Escolar Documentos
Profissional Documentos
Cultura Documentos
Abstract - A new Low Voltage Power Circuit Breaker trip devices are completely contained within a molded case,
(LVPCB) has been introduced which has higher interrupting and are not designed to be field maintainable. MCCBs as
capacity and higher short delay current ratings than previously standard are tested in open air and are de-rated to 80% when
available in LVPCBs. The entire new power circuit breaker placed in an enclosure. Optional MCCBs are available which
including operating mechanism and contacts has been designed
have been UL tested for applications at 100% in the
and tested to meet or exceed the stringent requirements of ANSI
standard C37.16 “Low-Voltage Power Circuit Breakers and AC enclosure. Molded case circuit breakers have over-center
Power Circuit Protectors – Preferred ratings, Related toggle operating mechanisms. For electrical operation, they
Requirements, and Application Recommendations”, ANSI are typically combined with external motor operating
C37.50 “Low-Voltage AC Power Circuit Breakers Used in mechanisms, which move the breaker handle. The external
Enclosures – Test Procedures” and ANSI standard C37.17 “Trip motor operator is not fast enough for synchronizing or many
Devices for AC Low Voltage PCBs”. This paper will discuss the automatic transfer scheme applications. MCCBs are also
evolution of technology in materials and electronics, which has available in current-limiting type.
enabled improved performance, as well as provide examples of Insulated Case Circuit Breakers (ICCBs) are also rated
specific applications in the industry where the new PCB higher
and tested in according to UL489. They are typically applied
interrupting capacity and short time ratings are beneficial to the
user. A need to review both short delay time as well as short as mains in Low Voltage Switchboards, Motor Control
delay current ratings of equipment will be discussed. Zone Centers and some transfer switches. Similar to the MCCB,
selective interlocking functions to reduce damage to protected the ICCB is generally contained in a sealed molded case, and
equipment while still maintaining coordination will also be is not designed to be fully field maintainable. ICCBs are
reviewed. found as either 80% rated devices or 100% rated devices
when mounted in the proper enclosure. ICCBs utilize 2 step
stored energy mechanisms, similar to LVPCBs. ICCBs are
I. A BRIEF DESCRIPTION OF AVAILABLE CLASSES OF LOW normally not fast enough to qualify as current-limiting type.
VOLTAGE CIRCUIT BREAKERS
II. THE HISTORIC EVOLUTION OF LOW VOLTAGE POWER CIRCUIT
Low Voltage Power Circuit Breakers (LVPCBs) are rated BREAKER TECHNOLOGY
and tested to ANSI C37 standards. They are mainly used in
Low Voltage Metal Enclosed Drawout Switchgear built per The first low voltage power circuit breaker designs go back
ANSI C37 standards. LVPCBs offer field maintainability of to the year 1929, when Dr. Slepian of Westinghouse invented
main contacts, operating mechanism, and arc chute the DE-ion arc chute. During a fault, this arc chute device
replacement. LVPCBs are tested in the enclosure and are enabled the LVPCB to effectively protect downstream
rated for 100% applications. They offer 2 step stored energy- equipment by splitting the resulting arc into several
closing mechanisms, which have typical opening or closing segments, which were then individually extinguished. Since
times of 3 to 5 cycles. For electrical operation, they are 1930, power circuit breaker technology has advanced in
typically combined with an internal motor to change the several areas as shown in the timeline, Fig 1.
breaker closing springs and solenoids to release the spring
stored energy for closing and opening of the breaker. They A. Interrupting Ratings
are typically applied in systems with selective coordination,
synchronizing schemes and automatic transfer scheme Interrupting capacity is defined as the maximum short circuit
applications. current the breaker can safely interrupt. Early designs of
Molded Case Circuit Breakers (MCCBs) are tested power circuit breakers were designed with interrupting
according to UL489. They are typically applied in Low capacity of 15/25kA. The latest designs of LVPCBs include
Voltage Switchboards, Motor Control Centers and interrupting ratings of up to 100kA at 480 volts, without the
Panelboards. MCCB current carrying parts, mechanism and use of integral current-limiting fuses. Many users have
_________________________________________________ elected to move away from the use of LVPCBs with current
Originally presented at the 1999 TAPPI Conference in March 1999. limiting fuses for some of the following reasons:
Copyright TAPPI 1999.
Presented at the 1999 IEEE IAS Pulp and Paper Industry Conference in Seattle, WA: © IEEE 1999 - Personal use of this material is permitted.
ANSI/UL Low Voltage Power Circuit Breaker Timeline
Figure 1: Timeline of Low Voltage Power Circuit Breaker Technology Developments including interrupting capacity improvements,
available mechanisms and trip sensors from 1930 through 1998.
1. When current limiting fuses are utilized as part of feeder the fault is absorbed in the frame. Increased interrupting
circuit breakers, medium to high fault currents will cause ratings mean higher spring energies in the operating
the limiter to open, thus losing coordination with mechanism. Steel frame breakers deflect during fault
downstream protective devices. interruption and in some cases must absorb up to 40% of the
2. Increased floor space of the low voltage metal-enclosed spring energy. Thus, open steel frame breakers require larger
switchgear is required when fuses are incorporated into springs and frames, which reduce overall mechanism life.
the assembly. Newer epoxy resin design frames have superior
3. Increased downtime and cost associated with the characteristics in overall frame deflection and include a
replacement of blown current-limiters. molded arc chamber that provides support to the current path
and protection from phase to phase arcing during
Increases in ratings have come primarily from improved interruption. The improved structural rigidity of the frame
materials in breaker frame construction. Earlier designs used allows higher interrupting and short time ratings in a smaller
an open type, metal frame. Today’s designs use engineered overall package. Typical 3200 amp breaker frames and power
thermoset composite resins in a molded frame. The rigidity of contact designs in both steel and molded frame breakers are
the frame is a critical design point during fault current shown in Fig. 2.
interruption, since much of the energy required to interrupt
Figure 2: Shown at left is a comparison in size of a new epoxy resin frame LVPCB versus a traditional open steel frame construction.
Both breakers are rated for 3200A at 600 volts. Shown at right is a newer finger-type design power contact assembly versus
the traditional wedge-type design.
B. Operating Mechanism A. Definitions: Short Delay Current And Short Delay Time
Ratings
Early designs of operating mechanisms included solenoid
operators. In 1967, higher closing speed requirements Short delay current ratings and short delay time settings are
resulted in development of a two-step stored energy critical factors in the overall function of a LVPCB when used
mechanism for Power circuit breakers. This mechanism in a selectively coordinated system. For purposes of this
allowed for the capability of fast reclosure (Open, Close- paper, in conjunction with trip unit settings, the following
Open duty cycle) via the addition of a charging spring. This definitions will be utilized:
also facilitated easy remote operation, fast reclosing (5 cycles
or less), and assured that energy was always on hand to • Short delay current rating of a LVPCB: The
open/close the breaker. The latest designs continue to use the maximum current for which the circuit breaker can
two-step stored energy operating mechanism. remain closed for a short delay time.
C. Trip Unit Sensing • The maximum short delay time of a LVPCB: The
time that a Power Circuit Breaker must keep its
Early design trip units in power circuit breakers were electro- contacts closed at a maximum short delay rated
mechanical type. Solid state sensing trip units were current (typically ½ second or 30 cycles).
introduced in the late 1960’s, which replaced the initial
designs. Early versions of solid state trip units used analog {The ANSI test standard for LVPCBs actually requires a
circuitry and were able to effectively sense and trip on peak short delay fault test of 30 cycle duration, a 15 second zero
currents. In some cases, this resulted in nuisance tripping current interval and then another 30 cycle short delay fault
conditions. In the 1980’s, digital solid state controls became test.}
available that were able to effectively integrate the current
waveform to calculate a true rms current value. This There are significant differences in short time delay ratings
effectively eliminated early nuisance tripping problems. for various circuit breaker types. Typically, the maximum
Microprocessor based rms trip units were introduced in the short delay time rating for Molded Case Circuit Breakers
early 1990’s and advanced versions of these are used in the (MCCB) equipped with electronic trips is 18 cycles and the
latest design LVPCBs. maximum short delay time rating for Insulated Case Circuit
Breakers (ICCB) is 30 cycles. It’s important to note that
Today, Low Voltage Power Circuit Breakers (LVPCBs) and although a ICCB may have a 30 cycle short delay time, the
metal-enclosed switchgear are designed and tested to ANSI, current magnitude of that 30-cycle delay is at significantly
NEMA, and UL standards [1]. less current magnitude than it’s rated interrupting capacity.
Most MCCBs and ICCBs available on the market are
II. APPLICATIONS OF POWER CIRCUIT BREAKERS equipped with a fixed instantaneous override circuit (when
adjustable instantaneous is not furnished). These breakers
ANSI offers the following definition for Rated Short-Circuit frequently have interrupting ratings, which are higher than
Current for LVPCBs: the breaker's short delay current rating. When the fault
current value exceeds the short delay current rating of the
Rated Short-Circuit Current for Unfused Circuit Breakers: breaker, the fixed instantaneous override circuit immediately
The rated short-circuit current of an unfused circuit breaker is trips the breaker. This means that system coordination can
the designated limit of available (prospective) current at only be achieved up to the short delay current rating of the
which it shall be required to perform its short-circuit current breaker. For fault currents above the short delay rating, the
duty cycle (O-15s-CO) at rated maximum voltage under the breaker opens and coordination is lost. However, the breaker
prescribed test conditions. This current is expressed as the can still interrupt currents up to its published interrupting
rms symmetrical value of current measured from the capacity.
available current wave envelope at a time ½ cycle after short
circuit initiation. Unfused circuit breakers shall be capable of The industry test circuit standards used for testing low
performing the short-circuit current duty cycle with all voltage circuit breakers include power factor test ranges and
degrees of current asymmetry produced by three-phase or X/R test ranges shown in Table 1. When circuit breakers are
single-phase circuits having a short-circuit power factor of used in actual installations where the X (reactance) and R
15% or greater (X/R ratio of 6.6 or less). [2] (resistance) represent the total X and R from the faulted point
in the circuit back to the utility generating source, a de-rating
factor should be applied to the circuit breaker interrupting
rating if the calculated X/R ratio exceeds those listed in the
test standards. Typical recommended de-rating factors are X to R ratio is the degree to which the first half cycle peak
shown in Table 2. The LVPCB derating factors shown in current exceeds the steady state rms value of the fault. The
Table 2, are essentially the reciprocals of the multiplying actual amount of asymmetry will depend on when the fault
factor based on ANSI C37.13, Table 3. This ANSI occurs in the voltage wave.
multiplying factor is applied to the calculated symmetrical The test circuit X/R ratio determines the first half cycle
short circuit current, before comparing it to the LVPCB Peak Multiplication Factor. The Peak Multiplication Factor
interrupting rating. times the calculated or test rms symmetrical current equals
The ratio of X to R determines the maximum degree of the first half cycle peak current. See Fig. 3 for the
asymmetry possible in the faulted circuit. In other words, the relationship of X/R ratio to Peak Multiplication Factor.
Using LVPCBs in the system shown in Fig. 4 can make a For example, where F4 is feeding an individual
substantial difference in overall system performance. If the transformer, the instantaneous current pick-up would be set
main M1 and the feeder F1 in the main service equipment slightly above (approximately 10%) the calculated maximum
were LVPCBs with a short delay current rating and fault current on the secondary of the 225 kVA transformer
interrupting rating without instantaneous trips of 65,000 (without secondary motor contribution), multiplied by the
amperes, and the available fault current at their point of transformer voltage ratio.
application was less than 65,000 amperes, the LVPCBs For a 225 kVA transformer with 5% impedance, the
would continue to stay closed up to their short delay time secondary maximum fault current with unlimited primary
setting. available current would be {(624 secondary FLA) / 0.05}
Feeder breakers such as those at F1, F2, F3, F4, and F5 equal to 12,480 amperes. The instantaneous pick-up setting
typically would have a short delay time setting of 6 cycles to
would then be {[12,480 x (208V / 480V)] x 1.10}, or approximately 6000 amperes. Values of current above this
6000-ampere instantaneous setting passing through F4 would more flexibility in utilizing spare breakers for different
have to be either a fault in the transformer primary winding applications.
or a fault on the primary side of the transformer. As a result,
coordination with secondary devices would not be required. F. The Time/Current Relationship
Short delay would still be furnished for this breaker to
give good low-level short circuit protection. It would also The relationship between time and current for the feeder
allow for transformer inrush current of approximately 12 x breaker F1 circuit of Fig. 4 is shown in Fig. 5. It uses PCBs
primary FLA for 0.1 seconds. In the case of an individual in the main service equipment, and MCCBs in DP-1 and LP-
motor, such as feeder F5, the instantaneous current pick up 1. At 2000 amperes, coordination is lost between the 200-
would be set slightly above (approximately 10%) motor ampere MCCB and the 50-ampere MCCB. Coordination is
inrush 1/2 cycle current (typically 15 times full load achieved between the 800-ampere PCB in the main service
amperes). equipment and the 200-ampere feeder breaker in DP-1.
New electronic trip units are available as standard with Coordination is also achieved between the 2500-ampere main
Long Delay, Short Delay and field selectable Instantaneous PCB and the 800 ampere feeder PCBs. To achieve complete
(instantaneous protection or no instantaneous protection). coordination for all devices, the breakers in Panel DP-1
This allows for more flexibility in applying the breakers for would have to be outfitted with ICCB or PCB units with
various applications in the electrical distribution system, and short delay current ratings equal to the available fault current
at their particular locations.
AIC Rating - Symmetrical RMS Amperes AIC Rating - Symmetrical RMS Amperes Short Delay
With Instantaneous Trips Without Instantaneous Trips Current Rating
1 2 3 4 5 6 7 8 9
AC Breaker ANSI Typical New PCB ANSI Typical New PCB New PCB
Voltage Frame C37, 16-1980 PCB Maximum C37, 16-1980 PCB Maximum Maximum
Amperes Table 1 Maximum Table 1 Maximum
(3) (4)
240 800 42,000 65,000 100,000 22,000 65,000 100,000 85,000
240 1,600 65,000 65,000 100,000 42,000 65,000 100,000 85,000
240 2,000 65,000 65,000 100,000 50,000 65,000 100,000 85,000
240 3,200 85,000 85,000 100,000 85,000 65,000 100,000 85,000
240 4,000 130,000 130,000 130,000 85,000 85,000 100,000 100,000
240 5,000 (1) (2) 130,000 130,000 (2) 85,000 100,000 100,000
480 800 30,000 65,000 100,000 22,000 65,000 100,000 85,000
480 1,600 50,000 65,000 100,000 42,000 65,000 100,000 85,000
480 2,000 50,000 65,000 100,000 50,000 65,000 100,000 85,000
480 3,200 65,000 85,000 100,000 85,000 65,000 100,000 85,000
480 4,000 85,000 85,000 100,000 85,000 85,000 100,000 100,000
480 5,000 (1) (2) 85,000 100,000 (2) 85,000 100,000 100,000
600 800 22,000 50,000 100,000 22,000 50,000 100,000 85,000
600 1,600 42,000 50,000 100,000 42,000 50,000 100,000 85,000
600 2,000 42,000 50,000 100,000 42,000 50,000 100,000 85,000
600 3,200 65,000 65,000 100,000 65,000 65,000 100,000 85,000
600 4,000 85,000 85,000 100,000 85,000 85,000 100,000 100,000
600 5,000 (1) (2) 85,000 100,000 (2) 85,000 100,000 100,000
Notes ( ) :
1. Not an ANSI listed frame rating. Conventional PCB's may utilize fan cooling to achieve the indicated frame continuous
rating.
2. No ANSI short circuit rating available.
3. Breakers can interrupt currents up to the indicated values in Column 8 without adjustable instantaneous circuit, but will
only maintain contacts closed (short time rating) up to the values in Column 9 at which time a non-adjustable instantaneous
override will initiate interruption.
4. Short Delay Current Ratings for the new PCB - current value that the breaker will remain closed (withstand) for 30
cycles or 0.5 seconds.
Table A: 3 Phase Short Circuit Ratings of ANSI Rated LVPCBs, Typical LVPCBs Available Today and the New LVPCB with Increased Ratings
III. EXAMPLES REQUIRING HIGHER THAN NORMAL SHORT added at Bus 1 and Bus 2 for a total available fault current at
DELAY CURRENT RATINGS each bus of 48,700 amperes.
If voltage should be lost to Line 1, main breaker M1
A. Example #1 –Double Ended Switchgear with 2 Mains automatically opens. Since the tie breaker T is open, the
& Tie with Closed Transition Transfer or Tie Breaker loads on Bus 1 experience a complete voltage outage. When
Normally Closed the tie breaker closes, voltage is returned to Bus 1, and motor
circuits on the bus would typically have to be restarted in
Fig. 6 shows a typical Double-Ended switchgear line-up sequential order.
with each incoming service fed by a 2000/2666 kVA When voltage is returned to Line 1, many industrial users
(AA/FA) Dry Type transformer. do not want to lose the loads to Bus 1 again during an open
transition retransfer, which first opens the tie breaker and
Condition # 1 -- Tie Breaker Normally Open With Closed then closes the main M1 breaker. A closed transition
Transition Re-Transfer retransfer is achieved by first closing the main M1 breaker
and then, a few cycles to a few seconds later, opening the tie
This system is normally operated with tie breaker "T" breaker.
open, and a closed transition retransfer is used. Both 480-volt During the time of retransfer when both mains and the tie
sources must be suitable for parallel operation, and properly breaker are closed, if a fault were to occur on the load side of
protected. The available fault current through each main one of the feeder breakers -- such as location "A" near its
breaker "M1" and "M2" is 39,100 amperes symmetrical rms. load side terminals -- then feeder breaker F2 would be
Using ANSI standards for lumping motor contribution at required to interrupt approximately {(2 x 39,100) + (2 x
the main bus for a 480 volt system, 4 x transformer 9600)} amperes, or 97,400 amperes. NEC 110-9 requires,
secondary full load amperes yields 4 x 2406 or approximately "Equipment intended to break current at fault levels shall
9600 amperes. This additional motor contribution would be have an interrupting rating sufficient for the nominal circuit
voltage and the current that is available at the line terminals
Figure 6: Double Ended Switchgear with 2 Mains & Tie with Closed Transition Transfer or Tie Breaker Normally Closed
of the equipment.” In order to avoid an NEC violation, feeder Same Bus
breakers would need an interrupting capacity of 97,400 or
nominally 100,000 A.I.C. If a full short circuit study was Parallel Operation with Utility
performed, the motor contribution at point "A" would
typically be somewhat less than the 2 x 9600 amperes utilized With the upcoming advent of electric utility de-regulation,
in the above calculation. This reduction would be due to the a growing number of industrial and commercial customers
cable impedance between the motors and point "A", and the have begun to consider local generation for either peak
fact that the motor contribution from MCC-2 does not pass shaving, selling power back to the utility or reducing overall
through breaker F2. If a fault occurred at point "B" on the power consumption from the utility. Another advantage of
load side of a combination starter in MCC-2 during the co-generation is a reliable back-up power source in the event
closed transition transfer, breaker F2 would require a short of a utility outage. The availability of an inexpensive source
time rating equal to the available fault current at point "B" to of power for the generator, such as process gas or steam, is a
ensure a coordinated system. The fault current flowing significant factor in justifying these systems. On-site
through breaker F2 during a fault at point "B" would be the generation is common place in the pulp & paper,
available fault current at point "A" reduced by the cable and petrochemical and other major industries.
combination starter impedance from "A" to "B". The simple system shown in Fig. 7 consists of two 1000
For increased coordination, a high short delay current kW generators paralleled on the same bus. They are then
rating of 85,000 amperes rms symmetrical would be desired. paralleled with the utility. Each generator has an
At a minimum, all feeder breakers and equipment approximate full load current of 1500 amperes, and can
downstream from the main switchgear should have an supply approximately 15,000 amperes of fault current, based
interrupting capacity rating for the higher available fault on a Z equal to 10%. The utility or customer supply has a
current when the sources are paralleled with the tie closed. 2500 kVA transformer, which will let through approximately
Since the mains do not experience fault currents higher than 50,000 amperes fault current.
the current provided by one source, they could have If the Generator Switchgear and the Main Switchgear are
interrupting capacity and short time ratings equal only to the relatively close together and G1, G2, GT1, GT2, and M1
one source feeding it. The tie breaker would experience only breakers are closed, approximately 80,000 amperes, plus
the fault current from one source and motor contribution motor contribution of approximately 12,000 amperes -- or a
from one side, and could have a rating equal to the highest total of 92,000 amperes -- would be available at both the
combination of one source, plus motor contribution on that generator bus and the main switchgear during parallel
bus. It is also recommended that reverse current protection be operation. This would require all LVPCBs except LB1
provided at the main breakers. (which would be operated only when GT1 was open) to have
an interrupting capacity of 100,000. The highest possible
Condition # 2 -- Tie Breaker Normally Closed - Paralleling short time rating would be needed for feeder breakers F1, F2,
Sources and F3 for coordination purposes. This would provide a
greater degree of coordination, as well as selective tripping
The same situation as described in Condition 1 when a with over-current devices in the motor control centers.
closed transition retransfer occurs, is applicable to parallel
source operation. Non-Parallel Operation With Utility
Many industrial systems are operated with both sources
paralleled due to the critical nature of processes where even a Fig. 8 illustrates how multiple generation can be used to
few cycles of lost power to the load could have significant serve the emergency and critical loads of a facility. The Tie
financial consequences. Many systems supplying welding breaker GT is normally operated closed, and the generators
equipment are operated with two or more sources in parallel each are paralleled to common bus L/R. Although not
in order to generate adequate voltage and current during the required, Tie breaker GT is provided to enhance reliability.
welding process. If a bus fault occurred on bus L or R, the generation
Referring to Fig. 6, reverse current and reverse power system would not go completely off-line, as would happen if
relaying, as well as a synchronism check must be included a solid bus without a Tie breaker were used instead. The Tie
with the main LVPCBs M1 and M2. It would be breaker allows for maintenance on either bus L or bus R,
recommended under this continuous parallel operation to while still keeping two generators available for supplying the
consider replacing M1 and M2 with Network Protectors emergency and critical loads.
equipped with forward phase and ground fault time
overcurrent protection in addition to network relaying.
From the generator bus, the emergency and critical loads rating for the LVPCB feeder breakers would also be needed
are supplied through a feeder breaker (GF1, GF2, GF3, or to allow the MCCB breakers in downstream EDP panels to
GF4) to a distribution panel, such as EDP2. Current is then open first if a fault occurred on the load side of an ATS (for
routed through a transfer switch -- in this case, ATS1. Since example at point "D"). This would keep the entire EDP panel
the emergency loads are typically lighting, and the critical from losing service.
loads are usually far from the emergency switchgear fed by A better design to support coordination and continuity of
smaller conductors, the motor contribution for this example is service to the critical loads would involve eliminating the
assumed to be insignificant. EDP panels equipped with MCCB breakers. Instead, each
Each generator is capable of supplying 24,000 amperes of transfer switch would be fed directly from additional
fault current. A total of 96,000 amperes of fault current for LVPCBs. However, this improved design would be more
the four generators would be available at the Bus L/R. costly, and would require automatic transfer switches able to
Generator LVPCBs G1, G2, G3, and G4 would only be withstand (momentary) time ratings equal to the short delay
required to have interrupting capacities of 3 x 24,000 time setting on the power circuit breakers [Refer to the
amperes, or 72,000 amperes. For example, for a fault at point discussion for example 3].
"A" in the conductors between Generator G2 and Generator
Breaker G2, generator breaker G2 would only have to Cautions to Keep in Mind
interrupt the fault current from Generators G1, G3, and G4.
Generator G2 fault current would not pass through generator In many cases, the X/R ratio of generators is very high,
breaker G2. For a load side main Bus L fault at point "B", and the system X/R ratio can exceed the tested X/R ratio
generator breaker G2 would only have to interrupt the fault equal to 6.6 for LVPCBs. This would require de-rating of
current from G2. the breaker interrupting and short delay current capability.
The tie breaker GT would have to be capable of For smaller generators, or systems where the symmetrical
interrupting 2 x 24,000 amperes. Feeder breakers GF1, GF2, rms interrupting capacity of the breaker appears to be
GF3, and GF4 would need to be capable of interrupting 4 x adequate for the calculated symmetrical rms current, de-
24,000 amperes, or 96,000 amperes. For example, if a fault rating may also be required. A breaker with higher
occurred at point "C", all four generators would contribute to interrupting capacity and a higher short delay current rating
the fault current. The highest possible short delay current may be needed so the
Figure 8: Power Distribution System with Multiple Generators
breaker's interrupting capacity will still exceed the system's With this configuration, several users have elected to rely
available symmetrical rms current when the de-rating on Insulated Case Circuit Breakers (ICCBs) to obtain an
appropriate X/R factor is applied. interrupting capacity that was high enough to support this
In large generating systems, it is critical that the X/R ratio application. Since this system has 78,466 amperes available
is checked when using load side molded case circuit from the transformer [3750 kVA / (0.480 x 1.732 x 0.0575
breakers. Also, spot network transformers may have a higher Z)], plus approximately 15,000 amperes of motor
X/R ratio than conventional transformers, and may require contribution, it required devices with 100,000 ampere
de-rating of conventional equipment and selection of higher interrupting capacity. The use of fused LVPCBs would
than normal device interrupting and short delay current result in likely loss of selectivity for high fault conditions and
ratings. significantly higher costs along with additional floor space.
Thus, ICCBs with higher 100KA interrupting ratings, has
C. Example #3 – Large KVA Transformers or Transformers been the historic best solution. However, this technology
with Low Impedance only supports short delay current rating of 25,000 amperes
for the feeder breakers and 35,000 amperes for the main
Since the installed cost for low voltage substations is breakers.
significantly lower in terms of $’s/KVA for larger KVA rated If a fault greater than 25,000 amperes occurred on the load
substations, there is a trend toward higher ratings including side of any of the combination starters within a motor control
3000KVA, 3750KVA and beyond. The example shown in center, total coordination for that MCC would be lost. In the
Fig. 9 utilizes an outdoor 3750 kVA liquid filled transformer event of a 50,000-ampere fault at point "A" on a branch
with a double secondary throat connection. The two circuit of MCC1, the entire MCC1 would be out of service
secondary bus runs feed a 3000 ampere main breaker, which because of breaker F1 opening. In addition, all MCCs
in turn feeds 800 ampere feeder breakers.
connected to switchgear bus 1 would be lost due to the opening of main breaker M1. If a fault were to occur,
a current magnitude greater than 35,000 amperes would be cycle short delay time setting. If the scheme incorporated
more than likely based on the high available fault current of two incoming lines with normal mains M1, M2 and a tie
the source. With the advent of new LVPCB technology with breaker, the tie breaker short delay time would be set at 24
short delay current ratings of 85,000 amperes and cycles and the main breakers short delay time set at either 24
interrupting ratings of 100,000 amperes, significantly better or 30 cycles.
coordination can be achieved without sacrificing the floor For a fault at point "A" of current magnitude at least ten
space required by fused LVPCBs. times the MCCB frame, the MCCB breaker in CP-1 would
open, while all upstream LVPCBs would stay closed. For a
IV. CONSIDERATION OF SHORT DELAY TIME SETTINGS AS fault at point "B" in the main bus of panel CP-1, or in the
THEY AFFECT LOAD SIDE EQUIPMENT PROTECTION conductors at Point "C", feeder breaker CF-1 would time for
6 cycles and then open to clear the fault. For a fault at point
Fig. 10 shows a facility fed by a basic single line, with "D" in the bypass feeder, breaker CBP would time for 12
normal loads served by LVPCB Feeders F1, F2, and F3. The cycles and then clear the fault.
facility has its critical computer or process loads served by If a fault occurred at point "E", Main Switchgear LVPCB
LVPCB feeder F4, through ATS 1, LVPCB feeder CUPS, short delay would time for 18 cycles and then clear the fault.
through the Uninterruptable Power Supply "UPS", and This would mean the fault current would be passing through
critical feeders CF-1, CF-2, and CF-3. In addition, there is a the main switchgear bus and ATS1 for the 18-cycle period of
maintenance bypass LVPCB that's designated CBP. Critical time. In this application, an Automatic Transfer Switch
panels CP-1, CP-2 and CP-3 serve the critical loads and "ATS1" would have to "withstand" the fault current passing
utilize molded case circuit breakers. Circuit Breakers CF-1, through it for a minimum of 18 cycles.
CF-2, and CF-3 were selected as LVPCBs to provide Most conventional contactor type automatic transfer
coordination with the molded case breakers in the critical switches have a "Momentary" or "Withstand" time rating of
panels. Typically with modern microprocessor trip units and only 3-cycles. Transfer switches outfitted with Insulated
breaker operating mechanisms, a 6-cycle short time delay Case Breakers or PCBs are available with up to 30-cycle
difference is sufficient to achieve coordination between these withstand time ratings. The transfer switch momentary
types of devices. current rating must be greater than the available fault current
Since coordination between breakers is desired at all levels, at its point of application.
bypass breaker CBP and CUPS would have their short delay Per ANSI standards, low voltage switchgear bus is
time set at 12 cycles. Feeder F4 would require an 18-cycle designed and braced to carry rated short circuit current for 30
short delay time setting and the main M1 would require a 24- cycles. On the other hand, the switchboard bus, the motor
Figure 10: Ratings of Load Equipment for Short Time Delay Service
control center bus, and the panelboard bus have only 3 cycle Zone selective interlocking makes the full short delay
momentary ratings. While busway is only required to be rated capability of the selected breaker available for coordination
for a 3-cycle momentary rating, some types are available with with load side protective devices, while it provides fast
a 6-cycle rating. opening of a breaker when a fault is located directly on its
If a fault were to occur at point "A" at the critical panel, at load side to minimize damage. If zone selective interlocking
point "F" at MCC 1, or at point "G" on the bus plug feeder, were specified for the power circuit breakers located in the
the appropriate molded case circuit breaker would open main switchgear in Figure 10, the time settings previously
within one cycle. As a result, the critical panel or MCC or discussed would still be used. A fault occurring on the main
busway 3-cycle momentary rating would be sufficient. switchgear bus at point "H", is on the load side of main
breaker M1, and the line side feeders, F1, F2, F3 and F4. Due
V. ZONE SELECTIVE INTERLOCKING to the location of the fault, only the trip unit in main breaker
M1 would sense high fault current. Since breakers F1, F2,
Today's modern microprocessor trip units are usually F3, and F4 did not sense a high fault current they would not
available with zone selective interlocking. If zone selective send a restraining signal to main breaker M1. This would
interlocking is specified to be wired between trip units within indicate that the fault was not on the load side of any of the
a switchgear assembly -- or from one switchgear assembly to feeder breakers. Instead of timing out to the M1 breaker
another switchgear assembly -- this feature can be used. preset value of 24 cycles, main breaker M1 would open in
Zone selective interlocking allows the short delay time approximately 3 to 5 cycles, minimizing damage.
settings to be set in 6-cycle steps for coordination purposes. If the fault were located at point "E", then breaker F4
However, it will override these settings when the fault would send a restraining signal to main breaker M1
condition is located directly on the load side of each indicating the fault was on the load side of the F4 feeder
protective device. breaker. Main breaker M1 would then continue to time out
to its preset 24-cycle value. When the F4 feeder breaker
opened in 18 cycles to clear the fault, the fault current would the circuit breaker protective devices. When the X/R ratio of
no longer be present at M1 main breaker and M1 breaker trip the application exceeds breaker test standards, a de-rating
unit would stop timing. factor must be used to calculate the effective short delay
Similarly, consider the results if zone selective current and interrupting rating of the breaker. There is a need
interlocking were wired between the Main Switchgear and to review both current and time ratings of load equipment
the UPS Switchgear breaker trip units. If a fault occurred at during design. The availability of a new LVPCB with higher
point “E”, breakers CUPS and CBP would not send a than previously available short delay current and interrupting
restraining signal to breaker F4. Without a restraint signal, capacity can in many applications enable the systems
breaker F4 would open in 3 to 5 cycles in lieu of its preset designer to engineer a fully coordinated system, resulting in
timing value of 18 cycles, and would minimize damage. On better protection while improving system performance.
the other hand, if a fault was at point “D”, breaker CBP
would send a signal back to breaker F4 allowing it to proceed VII. REFERENCES
and time out to its 18 cycle short delay setting. Meanwhile
breaker CBP would open after 12 cycles and cleared the [1] ANSI C37.13 IEEE Standard for Low-Voltage AC
fault. Obviously, if zone selective interlocking were wired Power Circuit Breakers Used in Enclosures
between the UPS switchgear breakers and the critical ANSI C37.16 Low Voltage Power Circuit Breakers
switchgear breakers, for the same fault at point “D”, breaker and AC Power Circuit Protectors – Preferred
CBP would open in 3 to 5 cycles. Ratings, Related Requirements, and Application
Problems can arise when Insulated Case Breakers or Recommendations
LVPCBs are used as both mains and feeder breakers in ANSI C37.17 Trip Devices for AC and General
switchboards (in lieu of ANSI metal-enclosed switchgear), Purpose DC Low-Voltage Power Circuit Breakers
and can subject the switchboard bus to momentary time ANSI C37.20.1 IEEE Standard for Metal-Enclosed
requirements past its 3-cycle rating. This being the case, the Low-Voltage Power Circuit-Breaker Switchgear
momentary current rating of load side equipment and ANSI C37.50 Low-Voltage AC Power Circuit
conductors, along with the momentary time rating must be Breakers Used in Enclosures – Test Procedures
considered. ANSI C37.51 Metal-Enclosed Low-Voltage AC
Power-Circuit-Breaker Switchgear Assemblies –
VI. SUMMARY Conformance Test Procedures
NEMA SG3 Low-Voltage Power Circuit Breakers
Adequate short delay current and short delay time ratings NEMA SG5 Power Switchgear Assemblies
are needed to facilitate coordinated distribution systems UL1066 Low-Voltage AC and DC Power Circuit
during fault conditions. This ensures that only the circuit Breakers Used in Enclosures
breaker closest to the fault opens. An MCCB and a LVPCB UL1558 Metal-Enclosed Low-Voltage Power
with identical published short delay current ratings will Circuit Breaker Switchgear
respond to the same fault current in a different manner, based [2] ANSI C37.13-1981, Paragraph 5.6.1
on their individual X/R ratio design test capabilities. The [3] UL489 and UL1066 Test Standards for low voltage
specifier should understand the circuit X/R ratio for his power circuit breakers
system, and it’s effect on the published short time rating of