DESIGN MANAGEMENT
CONTENTS
2.0 DEFINITIONS
3.0 FLOWCHART
5.0 REFERENCES
6.0 ATTACHMENTS
Copyright. This document is the property of PT Thiess Contractors Indonesia and all rights are
reserved in respect of it. This document may not be reproduced or disclosed in any manner
whatsoever, in whole or in part, without the prior written consent of PT Thiess Contractors
Indonesia. PT Thiess Contractors Indonesia expressly disclaims any responsibility for or liability
arising from the use of this document by any third party. Copies printed from the Thiess
Management Systems are UNCONTROLLED.
Revision Status
This procedure shall apply to projects where PT Thiess Contractors Indonesia has the
responsibility for Design.
2.0 DEFINITIONS
For the purpose of this procedure, the following definitions apply:
3.0 FLOWCHART
TCI-DES-SP001-FC3.1/A1-
Design Planning
TCI-DES-SP001
DESIGN MANAGEMENT
CLIENT
IS DESIGN BM/FM DM DM
REQUIRED FOR THE PROCURE DESIGN
YES APPOINT DM PREPARE "TENDER
TENDER SERVICES
PREPARATION PLAN"
SUBMISSION?
NO
TCI-PRO-SP001
PROCUREMENT OF
PRODUCTS & SERVICES
DOES PROJECT
NO END
REQUIRE DM?
YES
BM/FM
DM
PREPARE DESIGN FOR
APPOINT DM CONTRACT AWARDED TENDER SUBMISSION AS
APPROPRIATE
DM/PM
TCI-PRO-SP001
SOURCE DESIGN SERVICES PROCUREMENT OF
PRODUCTS & SERVICES
DM
PREPARE DMP TCI-OPS-SP001
IAW THIS PREPARATION OF
PROCEDURE MANAGEMENT PLANS
PM/DM
LEGEND
IS DMP ACCEPTABLE? NO
BM BUSINESS UNIT MANAGER
DM DESIGN MANAGER
DMP DESIGN MANAGEMENT PLAN
FM FUNCTIONAL MANAGER
IAW IN ACCORDANCE WITH
YES
PM PROJECT MANAGER
FORM REFERENCE
PROCEDURE REFERENCE
DM TCI-PRO-SP001
ENGAGE DESIGN
PROCUREMENT OF
CONSULTANTS
PRODUCTS & SERVICES
AS REQUIRED
PM/DM
DOES PM/DM
DMP REQUIRE CLIENT YES SUBMIT TO CLIENT
APPROVAL?
NO
CLIENT
DM PM/DM
IMPLEMENT
YES APPROVAL GRANTED? NO REVISE DMP
THE PLAN
TCI-DES-SP001-FC3.2/A1-
Design Management Process
STAGE ACTIVITY OUTPUT/RECORD
PROJECT PARAMETERS;
SEE DESIGN PLANNING
1. TENDER SUBMISSION & AWARD SITE;
APPROVALS;
STATUTORY AUTHORITIES;
SCOPE OF WORK CONSTRAINTS - ENVIRONMENTAL/
- CONSTRUCTIONAL
SELECT STAGE FROM
- EQUIPMENT
CONTRACT TYPE - TESTING REQUIREMENTS
PROJECT DELIVERY METHOD
TCI-DES-SF013
DESIGN/PLANNING
2. PROJECT DEFINITION DESIGN & CONSTRUCT/ ACTIVITY CHECKLIST
TIME SCHEDULE PROJECT MANAGEMENT/ROLES & AS REQUIRED
RESPONSIBILITIES
ENGAGE CONSULTANTS
OVERALL PROJECT BUDGET ESTIMATE
BILL OF QUANTITIES /
DESIGN CERTIFICATION SCHEDULE OF RATES
TCI-ADM-SP001
DOCUMENT CONTROL SUBCONTRACT TENDER
CONDITIONS OF CONTRACT
4.1.1
Where a design submission is a tender requirement, the Manager (Building, Civil,
Mining or process) shall determine the extent, the format and appoint the personnel
responsible for the preparation of the design.
4.1.2
The Design Manager shall determine the content, format etc. and shall prepare a
"Bid Preparation Plan" to ensure that compliance with the tender requirements is
achieved.
4.1.3
Where the services of external design consultant(s) are required they shall be
procured in accordance with Procedure TCI-PRO-SP001 - "Procurement of
Products and Services".
4.2 Procurement of External Consultant Services.
4.2.1
Where the services of external design/specialist consultants are required during any
stage of the design process, the Design Manager or personnel responsible for
procurement shall ensure that such services are procured in accordance with
Procedure TCI-PRO-SP001- "Procurement of Products and Services".
4.2.2
The Design Manager shall evaluate and appoint necessary external consultants
based upon factors including:
Professional registration;
Ability to assign appropriately qualified staff to the project and the ability to
complete the required service;
The Business Unit Manager/ Manager (BCMP) shall appoint a Design Manager to
facilitate and manage the design process.
4.3.2
The Design Manager shall prepare a DMP in accordance with Procedure TCI-OPS-
SP001 – “Preparation of Management Plans”, with the exception of Section 5,
which shall comprise of a statement of the management concepts and controls to be
exercised in relation to the specific project.
4.3.3
The Design Manager shall prepare checklists for each individual phase of the design
process. The Design Manager shall sign off each checklist upon completion of the
relevant phase. The Project Manager or nominee by signature shall verify
completion of the relevant phase. The Design/Planning Activity Checklist TCI-
DES-SF013 is deemed to be suitable for this purpose, however not mandatory.
It is the responsibilities of the Project Manager or appointed Project Design
Manager to prepare design verification checklists on a project specific basis.
4.3.4
The DMP shall be authorised by the Design Manager and the Project Manager,
where appointed, and endorsed by the Business Unit Quality Manager and Manager
(BCMP).
4.3.5
Where the contract requires the DMP to be submitted to the Client for appraisal or
approval, the Design Manager shall forward a copy to the Client. Where approval is
not granted, valid changes shall be effected and the plan resubmitted.
4.4 Design Process.
The Design Manager shall ensure that clear communication exists relating to
the full disclosure of facts, the Client's requirements and expectations, the
scope of work, the schedules and funding which are critical to the project.
The Design Manager shall keep senior management fully acquainted with
negotiations and areas of conflict shall be resolved prior to proceeding to
the next design stage.
Where a Project Brief has been developed by others the Design Manager or
management responsible for the preliminary Client negotiations shall check
the brief and resolve any conflicting expectations and requirements.
The Design Manager, in conjunction with the Design Team, shall review the
brief to ensure that the requirements of the Client with respect to function
and appearance, time & cost schedules, operability and maintainability,
environmental, safety, health and people impacts are clearly defined and
communicated.
The Design Manager, in conjunction with the Design Team, shall establish
policies and procedures for the effective and efficient functioning of the
Concept Development process including; drafting procedures, filing and
storing of documents, control of interfaces, change control, design reviews,
constructability reviews and costs, approvals and permits etc.
The Design Manager, in conjunction with the Design Team, shall establish
policies and procedures for the effective and efficient functioning of the
Design Development and Documentation process including; drafting
procedures, filing and storing of documents, control of interfaces, change
control, design reviews, constructability reviews and costs, approvals and
permits etc.
4.4.4 Documentation
The Design Manager, in conjunction with the Design Team, shall establish
policies and procedures for the effective and efficient functioning of the
Documentation process including; drafting procedures, filing and storing of
documents, control of interfaces, change control, design reviews,
constructability reviews and costs, approvals and permits etc.
The Design Manager shall ensure that procedures for handling changes to
documentation are established and are effectively implemented.
The Design Manager shall ensure that the design consultant who is
responsible for the design, approves the design and that he/she has the
authority to commit the design organisation.
4.4.5 Procurement/Construction.
The Design Manager shall determine the scope of work required of the
design consultants in the administration and monitoring of construction (e.g.
certification, review and approval of shop drawings, requests for
substitution, falsework design etc), dependent upon the need for material
and workmanship control/inspection.
The Design Manager shall ensure that such arrangements are documented in
the consultancy agreement between PT Thiess Contractors Indonesia and
the consultant.
review of complaints;
The Design Manager shall ensure that all appropriate records which
demonstrate compliance with the project requirements and records
which demonstrate achievement of the effective operation of the
design quality system are identified and filed in accordance with
procedure TCI-ADM-SP001 - "Document Control".
The Design Manager shall assist the Project Manager as required with
administration of the rectification of latent defects. Where necessary the
Design Manager shall enlist the aid of the Consultants to identify the cause
of latent defects and plan the rectification required.
4.5.1
The Design Manager in conjunction with the Business Unit Quality Manager shall
be responsible for ensuring that consultant prepared Design Plans comply with the
relevant quality standard and specified requirements.
4.5.2
The Design Manager shall ensure that the Design Plans employ a minimum of the
following design control measures:
Validation
4.5.3
The Design Manager shall periodically verify that consultant supplied Design
Plan(s) are being implemented. Verification may be achieved either through audit,
surveillance, design co-ordination meetings. etc.
4.6.1
The Design Manager shall hold design co-ordination meetings on a regular basis
during the relevant phases of the project. The meetings shall be conducted to a set
agenda and the meeting minutes filed in the project filing records.
4.7 Documentation Control & Records.
4.7.1
Quality records for activities associated with this procedure shall be maintained in
accordance with procedure TCI-ADM-SP001 - " Documentation & Record
Control".
5.0 REFERENCES
TCI-PRO-SP001 - Procurement of Products and Services
TCI-OPS-SP001 - Preparation of Quality Plans
TCI-ADM-SP001 - Document Control
TCI-DES-SF013 - Design/Planning Activity Checklist
6.0 ATTACHMENTS
Not Applicable to this procedure