Você está na página 1de 2

Checklist for Internal Plastering

Client Inspection Report No

Consultant Date

Vendor
Package Civil finishes
Description of Work INTERNAL PLASTERING -- CEILING/WALL
Wing Dwg.Ref.No Rev Inspection Request
Floor Inspected by By Time
Details :
Location
Sl. No Description YES NO NA Remarks
MEP CLEARANCES

Have the Electrical conduits & LV conduits works been completed as


1
per check list & accepted & signed by all concerned

Have the Electrical junction boxes works been completed as per


2
check list. Has it been Accepted & signed by all concerned.

Has the packing for the Electrical conduits and boxes fixed in wall
3 using thermocol, cement mortar, mesh works been completed as per
check list. Has it been accepted & signed by all concerned.

Has the PHE piping works in toilets and kitchen been completed as
4
per check list. Has it been accepted & signed by all concerned.

Has the A/C drain piping works been completed as per check list. Has
5
it been accepted & signed by all concerned

Vendor CBRE Client

Signature Signature Signature


Name Name Name
Date Date Date
During Plastering YES NO NA
1 Is the latest "Good For Construction" drawing available
2 Has the method statement submitted
Check if raking of masonry joints and hacking on RCC surfaces been
3
done.
Check if the Masonry , RCC surfaces is cleaned & free from lumps of
4
dead mortars
Check if the scaffolding is safe and suitable for executing the said
5
works.
Check if the CM Mix proportion for plastering work is as per the
6
technical specification

Check if Chicken mesh is provided at the junctions of RCC & Block


7
work, and over electrical conduit.

8 Check for bull marks and record the average thickness of plaster

Check if true level surface, right angle, plumb, room dimension &
9
straight edge are available before commencing to plaster the surface

Check if architectural features such as Groove, Band etc. are being


10 provided as specified while plastering. (Both supervisor and the
mason to be made aware of the same)
Post plastering YES NO NA
Check if a true level surface has
Check for trueness of plastered surface and record the variance if
1 been achieved after Plastering and
any
record the variation .

CBRE South Asia Pvt. Ltd. Project Management, India 1 of 2


Check to ensure that the straightness of edges, right angels and
2
plumb have been achieved

3 Has dead mortar been removed and plumb checked subsequently

Check if the scaffolding has been completely removed and all


4
openings have been sealed.
By gently Tapping the surface with
5 Check if there is any hollowness in the plaster.
wooden mallet
Check if the Curing arrangements have been made and the
6
sufficiency of curing period, if specified
Observations if any :

Above Observations attended to and completed YES NO NA


The above works have been completed and accepted
CBRE
Contractor Civil Contractor Quality Contractor Safety CBRE Safety Client Representative
Representative

Signature

Name
Date
Time
Distribution Original : CBRE - QS cc : Vendor
Format No. F021-QC-Ch-024/Rev01/Oct2013

CBRE South Asia Pvt. Ltd. Project Management, India 2 of 2

Você também pode gostar