following
criteria. The Ambient air quality monitoring locations have been designed keeping in
view the available climatological norms of predominant wind direction and wind speed
of the area.
The following points were also taken into consideration in designing the sampling
locations
For the noise monitoring locations the above factors has been considered. Water
sampling locations were collected based on the availability of the bore wells / open
wells in the area. Geological environment has been considered for the collection of Soil
sample collection.
3.4. MICROMETEROLOGY
3.4.1. Temperature
The mean maximum and minimum temperatures during summer and winter vary
between 34.3°C and 25.8°C. The highest temperature ever recorded is 43°C.
3.4.2. Rainfall
Thiruvallur district generally experiences hot and humid climatic conditions. The
district receives the rain under the influence of both southeast and northeast monsoons.
Most of the precipitation occurs in the form of cyclonic storm caused due to the
depressions in Bay of Bengal chiefly during northeast monsoon period. The southwest
monsoon rainfall is highly erratic and summer rains are negligible.
The average normal rainfall of the District is 1104 mm. Out of which 52% has been
received during North East Monsoon period and 41% has been received during South
West Monsoon period.
42
3.4.3. Relative Humidity
High relative humidity between 67 and 85% prevail throughout the year. Higher rates
of relative humidity are observed between November and January i.e., 83 to 85%. In the
months of June, the humidity is lower i.e., around 58%. Average relative humidity in the
morning and evening are 74 and 64% respectively. The minimum and maximum
temperature is 20°C & 37°C respectively.
43
44
3.4.5. Cloud cover
Cloud Cover During the winter and the summer seasons, the skies are observed to be
generally very clear. In the post -monsoon season, generally light clouds were observed
i n the evenings, with clear mornings. During the monsoon season, both in the mornings
and evenings, the skies were found to be overcast
The Ambient Air Quality (AAQ) status with respect to the study zone of 10 km radial
distance from the plant site formed the baseline information over which the predicted
impacts due to the proposed project were determined based on which the
Environmental Management Plan (EMP) was prepared. The baseline status of the
ambient air quality can be assessed through a scientifically designed ambient air
quality-monitoring network based on the following considerations:
To establish the existing baseline status of air quality in and around the STP site a
network of seven AAQ sampling locations were selected within 10 km aerial distance.
The locations were decided on the basis of meteorological data and the topography of
the area. Further, a monitoring location was selected at the project site to get the
baseline status of the air quality within 10 Km around the project site. The AAQ
45
sampling locations and their direction with respect to the project site are given in Table
3.3. The Ambient Air Quality results are given in Table 3.4.
The existing ambient air quality at the identified locations and the corresponding
standards are presented in Table 3.4. The table below lists minimum, maximum, 98th
percentile and mean values of concentrations of PM10, PM2.5, SO2 and NO2 are
monitored.
46
Figure 3-2 AAQ Sampling Location map
47
Table 3-3 Air Quality sampling Locations
Direction with Distance with
Location Geographical Elevation Environmental
Location respect to project respect to project
Code location (mt) Setting
site site (km)
N-13º07’58.37”
AAQ3 Kodungaiyur SW 4.15 7.92 Residential Area
E-80º15’18.75”
N-13º07’57.65”
AAQ4 New Residential
SSE 2.43 10.06
Washermanpet E-80º17’16.60”
N-13º09’19.38”
AAQ5 Tondiyarpet E 1.48 9.14 Residential Area
E-80º18’00.20”
48
Table 3-4 Air Quality Results
Code Location
98 98 98 98 98
Min Max Avg Min Max Avg Min Max Avg Min Max Avg Min Max Avg
Per Per Per Per Per
AAQ1 Project Site 52 68 59 67.8 26 35 30 34.6 8.6 11.7 9.8 11.5 13.3 17.6 15.4 17.1 11.2 19.6 15.4 19.4
AAQ2 Wimco Nagar 57 75 65 74.1 27 39 33 38.7 8.2 10.4 9.3 10.3 15.2 21.6 18.2 21.5 15.6 25.3 20.1 23.1
(Tiruvottiyur)
AAQ3 Kodungaiyur 55 66 60 65.5 28 37 32 36.9 9.2 12.1 10.7 12.0 14.1 18.6 16.3 18.4 13.2 21.3 17.1 21.0
AAQ4 New 54 71 63 70.7 25 33 29 32.8 7.4 9.7 8.6 9.6 15.6 21.8 18.3 21.5 7.5 12.6 10.1 12.4
Washermanpet
AAQ5 Tondiyarpet 60 72 66 71.8 32 40 36 39.5 8.1 10.6 9.4 10.5 16.4 23.7 20.2 23.5 10.1 18.8 14.5 18.6
AAQ6 Manali 64 81 73 80.7 35 44 39 43.5 10.8 13.1 12.2 13.0 17.8 28.3 22.7 28.1 20.2 36.4 28.3 36.1
Industrial /Residential /
100 60 80 80 400
Rural and Other Area
49
3.5.1.2.1. Observation for AAQ results:
The maximum value (PM10) of 81 µg/m3 was observed at Manali (AAQ6) and next
higher value of 75µg/m3 was observed at Wimco nagar (AAQ2). The lower value of 52
µg/m3 was observed at the project site (AAQ1). The maximum value (PM2.5) of 44 µg /
m3 was observed at Manali (AAQ6). Similarly SO2, NO2 and NH3 were found to be high in
Manali (AAQ4). However, all the ambient air quality levels are found to be within the
CPCB Standards.
The baseline noise levels in and around 2 km radius of the proposed project site were
established in-line with the Noise Standards. Noise monitoring was carried out at
following 7 locations given in the Table 3.5.
Noise levels were monitored using a calibrated portable noise level recorder on an
hourly basis for 24 hours, once at each location. Levels of noise monitored during 6 AM
to 9 PM were considered for the day noise levels and those monitored during 9 PM to 6
AM were considered for night noise levels. Day and night Leq values were computed
based on the monitored noise levels and are presented in Table 3.5.
50
Figure 3-3 Noise Sampling Location map
51
Table 3-5 Noise Monitoring Locations & Results
Tondiyarpet N-13º08’59.96”
N2 Residential Area
(Railway SSE 0.56 53.1 43.1 51.5
E-80º17’18.14”
Colony)
N-13º09’50.27”
N3 Tiruvottiyur Residential Area
NNE 1.12 52.3 42.6 50.7
(Nehru Nagar) E-80º17’26.15”
N-13º07’58.37”
N5 Residential Area
Kodungaiyur SW 4.15 52.8 42.8 51.2
E-80º15’18.75”
N-13º08’07.67”
N6 Residential Area
Washermanpet SSW 2.38 53.4 43.5 51.8
E-80º16’36.78”
52
3.7. WATER ENVIRONMENT
Buckingham Canal lies very near to the project (Above 155 mts) and the treated water
will be discharged (31,000 m3) into the same. Sampling has been conducted and the
stud report is given in Table 3.8
Ground water table in the study area during pre-monsoon is about 2.0 m BGL and about
1.5 mt BGL during post monsoon period
Detailed water quality assessment is necessary in areas where there is intensive ground
water development, Industrialization and urbanization as it is also subjected to
qualitative changes in the environment around. Quality of water is influenced
considerably by the quality of its source and occurrence. In order to describe and assess
the impact on water quality by the proposed project, ground water and surface water
samples at 6 locations were collected within the 10 km radius and tested for physical
and chemical parameters.
Initially, reconnaissance survey was carried out to identify suitable water sample
collection locations. During the reconnaissance survey on site, TDS and pH were tested
and the locations were captured using GPS. While selecting the sampling locations for
detailed hydro geochemical analysis the following were given much importance.
Those water bodies on which human activities could have an impact, either by
utilizing water or by discharging effluents.
Water abstraction and utilization by domestic users.
Six water sources were selected for sampling for ground water and one surface water
sampling was done in B’Canal during this period. The location and source of water
samples collected are given in Table 3.6 and 3.7.
53
Figure 3-4 Water Sampling Location map
54
Table 3-6 Water Sampling Locations
N-13º10’46.89”
W1 Tiruvottiyur NE 3.40 Ground Water
E-80º18’15.87”
N-13º09’19.38”
W2 Tondiyarpet E 1.48 Ground Water
E-80º18’00.20”
N-13º09’53.62”
W3 Manali WNW 3.13 Ground Water
E-80º15’34.40”
N-13º07’57.65”
W4 New
SSE 2.43 Ground Water
Washermanpet E-80º17’16.60”
N-13º07’58.37”
W5 Kodungaiyur SW 4.15 Ground Water
E-80º15’18.75”
N-13º09’12.83”
SW1 Buckingham Canal WSW 0.28 Surface Water
E-80º17’02.85”
55
Table 3-7 Ground Water quality results
Limit as per
S.
Parameters Unit Test method IS 10500 : W1 W2 W3 W4 W5
No
2012
Total Hardness
7 mg/l IS : 3025 Part 21-2009 200 956 458 657 2490 359
as CaCO3
56
APHA 21st EDI-4500-
10 Sulphate as SO4 mg/l 200 271 233 242 617 237
SO42- E
Magnesium as
18 mg/l APHA 21st EDITION 30 106 63 54 338 44
Mg
19 Iron as Fe mg/l IS : 3025 Part 53-2003 0.3 0.21 0.16 BDL(<0.05) 0.31 0.41
Chemical
20 mg/l IS:3025:Part-58:2006 Not Specified 8.2 4.6 BDL(<4) 8.0 12
Oxygen Demand
4 Electrical Conductivity, μS/cm IS : 3025 Part 14- 1984 (Reaff: 2002) 3050
6 Total Dissolved Solids mg/l IS : 3025 Part 16-1984 (Reaff: 2003) 1580
58
15 Sodium as Na mg/l IS : 3025 Part 45-1993 (Reaff:2003) 380
16 Potassium as K mg/l IS : 3025 Part 45-1993 (Reaff:2003) 37
17 Calcium as Ca mg/l IS : 3025 Part 40-1991 (Reaff:2003) 82
59
3.7.4.1. Observations
The pH of ground water in the study area varies between 6.75 to 7.47 and Conductivity
varies from 1370 to 5350 µS/cm.
TDS values were found to be from 3120 to 14508 mg/l and Total Hardness varied from 359
– 2490 mg/l. This indicates that water in the study area were very hard in nature. The Total
alkalinity also varies from 182 to 540 mg/L.
Sodium and potassium are naturally occurring elements of groundwater. Industrial and
domestic wastes also add sodium to groundwater. It is one of the major contributors to
salinity of water. The concentration of sodium in the studied samples varied from 270 to
2200 mg/l. The potassium content ranged from 8.2 to 125 mg/l.
The chloride content in the studied area ranged from 403 - 4829 mg/l. The sulphate, nitrate
and fluoride content in the ground water are found to be within the IS standards in all the
samples.
The pH of surface water is slightly alkaline in nature and Conductivity is about 3050 µS/cm
which indicate that water is not saline in nature
TDS values was found to be 1580 mg/l. Perusal on the ionic contents of the surface water
sources, the quality of surface resource are fresh to brackish in nature.
Based on the physic-chemical analysis, the surface water samples are unacceptable for
drinking purposes.
Dissolved oxygen levels of the surface water are more than 94 mg/l which indicate that
surface water source are good medium for aquatic life.
It is also noted that coliforms are observed in the surface water samples (>161/100ml)
60
3.8. LAND ENVIRONMENT
It is essential to determine the type & quality of .soil in the study area and identify the
current impacts of urbanization on soil quality and also predict probable impacts due to
the proposed plant. Accordingly, a study of assessment of the baseline soil quality was
carried out.
For studying soil quality of the region, sampling locations were selected to assess the
existing soil conditions in and around the 'Project area based on various land use
conditions. The physical and chemical concentrations were determined. The samples
were collected from different specified depths viz., 30cm, 60cm and 100cm
The present study of the soil quality establishes the baseline characteristics and this will
help in future in identifying the incremental concentrations if any, due to the operation
of the proposed plant. The sampling locations have been identified with the following
objectives;
Various locations within 10-km radius of the plant site were selected for soil sampling.
At each location, soil samples were collected from three different depths viz., 30cm,
60cm, and 100cm below the surface. The samples were analyzed for physical and
chemical characteristics. The samples have been analyzed as per the established
scientific methods for physio-chemical parameters.
61
3.8.1. Soil Characteristics
a) Soil Type
Soil type and its fertility of an area are essential to plan for cropping. Soils are primarily
derived from parent rocks. The colour, texture and mineral content are normally used
to classify the soil. The soil in the study area is classified into 3 types. They are as
follows.
S. No Soil Classification
1 Deep, moderately well drained, calcareous, clayey soils
2 Very shallow somewhat excessively drained, gravelly loam soils
3 Moderately deep, moderately well drained, gravelly clay soils
b) Soil quality
To assess the soil quality in the study area, soil sample was collected and analyzed for
physical and chemical parameters as per the standard methods. The sampling locations
are given in Table 3.9.
62
Table 3-9 Soil Sampling Locations
N-13o09’16.60”
S1
Project Site - -
E-80 o17’11.26”
N-13o09’53.62”
S4
Manali WNW 3.13
E-80 o15’34.40”
N-13o07’58.37”
S5
Kodungaiyur SW 4.15
E-80o15’18.75”
N-13 o08’07.67”
S6
Washermanpet SSW 2.38
E-80o16’36.78”
63
Figure 3-5 Soil Sampling Location map
64
Table 3-10 Soil Analysis Results
S.No Parameters S1 S2 S3 S4 S5 S6
Sandy Sandy
10 Texture Classification Clay Clay Clay Clay
Clay Clay
65
Discussion:
The pH indicates that the soils in the study areas are basic in nature, with the pH
varying in the range of 8.28 to 8.58. The Electrical Conductivity was observed in the
range of 0.264-0.821 mS/cm.
The Nitrogen values are in the range of 11.9 – 24.6 mg/kg indicating that soils have very
low Nitrogen levels. The Phosphorous values are in the range of 31.7 – 44.7 mg/kg
indicating that soils have high Phosphorous levels. The Potassium values range between
158 – 311 mg/kg, which indicate that the soils have better quantity of Potassium. The
Organic matter (%) values range between 0.31- 0.71. The soil from the study area
shows that they are not fertile.
Flora
Some of the common plant species found in the study area are Hibiscus rosasinensis,
Zizyphus mauritiana, Delonix regia, Cassia marginata, Tamarindus indica, Cassia
auriculata,Terminalia catappa, Eucalyptus sp., Acacia auriculiformis etc.
Acacia arabica
Bambusa aryndinacea
Lannea coromandalica
Pongamia pinnata
Euphorbia hypericifilia L.
Nepuntia oleracea Lam
Lemna Spp,
Tamarindus indica L.
66
Field studies conducted to assess fauna in study area. On the basis of field studies and
secondary sources, there are no endangered animal species present in the study area.
Fauna
Reptiles
Ptyas mucosus Rat snake
Nerodia piscator Fresh water snake
Naja naja Cobra
Vipera russeli Viper
Calotes versicolor Garden lizard
Amphibian
Rana hexadactyla Frog
Rana tigrina Bull frog
Mammals
Lepus nigricollis Hare
Canis auries jackel
Funambulus Sp. Squirrel
Rattus norvegicus Fiedld mouse
Macaca radiata Bonnet monkey
Review of secondary data (District Census Statistical Handbooks - 2001) with respect to
population, occupation structure and infrastructure facilities available for 10 km radius
67
study area. As per 2001 census the study area had a total population of 15, 557.Socio-
Economic status of the population is an indicator for the development of the region. Any
developmental project of any magnitude will have a bearing on the living conditions and
on the economic base of population in particular and the region as a whole. Similarly,
the proposed activities will have its share of socio-economic influence in the study area.
The section delineates the overall appraisal of society relevant attributes. The data
collection for evaluation of impact of proposed project on socioeconomic aspects in the
study area has been done through primary household survey method and through the
analysis of secondary data collected for the given study area.
68
Workers
Non Workers 1857 645 1212 65.16 1879
Households 670
69
TIRUVOTTIYUR (M) - WARD NO.3-URBAN
Parameter Total Male Female Percentage Sex Ratio
Population 5809 3006 2803 100 932
Population (0-6) 691 362 329 13.5 909
Scheduled Castes 2057 1051 1006 40.19 957
Scheduled Tribes 1 1 0 0.02 0
Literates 4201 2388 1813 82.08 759
Illiterates 1608 618 990 17.92 1602
Workers 1901 1619 282 32.73 174
Main Workers 1030 924 106 17.73 115
Main Cultivators 4 3 1 0.39 333
Main Agricultural
0 0 0 0 14
labourers
Main Workers in
household 6 8 1.36 1333
industries
Main Other Workers 1012 915 97 98.25 84
Marginal Workers 871 695 176 14.99 127
Marginal Cultivators 4 1 3 0.46 3000
Marginal
Agricultural 4 4 0 0.46 0
labourers
Marginal Workers
in Household 24 12 12 2.76 1000
industries
Marginal Other
839 678 161 96.33 237
Workers
Non Workers 3908 1387 2521 67.27 1818
Households 1260
71
Main Other Workers 1052 912 140 99.34 183
Marginal Workers 49 28 21 1.4 107
Marginal Cultivators 0 0 0 0 0
Marginal
Agricultural 0 0 0 2 0
labourers
Marginal Workers
in Household 2 4.08
industries
Marginal Other
47 28 19 95.92 679
Workers
Non Workers 2396 798 1598 68.38 2003
Households 800
72
industries
Marginal Other
100 1000 2235 833 1402
Workers
Non Workers 71.43 1683
Households 679
73
Population 3372 1691 1681 100 994
Population (0-6) 380 195 185 12.7 949
Scheduled Castes 1265 619 646 42.28 1044
Scheduled Tribes 0 0 0 0 0
Literates 2576 1391 1185 86.1 852
Illiterates 796 300 496 13.9 1653
Workers 1087 967 120 32.24 124
Main Workers 880 791 89 26.1 113
Main Cultivators 7 5 2 0.8 400
Main Agricultural
0 0 0 0 32
labourers
Main Workers in
household 22 10 3.64 455
industries
Main Other Workers 841 764 77 95.57 67
Marginal Workers 207 176 31 6.14 222
Marginal Cultivators 1 0 1 0.48
Marginal
Agricultural 2 1 1 0.97 1000
labourers
Marginal Workers
in Household 2 2 0 0.97 0
industries
Marginal Other
202 173 29 97.58 168
Workers
Non Workers 2285 724 1561 67.76 2156
Households 767
75
Marginal Workers 263 210 53 3.37 105
Marginal Cultivators 1 0 1 0.38
Marginal
Agricultural 5 5 0 1.9 0
labourers
Marginal Workers
in Household 16 4 12 6.08 3000
industries
Marginal Other
241 201 40 91.63 199
Workers
Non Workers 5171 1723 3448 66.18 2001
Households 1871
76
Marginal Other
95 75 20 97.94 267
Workers
Non Workers 3534 1208 2326 70.16 1925
Households 1167
77
TIRUVOTTIYUR (M) - WARD NO.13-URBAN
Parameter Total Male Female Percentage Sex Ratio
Population 4377 2197 2180 100 992
Population (0-6) 617 327 290 16.41 887
Scheduled Castes 290 150 140 7.71 933
Scheduled Tribes 101 58 43 2.69 741
Literates 2445 1338 1107 65.03 827
Illiterates 1932 859 1073 34.97 1249
Workers 1448 1192 256 33.08 215
Main Workers 1395 1158 237 31.87 205
Main Cultivators 2 0 2 0.14
Main Agricultural
1 1 0 0.07 1000
labourers
Main Workers in
household 22 5 17 1.58 3400
industries
Main Other Workers 1370 1152 218 98.21 165
Marginal Workers 53 34 19 1.21 1265
Marginal Cultivators 0 0 0 0 0
Marginal
Agricultural 0 0 0 2 2
labourers
Marginal Workers
in Household 0 3.77 0
industries
Marginal Other
51 32 19 96.23 594
Workers
Non Workers 2929 1005 1924 66.92 1914
Households 972
79
Main Other Workers 870 789 81 97.75 66
Marginal Workers 76 71 5 2.47 563
Marginal Cultivators 0 0 0 0 0
Marginal
Agricultural 0 0 0 0 0
labourers
Marginal Workers
in Household 0 0 76 71 5
industries
Marginal Other
100 70 2113 671 1442
Workers
Non Workers 68.63 2149
Households 717
80
industries
Marginal Other
217 178 39 98.19 219
Workers
Non Workers 3245 1092 2153 66.93 1972
Households 1155
81
Population 4052 2086 1966 100 942
Population (0-6) 445 235 210 12.34 894
Scheduled Castes 139 77 62 3.85 805
Scheduled Tribes 15 5 10 0.42 2000
Literates 3128 1696 1432 86.72 844
Illiterates 924 390 534 13.28 1369
Workers 1385 1210 175 34.18 145
Main Workers 1337 1174 163 33 139
Main Cultivators 6 4 2 0.45 500
Main Agricultural
2 0 2 0.15 0
labourers
Main Workers in
household 16 11 5 1.2 455
industries
Main Other Workers 1313 1159 154 98.2 134
Marginal Workers 48 36 12 1.18 972
Marginal Cultivators 1 1 0 2.08 0
Marginal
Agricultural 0 0 0 0 0
labourers
Marginal Workers
in Household 0 0 0 47 35
industries
Marginal Other
12 97.92 343
Workers
Non Workers 2667 876 1791 65.82 2045
Households 963
82
Main Workers 1347 1189 158 31.41 133
Main Cultivators 34 27 7 2.52 259
Main Agricultural
10 9 1 0.74 900
labourers
Main Workers in
household 4 2 2 0.3 1000
industries
Main Other Workers 1299 1151 148 96.44 118
Marginal Workers 105 70 35 2.45 200
Marginal Cultivators 14 5 9 13.33 1800
Marginal
Agricultural 1 0 1 0.95
labourers
Marginal Workers
in Household 2 0 2 1.9
industries
Marginal Other
88 65 23 83.81 354
Workers
Non Workers 2836 942 1894 66.14 2011
Households 1032
83
Marginal Workers 66 52 14 1.46 327
Marginal Cultivators 1 1 0 1.52 0
Marginal
Agricultural 3 1 2 4.55 2000
labourers
Marginal Workers
in Household 3 1 2 4.55 2000
industries
Marginal Other
59 49 10 89.39 204
Workers
Non Workers 2951 1024 1927 65.23 1882
Households 1039
84
Marginal Other
77.5 348 3089 1069 2020
Workers
Non Workers 67.31 1890
Households 1086
85
Population (0-6) 366 190 176 11.98 926
Scheduled Castes 85 40 45 2.78 1125
Scheduled Tribes 0 0 0 0 0
Literates 2835 1566 1269 92.8 810
Illiterates 586 245 341 7.2 1392
Workers 1273 1116 157 37.21 141
Main Workers 1212 1072 140 35.43 131
Main Cultivators 10 8 2 0.83 250
Main Agricultural
11 7 4 0.91 636
labourers
Main Workers in
household 47 29 18 3.88 621
industries
Main Other Workers 1144 1028 116 94.39 199
Marginal Workers 61 44 17 1.78 1114
Marginal Cultivators 2 0 2 3.28
Marginal
Agricultural 1 1 0 1.64 0
labourers
Marginal Workers
in Household 12 3 9 19.67 3000
industries
Marginal Other
46 40 6 75.41 150
Workers
Non Workers 2148 695 1453 62.79 2091
Households 831
86
Main Cultivators 10 2 8 1.32 4000
Main Agricultural
5 5 0 0.66 1000
labourers
Main Workers in
household 4 4 0 0.53 0
industries
Main Other Workers 741 583 158 97.5 148
Marginal Workers 105 56 49 4.08 339
Marginal Cultivators 2 1 1 1.9 1000
Marginal
Agricultural 0 0 0 0 0
labourers
Marginal Workers
in Household 0 0 0 103 55
industries
Marginal Other
48 98.1 873
Workers
Non Workers 1708 649 1059 66.38 1632
Households 521
87
Marginal Cultivators 0 0 0 0 1
Marginal
Agricultural 1 0 1.09 0
labourers
Marginal Workers
in Household 2 2 0 2.17 0
industries
Marginal Other
89 70 19 96.74 271
Workers
Non Workers 2958 967 1991 68.74 2059
Households 911
91
labourers
Marginal Workers
in Household 8 0 8 6.3
industries
Marginal Other
109 39 70 85.83 1795
Workers
Non Workers 2374 830 1544 64.86 1860
Households 826
92
TIRUVOTTIYUR (M) - WARD NO.32-URBAN
Parameter Total Male Female Percentage Sex Ratio
Population 4216 2190 2026 100 925
Population (0-6) 466 256 210 12.43 820
Scheduled Castes 41 19 22 1.09 1158
Scheduled Tribes 0 0 0 0 0
Literates 3385 1829 1556 90.27 851
Illiterates 831 361 470 9.73 1302
Workers 1409 1185 224 33.42 189
Main Workers 1208 1049 159 28.65 152
Main Cultivators 43 26 17 3.56 654
Main Agricultural
3 3 0 0.25 1000
labourers
Main Workers in
household 28 23 5 2.32 217
industries
Main Other Workers 1134 997 137 93.87 178
Marginal Workers 201 136 65 4.77 250
Marginal Cultivators 45 16 29 22.39 1813
Marginal
Agricultural 3 2 1 1.49 500
labourers
Marginal Workers
in Household 6 5 1 2.99 200
industries
Marginal Other
147 113 34 73.13 301
Workers
Non Workers 2807 1005 1802 66.58 1793
Households 977
96
Parameter Total Male Female Percentage Sex Ratio
Population 4259 2193 2066 100 942
Population (0-6) 465 239 226 12.26 946
Scheduled Castes 419 218 201 11.04 922
Scheduled Tribes 0 0 0 0 0
Literates 3413 1831 1582 89.96 864
Illiterates 846 362 484 10.04 1337
Workers 1423 1199 224 33.41 187
Main Workers 1352 1167 185 31.74 159
Main Cultivators 2 1 1 0.15 1000
Main Agricultural
19 19 0 1.41 1000
labourers
Main Workers in
household 17 8 9 1.26 1125
industries
Main Other Workers 1314 1139 175 97.19 210
Marginal Workers 71 32 39 1.67 313
Marginal Cultivators 1 0 1 1.41
Marginal
Agricultural 2 2 0 2.82 0
labourers
Marginal Workers
in Household 4 0 4 5.63
industries
Marginal Other
64 30 34 90.14 1133
Workers
Non Workers 2836 994 1842 66.59 1853
Households 1002
97
Workers 1054 860 194 33.19 226
Main Workers 1031 847 184 32.46 217
Main Cultivators 5 2 3 0.48 1500
Main Agricultural
2 1 1 0.19 500
labourers
Main Workers in
household 17 11 6 1.65 545
industries
Main Other Workers 1007 833 174 97.67 181
Marginal Workers 23 13 10 0.72 923
Marginal Cultivators 0 0 0 0 0
Marginal
Agricultural 0 0 0 0 0
labourers
Marginal Workers
in Household 0 0 23 13 10
industries
Marginal Other
100 769 2122 726 1396
Workers
Non Workers 66.81 1923
Households 705
98
Main Other Workers 1108 961 147 95.85 14
Marginal Workers 52 40 12 1.4 8475
Marginal Cultivators 0 0 0 0 1
Marginal
Agricultural 0 1 1.92
labourers
Marginal Workers
in Household 0 0 0 0 51
industries
Marginal Other
40 11 98.08 275
Workers
Non Workers 2513 894 1619 67.54 1811
Households 861
99
industries
Marginal Other
15 6 9 55.56 1500
Workers
Non Workers 1801 661 1140 69.11 1725
Households 573
100
Population 4927 2532 2395 100 946
Population (0-6) 575 301 274 13.21 910
Scheduled Castes 250 129 121 5.74 938
Scheduled Tribes 4 2 2 0.09 1000
Literates 3669 2026 1643 84.31 811
Illiterates 1258 506 752 15.69 1486
Workers 1707 1453 254 34.65 175
Main Workers 1657 1414 243 33.63 172
Main Cultivators 0 0 0 0 0
Main Agricultural
0 0 0 25 10
labourers
Main Workers in
household 15 1.51 1500
industries
Main Other Workers 1632 1404 228 98.49 85
Marginal Workers 50 39 11 1.01 2282
Marginal Cultivators 1 1 0 2 0
Marginal
Agricultural 0 0 0 0 1
labourers
Marginal Workers
in Household 0 1 2 48 38
industries
Marginal Other
10 96 263 3220 1079
Workers
Non Workers 2141 65.35 1984
Households 1176
101
Main Workers 3162 2751 411 28.65 149
Main Cultivators 16 4 12 0.51 3000
Main Agricultural
9 8 1 0.28 889
labourers
Main Workers in
household 82 58 24 2.59 414
industries
Main Other Workers 3055 2681 374 96.62 381
Marginal Workers 468 379 89 4.24 47
Marginal Cultivators 1 1 0 0.21 0
Marginal
Agricultural 1 1 0 0.21 0
labourers
Marginal Workers
in Household 23 14 9 4.91 643
industries
Marginal Other
443 363 80 94.66 220
Workers
Non Workers 7407 2554 4853 67.11 1900
Households 2567
102
Marginal Workers 46 28 18 1.18 1286
Marginal Cultivators 0 0 0 0 2
Marginal
Agricultural 0 2 4.35
labourers
Marginal Workers
in Household 18 15 3 39.13 200
industries
Marginal Other
26 13 13 56.52 1000
Workers
Non Workers 2700 977 1723 69.44 1764
Households 890
103
Marginal Other
133 99 34 98.52 343
Workers
Non Workers 3194 1069 2125 64.46 1988
Households 1213
104
Population 6710 3507 3203 100 913
Population (0-6) 714 372 342 11.91 919
Scheduled Castes 1555 802 753 25.93 939
Scheduled Tribes 11 8 3 0.18 375
Literates 5321 2953 2368 88.74 802
Illiterates 1389 554 835 11.26 1507
Workers 2129 1890 239 31.73 126
Main Workers 1791 1606 185 26.69 115
Main Cultivators 6 2 4 0.34 2000
Main Agricultural
1 0 1 0.06 0
labourers
Main Workers in
household 30 23 7 1.68 304
industries
Main Other Workers 1754 1581 173 97.93 140
Marginal Workers 338 284 54 5.04 81
Marginal Cultivators 0 0 0 0 1
Marginal
Agricultural 0 1 0.3
labourers
Marginal Workers
in Household 7 0 7 2.07
industries
Marginal Other
330 284 46 97.63 162
Workers
Non Workers 4581 1617 2964 68.27 1833
Households 1563
105
Main Workers 1387 1244 143 28.47 115
Main Cultivators 6 5 1 0.43 200
Main Agricultural
4 3 1 0.29 750
labourers
Main Workers in
household 2 0 2 0.14
industries
Main Other Workers 1375 1236 139 99.13 23
Marginal Workers 132 109 23 2.71 5706
Marginal Cultivators 4 1 3 3.03 3000
Marginal
Agricultural 1 1 0 0.76 0
labourers
Marginal Workers
in Household 1 0 1 0.76
industries
Marginal Other
126 107 19 95.45 178
Workers
Non Workers 3353 1165 2188 68.82 1878
Households 1153
106
4. ENVIRONMENTAL IMPACT ANALYSIS
4.1. INTRODUCTION
This section identifies and assesses the potential changes in the environment that could
be expected from the proposed project. The impacts have been predicted for the
proposed activities assuming that the impact due to the existing activities has already
been covered under base line environmental monitoring and continue to remains same
till the operation of the project. The proposed project activities would create impact on
the environment in two distinct phases i.e., construction and operation phases. Impacts
are identified, predicted and evaluated based on the analysis of the information
collected from following:
This section also describes mitigation measures, which have been suggested for the
adverse impacts likely to be caused due to activities of both construction and operation
phases of the project.
The identification of likely impacts during construction and operational phases of the
proposed project has been done based on likely activities having their impact on one or
another environmental parameters. The details of the activities and their impacts have
been worked out in the following sections.
107
4.2. IDENTIFICATION OF LIKELY IMPACTS
Every activity and operation has either adverse or beneficial impacts on the
environmental. The environmental impact identification has been done based on
proposed project activities. All the activities from construction phase to operational
phases of the project have been broadly covered, which is given in Table 4.1 and 4.2.
The activities and operations are considered on the basis of proposed process as
described in the Project Description Section 2.
108
Table 4-1 Activity-Impact Identification Matrix for Construction Phase of the Proposed Project
Construction phase Potential impacts
Culture/ Heritage
Agriculture in the
Socio –economic
Surface /Ground
water resources
Water Quality
Resource use
Main Activities Sub Activities
surroundings
environment
Solid waste
generation
Air Quality
Landscape
Land/Soil
Land use
(Energy)
Ecology
density
Site Site Clearing & Cleaning
Preparation Ground leveling √ √ √ √ √ √
Waste handling and its transportation
Soil Compaction
Labour Construction of Labour sheds to
deployment accommodate labour
camp siting Supply of water √ √ √ √ √ √ √ √ √
Supply of fuel/ Energy
Waste handling & its disposal
Sewage disposal
Excavation Moving of Heavy Machinery
Soil Extraction and Slacking
Soil Loading and Transportation for
Disposal
√ √ √ √ √ √ √
Various Tools Like Crow Bar
Foundations for heavy machinery
installation
Construction Power through onsite
Diesel Generators
109
Material Transportation and Unloading of
handling & material from trucks
Storage Storage &Handling of steel sheets,
√ √ √ √ √ √ √
metals, Fabricated structure, Cement,
Concrete, Bricks, Steel etc.
Conveyance of material within the
project site
Plant Building Transportation of material to
construction construction site
Preparation/ Mixing of construction
material
Supply of water Operation of √ √ √ √ √ √ √ √ √ √ √ √
construction machinery (like cranes,
Concrete Mix Plant, Floor Developer,
Forklift etc,) Handling and disposal of
construction wastes , Diesel
Generator Operation
Erection of Erection of sheds -welding/ cutting
sheds, onsite Installation .of heavy
installation of machinery, pumps Mechanical
Machinery installation and sand blasting
√ √ √ √
Building Electrical installation Drilling and
Fittings Fixing Painting/ White washing
&Furnishing Disposal of Wastes (empty paint cans,
containers, electrical waste, wooden
and metal waste etc.)
Demobilization Dismantling of temporary support
of construction construction structures/ equipments
equipment Removal of construction machinery √ √ √ √ √
Transportation of Construction/
Dismantled waste
Site cleaning/ washings
Site Trials functioning of
Commissioning Production &Warehousing units,
Conveying and packing system,
√ √ √ √
plumbic fixtures, Electrical gadgets,
Fire fighting system, Effluent
treatment plant, Lifts etc.,
Recruitments
110
Table 4-2 Activity – Impact Identification Matrix for Operation Phase of the Proposed Project
soil quality
Air quality
Ecological
Potential
resources
resources
economic
Land and
Land use
Cultural
hazards
tourism
cultural
Ground
pattern
volume
Surface
quality
quality
impact
Traffic
Onsite
Water
water
water
risks-
Noise
Socio
Agri
Activities
Employment √
√ √
111
4.3. IMPACTS IDENTIFIED
Based on activity – impact interaction matrix for construction and operation phase of
the proposed project as shown in Table 4.1 & 4.2 respectively, following impacts have
been identified:
ii. Operation phase of the project would have likely impacts on the following
• Air Quality
• Water Quality
• Ground water Resources & Surface water Resources
• Land and Soil Quality
• Noise Quality
• Traffic Volume
• Ecological
• Socio-economic
• Onsite Risks – Hazards
112
4.3.1. Construction Phase
The proposed facility is being developed at Thiruvottiyur zone, Tamil Nadu. The
development period for the initial phase is considered as 1 to 2 years.
The likely temporary and permanent changes on the topography of the site would be
following:
• Air quality in and around the project site would be impacted to some extent due
to construction and construction related activities. The main impact will be
• During site leveling, excavation, construction material handling etc., the likely
emissions from construction activities would include the following:
• Fugitive dust emissions from excavation work, digging, stacking of soils, filling,
handling of construction material, transportation of material, emission due to
movement of tyres and plying of heavy construction machinery etc.,
• Traffic movement at the site and also increase in traffic volume on the
connecting roads will rest in increase in vehicular emissions and
• Gaseous emissions from operation of diesel generators for power requirement
during construction phase.
113
• However, the fugitive and other emissions due to the construction activities will
most likely remain localized and confined to the project area, but adequate
mitigation measures would be required to reduce the pollutant concentration
and prevent their spread around the site.
• The impact of emissions both from tyre movements and vehicular exhaust
emissions required to be minimized by proper maintenance of vehicles,
sprinkling of water on unpaved roads at the construction site and planned
movement of vehicles.
• The emissions from diesel generators need to be controlled to minimize impacts
of air emissions by optimized operations, orientation at the site and providing
adequate stack height for wider dispersion of gaseous emissions.
• Drawn conclusion is that no significant impact on air quality is envisaged due to
construction and related activities. Any impact on air quality will likely be
restricted within the localized area. Application of adequate mitigation measures
by the Construction Management Contractors will further reduce the intensity of
such impacts.
• Construction of Proposed Project would be carried out. However, construction
dust from Proposed Project was not considered as a key issue and therefore dust
impact from the proposed project is considered insignificant. In addition, no
other dust emitting activities has been identified to be carried out concurrently
with the proposed Project.
The major sources of noise due to construction activities can be classified under three
heads.
The mains concerns during construction activities are the emissions generated by the
vehicles and the machineries. The main emissions are the noise and the vibrations,
which have been discussed below.
Noise generation disturbs the community residing nearby the site. The main sources of
noise in the process of construction and demolition activities are pulverizing, cement
concrete mixing, welding, aluminum channel folding, drilling and several other
machineries and Vibrations are caused due to heavy dumpers, DG sets, machineries and
bulk careers. These affect the vegetation, organisms as well as the structures on the site
too. There is a risk of hearing disorder in the workers.
It is envisaged that operation of these construction material will generate noise levels
between 75-80 dB (A). The combined effect of these noise sources may cross 90 dB (A)
at the construction site, however noise dissipates as it spreads in area beyond the site
boundary. There will be requirement of providing adequate mitigation measure so that
at the boundary of the construction site, the noise level can be kept less than 75 dB (A).
Noise not only interferes with the communications but also affects peace of mind, health
and behavior. Sudden loud sound can cause acute damage to the eardrum and the tiny
hair cells in the internal ear whereas prolonged noise result in a temporary loss of
hearing or even permanent impairment. It not only causes headache and irritability but
also affect the sensory and nervous system of the body.
Any behavioral changes are recorded as a result of exposure to high-level noise not only
in human being but also in animals. The undesired sound may cause annoyance. Noise
can cause tension in muscles, nervous irritability and strain. Several birds have been
observed stop-laying eggs; animal’s changes their places, and also stop migration of
birds.
115
4.3.1.3. Impact on Water Quality
During the construction process, it is necessary to use pure drinking water to prepare
lightweight concrete. It is expected that no wastewater from construction activities will
be generated onsite during construction activities except domestic sewage from
campsite. Proper mitigation measures (like provision of sewage collection tank and
soak pit) for treatment and disposal will be required for the sewage-generated onsite
during the construction phase. This will minimize any potential impacts due to
escape/discharge of untreated sewage into the nearby land or drain.
During the construction process, it is necessary to use pure drinking water to prepare
lightweight concrete; In the absence of pure water, the seawater may be used with
hydraulic lime and cement. It helps in preventing too quick drying of the-mortar.
However, it is not advisable to use sea water in making pure lime mortar or surkhi
mortar because it will lead to efflorescence.
116
A major source of terrestrial water quality impact will be run-off from storm water, and
site construction activities associated with construction works. Minimal water quality
impact is anticipated for lying of inlet pumping mains. Pollutants in the runoff would
mainly contain suspended solids from excavation or dredging and/or oil and grease
from mechanical equipment operation. Such runoff may pollute the receiving waters
when entering the river environment.
Runoff water has to be properly diverted, collected, settled, and returned to the inlet of
the sewage treatment works as much as practicable for further settling and treatment.
The following solid wastes are likely to be generated during the initial construction
phase:
Materials and equipment used on site would produce packaging and container wastes.
Mitigation measures should include provision of a collection area where waste can be
stored and loaded prior to removal from the site. The volume of general site wastes
generated will be dependent on the Contractor’s operating procedure and practices and
cannot be quantified. With the implementation of the recommended mitigation
measures (including site practices), the potential environmental impacts resulting from
the storage, handling and transportation of general site wastes would be minimal.
b) Workforce Wastes
Construction plant and equipment will require regular maintenance and servicing,
which would generate waste. Substances generated are likely to include some chemical
wastes such as cleaning fluids, solvents, lubrication oil and fuel. Equipment
maintenance activities would also involve the use of a variety of chemicals, oil and
lubricants, including heavy-duty cleaners, organic solvents, degreasers, brake fluids,
battery acid and soldering fluids.
Chemical wastes arising during the construction phase may pose serious environmental,
health and safety hazards if not stored and disposed of in an appropriate manner as
outlined in the Chemical Waste Regulations (CWR). These hazards include:
d) Ecology
118
e) Socio-economic
The proposed project will also employ skilled people and that may be sought from
outside. These people will largely be based in nearby small towns.
Overall, the construction phase will have positive impact on socio-economic condition of
the people in the area, as it will provide direct and indirect revenues of income
generation.
119
• As the sludge pumping system is confined to pipes, the odour emission from it is
also considered insignificant.
The major noise generating equipment during operational phase are the air blowers,
ventilation fans, water pumps and DG Sets.
The noise impact on the surrounding areas from the pumping station is not expected to
be significant since it is to be enclosed in a concrete structure.
Noise generation due to plying of vehicles on the roads bringing raw material and taking
finished products can be reduced by proper time scheduling and planning.
The Proposed STP aims at improving overall ground water quality of Chennai. Raw
sewage from Chennai households would be collected, treated and discharged via the
proposed river outfall. After primary & biological treatment process, the pollution load
entering into the river environment would be almost nil compared with the existing
conditions. The impact from the proposed Project is considered to be positive. The
environmental impacts identified during operational phase are the chemical species of
concern which exists in the sewage effluent.
d) Chlorination
Chlorination will be used in Proposed STP for disinfection purpose in the effluent.
120
e) Emergency Overflow
The emergency overflow events are anticipated in case of pump failure, the electrical
power supply interruption, mechanical failure of primary, secondary and tertiary
treatment units, .disinfection units, as well as blockage of river outfall. These emergency
overflow events· is expected to be iii-frequent and of short duration. The emergency
overflow due to electrical power supply interruption will be prevented by using DG Set.
Sludge will be produced from the primary and secondary biological treatment of the
sewage. The arrangements of sludge dewatering and disposal, namely on site centrifuge
dewatering scheme would be adopted. The dewatered Sludge would be used as manure.
The wet-sludge would be stored on site temporarily and would be barged for further
treatment at regular intervals to prevent any excessive odour emission. The storage
container would be covered to minimize the potential odour nuisance.
The grit collected from the pumping stations will be utilized for filling the low lying
areas. The screenings removed from the pumping stations &process will be given to
concerned local body for disposal into Solid Waste Management Facility.
121
4.3.3. MITIGATION MEASURES
The impacts during the construction phase on the environment would be basically of
transient nature and expected to reduce gradually on completion of the construction
activities. In order to mitigate them, the following measures are proposed.
• The construction site would be provided with sufficient and suitable toilet
facilities for workers to maintain proper standards of hygiene. These facilities
include provision of septic tank followed by soak pit and maintained to ensure
minimum impact on nearby water bodies and environment;
• The diesel generators (DG Sets) to be installed will be in conformance with
recent requirement of acoustic enclosure to achieve 75 dB (A) level at 1m from
its enclosure. It is also advisable that on site workers using high noise equipment
adopt noise personal protective devices;
Some good practices in construction facilitate waste reduction, easy collection and
segregation as given below.
122
site only. Crushed masonry and concrete is even good for manufacture of
synthetic aggregate.
4. The recyclable items like metal, plastic should be sent to recyclable industry, and
rest of this scrap should be stored in a covered area.
5. Dry processes of construction are effective for reduction of water requirements
and even the waste generation. Use of Interlocking bricks, pre-cast roofing and
wall panels etc. will be suitable for this purpose.
6. Materials, which are durable and do not require frequent maintenance, should be
used. Exposed brickwork in hot and dry climate with Class I bricks requires
minimum maintenance. Instead of using stone masonry, stone cladding is a
better way to minimize the maintenance.
7. Wherever materials (aggregates, sand, etc.) are more likely to generate fine
airborne particles during operations, nominal wetting by water could be
practiced. Workers / labour should be given proper air masks and helmets.
8. Skilled labour and good workmanship is must for judicial utilization of materials
and minimizing the waste.
9. Construction is more of management. Proper estimate of material is a very first
measure to minimize the undue wastage.
10. Contaminated runoff from storage should be captured in ditches or ponds with
an oil trap at the outlet. Contaminated plastic sheeting should be packed and
disposed off site.
11. Communities nearby the blasting site should be consulted before deciding
blasting timings / durations and they should be informed / evacuated as
required with the knowledge of the district collector’ office.
12. Bitumen emulsion should be used wherever feasible. Contractors should be
encouraged to heat with kerosene, diesel or gas to gradually substitute fuel
wood. Fuel wood usage for heating should be limited to unsound log i.e. dead and
fallen trees.
13. Bitumen should not be applied during strong winds to avoid danger of forest fire.
Bitumen emulsion should not be used in rains. No bitumen must be allowed to
flow into the side drain. The bitumen drums should be stored in a designated
place and not be scattered along the roadside.
123
14. Rubbish, debris and bitumen wastes remaining after blacktop works should be
cleaned and disposed off in a safe place.
15. Materials wasted on site should be reused at the same place. For example, use of
excavated earth in landscaping, or use of waste pieces of floor tiles in floor of
porch or outdoor spaces, or use of remaining pieces of glass from window panes
into ventilators, skylights and boundary wall, or reuse of ply and other timber
pieces into furniture etc.,
These practices suggest the measures for reduction of waste. However, each type of
waste needs special attention and specific kind of management, as the wastes from
different activities poses different characteristics.
The Air Pollution Control (Construction Dust) Regulations shall be implemented during
the construction activities to minimize the dust impact. It is recommended that typical
dust control methods including the following good site practices should be incorporated
during construction phase:
Vegetation buffers can minimize the build –up of Air pollution levels in urban areas by
acting as pollution sinks. Studies have established that air pollution, smoke and sulphur
di oxide leads to an exacerbation of chronic respiratory diseases and they are linked to
lung cancer, pneumonia, tuberculosis, chest disease in children, stomach cancer and
124
cardiovascular diseases. Lead from vehicle exhausts may have an adverse effect on
mental health of children, asbestos from disintegrating clutch and break linings has
been considered as a casual factor in lung cancer.
Plant leaves function as efficient gas exchange system. Their internal structure allows
rapid diffusion of water soluble gases. These characteristics allow the plant to respire
and Photosynthesis and they can also remove pollutant from the air. Some of the
beneficial results of plantations may be
• They are good absorbers of sulphur dioxide. Parks with trees have an SO2 level
lower than city streets
• Roadside hedges can reduce traffic generated air borne lead, on leeward side
• Heavy roadside planting in the form of shelterbelts can result in reduction in
airborne lead
• Complete dust interception can be achieved by a 30 m belt of trees. Even a single
row of trees may bring about 25 percent reductions in airborne particulate
• Trees, shrubs should have dense foliage with a large surface area, because leaves
absorb pollutants.
• Evergreen trees are found to be more effective.
• The species chosen must be resistant to pollutants, particularly in the early
stages of their growth.
The following species may be examined for their likely potential for pollution control:
125
• Tamarindus indica (Imli)
• Thuja occidentallis (Cedar)
• Prospis Juliflora (Mesquite)
• Zizypus jujuba (jujuba), etc.
Filtering of pollutants is most effective when plants are close to the source of pollution.
The design of shelterbelts against pollution is similar to those for protection from wind.
They should be permeable to encourage air turbulence and mixing within the belt.
There should be no large gaps. The profile should be rough and irregular and should
present a tall vertical leading edge to the wing. Spaces should be left within the
shelterbelt to allow gravity settlement of particles.
a) Paving- Paving is a more permanent solution to dust control, suitable for longer
duration projects. Paving may be an appropriate solution for access roads to large
development projects, where the road can eventually be incorporated in the overall
plan for the area. Another appropriate use of paving might be "maintenance" projects,
such as parking lots and material storage areas, where gravel cover is not adequate for
dust control or erosion.
Applying Dust Suppressants - There are many types and brands of chemical dust
suppressants which work by binding lighter particles. Biodegradable suppressants may
be applied as a surface treatment to "seal" the top of an area, or may be applied using a
mixing method that blends the product with the top few inches of the land surface
material. It is important to note that used oil may NOT be used as a suppressant.
b) Graveling- Applying locally found gravel to access roads and lots adds a
protective layer over the exposed soil and helps control dust generation in some
situations. It is important that gravel contain a minimal percentage of fines and clean
gravel be added periodically, as the fines migrate to the surface and create dust.
126
Using Water Sprays - Water spray through a water truck for large projects, is an
effective way to keep dust under control. Misting systems and sprinklers are
mechanisms that can be employed to deliver continuous moisture. Keep in mind,
however, that fine mists should be used to control fine particulate. The size of the water
droplet must be comparable to the size of the dust particle so that the dust adheres to
the water.
There are several constraints to using water. Water can be very costly for larger
projects in comparison to other methods. Heavy watering can also create mud, which
when tracked onto paved public roadways, must be promptly removed. Also, there must
be an adequate supply of clean water nearby to ensure that spray nozzles don’t get
plugged.
c) Reducing Vehicle Speed - High vehicle speeds increase the amount of fugitive
dust created from unpaved areas. Reducing the speed of a vehicle to 20 kmph can
reduce emissions by a large extent. Speed bumps are commonly used to ensure speed
reduction. In cases where speed reduction cannot effectively reduce fugitive dust, it may
be necessary to divert traffic to nearby paved areas.
127
e) AMBIENT NOISE QUALITY
The other norms for DG sets are that the diesel generator sets should be provided with
integral acoustic enclosure at the manufacturing stage itself. There must be sufficient
space for Fuel Tank inside canopy. There must be enough space to house panel. There
must be Strong and Heavy-duty steel base frame for housing D.G. Set. There must be
provision for Air-Intake and Air-Exhaust silencer(s) for preventing leakage of sound.
There must be a provision of Operable doors for easy access to virtually every part of
D.G. Sets. There must be Provision of additional screen and hoods for multi-medium
noise suppression.
Noise limits for DG sets- The maximum permissible sound pressure level for new diesel
generator (DG) sets with rated capacity up to 125 KVA, manufactured on or after the 1st
July, 2003 shall be 75 dB(A) at 1 meter from the enclosure surface.
The Canopies are must for DG sets and must meet CPCB norms of government of India
for noise Pollution effective July 2004 and Environment protection Rules, 1986 schedule
1, by Ministry of Environment and Forests.
128
Measures for quality control of various water source such as fresh water, underground
water, municipal, tankers, rainwater and recycled water.
• Curing water should be sprayed on concrete structures; free flow of water should
not be allowed for curing.
• After liberal curing on the first day, all concrete structures should be painted
with curing chemical to save water. This will stop daily water curing hence save
water.
• Concrete structures should be covered with thick cloth/gunny bags and then
water should be sprayed on them. This would avoid water rebound and will
ensure sustained and complete curing.
• Ponds should be made using cement and sand mortar to avoid water flowing
away from the flat surface while curing.
• Water pounding should be done on all sunken slabs; this would also highlight the
importance of having an impervious formwork.
To minimize the potential water quality impacts from construction site runoff and
various construction activities. Perimeter channels are to be installed in the works areas
to intercept runoff at site boundary prior to the commencement of any earthwork.
Intercepting channels are to be provided to prevent storm runoff from washing across
exposed soil surfaces. Drainage channels are also required to convey site runoff to
sand/silt traps and oil interceptors. Regular cleaning and maintenance are to be
provided to ensure the normal operation of these facilities throughout the construction
period.
It is anticipated that the wastewater generated from the works areas would be in small
quantity as the construction scale is not considered large. The construction programme
should be properly planned to minimize soil excavation in rainy seasons. This would
prevent soil erosion from the exposed soil surfaces. Any exposed soil surfaces should
129
also be properly protected to minimize dust emission. Exposed stockpiles should be
covered with tarpaulin or impervious sheets at all times.
Good site practices should be adopted to clean the rubbish and litter on the construction
sites so as to prevent the rubbish and litter from dropping into the nearby river
environment. It is recommended to clean the construction sites on a regular basis.
a) Air environment
The gaseous pollutants will be generated mainly from Diesel Fuel combustion from
diesel generators, material handling and also from operation of transportation vehicles.
Following measures should be taken up for control of gaseous emissions:
The emission' source i.e., diesel generators will have adequate stack height will
conformance to the set norms of GPGS as described in section
Diesel generators will be operated only for emergency power backup. Regular
maintenance of diesel engines has to be ensured;
A part from the above, the possible sources of dust emission will be the transportation
vehicles. These will mainly contribute to NOx and Carbon Monoxide. Since the truck
trips are less, vehicular emissions will be insignificant. However, management will
ensure that all the private and commercial vehicles entering into the site are in proper
condition and there is no visual sign of major emissions from the vehicles. Also it is to be
ensured that all the vehicles are regularly holding valid Pollution under Control
Certificates. The recommended mitigation measure to minimize potential odour impact
130
is to enclose all the major odour sources. The sludge should be carried by enclosed
container during sludge transportation.
Discharge of treated effluent will be diverted to the emergency overflow pipe if the case
of damage of river outfall pipe. Under normal circumstance, each process unit will be
backed up with a standby unit. .The standby generator will ensure the continuous
electricity supply for the STP. From the water quality point of view, the discharge of
treated effluent from the emergency overflow pipe will likely meet the minimum
effluent standard for this project. As such, the emergency overflow pipe serves as a
standby unit for the river outfall pipe from this perspective.
For conditions where damages occurred in any of the STP unit, standby unit will be
operated and the designed treatment capability would be restored immediately to
ensure that water quality of the effluent can meet the discharge requirement. Hence, no
observable impact to both the canal outfall and the emergency overflow pipes is
anticipated. Under abnormal conditions where any treatment units fail to achieve the
targeted effluent quality, the impact to the receiving water body can be alleviated
through the dilution after discharging from the canal outfall or emergency overflow
pipes. Notwithstanding that the chance of such failure is unlikely to occur, the impact is
considered acceptable as the effect will only happen in short-run.
In the case of STP overflow, raw sewage may also be diverted to emergency overflow
outfall although discharge through river outfall is more preferable for dilution and
dispersion. In an extreme situation where no electricity supply is available (including
the failure of the standby generator), the impact from the untreated raw sewage can
also be alleviated through the initial dilution after discharging from river outfall for
emergency overflow pipes. Although the level of E coli. may be over the acceptable
131
range, this approach is considered as the best option in view of the low chance of
discharging the raw sewage directly to the receiving body in a long run.
Based on the above, it is extremely unlikely that major duty and standby units of the
STP, the river outfall pipe and electricity supply would have problem simultaneously.
Besides, it is very rare that the event will last for a long time. Hence, the probability of
diverting the discharge via emergency overflow is quite low.
The Sludge would be dewatered on site by centrifuge and utilized as manure in the later
stage of STP operation when necessary. The grit collected from the pumping stations
will be utilized for filling low lying areas. The screenings removed from the pumping
stations & process will be given to concerned local body for disposal into Solid Waste
Management Facility.
It is also recommended to cover the storage container before disposal to minimize the
potential odour nuisance.
d) Socio-Economic aspect
132
5. ENVIRONMENTAL MANAGEMENT PLAN
5.1. OBJECTIVES
There is no activity of tree cutting for the proposed STP. Hence, no need to implement
the precautionary measures to mitigate the impacts due to clearing of vegetation during
the construction phase.
Green belt of 6800 m2 is proposed to implement in the project site and around 600 trees
134
5.2.2.1. Managing Impacts due to movement of Construction Machinery
In operational stage, one DG set of capacity 125 KVA will be installed with inbuilt
The potential impacts on the Noise environment envisaged from the proposed facility
Construction Activity
Vehicle Movement
Sources of noise pollution during the construction of the facility is from the plant and
machinery comprising of mainly bull dozers, Front end loaders, standby generators, and
other heavy earth machinery used in construction in addition to the vehicular
movement within the project boundary.
The major noise generating equipment during operational phase is the air blowers,
ventilation fans, water pumps and DG Sets.
The noise impact on the surrounding areas from the pumping station is not expected to
be significant since it is to be enclosed in a concrete structure. Noise generation due to
plying of vehicles on the roads bringing raw material and taking finished products can
be reduced by proper time scheduling and planning.
136
Table 5-2 Impact and Mitigation Measures for Noise Emissions
S.No Sources of Impact Mitigation Measures
The acoustic enclosure will be of free standing, floor mounting type integral with the DG
set. The enclosure will be provided with rugged heavy-duty structural steel base frame
with chequered plate flooring on which the DG set is to be mounted. The enclosure will
be prefabricated factory – built and modular in construction, so that it can be easily
assembled at site around the DG set. The enclosure will consist of acoustically treated
137
panels housed in rugged steel frames, which will be bolted together to form the body of
the enclosure. Sliding doors will be provided, on either side, which will also be
acoustically treated, thereby providing easy access to the DG set while minimizing the
operating space requirements. The construction of the acoustic enclosure will be such
that with both the acoustic doors open on the either side, full access is available to the
engine and attenuator. For fresh air inlet into the system a parallel baffle air inlet
silencer will be provided. Additionally, to augment the fresh air inlet requirements, a
forced air ventilation duct with associated silencer will be provided above the
alternator. For hot air discharge, an acoustic discharge plenum will be provided in front
of the engine radiator, for discharge of hot air into the surroundings through a parallel
baffle air outlet silencer. The enclosure will have suitable openings in the roof module
for exhaust piping. Acoustic enclosure Designed to meet stringent MoEF/ CPCB norms
of 75 dBA at 1mtr at 75% load under free field conditions.
Accessories:
Silencer suitably optimized to meet stringent sound emission standards
laid down by MoEF / CPCB
Base rail with integral fuel tank (285 liters capacity) is provided with
drain plug, air vent, inlet and outlet connection, level indicator, manhole
etc.
2 x 12 V dry, uncharged batteries with connecting leads and terminals
Acoustic enclosure:
Specially designed to meet stringent MoEF/ CPCB norms of 75 dBA @
1mtr at 75% load under free field conditions
Designed to have optimum serviceability
Air inlet louvers specially designed to operate at rated load even at 500C
air inlet temp.
Made on special purpose CNC machines for consistency in quality and
workmanship
Powder coated for long lasting service life and superior finish
With UV resistant powder coating, can withstand extreme environments
138
Use of stainless steel hardware
Insulation material meets exacting IS 8183 specs for better attenuation
Construction activities and the consequent transportation activities add to the air
pollution in the region. Impact of the air pollution will be moderate and short term at
sewage pumping stations, STPs and while laying sewer lines.
139
5.2.5. MANAGING IMPACT DUE TO LABOUR CAMPS
Considering the long construction period of the project, the local and migrant labourers
will pose some stress on utility services, such as water supply and sanitation.
Planning of labour camps needs to be done with adequate water supply, sanitary
facilities and drainage in temporary colonies of the construction workers, necessary
transportation facilities to the labourers will be provided.
The main pumping station is located inside the project site. The land to be alienated for
locating the pump house is open land without squatters or structures, or trees or crops.
There are no project affected persons (PAPs). The possible environmental issues are (a)
Noise (b) Smell.
The pump house is located sufficiently away from the dwelling areas. Adequate care
would be taken to ensure that the noise levels of the pumps and motors are within
permissible limits. Trees will be planted around the pump houses to reduce the noise.
Spillage of sewage in the pump house will be avoided to ensure that there is no bad
smell emanating from the area. UGSS are responsible for Main Pumping Station.
Pumping main will be laid along the beam of the road. The possible environmental issue
is leakage from the pipeline leading to smell and soil/water contamination. During
installation pipeline would be tested to ensure that there would be no leakage. The
pumping main will be inspected at regular intervals and any leakages noticed will be
attended at the earliest notice.
140
5.2.5.4. Safety Measures:
The station site will be enclosed with 1.8m chain link fence, lockable gates,
designed to discourage entry by unauthorized persons and animals.
Provide safety, unauthorized entry and municipal address signage, as per City
standards;
Handrails and guards will be installed around tanks, trenches, pits, stairwells,
and other hazardous areas.
All personnel must be trained to operate and maintain pumping station
equipment and facilities to the satisfaction of the Pollution Control Operation.
Gas detection and monitoring equipment where required. Where gas alarms are
provided, install an indicator light outside the building so that the operator can
check gas levels before entering the building.
Portable ventilation and blower equipment, intrinsically safe, with sufficient
hose, where required;
Portable lighting equipment intrinsically safe, where required;
Confined space entry shall comply with the Pollution Control Operation and
OHSA regulations.
Facility design and layout shall have due regard to make confined space entry
user friendly, optimizing sight and retrieval lines.
Adequate ventilation in pumping chambers.
Within the plant site during construction phase, the base emanating such as toilet,
drinking water, electricity health and safety gadgets will be provided.
1. All personnel in the construction area to wear safety gears such as shoes, helmets,
hand gloves.
141
2. All personnel working at height to wear Safety belt clinged on to nearby permanent
support System.
3. Approved scaffold materials will be used during construction.
4. All Construction will be carried out after necessary approvals from the respective
Municipal authority. Deviations shall be recorded and notified to concern parties for
approval before construction.
5. The person who works in the welding areas of the pipeline will be provided with
goggles, welding shield, gloves etc, as protective measures.
6. Electrical workers who undertake works in electrical cabeling, transformer erection,
high tension poles erection areas will be provided with electrical hand gloves, gum
boots etc as preventive safety measures.
7. During erection of underground pipelines and tank surface connecting areas, proper
work permit will be given and approved by Project Manager and then the work will be
executed.
1. All O&M personnel will be provided with Personal Protective Equipments (PPE) for
protection from hazardous or harmful substances. PPE includes gloves, face shields,
goggles, helmets and other protective shields, canisters and barriers.
2. Standard operating procedures will be provided for the workers involved in the O&M
of STP and the same procedure will be followed for routine and preventive
maintenance.
3. All storage tanks will be covered with RCC cover slab with Access man holes and steps
for maintenance access. Necessary ventilation facilities are provided for non-
accumulation of obnoxious gases. Also aeration is provided in the storage tanks.
4. All process tanks are provided with walkway slab all around with handrails.
5. A safety officer nominated by the contractor in approval of the municipal authority
will give a regular safety training to work force in a monthly or quarterly basis in a year.
6. All the employees who work in STP site will be given safety training and they will be
allowed to operate STP.
7. A good practice of safety is maintained by way of a safety week once in six months
and awareness programmes will be conducted once in six months.
142
5.2.5.7. EMERGENCY PREPAREDNESS PLAN:
1. Employees must know how to report an emergency. This may include the activation
of pull alarms or notifying the facility security center. Consideration must be given to
methods of notifying local agencies such as the fire department.
2. All emergency phone numbers should be identified, listed in the emergency
preparedness plan and posted. Emergency phone numbers should include any facility
numbers, local agencies, and any emergency-facility personnel. Consideration should
also be given to recovery of operations.
3. Safe shutdown procedures for equipment should be established to prevent
equipment damage and additional hazards. Evacuating employees to a safe location is a
top priority.
4. The emergency preparedness plan should be a working document used for training
and practice. The plan must be updated to reflect any changes in the workplace.
5. Employees must understand the hazards of flammable and combustible materials and
proper handling procedures.
6. Only approved piping, containers, tanks, and rooms designed, safeguarded, and
constructed specifically for the storage and handling of flammable and combustible
liquids, including waste solvents, should be allowed for use.
7. All use and storage locations of flammable and combustible materials and wherever
danger could be caused by ignition must be identified and posted with appropriate "NO
SMOKING" signage. Management must ensure that all personnel adhere to the posted
safety warnings.
8. Safety shoes or boots with non-slip soles will be provided to the workers at site.
9. Personal protective equipment and chemical resistant clothing to avoid exposure of
skin or eyes to corrosive and/or polluted solids, liquids, gases or vapors.
10. No employees will be allowed to mix chemicals without the supervision of a
qualified chemist orproject manager.
143
11. Safety instructions regarding the storage, transport, handling or pouring of
chemicals will be strictly followed.
12. Electrical equipment for safety before use will be checked; verified that all electric
cables are properly insulated.
13. Extreme care will be taken when handling highly corrosive agents such as liquid or
gaseous chlorine, concentrated acids or alkalis, or when toxic gases may be emitted
from the reagents, etc.
14. The workers will not be allowed to smoke, eat or drink in areas where chemical or
biological contamination may be expected.
15. All workers will undergo periodic examinations by occupational physician to reveal
early symptoms of possible chronic effects or allergies.
5.2.5.8.1. Safety Measures for the Persons working in the Inlet Pumping
Station/ Screening/ Grit Area.
1. Gas detection and monitoring equipment where required. Where gas alarms are
provided, install an indicator light outside the building so that the operator can check
gas levels before entering the building.
2. Operation staff must wear high-vis jackets at all times when working in the area.
3. All PPE (gloves, ear protectors, safety boots, waterproof overalls, etc.) must be worn.
4. Wearing of hard-hat is recommended.
5. Spillages must be cleaned up immediately.
6. The area should be kept clean and clutter free.
7. Be aware of who is in the area/buildings - challenge and enforce the safety rules.
8. Note location of firefighting equipment and alarm points.
9. Note the location of First Aid boxes and other help information.
10. Hands and exposed skin areas should be washed with the anti-bacterial soaps.
11. No smoking - follow welfare procedures.
12. Report poor housekeeping to the Plant Supervisor.
13. Drive work vehicles slowly and safely. Be aware of pedestrians and other vehicles.
144
14. Training – Safe Pass, Chemical Awareness, First-Aid, Fire
PPE Required:
High-vis jacket or vest, waterproof overalls, standard overalls, hard hat, safety boots,
Hazards Identified:
1. Noise
2. Mechanical hazards
3. Biological contamination
Persons at Risk:
Control Measures:
PPE Required:
High-vis jacket or vest, waterproof overalls, standard overalls, hard hat, safety boots,
2. Poor housekeeping
3. Inexperienced operators
4. Contractor awareness
148
6. Oil spillages
7. Slips & trips
Persons at Risk
Staff, Fitter, Contractors
Control Measures
1. Before commencing start-up procedures check that maintenance is not being
performed.
2. The wearing of ear protection is mandatory when working in the air blower building.
3. Replace all safety covers/inspection hatches.
4. Inexperienced operatives must be supervised.
5. Do not attempt work you are not trained for. E.g. electrical work is to be performed by
the Electrician.
6. Tie back loose clothing and long hair.
7. Be aware of who is in the building - challenge and enforce the safety rules.
8. Note location of firefighting equipment.
9. No smoking - follow welfare procedures.
10. Report all faults, unusual occurrences immediately to Plant Supervisor.
11. Fix ladders securely. Never work from a ladder.
12. Noise monitoring to be conducted annually.
13. Clean up spills immediately. Dispose of oil and rags safely - waste rags, etc. can pose
a fire risk.
14. Tidy up tools and other equipment such that it does not pose a trip hazard.
15. Training - SafePass, Chemical Awareness, Fire.
PPE Required:
High-vis jacket or vest, standard overalls, hard hat, safety boots, gloves dust mask, ear
protectors and safety glasses.
Other Hazards Considered Low Risk:
1. Electrical shock risk during normal operation of equipment
2. Poor housekeeping - trip hazards
3. Contractor awareness
149
5.2.5.8.2. Safety Measures for the Persons working in the Bio Aeration
Tank/ Primary and Secondary Clarifiers/ Sludge Thickener Area.
1. Operation staff must wear high-vis jackets at all times when working in the area.
2. All PPE (gloves, ear protectors, safety boots, waterproof overalls, etc.) must be worn.
3. Wearing of hard-hat is recommended.
4. Note the location of First Aid boxes and other help information.
5. Training – Safe Pass
6. Fix ladders securely. Never work from a ladder.
7. Use harness or other safety measures if entering a tank.
PPE Required:
High-vis jacket or vest, waterproof overalls, standard overalls, hard hat, safety boots,
gloves dust mask, ear protectors, safety glasses (standard)
Moving:
Use a properly balanced hand truck with clamp or chain to move full chlorine
cylinders.
Never use a chain, rope sling or magnetic device to lift chlorine cylinders.
Use a suitable lifting beam in combination with a hoist or crane of at least two
tons capacity to lift chlorine ton containers.
Never move chlorine containers without valve outlet cap (s) and protection hood
in place.
150
Storing:
Store all chlorine containers, full or empty in a clean, well-ventilated fire-
resistant area, away from all heat sources and segregated from other
compressed gas containers.
Keep area free of trash to avoid fire hazard. Avoid sub-surface storage area.
Store full and empty containers separately.
Provide a suitable gas mask for every employee involved with chlorine handling.
Provide suitable respiratory protective equipment at the outside of chlorine
rooms, near the entrance, and at several other locations if chlorine is used wide
area.
Inspect all such equipment at regular intervals and after each use.
Fire:
Move chlorine containers immediately from fire areas.
If they cannot be moved notify fire-fighting personnel that chlorine containers
are in the fire area.
Apply water to cool containers that cannot be moved provided no chlorine is
escaping keep all unauthorized persons a safe distance away.
Emergency precautions:
Hold head high, as the chlorine concentration is greatest at floor level.
Keep mouth closed.
Avoid deep breathing and gasps caused by coughs.
Seek safety.
CO2 based fire extinguishers of suitable capacity and numbers will be provided at the
site near the substation, PMCC/MCC and control rooms before start of work. The fire
extinguishers will be fully updated before the operation phase. These fire extinguishers
will be installed in such a manner that their use is facilitated in case of fire emergency.
First aid kit will also be provided containing all the materials, medicines necessary for
treatment of cuts, wounds, burns etc. The materials in the kit will be checked and
replenished periodically.
151
5.2.5.10. OCCUPATIONAL SAFETY AND HEALTH:
Infectious diseases are serious potential health hazards at Sewage Treatment Plant.
Some general recommendations for the prevention of disease include:
1. Wear heavy-duty rubber gloves (especially if the hands are out or have open sores)
and boots that are not water absorbent and are resistant to punctures.
2. Wear protective clothing including goggles, if there is any chance of wastewater
spraying into the air.
3. Change uniforms or other protective clothing that is visibly soiled or contaminated as
soon as possible.
4. Work clothes should be separated from other household laundry and washed in the
hot water cycle.
5. Shower before changing into clean clothing and shoes to be worn home. Workplace
bathrooms, showers, and locker facilities should be clean, well-maintained, adequately
supplied with soap, towels or hand driers.
6. Wash hands frequently, with soap and water after coming in contact with wastewater
and hands should also be washed at the end of the work shift.
152
Table 5-4 Environmental Management Plan for Pre-Construction
Phase
S.No Potential Negative Mitigation measures Time frame Responsible
Impacts agencies
1 Clearances Clearances from TNPCB: Before
Application submitted to construction
DEE, TNPCB,
Kancheepuram District
for Consent to Establish
(CTE) and obtained the
same
2 Tree cutting i) The proposed STP site Pre-
identified is a barren land construction
and does not involve tree &
cutting. Hence, there is no construction
activity of tree cutting for phase
the proposed STP site.
157
Electrical will be taken to prevent Construction
Equipment(s) danger from electrical
equipment and ensure
that
i) No material will be
stacked or placed as to
cause danger or
inconvenience to any
person or the public.
ii) All necessary fencing
and lights will be
provided to protect the
public in construction
zones. All machines to be
used in the
construction will conform
to the relevant Indian
Standards (IS) codes, will
be free from patent defect,
will be kept in good
working order, will be
regularly inspected and
properly maintained as
per IS provision and to
the satisfaction of the
Engineer.
10 Disposal of i) The treated water During
treated waste quality will be complied Construction
water with the standards of
TNPCB before let out into
the stream and necessary
permission has been
obtained from the
concerned department.
ii) Efficient working
condition of treatment
plant will be maintained.
iii) Stream water and
other water bodies
receiving STP discharge
will not be polluted.
11 Disposal of The sludge should be During
sludge carried by enclosed operation
container during sludge
transportation. It will be
disposed as manure and
158
to be used by farmers
161
3 Monitoring of i) Seasonal monitoring of Project area
environment Air, Water, Noise and Soil
parameters quality will be done.
ii) The parameter will be
monitored according to
Environmental Monitoring
Plan.
4 Sensitive Areas i) The dust and noise Project area
impacts due to vehicle
movement during
construction and their
effectiveness will be
checked and minimized
with precautionary
measures.
5 Clearing of Site restoration plans will During
construction be prepared for approval construction
of camps and by the engineer. On period
restoration completion of the works,
all temporary structures
will be cleared away, all
rubbish cleared, excreta or
other disposal pits or
trenches filled in and
effectively sealed off and
the site will be left clean
and tidy.
6 Tree Protection, i) Due protection will be Corridor of
Tree Planting given to the tree that might Impact
fall in the shoulders /
corridor of impact.
ii) Construction of Masonry
tree guards,
Low level RCC tree guards,
Circular Iron Tree Guard
with Bars, use of plate
compactors near trees will
be provided wherever
necessary.
iii) Re-plantation of at least
twice the number of trees
cut will be carried out
along the project area.
Planting of trees along the
entire stretch of road will
be carried out as an
enhancement measure.
162
iv) Growth and survival of
trees planted will be
monitored at least for
period of 5 years. Survival
status will also be reported
on monthly basis to
Engineer
To monitor the extent of environmental impact of the proposed project, the ambient
environmental quality along the proposed project area should be monitored
periodically. The monitoring requirement for the different environmental components
is presented in Table 5-8.
Table 5-7 Environmental Monitoring Plan
AIR QUALITY MONITORING
Project stage Pre-Construction, Construction & Operation Phase
Parameter PM10, PM2.5, SO2, NOx, CO, Pb and Odour
Sampling Method specified by CPCB for analysis
method
Standards Air (Prevention and Control of Pollution ) Rules, CPCB, 1994
Frequency Once before start of work & once every season of the year during
construction period and every season of year at two locations during
operation period.
Duration Continuous 24 hours / or for 1 full working day
Sampling Two stations – 1. STP boundary in the downwind direction
Location i). Project Site
2. Nearest residential area
ii) Institutions and schools are located away at a distance of 1.5 km
away from the
STP site in W direction.
Measures Wherever air pollution parameters increase above specified
standards, additional measures as decided by the engineer will be
adopted
Implementation Will be implemented through approved monitoring agencies
Supervision Implementing agency
WATER QUALITY MONITORING
The Greenbelt has been designed to minimize the predicted levels of the possible air
and noise pollutants.
Greenbelt will be effective in containing the pollutants due to the plant operations. The
main purpose of green belt development is to contribute to the following factors:
To attenuate noise level generated from the plant;
To improve the aesthetics of the plant area;
To trap the vehicular and fugitive dust emissions;
To act as a pollution sink for gaseous emissions;
To maintain ecological balances;
To prevent soil erosion and to protect the natural vegetation;
To utilize the treated effluents.
The total trees after the implementation of this plant will be around 600 trees (6800
Sq.m). This will serve the important environmental objectives of the dust and fumes
capture, noise attenuation and wind barrier while also improving the aesthetics.
The proposed green belt will be implemented with locally available and sustainable
species will only be chosen for plantation.
While selecting the plant species for the proposed green belt, the following points have
been taken in to consideration:
Based on climate and soil characteristics of the study areas, some species are
recommended for plantation. The climate of the region is tropical, where there is
medium rainfall as well as extreme heat and soil temperature is very high in summer.
Hence, in order to have a ground cover, some fast growing species which do not require
watering have been recommended for mass plantation.
The below mentioned species not only resist water stress but also covers the ground
quickly and also have wider soil adaptability. For protecting the environment from dust,
167
temperature, chemicals, and emissions the following species have been recommended.
The above given suitable trees will be planted in consultation with the local body at the
time of implementing green belt operation.
Planting will be carried out in vacant space wherever possible using shrubs and ground
covers. Planting will be aimed to create a conductive microclimate and a visual impact.
5 Energy Management 5 1
168
6. SUMMARY & CONCLUSION
The proposed STP is an Activated Sludge Process that will produce quality effluent after
the treatment, before discharge into the Buckingham canal. The nature of the proposed
system will prevent the production of odour and sludge thus, making the facility little
nuisance to the surrounding communities. The entire STP project has been conceived,
planned and developed as a pollution control-cum-resources recovery measure
following the direction of TNPCB. The project will therefore contribute significantly
positive impact on the prevailing environment. In addition, this project envisages the
following:
1. The clean and healthy environment of the town and the socio economic health
conditions of the public will improve by the implementation of such project.
2. Downstream of the Buckingham canal after the STP will get improved and it will be
more useful for cultivation.
3. The project envisages more cost benefit ratio due to least maintenance and more
revenue to the CMWSSB by selling the sludge cakes as manure used for agricultural
purposes.
All possible environmental aspects have been adequately assessed and necessary
control measures have been formulated to meet statutory requirements. Thus,
implementing the proposed project will not have any appreciable negative impacts.
With proper maintenance and environmental monitoring, the facility is not expected to
have any adverse effects on the surrounding communities.
169
7. DISCLOSURE OF CONSULTANT
The consultant engaged and the brief description of the key personnel is furnished
below.
ABC Techno Labs India Private Limited an ISO 9001, ISO 14001 & OHSAS 18001
Certified Company & leading Environmental Engineering & Consultancy Company. We
are the first firm to be accredited by NABET (National Accreditation Board for
Education and Training), Quality Council of India, as an EIA Consultant. We are
equipped with in-house, spacious laboratory, accredited by NABL (National
Accreditation Board for Testing & Calibration Laboratories), Department of Science &
Technology, Government of India.
We are having a well experienced team of Scientists & Engineers who are looking after
our well equipped analytical laboratory with a facility including analysis of physical,
chemical and biological parameters as per the requirements of the State Pollution
Control Board and our clients.
Environmental Baseline data collection for Air, Meteorology, Noise, Water, Soil,
Ecology, Socio-Economic and Demography etc;
Environmental Monitoring
Other Services
Chemical Testing
Environmental Testing
Microbiological Testing
Food Testing
171
7.2.4. METALLURGICAL TESTING
Mechanical Test
Chemical Testing
Corrosion Testing
Chlor-alkali Industry
Chemical Fertilizers
Distilleries
Sugar Industry
Airports
172
7.4. STUDY TEAM
ABC Techno Lab India Private Limited has been carried out this Environmental Impact
Assessment (EIA) study. The multidisciplinary team included expertise in
Environmental Impact Assessment, Air & Water pollution & Control measures, Noise
Control measures, Ecology & bio-diversity, Land use, Geology, Environmental Chemistry
and Socio-Economic planner.
NAME ROLE
Dr. R.K. Jayaseelan EIA Coordinator & Functional Area Expert – Land Use
Mr. M. Senthil Kumar Functional Area Expert – Risk Assessment & Hazard
management
Mr. Vivek Mariappan Functional area Expert – Meteorology, Air Quality
Modeling & Prediction
173
Annexures
174
Annexure-I
Land Allotment G.O
176
· ,
044-25993494 (Per.)
044-25990232(~
In the letter first cited a site measuring 5.0 Acres of land lying in Ward
No.D, Block No.14, Ts.No.4/3 has been handed over for commencing the
construction of Sewerage treatment plant.
r ~ -~ ~ In the letter 2nd cited it has been informed to sort out issues regarding
11~~fV' the encroachments in the said land to fascilitate the CMWSSB to start the
~#~ _' ~I'\",~ork. In this connection after considering the technical requirements with the
~r . \\)~ r 'Executive Engineer Mr.Chandran, a conclusion has been arrived to locate
_ ~\ \ the STP in the existing Compost Yard lying in Ts.No.3 on the Sourthern side
of the already handed over site for STP.
As required by the Executive Engineer, a land measuring about 100m
x 150 m lying in Ward No.D, Block No.14, Ts.No.3 (pt) is hereby handed over '
and it is requested that the work may be commenced immediately. Sketch
showing the new site is enclosed. ~ ~ _
~\A.~
--_...--'"
Commissioner
Thiruvottiyur Municipality
)..~l '--
Enclosed: Sketch
E:\F1\Fl.doc - 188
311 soUra;t::.: :survey ana Lana N.ecoro~ uepanmen(
I
'I\.
-' .~~
·r · ~
FOOT PATH
- rol-
MATELLED ROAD
, '4tow~.: H EARTH ERN ROAD
-< RAILWAY LINE
r~fX' rED ~~ to:\
WATER BODIES
YJ]" ),J "W I:l'~H~;;4' SURVEY BOUNDARY
SOURCE: CLIENT
44
PREPARED BY
FOR
THE MUNICIPAL COMMISSIONER
THIRUVOTTlYUR MUNICIPALITY
CHENNAI - 600 019
PREPARED BY I K.'
VERIFI(:D BY
APPROVED BY
;i
n /~
. ·V~
\.
, \. .
' ~i. .'1~)(!})litlfji:r~Fi' Wrr61ILL .g)1LffltuFf}6irr . ffill}-~ 6'f6linr!ll.ffi.t~247/2007t~, ~rrk 3fl;1~:W07
.' ~il!DIDJili '10.7.20tlB. '
.~9lflUIi1fT:.- jd'
(,
".'. .
..
".-' >b1®&~~i:r~ff LOrr~1Jl:'Lw, .~Lhl:l~1iM1f 5HLUD,
l~lliiFrrA; . 14,. ..lli:~iT~~~j6lf1i1n6l..l
,!~p;lJ!liYJJ,,. %1ti\iLD~/fhQ~Jrr,:nn<lI'11 0
!IT. 4 tw~~.
1&.C!>!tIlJ':'~
(llL.D''i'OJ<T.mou
.
,. "iil;;ro'I:tJ'''lB1l~tbl® .';~f11i¥~®fMafjifwC~ &l' ~l
~~mU61J~I .~rrLfrifjlrrffi .' rffi®6l16ir@!j~ JIJ~L Jibf.~lU& ~6lIf!l.1.
(M.~~.~6Tr6Tf.mT.' . .'. . .
. \ .. . . .' ,,' . ' . "
~~.4,j!jp.lD.$t';nIT~YWlbaurre;@ ,5.60O:P:O . C/',ill'. UIRJl511iU 4.0000.D 0'.111. {i@ " lij"fj,(T; lr)
'<JrlI
. •'. ~,:i?' r:~:.;~
4.
(ii) ffi6i.Jffi)fJ1U\.D, lmr8;~IJ1ULD l1l.mww. ~!':"t5hfl6?-l ffiLUn1lTW ~ffi1lU~ a.~Lq Jt1~16l.16llTln ~fii6ilr61
tPl6l\\6\1"0'1
QB'~J~!b GlrudtrrCblw;
. @.~m\f
(tin .' ~.llip; ~!.J)rr$ffi~~tDffilfffi. @6\J' : !l1;~rfl6ll'Lf) I.Drrtb!lith. Q8:1Llt.uuuQ)l4T!ti<il~rf ~1$b6:Kr,'rr&" f:[lI~. (j)I(gl. n
..,m~@.)~ UtW~®~tD (g6);/~@tD;
,
"63;I;}~i)titU~tIDm:,~~~; : 'WJlGltf6U6illriiQ$6UT 6T6;·J~· .1-ffi®. ~9·6,OOO/-·
;'~~lfj:rtl:j·, · fri1&@iJ~_~~ ... " .~~; .' , "' .. ,. c...· :,;"." ,; ,:"" c· : ""~:';"!1"'C ..Ii ', . ~ .
{vi·i ) tmfffi:m4.{b)u~j)P}:JrrJf]111~.$®.LlQl®~@).I::.~1~Q6lJrqD~lliJjtT :!Jj<h1]l11:"6'l ~(i1l)l·.lIJ1.ftim:6lll)r l'ftHiilTjlll .. " .:.~ :
I
(vHi )@jl~6tnW6M' ~IJ}~ ~rizi:@jtD ~J5'$)omrr8;(g~U 611®rurniJ ffi6lJUf&@cfiiifittl 2ujliu
., U~iffi5ir~M~~rr-6W~Uuk. . {N~@cl~;;,~'
,I
iI
I'
I I
~f~Ln51 6l/GTf6tf
r;ro"'."
." vd<9l
- - .-;:: -, .
IIV~ ' /
Annexure-II
TNPCB Consent Copy- Water Act
178
180
181
182
183
184
185
186
Annexure-III
TNPCB Consent Copy- Air Act
188
190
191
Annexure-IV
Permission letter from
WRD for the disposal
of treated effluent into
Buckingham canal
CMWSSB
To
Sir,
In the reference cited above, you have requested the permission of this department
letting the treated effluent from the 31 MLD vca-pacitY STP -under construction in
.
Sathankadu village in to the 8'cana/.
The proposed site was inspected and ascertained that the proposed letout pointis
located in the North Buckingham canal at the downstream side of Indian Oil Corporation
Bridge at LS 7900m. The canal wasstagilated with water without remarkable discharge.
Hence, the pipes should be laid in rows for the existing bund width of 20 meters in order
to allow free discharge without any obstruction. The Maximum Flood Level of North
Buckingham Canal is (+) 2.40m. Hence, the pipe line from the 31 MLD capacitySTP for
. letting of treated effluent into Buckingham Canal sh()~19.._be laid above the leveL oL_._.. ' .
. - '-~ -- -
. .. .. -.--'--"""~ - .
(+)2.400m.
Based on the flood experience and in view of the presence site condition observed
during the site inspection "permission" is granted for letting of treated effluent in to the
. .
B'canal near Thiruvottiyu(subject to the followirigterms and conditions.
CMWSSB
1 The pipe line of the proposed letting point located at the North Buckingham Canal at
the downstream side of Indian Oil Corporation Bridge at LS 7900m should be laid in
rows over th~ existing bund width of 20 meters in order to allow free discharge of
letting of treated effluent into Bunking ham Canal.
2 CMWSSB is allowed to lay the pipe line in North Buckingham Canal in the work of .
Construction of 31 MLD capacy STP for letting of treated effluent into Buckingham
Canal only above the level of (+)2.400m. ie.the MFL of the North Buckingham canal
and this is allowed for a temporary occupation of 3 years from the date of
agreement.
3 The CMWSSB is responsible for assuring that the secondary treated effluent let out
into the B'canal will have the quality parameter as stipulated by TNPCB. A monthly
report should be sent to the Executive Engineer, Araniyar Basin Division, Chennai
for monitory this. .
5 The work schedule should be informed to the Executive Engineer, WRD., Araniyar
Basin Division, Chepauk, Chennai=5 for monitoring.
6 CMWSSB should inform every stage of process prior enough and the WRD officials
may be called for inspection of the works periodically
7 CMWSSB .should do the above work at their own cost and they are solely
.
responsible for the structural safety and stability of the proposed structure .
8 The CMWSSB should enter into an agreement with the Executive Engineer, WRD,
years.
9 A sum of Rs.1.00 Lakh shall be deposited towards the Caution Deposit in the form of ..
Demand Draft drawn .in favour of the Executive Engineer. WRD., Araniyai' Basin
Division, Chepauk, Chennai-5 which is refundable . .
10 After the completion of the work, the damaged portion of the BUckinghamCanal-:and
'WRD ·properties·etc if any should be set right and restored to the original condition
by the CMWSSB at their own cost. .
11 The Caution Deposit will be retained by Water· Resources Department for the period
. of 5(five) years to watch the effect of Buckingham Canetl waters and the damage
caused to the Buckingham Canal at this junction due to the construction of laid in
rows of pipes, If any damage is noticed during this period, which is leftout by the .
CMWSSB the repair will be carried by WRD and the cost of repair will be deducted
from the Caution Deposit. If the cost exceeds the Caution Deposit, the excess
amount should be remitted by CMWSSB. ·
0 · .... ' ;1l _ _ _ _ _ _. •,
...
CMWSSB
thousand five hundred and sixty only) in the form of Demand Draft drawn in
Chennai-5.
13 The lease rent should be paid in one lumpsum for 3 years of (14560 x 3)
Rs.43,6801- as advance.
14 The lease. rent now fixed will be revised from time to time based on the G.O in future
Department. For which, CMWSSB have to apply within two months before the
17 CMWSSB should not carry out any activity which obstructs·& or encroaches the
18 CMWSSB should allow the Water Resources Department officials for inspecting the
.Buckingham Canal and construction point of the proposed laid in rows of pipes as
Buckingham canal. .
20 CMWSSB should not carry out any cross masonry works across the Buckingham
21 If any change of alignment arises that shoule be got approved by Water Resources
22 Any clearance like pollution control, Coastal zone clearance,environment and other
related department etc., as per the rules has to be obtained from the respective
departments before executi9~.~_____ _
23 CMWSSB should abide by the rules and regulations of the Water Resources
Department from time to time.
. . .
24 CMWSSB should not privileage on the above lease portions of WRD lands . ..
25 CMWSSB should carry out periodic;:ll desilting works and removal of obstructions in ·
any formed in the Buckingham canal within their boundary at their own cost as and
when required and ensure free flow of water.
27 The WRD permits only treated water with standards as per the norms prescribed by
the TNPCB and assured by the CMWSSB into the North Buckingham Canal.
28 After the completion of the work, the waste materials used should be
removed complete/y.
29 Necessary Provisions shall be made by the CMWSSB to maintain the normal flow in
Buckingham Canal at any time during execution.
30 There should not be any hindrance at any time to the free flow of water through the
Buckingham Canal to the downside.
31 Failing to comply with any of the above conditions, the Water Resources Department
reserves the rights to withdraw the No Objection Certificate issued and in that even,
the CMWSSB shall not be eligible for any compensation what so ever.
G.ftr~)~~:~
for Chief Engineer, WRD.,
Chennai Region, Chennai~5.