FORM # K-001 (4/19) SHT 1 of 2

EQUIPMENT TYPE: USER REFERENCE:


EQUIPMENT TAG NO.: DESCRIPTION:
BI/JO NO.: PLANT NO. / LOCATION:
MODEL NO.: SERIAL NO.:
COMMISSIONING DATE:

HEATING VENTILATION & AIR CONDITIONING (HVAC)


Yes No NA

1- Verify that engineering drawings, calculations, specifications,


data sheets, performance curves and diagrams are
provided and complete, in accordance with the design
documents and Saudi Aramco requirements.

2- Verify that all Vendor documentation including installation,


start-up, and operation and maintenance manuals are
provided and complete, in accordance with the
documents and Saudi Aramco requirements.

3- Verify that all design drawings are certified " as-built "

4- Verify that the following components and systems installed in


accordance with design documents, Saudi Aramco
Standards, and manufacturer's recommendations,
including: Packaged A/C units, Air Handling units,
Condensing units, Fans, Filters, Hydronic coils, Electric
coils, Humidifiers, Pumps, Chillers, Cooling Towers,
Hydronic Piping, Refrigerant Piping, Piping attachments
and accessories, Ductwork attachments and accessories,
Thermostats, Valves, and Fire dampers and operating
dampers.

NOTE: This non-mandatory form may be used as the starting point to


assemble a pre-commissioning checklist. Entries should be revised,
added and deleted and approvals adjusted to reflect the needs of the
Project Acceptance Committee.
APPROVALS SAPMT INSPECTION OTHER DEPT. OPERATIONS
Signature & Date
FORM # K-001 (4/19) SHT 2 of 2

EQUIPMENT TYPE: USER REFERENCE:


EQUIPMENT TAG NO.: DESCRIPTION:
BI/JO NO.: PLANT NO. / LOCATION:
MODEL NO.: SERIAL NO.:
COMMISSIONING DATE:

Yes No NA

5- Ensure that all equipment are clean and all debris and foreign
matter are removed.

6- Check if any of the equipment and components are damaged.

7- Ensure that adequate clearances are provided for service and


maintenance as required by the manufacturer and design
drawing.

8- Ensure that all nameplate data and equipment tags are in


accordance with the design documentation, certified
vendor's documents, and Saudi Aramco Standard.

9- Ensure that spare parts provided in accordance with the


design and vendor's documents, and spare parts are
original and the same as the parts they are to replace.

10- Check that all safety systems and devices are in place and
functional, in accordance with the design documents and
Saudi Aramco Standard.

11- Verify that Testing, Adjusting and Balancing (TAB) of the


HVAC System is completed in accordance with the
requirements of the design documentation.

NOTE: This non-mandatory form may be used as the starting point to


assemble a pre-commissioning checklist. Entries should be revised,
added and deleted and approvals adjusted to reflect the needs of the
Project Acceptance Committee.
APPROVALS SAPMT INSPECTION OTHER DEPT. OPERATIONS
Signature & Date